1 Franklin Pierce School District Capital Projects Journal
2 Capital Projects Levy
3 Capital Projects Levy Envisioned and defined by FPS 2030 committee Levy collections began in 2012 Provides $27,500,000 in funds over 5 years for capital construction and improvements to District schools Over $11,000,000 in revenue raised to date
4 Promises Made Renovate Keithley Middle School Cafeteria (Building 600) Renovate Ford Middle School Cafeteria Installation of Learning Walls in District schools Energy Upgrades Including Mechanical Source of Funds for Small Projects
5 Promises Kept Keithley Middle School Cafeteria Renovation Project Duration: February 2013 to December 2014 Project Budget: $8,400,000 Scope of Work: Renovation of 14,720 square feet New Construction of 4,272 square feet Construction of a Central Kitchen Commons Space Administration Space Band Room Choir Room Computer Lab Site Improvements
6
7
8
9 FPS 2030 Report - January 20, 2015
10
11 Promises Kept Learning Wall Technology in Each Classroom Phase 1: June 2013 August 2013 Harvard Elementary James Sales Elementary Central Avenue Elementary Brookdale Elementary Transportation Training Room WHS Ridgeway Room FPHS Corrigan Room Project Budget: $694,651 Phase 2: June 2014 August 2014 Christensen Elementary Elmhurst Elementary Midland Elementary Collins Elementary Board Room New Portables Project Budget: $407,087
12 Phase 1
13 Phase 2
14 Promises Kept Energy Upgrades (Phase 1) Energy Upgrades to: Washington High School James Sales Elementary Central Avenue Elementary Brookdale Elementary Transportation Training Room WHS Ridgeway Room FPHS Corrigan Room Project Budget: $2,000,000 Grant Funds: $1,000,000 Levy Funds: $973,409 Projected Operational Savings: $30,259/year
15 Energy Upgrades Grant Phase 1
16 Phase 1
17 Promises Kept Provide Additional Classrooms Provide Ten Classrooms Over Summer of 2014 to Meet New Class Size Standard Five Double Portable Classrooms Added to Campuses at: Central Avenue Elementary (4 Classrooms) Harvard Elementary (2 Classrooms) Collins Elementary (2 Classrooms) Midland Elementary (2 Classrooms) Project Budget: $1,641,145
18
19 FPS 2030 Report - January 20, 2015
20
21 Promises Kept In Process Ford Middle School Cafeteria Renovation Current Status: In Design Project Duration: May 2015 to February 2016 Project Budget: $6,500,000 Scope of Work: Renovation of 12,150 square feet New Construction of 5,756 square feet Renovated Kitchen Commons Space Band Room Choir Room Site Improvements
22
23
24
25 Promises Kept In Process Energy Upgrades (Phase 2) Energy Upgrades to: Franklin Pierce HS Ford Middle School Gates High School Keithley Middle School Christensen Elementary Elmhurst Elementary Collins Elementary District-wide Computers Project Budget: $888,138 Grant Funds: $204,263 Levy Funds: $683,875 Projected Operational Savings: $31,500/year
26 Energy Upgrades Grant Phase 2
27 Promises Kept In Process Learning Wall Technology in Each Classroom Phase 3: June 2016 August 2016 Keithley Middle School Ford Middles School Gates High School Phase 4: June 2017 August 2017 Franklin Pierce High School Washington High School Project Budget: $460,402 Project Budget: $895,745
28 Capital Projects Other Funds FPS 2030 Report - January 20, 2015
29 Other Funds Sources of Funds: General Fund Dedicated Funds Grants Incentives Rebates Special Appropriations
30 2010 District Office
31 2010 District Office
32 2013 Portables
33
34 2013 Stadium Artificial Turf Replacement
35
36 2013 T&L Office Remodel
37 2013 Lower KMS Sports Field Restoration
38 2013 Classroom Renovation - James Sales
39 2013 Improvements at New Pathways
40 2013 Walk-in Cooler for Midland
41 2014 Stadium Repairs
42 2014 Collins Office Remodel
43 2014 Basketball Court Graphics - FPHS
44 KMS Lighting Re-Support FPHS Bleacher Seat Replacement FPHS Kitchen Equipment Upgrade
45 2014 Lower Ford MS Sports Field Restoration
46 2014 Re-Purposing of Gates Restroom
47 2014 Tile Floor Replacement - WHS
48 2014 Walk-in Cooler & Freezer- WHS
49 2015 Christensen Office Remodel
50
51 2015 Resurfacing of WHS Track
52 2015 Early Learning Center Project
53
54
55
Centinela Valley Union High School District. Measure CV Masterplan Update June 2011
Centinela Valley Union High School District Measure CV Masterplan Update June 2011 Hawthorne High School (Phase 1) Hawthorne High School Phase 1: Science, Engineering, and Media Arts Center (Funded) 3
More informationCONSTRUCTION UPDATE. Thank you for your continued support! Noemi Avila-Zamudio Coordinator, Facilities Planning & Construction SEPTEMBER 2012
CONSTRUCTION UPDATE WWW.SVUSD.ORG SEPTEMBER 2012 The 2012-2013 school year is proving to be another year filled with exciting, much needed Measure B building projects. Facilities Planning & Construction
More information2006 Bond. 2011 Bond. 11/12/2015 2015 Bond Timeline Report to Board of Trustees November 17, 2015
2015 Bond Timeline Report to Board of Trustees November 17, 2015 2006 Bond $875k allocated to parking lot improvements on Shriner property Projects to be completed August 2016 Completes 2006 bond program
More information1. Background. 2. Why this is Relevant to the 2014 Bond. 3. Attachments
Issue Paper # 8: Modernization Renovation Projects 1. Background BSD s student population has grown since the last capital bond in 2006 and facilities have experienced normal wear and aging leading to
More informationNovember 3, 2015 Bond and District Additional Assistance Election Information
November 3, 2015 Bond and District Additional Assistance Election Information Proposition 432 - $22 million General Obligation Bond 150+ facility projects across all schools Building renovations and improvements
More informationCherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016
Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Year Opened 2003 Current Square Footage 391,000 Site Acreage 86.22 cherokeetrail.cherrycreekschools.org $279,200 Asphalt and concrete
More informationElection Type: Bond, BEST, Mill Levy District. Nov. 4: Pass/Fail. Bond, BEST, Mill Levy Override, Sales Tax. Comments (optional) Dollar Amount
Sources: School reports to CSFP, district websites and media reports BOND / BEST - CAPITAL OPERATIONS Adams 12 Five Star Bond Fail $220,000,000 Extending the useful life of existing school buildings, renovating
More informationPAGE INTENTIONALLY LEFT BLANK
PAGE INTENTIONALLY LEFT BLANK TABLE OF CONTENTS I. Introduction 1 Page II. Documentation of Existing Educational Programs 1 and Instructional Space III. State Square Footage Standards 2 IV. Space Allocation
More informationDistrict Information
Bond 2010 District Information 95.5% College Bound 2009 College Readiness Award from Texas ACT Council #1 Ranked Traditional High School in San Antonio by Children at Risk 458 AP test takers/ 875 tests
More informationCherry Creek School District Update - 2012 Bond Projects
Cherry Creek School District Update - 2012 Bond Projects Summer Projects, 2013 September 9, 2013 School Locations Where Projects Have Been Completed Summer, 2013 Elementary Schools: Cimarron Creekside
More informationCALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN
DISTRICT "SHELL" SUBMISSION DATE: 4/17/13 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 4/19/13 (delete following Hearing) KBE APPROVAL DATE: JUNE 2013 CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES
More informationBond Referendum Presentation. Dr. Ralph P. Ferrie, Superintendent of Schools May 12, 2014
Bond Referendum Presentation Dr. Ralph P. Ferrie, Superintendent of Schools May 12, 2014 Mr. David Fowler President Floral Park- Bellerose Mr. David Del Santo Vice-President New Hyde Park Garden City Park
More informationSchematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects
To r r e y P i n e s H i g h S c h o o l M a s t e r P l a n Schematic Plan Submittal, 21 November, 2011 Roesling Nakamura Terada Architects I n t r o d u c t i o n 1.0 INTRODUCTION The vision for the
More informationFrequently Asked Questions
Byron Area Schools Frequently Asked Questions Bond Proposal How did this come about? For several years the Byron Area Schools Board of Education has included upgrading facilities as one of the district
More informationBensalem High School Renovation 2014-2016
Bensalem High School Renovation 2014-2016 Design Problems Inability to close off sections of the building during evening and weekend events. Concerns about the efficiency of staffing and supplying three
More informationVan Vleck ISD Bond Election
Van Vleck ISD Bond Election November 4, 2014 The Van Vleck ISD School Board called a bond election at their meeting on August 18 for $42.7 million. 2 School districts must ask voters for permission to
More informationFRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009
FRANCIS L. CARDOZO HIGH SCHOOL 1200 CLIFTON STREET NW WASHINGTON, DC 20009 FRANCIS L. CARDOZO HIGH SCHOOL SCHOOL HISTORY Francis L. Cardozo High School, located at 1200 Clifton Street and bounded by Florida
More informationItems in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes.
Office of Safe and Orderly Schools Facility Safety Assessment Dennis Meador, School Facilities Supervisor Mark Hobson, School Facilities Supervisor Division of School Building September 18 19, 2007 Items
More informationMequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule
Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal
More informationDEARBORN HEIGHTS SCHOOL DISTRICT NO. 7 Sinking Fund Projects 10 Year Plan Proposal (2016 2025)
DEARBORN HEIGHTS SCHOOL DISTRICT NO. 7 Sinking Fund Projects 10 Year Plan Proposal (2016 2025) Year One $995,000.00 Polk electronic marquee Annapolis roof needs half of building replaced Phase One District
More informationColorado School Finance Project 1200 Grant Street, Denver, Colorado 80203 303-860-9136 - Fax: 303-832-1086 - @COSFP - cosfp.org
Student Count Colorado School Finance Project Override, Sales Tax Dollars Purpose Comments BOND ELECTIONS: Alamosa 2,098 Bond $4,990,000 Constructing, equipping and furnishing an athletic complex on the
More informationMEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010
MEASURE G-2010 EXHIBIT B FULL TEXT BALLOT PROPOSITION OF THE SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT BOND MEASURE ELECTION NOVEMBER 2, 2010 To better prepare San Jose City College/ Evergreen Valley
More informationFive-Year Capital Plan Request FY 2015-16 through FY 2019-20
Section Contents Five-Year Capital Plan Request FY 2015-16 through FY 2019-20 Project Funding Type Total ($ 000s) Critical Maintenance for Community Colleges bonded $417,500 Health and Safety bonded $91,088
More informationColorado School Finance Project 1200 Grant Street, Denver, Colorado 80203 303-860-9136 - Fax: 303-832-1086 - @COSFP - cosfp.org
BOND ELECTIONS: Alamosa Bond $4,990,000 Constructing, equipping and furnishing an athletic complex on the high school site, including locker rooms, an athletic storage building, a team building, track
More informationProject Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT February 2015 Project Management Division BELOW: Collins Construction crews complete recent exterior work and await delivery of exterior siding. Collins
More informationHERMANTOWN COMMUNITY SCHOOLS. New High School Addition End of DD Design Review
HERMANTOWN COMMUNITY SCHOOLS New High School Addition End of DD Design Review SITE AERIAL HIGH SCHOOL ELEMENTARY SCHOOL BUS GARAGES HOCKEY ARENA / DISTRICT OFFICE SITE FORCES EXISTING BUILDING INFORMATION
More informationCAMPUS HIGH SCHOOL ADDITION AND RENOVATION
LEGEND RENOVATION ADDITION DRIVE IMPROVEMENTS WIDEN BUS LOOP ROAD TO WEST PROVIDE SECURE ADMINISTRATION ENTRANCE REPLACE AGING ELECTRICAL PANELS RENOVATE SPACE FOR FIVE (5) SCIENCE CLASSROOMS CONVERT EXISTING
More informationGregory-Portland Independent School District. G-PISD BOND ELECTION November 6, 2012. Information Guide
G-PISD BOND ELECTION November 6, 2012 Information Guide Información en Español Información sobre la emisión de bonos del Gregory- Portland Independent School, el dia 6 de Noviembre 20012, es disponible
More informationDISTRICT-WIDE ELEMENTARY PROGRAMMING
DISTRICT-WIDE ELEMENTARY PROGRAMMING PREPARED BY: GIBRALTAR DESIGN SUBMITTED TO: BOARD OF SCHOOL TRUSTEES School Board Meeting September 17, 2015 2015 Gibraltar Design, Inc. Table of Contents SECTION I.
More informationNorth East Independent School District 2011 Bond Proposal
North East Independent School District 2011 Bond Proposal North East ISD Garrett J. Sullivan, Executive Director Construction Management & Engineering Department The Process Community Planning and Advisory
More informationPublic Building Commission of Chicago. Board Meeting August 20, 2013
Public Building Commission of Chicago Board Meeting August 20, 2013 Board Meeting August 20, 2013 Recent Events Enrico Tonti Elementary School Kindergarten Modular Opening August 5, 2013 Board Meeting
More informationDESIGN AND CONSTRUCTION DEPARTMENT - July 2014
DESIGN AND CONSTRUCTION DEPARTMENT - Project or 1 Elementary School 46 (Aliana) AutoArch Bartlett Cocke General ors Construct a new 850 capacity elementary school in the Aliana Master Planned Community.
More informationNewtown and Holland Middle Schools Construction Project Bid Review
Newtown and Holland Middle Schools Construction Project Bid Review *Includes clarifications requested at 30MAR16 FACCOM Meeting (italicized) Facilities Committee Meeting March 30, 2016 (Updated March 31,
More informationChicago Public Schools
Ames Middle School 1920 N Hamlin Ave 1997 Completed The scope of this project is to construct a new school $16,913,379 2014 Construction The intent of this project is to expand existing Ames middle school
More informationENERGY USAGE GUIDELINES
Mission ENERGY USAGE GUIDELINES The mission of Coppell ISD s Energy Management is to develop and implement energy resource strategies that increase conservation awareness from students, staff, and community,
More informationOnline Survey Executive Summary
Online Survey Executive Summary Center Moriches School District March 9, 2015 Online Survey Executive Summary METHODOLOGY The following results are based on a website and paper survey of 356 residents
More informationWausau School District. Please vote! Referendum Tuesday, April 7, 2015. Our Mission To advance student learning, achievement, and success.
Wausau School District Referendum Tuesday, April 7, 2015 Please vote! Our Mission To advance student learning, achievement, and success. Background Shared Key Interests (Align to Referendum) May 2011 A
More informationFebruary 2014 Maintenance & Operations (M&O) Levy Question and Answers, Updated 12-17-13
February 2014 Maintenance & Operations (M&O) Levy Question and Answers, Updated 12-17-13 Where do public schools get their money? We receive our funding from three sources - State, Federal and Local. About
More informationCONSTRUCTION UPDATE November 6, 2015
CONSTRUCTION UPDATE November 6, 2015 Donaldsonville High School Athletic Addition East Ascension High School Athletic Addition St. Amant High School Athletic Addition St. Amant High School Freshman Academy
More informationBond Priorities. Repairs and Maintenance. School Safety. Capacity
Replace old windows, boilers, heating and air conditioning system. Improve accessibility for disabled persons. Keyless entry lock systems, redesign of school entrance, and wireless access throughout building.
More informationMay 2014 Texas School Bond Elections
May 2014 Texas School Bond Elections What are the individual districts needs? New facilities Renovations Technology Central facilities How much tax revenue can the district generate? Depends on district
More informationDAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN
DISTRICT "SHELL" SUBMISSION DATE: 11/13/12 questions 11/26/12 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 11/19/12 revised 11/26/12 (delete following Hearing) KBE APPROVAL DATE: FEBRUARY
More information3 Facility Organization Strategy
3 Facility Organization Strategy TVC Master Plan McCool Carlson Green Architects 3 3 Facility Organization Strategy UAF s Tanana Valley Campus currently offers more than 40 certificate and degree programs
More informationDESIGN DEVELOPMENT PRESENTATION
October 26, 2015 DESIGN DEVELOPMENT PRESENTATION NEW SHIRLEY HALL MIDDLE SCHOOL & JOE M. TISON MIDDLE SCHOOL ADDITIONS AND RENOVATION WEATHERFORD INDEPENDENT SCHOOL DISTRICT Acknowledgments 3 Narrative
More informationSTATE UNIVERSITY OF NEW YORK COLLEGE OF OPTOMETRY 2015 CAMPUS STATEMENT
STATE UNIVERSITY OF NEW YORK COLLEGE OF OPTOMETRY 2015 CAMPUS STATEMENT The College of Optometry, located at 33 West 42nd Street in mid-manhattan, was founded as a State College within the SUNY system
More informationPortland Parks & Recreation Budget Advisory Committee January 15, 2015 Public Comment and BAC Prioritization Summaries One-time Funding The following chart shows the budget proposals presented by PP&R
More informationPath to a New Horizon:
Path to a New Horizon: Bond Committee Report & Preliminary Recommendations Board of Education July 9, 2015 Bond Committee Peter Spadafore, Co-chair, LSD Board President Nancy Mahlow, Co-chair, Eastside
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationSchool Board Proposed Capital Improvements Program. Fiscal Years 2014-2023
School Board Proposed Capital Improvements Program Fiscal Years 2014-2023 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-6 Capital Projects Description Pages 7-14 SCHOOL BOARD PROPOSED CAPITAL
More informationSCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL
March 16, 2015 SCHEMATIC DESIGN PRESENTATION ACTON ELEMENTARY SCHOOL DUNCANVILLE INDEPENDENT SCHOOL DISTRICT Acknowledgments 2 Narrative 3 The Process 4 Site Analysis 6 Site Plan 7 ACTON ELEMENTARY SCHOOL
More informationHigher Education Projects University of Illinois at Urbana-Champaign Gorski Reifsteck
Laboratories Bevier Hall Food Labs Renovation College of ACES Everitt Lab 4th Floor Remodel - Phase I Renovation College of Engineering MATSE Kiln House Renovation Phase I College of Engineering MATSE
More informationD. Scott Babbit 218 Wilkes Street Steilacoom, WA 98388
D. Scott Babbit 218 Wilkes Street Steilacoom, WA 98388 S U M M A R Y Principal of Babbit Neuman Construction Co. (BNCC, Inc.), overseeing the office staff including accounting, estimating, project management
More informationMAIN IDEA The rectangle at the right has an area of 20 square units. The distance around the rectangle is 5 + 4 + 5 + 4, or 18 units.
1-9 Algebra: Area Formulas MAIN IDEA The rectangle at the right has an area of 20 square units. The distance around the rectangle is 5 + 4 + 5 + 4, or 1. Find the areas of rectangles and squares. New Vocabulary
More informationALEXANDRIA CITY PUBLIC SCHOOLS (ACPS)
ALEXANDRIA CITY PUBLIC SCHOOLS (ACPS) The entire ACPS Capital Improvement Program can be found on-line at: http://www.acps.k12.va.us/budgets/ Approved FY 2016-2025 CIP Page 87 PAGE LEFT BLANK INTENTIONALLY
More informationCITY OF SANTA ROSA HIGH SCHOOL DISTRICT Sonoma County, State of California 2014-15 RESOLUTION NO. 2014/15-003
CITY OF SANTA ROSA HIGH SCHOOL DISTRICT Sonoma County, State of California 2014-15 RESOLUTION NO. 2014/15-003 RESOLUTION CALLING FOR AN ELECTION AUTHORIZING THE ISSUANCE OF GENERAL OBLIGATION BONDS OF
More informationFinish Floor System Analysis
Finish Floor System Analysis Introduction: When conducting a finish floor system analysis, it is important to consider not only the type of building the floor is going into, but also what space it is for.
More information1/9/2015 P:\130217-03\Project Management\Program\Ripon Space Program - 7 January 2015.xlsx
MIDDLE SCHOOL Administration Office Principal's Office 200 1 200 Desk, conference table for 4-6 Conference Room 250 1 250 Conference table for 12 Open Office Area 250 1 250 2 Workstations Mail / copier
More informationPROPOSITION E. Associated General Contractors of America San Diego Chapter September 17, 2014
PROPOSITION E Associated General Contractors of America San Diego Chapter September 17, 2014 1 Facilities Centric Bond Aging Facilities Emphasis on Technology Infrastructure School Site Safety and Security
More informationM E M O R A N D U M. April 15, 2010. Planning, Housing, and Economic Development Committee
M E M O R A N D U M April 15, 2010 TO: FROM: SUBJECT: Planning, Housing, and Economic Development Committee Jennifer Renkema, Research Associate Office of Legislative Oversight Examples of Proposed FY11
More informationBoard Seminar Facilities. School Year 2012-2013. Submitted by Joseph L. Lisa-Director of Facilities
Board Seminar Facilities School Year 2012-2013 Submitted by Joseph L. Lisa-Director of Facilities High School Installed new fence for Pre-K activities by weight room. Installed new rails and side walks
More informationGuideline for Construction Reimbursement Rates. 160-5-4-.16 (a) 7. Educational Facility Site, Construction, and Reimbursement
Guideline for Construction Reimbursement Rates 160-5-4-.16 (a) 7 Educational Facility Site, Construction, and Reimbursement Facilities Services Unit Effective Date: 05-30-12 NEW CONSTRUCTION REIMBURSEMENT
More informationHow To Plan A School District
OCPS Building Program Presentation to Central Florida ABC May 14, 2013 1 AGENDA Facilities Update Where are we now? Recent Facilities Condition Assessment Efficiencies Questions 2 In Planning Comprehensive
More informationL&S Associates, LLC. Educational, Environmental, Maintenance & Operations Consultants (EEMOCo)
L&S Associates, LLC Educational, Environmental, Maintenance & Operations Consultants (EEMOCo) League City, Texas Home Office 281-386-6042 Tyler, Texas Area Office 903-504-1111 Athens, Texas Area Office
More informationSCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL
June 15, 2015 SCHEMATIC DESIGN PRESENTATION NEW JOSHUA MIDDLE SCHOOL JOSHUA INDEPENDENT SCHOOL DISTRICT Acknowledgments 2 Narrative 3 The Process 4 Site Analysis 5 Independent School District Site Plan
More informationstadium designs BLRB architects TACOMA // SPOKANE // PORTLAND // BEND
stadium designs TACOMA // SPOKANE // PORTLAND // BEND about blrb architects Founded in 1953, BLRB is a mid-size regional firm with offices throughout the Northwest in Tacoma, Spokane, (Washington) Portland
More informationDISTRICT WIDE: MAGNET, CHARTER SCHOOLS AND PROGRAMS
DISTRICT WIDE: MAGNET, CHARTER SCHOOLS AND PROGRAMS FEEDER SYSTEM: 1 HIGH SCHOOLS = (3) Garrett Academy of Technology Academic Magnet HS Septima Clark Academy MIDDLE SCHOOL + HIGH SCHOOL = (2) School of
More informationBUNKER HILL ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 98,200 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 387 WARD 5 PROPOSED PROGRAM CAPACITY 750 Site Plan BUNKER HILL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationBy James Britt, Elizabeth Erbes, Julie Rosin and Bill Good
connecting students, creating futures at central campus By James Britt, Elizabeth Erbes, Julie Rosin and Bill Good Central Campus... evolving as a 21st century educational environment... connecting students
More informationCAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT RIGHT: the proposed conceptual profile of the new Joe Redington Sr. JR/SR High School January 2014 Project Management Division New Knik Area Middle/High
More informationProperty Tax Incentives Will Support Five Industrial and Commercial Projects
FOR IMMEDIATE RELEASE June 25, 2014 CONTACT: Mayor s Press Office 312.744.3334 press@cityofchicago.org Department Planning and Development (DPD) (312) 744-9267 Property Tax Incentives Will Support Five
More informationLincoln Public Schools
VANDERWEIL Lincoln Public Schools Technology Plan Introduction Agenda Technology Improvements Introductions Background, review of requirements Status Priorities and goals Budget options and discussion
More informationSchool District. Dr. Barry Amacker, Superintendent Jackson County School District
Dr. Barry Amacker, Superintendent Jackson County School District Greetings JACO Nation, As we look forward to the 2015-16 school year, I would like to thank you for another great year in 2014-15. As you
More informationORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT
1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.2 Water damage in many classrooms. Replace tiles. 1.1.3 Cabinets, Equipment 1.1.4 Portables
More informationINDIVIDUAL CAMPUS PLAN ASSESSMENT. No. of Non- Non-Instructional Area. Size Sq. Ft.
ED. SPEC. ELEMENTARY SCHOOL SPACE BUDGET Program Menchaca ES Page 1 of 6 INDIVIDUAL CAMPUS PLAN ASSESSMENT al s Non- al s Size Pre-Kindergarten / Kindergarten - Classrooms 8 8 925 7,400 (minimum or 25
More informationJinyung Cha (Ms.) E-mail: jycha@business.kaist.ac.kr. Phone: +82-2 - 958-3244 Fax: +82-2 - 958 3210
1 KAIST Business School International Center 85 Hoegiro, Dongdaemun - gu Seoul 130-722 KOREA ASCHOOL FACT SHEET 2012-2013 Last updated March 21. 2012 KAIST is the first school to offer MBA programs in
More informationREQUEST FOR QUALIFICATIONS FOR ARCHITECTURAL SERVICES. PARKVIEW ELEMENTARY SCHOOL October 2014
REQUEST FOR QUALIFICATIONS FOR ARCHITECTURAL SERVICES PARKVIEW ELEMENTARY SCHOOL October 2014 I. PROJECT INFORMATION A. Name: Bellingham School District Parkview Elementary School B. Location: 3033 Coolidge
More informationOnce you see it, you get it! A quick overview of projects..
Once you see it, you get it! A quick overview of projects.. Bank of Arizona, Scottsdale We re used to building in 22 months; Modular Technology built our 3 branches in just 5 months! Their quality is superior
More informationBellingham, WA. (360) 555-5555 susancarey@email.net
Sample Chronological Résumé Susan Carey 4444 A Street 98229 susancarey@email.net Objective To obtain a nursing assistant position while completing my Practical Nursing Certificate. Highlights of Qualifications
More informationThe Student Affairs Program Review Narrative Report. Members of the Student Affairs Program Review Team: John Beam/Josh Ramos/Johnnie Williams
The Student Affairs Program Review Narrative Report 1. COLLEGE: Laney College Discipline, Department or Program: Athletics Date: November 25, 2012 Members of the Student Affairs Program Review Team: John
More informationAngelo State University Construction Report
May 12, 2009 Angelo State University Construction Report Modular buildings will temporarily house ASU staff during the Hardeman renovation starting this fall. Prepared for: John Russell, Director of Planning
More informationTECHNOLOGY PLAN SUMMARY
IV. TECHNOLOGY PLAN SUMMARY The Oklahoma City Metropolitan Area Public Schools (OCMAPS) Technology Plan serves as a guide for OCMAPS funding of technology into the Oklahoma City Public School District
More informationElectrical. This section applies to the design and installation of building power distribution systems.
Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions
More informationA Self-Audit of Your Current Campus Security Systems
A Self-Audit of Your Current Campus Security Systems Security Solutions for Education, Business & Public Safety Free Consultations on ID Card Systems, Access Control, Call Recording, Video Surveillance,
More informationSODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000
More informationORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT
1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.3 Cabinets, Equipment 1.1.4 Portables 1.2 Fire / Life Safety 1.2.1 Corridor, Separation
More informationCentennial Building Campaign
T H E B U C K L E Y S C H O O L Centennial Building Campaign THE BUCKLEY SCHOOL HAS PURSUED EXCELLENCE in educating boys since it was founded in 9. Over the past decade, it has become clear to the Board
More informationFayette County Schools Reconfiguration and Realignment
Fayette County Schools Reconfiguration and Realignment Response to Questions: 1. What will happen to Collins Middle next year? Will the students stay split up for three more years? Yes, in the current
More informationElgin ISD 2015 16 Salary Scale Classroom Teachers, Librarians, Specialists & Registered Nurses
Elgin ISD 2015 16 Salary Scale Classroom Teachers, Librarians, Specialists & Registered Nurses Years Daily Annual Experience Rate Salary 0 $235.29 $44,000 1 $237.97 $44,500 2 $239.30 $44,750 3 $240.64
More informationPendergast Students Among First in U.S. to Take Online PARCC Test Thanks to Bond
Register for kindergarten NOW! See details on page 3 Serving the Community of Pendergast Elementary School District #92 Pendergast Students Among First in U.S. to Take Online PARCC Test Thanks to Bond
More informationSPONSORSHIP PROPOSAL 2014-2015
HOUGHTON COLLEGE ATHLETICS SPONSORSHIP PROPOSAL 2014-2015 One Willard Avenue Houghton, NY 14744 P 585.567.9556 F 585.567.9365 brianna.allen@houghton.edu athletics.houghton.edu THE HIGHLANDER EXPERIENCE
More information30401 Agoura Road, Agoura Hills, CA 91301. Property Photos
Roger Beck, SIOR Senior Managing Director Lic. # 00917957 rbeck@charlesdunn.com Direct 818.455.8208 Office 818.455.8200 Fax 818.304.8991 Gelena Skya-Wasserman Director Lic. # 01813986 gskya@charlesdunn.com
More informationTempe Elementary School District No. 3- Tempe, AZ Escalante Park
Tempe Elementary School District No. 3- Tempe, AZ Escalante Park The NFL Foundation Grassroots Program has awarded Tempe Elementary School District No. 3 a $100,000 field surface grant to help install
More informationWorkforce Investment Area 13. an adjusted full-time equivalent enrollment of 611 students.
Workforce Investment Area 13 A R K A N S A S The Tennessee College of Applied Memphis Main Campus is located on Alabama Avenue, just across Interstate 40 from St. Jude s Hospital and only half a mile from
More informationBoard of Regents Meeting June 16-17, 2005 Agenda Item #11 Arizona State University EXECUTIVE SUMMARY Page 1 of 5
EXECUTIVE SUMMARY Page 1 of 5 ACTION ITEM: Academic Renovations and Deferred Maintenance Phase I, Revised Revised Project Implementation Approval, (ASU). ISSUE: ASU requests Revised Revised Project Implementation
More informationPRIVATE BUSINESS USE FOR QUALIFIED 501(C)(3) BONDS
PRIVATE BUSINESS USE FOR QUALIFIED 501(C)(3) BONDS Courtney A. Strutt Todd Davis Brown Law Firm PRIVATE BUSINESS USE GENERAL RULE Borrowers may lose their tax exemption if they have more than 5% of Private
More informationSchools Under Construction for N.I.S.D.
October 2009 NORTHSIDE INDEPENDENT SCHOOL DISTRICT Schools Under Construction for N.I.S.D. Facilities Construction Vernon Dunagin, AIA Assist. Superintendent of Facilities & Operations Leroy San Miguel
More informationE X I S T I N G F A C I L I T I E S
Los Angeles Unified School District Facilities Services Division E X I S T I N G F A C I L I T I E S 68 TH STREET ELEMENTARY SCHOOL FOOD FACILITIES BUILDING Monthly Program Status Report August 2011 Prepared
More informationSMART Initiative Information
SMART Initiative Information On November 4 th, Broward County voters will have an opportunity to cast their ballots regarding an $800 million General Obligation Bond. The proceeds of this bond will be
More informationElementary School to enclose the open plan design of some classrooms.
2012 BOND The 2012 Bond included renovations of Bromwell Elementary School to enclose the open plan design of some classrooms. It also included renovations to correct some current code deficiencies and
More informationWe know what brings schools together.
School Work We know what brings schools together. About Us Martin Gardner Architecture, P.C. has been providing excellence in design and building consulting services in eastern Iowa for nearly 30 years.
More information