1 North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T5-03 Miami-Dade s Force Main Government Cut Replacement Project Norman Joyal, PE 1, Steve Mancini 2, Orlando Castro, PE 3, Ray Post 4, Jeffrey Weakly 5, Glenn Boyce, PhD, PE 1, Eduardo Vega, PE 6 1 Jacobs Associates, Walnut Creek, CA, USA 2 Ric-Man Construction, Inc., Detroit, MI, USA 3 Hazen & Sawyer, PC, Coral Gables, FL, USA 4 Michels Corporation, Brownsville, WI, USA 5 Super Excavators, Inc., Menomonee Falls, WI 6 Miami-Dade County Water & Sewer Department, Miami, FL, USA ABSTRACT: Miami-Dade Water and Sewer Department (MDWASD) owns and operates a 54-inch (1,370 mm) force main that transmits sewage from Miami Beach to Fisher Island and then onto the Central District Wastewater Treatment Plant on Virginia Key. The force main crosses Government Cut with a top-of-pipe elevation that conflicts with the Federal Navigational Dredging Project, which proposes to widen and deepen the channel to increase the Port of Miami s capacity. To accommodate the US Army Corps of Engineers dredging project schedule, the replacement force main must be designed, constructed, and commissioned prior to the start of channel deepening. Ric-Man Construction s design-build team designed the replacement force main as a two-pass microtunnel containing a 72-inch-diameter (1,830 mm) steel casing with a 60-inch-diameter (1,525 mm) fiberglass carrier pipe. The 1,178-foot-long (359 m) force main was constructed from a secant pile shaft on Fisher Island to the secant pile receiving shaft constructed in the water. During an inspection of the then-existing prestressed concrete cylinder pipe force main after construction started, the segment of force main that passes beneath the Miami Beach Marina was deemed vulnerable to imminent failure. Therefore, a second 689-foot-long (210 m) drive from Miami Beach to the Water Shaft was added to the project. The first drive across the shipping channel was completed in February 2013, and the second drive from Miami Beach to the Water Shaft was completed in May This paper discusses design and construction of the pipeline crossing, and presents information collected during construction. 1 INTRODUCTION The Miami-Dade Water and Sewer Department (MDWASD) recently completed a project to replace the existing sewer force main under the Port of Miami navigation channel in Biscayne Bay. The existing 54-inch (1,370 mm) force main was a prestressed concrete cylinder pipe (PCCP) that conflicted with the Port of Miami s Federal Navigational Dredging Project, which will deepen and widen the harbor and channels, beginning in The Port of Miami s dredging project will expand the Port by dredging the bay to allow new, larger cargo ships to enter the port. This project is related to the New Panamax project, which involves a major expansion of the Panama Canal. The Port, which is currently 42 feet (13 m) deep, will have to be dredged to 50 feet (15 m) in depth to allow the new Super Post Panamax megaships to enter the Port. The dredging project along with port facility improvements will make the Port of Miami capable of berthing even the second largest container vessels in the Paper MA-T

2 world, the new Maersk Triple E Class vessels, which will have a draught of 48 feet (14.6 m) and will be nearly 200 feet wide (61 m). MDWASD owns, operates, and maintains a 54-inch-diameter (1,370 mm) prestressed concrete cylinder pipe (PCCP) force main that transmits wastewater from the City of Miami Beach and from communities further north including Surfside, Bal Harbour, Bay Harbor Islands, and North Bay Village, under Government Cut, across Fisher Island and under Norris Cut to the 143-mgd Central District Wastewater Treatment Plant (CDWWTP) at Virginia Key. The pipe does not have redundancy and could not be taken out of service. The tie-in to the existing force main was originally going to be made from the Water Shaft constructed adjacent to the existing force main just outside the Miami Beach Marina (see Figure 1). During construction, an inspection of the condition of the existing 54-inch force main found several defective segments between the in-water retrieval shaft and the City of Miami Beach force main, which discharges into the MDWASD pipeline. The inspection was made by Pure Technologies (2011) via an electromagnetic survey launched from Miami Beach. As a result of the inspection, the design-build team installed a second 689-foot-long (210 m), 72-inch-diameter (1,830 mm) microtunnel from a new launch shaft at the very southern tip of Miami Beach to the Water Shaft to replace the defective pipe segment (see Figure 2). Figure 1. Microtunnel sewer main alignment between Fisher Island (left) and the Water Shaft (right). Figure 2. The various alternative alignments considered between the Water Shaft and Miami Beach and new surface alignment to tie-in point. Paper MA-T

3 The first microtunnel drive from Fisher Island to the Water Shaft was completed by Michels Corporation in the latter part of February The second microtunnel drive between Miami Beach and the Water Shaft was completed in the early part of May The intervening period between the two drives was used by Ric-Man Construction to construct the secant pile launch shaft in South Pointe Park. In the fall of 2010, MDWASD solicited proposals from design-build teams to replace the water and sewer mains. MDWASD received five proposals and conducted interviews. The design-build team of Ric-Man Construction with Hazen & Sawyer as the civil designers was selected. The design-build teams were required to provide base bids for the replacement mains using microtunneling technology. However, the teams were allowed to include bid alternates to the base bid at no cost to MDWASD. The water main replacement was completed using horizontal directional drilling in 2011 and a 1,583-foot-long (482 m), 24-inch (610 mm) ID HDPE pipeline was installed (Boyce et al., 2013). 2 SELECTION OF ALIGNMENT In the predesign stages, MDWASD s design engineer AECOM looked at alignment alternatives. The more straightforward approach was an alignment that went directly from Fisher Island to South Pointe Park. From there, the new alignment would follow city streets to an on-land tie-in point near the Miami Beach Marina. Because South Pointe Park is surrounded by several high rise condominiums that look out across Government Cut at their richer counterparts on Fisher Island, this alignment was met with a lot of resistance. There was so much resistance that MDWASD located the tie-in point outside the city limits of Miami Beach out in the water near the existing force main. That is the concept design the design-build team had to carry forward to final design (see Figure 2). To get a better understanding of the political climate that MDWASD had to navigate through for the Fisher Island work, a brief history of Fisher Island s origination is warranted. Named for automotive parts pioneer and beach real estate developer Carl G. Fisher, who once owned it, Fisher Island is 3 miles (4.8 km) offshore. No road or causeway connects to the island, which is only accessible by private boat or ferry. Once a one-family island home of the Vanderbilts, and later several other dignitaries, the island was sold for development in the 1960s. After years of legal battles and changes in ownership, commercial development of the island was finally started in the 1980s, with architecture matching the original 1920s Spanish-style mansions that occupied the island. Although no longer a onefamily island, Fisher Island still remains inaccessible to the public and uninvited guests, and is as exclusive by modern standards as it was in the days of the Vanderbilts, providing similar refuge and retreat for its residents. The tie-in point on Fisher Island was more straightforward as the microtunnel had to originate somewhere near the landfall of the existing 54-inch (1,370 mm) force main that cuts across Fisher Island. As it turns out, the tie-in was conveniently located in the parking lot for the golf course carts. Even so, the island residents and Fisher Island s Home Owners Association imposed difficult restrictions on Ric-Man Construction. This included severe limitations on use of the island ferries, which required the Ric-Man Construction to barge its equipment and materials to a separate landing with its own set of restrictions. Manpower was brought to the site by a boat dedicated to shuttling the contractor s resources between sites and a staging area on the Port of Miami property. As part of the MDWASD design-build contract, Ric-Man Construction was required to inspect the existing force main at the tie-in location after the Water Shaft was under construction. Those efforts revealed that concrete pipe was severely distressed, and it was determined that the existing force main was facing imminent failure. Failure of the existing force main, especially in the segment that extends beneath the Miami Beach Marina, would have been an environmental disaster not only for the aquatic life and local beaches, but for the economic life of Miami Beach. Failure of the existing force main would have necessitated a severe curtailing of sewer service for all of Miami Beach. To circumvent such a disaster, MDWASD was left with one option to bypass the force main segment that was aligned beneath the marina. This necessitated a second microtunnel alignment to bypass the water shaft tie-in and reroute the existing force main to mainland Miami Beach. Few options were available to locate a shaft on the Miami Beach mainland (in South Pointe Park). Figures 3 and 4 show the shaft location selected to minimize the amount of disruption to the park, and the new alignment through city streets to the new tie-in location. Paper MA-T

4 Figure 3. Final alignment to tie back into the existing force main. Figure 4. Construction work site for the jacking shaft at South Pointe Park, Miami Beach. Paper MA-T

5 3 GEOTECHNICAL CONDITIONS MDWASD hired AECOM as its designer to assemble the design-build criteria documents. The AECOM team undertook a site-specific subsurface exploration and testing program. The program was divided into four phases: Phase I: Desk Study conducted during preliminary design to research and compile existing subsurface data in the project vicinity. Phase II: Subsurface explorations consisting of seven borings and associated laboratory testing, completed by Geosol in Phase III: Geophysical survey consisting of bathymetry, seismic reflection, and seismic refraction, completed by Technos in 2009 and Robayna & Associates in Phase IV: Exploration program (supplemental program) consisting of 12 borings and laboratory testing, completed by Geosol in Ten borings were drilled for the original sewer force main crossing three land borings and seven water borings. For the second microtunnel, six soil borings were drilled, two of which were drilled over water, and two rock core borings were drilled one of which was drilled over water. The geological setting for the sewer force main crossing basically consists of four units: Artificial Fill (Af), Miami Formation (Qm), Fort Thompson (FT), and Tamiami Formation (TT). The units are subdivided by layers of sand and limestone. Table 1 provides a summary of the geological units and their subunits. Of note is the presence of sand layers sandwiched by limestone rock above and below. The limestone is also porous, with numerous voids and cavities, most of which are filled with sands and silts. The geotechnical profile for the proposed sewer force main alignment and the interpreted geologic conditions between borings are presented in Figure 5, with unit symbols provided in Table 1. Based on the heterogeneous nature of all the ground anticipated to be encountered along the alignment, the face conditions were considered to be mixed face (soil/bedrock). Engineering characteristics and properties will differ markedly between some strata groups such that ground behavior will vary as each strata group is excavated. The main construction risks associated with the formations along the alignment consisted of: Mixed-face conditions with competent zones embedded in softer materials Sudden and large-scale water inflow from karst features and zones Flowing sands Rock mass with frequently changing deformation and hydraulic characteristics FT-1/FT-6 TT-1/TT-2 Figure 5. Vertical profile for the microtunnel crossing between Fisher Island (left) and the Water Shaft (modified from AECOM, 2010). Similar ground conditions were encountered in the soil and rock core borings completed for the second microtunnel alignment from Miami Beach to the Water Shaft. Because this alignment did not encroach upon the future dredge area, the vertical alignment could be set much higher in the Fort Thompson formation. However, the borings revealed that the preferred vertical alignment would transition from limestone materials into loose sand and back Paper MA-T

6 into limestone materials as the alignment transitioned from land to water. To minimize the potentially adverse impacts of microtunneling through these varied ground conditions, the alignment was lowered to set the tunnel zone entirely within the limestone of the Fort Thompson formation. This required a South Pointe Park Shaft about 68 feet deep (22.3 m) from the ground surface to the working slab. Table 1. Geological units in the Miami/Government Cut Area. Geological Unit Description Symbol Artificial Fill SILTS to fine SAND with LIMESTONE rock fragments Af Miami Formation Soft to medium marine LIMESTONE Qm Fort Thompson Tamiami Formation Loose to medium dense fine SAND Medium to hard sandy LIMESTONE Hard to very hard freshwater LIMESTONE Medium to hard shelly LIMESTONE Loose to medium SAND Medium hard porous shelly LIMESTONE Medium dense to very dense SAND Soft to hard porous to vuggy LIMESTONE FT-1 FT-2 FT-3 FT-4 FT-5 FT-6 TT-1 TT-2 4 SHAFT CONSTRUCTION The tunnel horizon for the channel crossing was set at about 92 feet (28 m) below Fisher Island ground elevation. This necessitated a shaft that was about 97 feet (29.5 m) deep to the working slab. Ric-Man Construction elected to use 10-foot-long (3 m) sections of 72-inch-diameter (1,830 mm) Permalok steel casing. The jacking shaft was constructed with an interior clear diameter of 22 feet (6.7 m). A wet extraction of the microtunnel machine was planned and this required a receiving shaft with an interior clear diameter of 13 feet (4 m). The jacking shaft on Fisher Island consisted of 42-inch-diameter (1,067 mm) by 122-foot-long (37 m) secant piles drilled in a circular arrangement along a 28 foot (8.5 m) layout diameter. Pregrouting along the layout diameter was completed at 6-foot (1.8 m) intervals prior to excavating and concreting the secants to minimize erosion and loss of secant concrete into the porous formational materials. After the circular secant pile wall was constructed, the shaft interior was excavated in the wet. Upon completion of the excavation, reinforcing steel for the structural bottom slab was set. This was followed by lowering of an open-ended bolted steel corrugated metal pipe (CMP) liner sleeved inside the excavated shaft (see Figure 6). Once this was in place, concrete for the structural slab was placed with a short protrusion of the CMP liner into the slab concrete. To complete the shaft, the annular space between the secant piles and the CMP liner was grouted. The shaft interior was dewatered when the structural concrete attained its design strength. The receiving shaft was constructed using the same construction technique except that all of the work had to take place from a work platform built out over the water (see Figure 7). The receiving shaft was 97-feet-deep (29.5 m) from the platform down to the shaft working slab. Like the other two shafts, the South Pointe Park jacking shaft required for the second microtunnel drive was constructed using the same technique. The primary difference was that the alignment could be set higher as this new alignment did not encroach upon the planned dredging work. Consequently, a jacking shaft only 68 feet deep (22.3 m) was required. However, that also meant that a temporary work platform had to be constructed inside the 97-foot-deep (29.5 m) Water Shaft to receive the microtunnel boring machine from Miami Beach. Paper MA-T

7 Figure 6. CMP liner being readied for lowering into shaft. Note the assembled structural steel for the slab bottom (middle foreground). (Photo courtesy Ric-Man Construction) Figure 7. Receiving shaft construction from the over-water platform. Note drill used to core and excavate the secant piles. (Photo courtesy Ric-Man Construction) 5 MICROTUNNELING The Ric-Man Construction hired Michels Corporation to construct the microtunnel beneath the navigation channel. Michels elected to use an SL-74 Akkerman machine to tunnel the 72-inch (1,830 mm) steel casing. A lubrication plan was submitted as part of the Michels work plan. In general, it consisted of grout/lubrication ports in every pipe and a primary lubrication line from which whip lines emanated for manual servicing of the lubrication ports. However, within the first 250 feet (76 m) of tunneling, the jacking forces were increasing rapidly. Projecting out the increase in the first 250 feet over the length of the tunnel, it was apparent that the capacity of the jacking system (800 tons, 725 Mg) would be reached a little over halfway through the drive. This far exceeded the jacking forces predicted (see Figure 8). The belief was that the lubrication, which was being injected in the first 250 feet was not staying within the annular space and was probably bleeding out in the porous formational materials or being washed Paper MA-T

8 out by tidal flows through the interstitial spaces of the limestone (see Figure 9). If indeed that was the case, this could also have allowed sand to pack into the annular space, thereby contributing to a rapid increase in jacking forces. Trend line for jacking forces based on increase in first 250 feet (76 m) Figure 8. Jacking force records for the Fisher Island to Water Shaft microtunnel drive. Figure 9. Porous limestone rock (coral) from the core drilling for the secant piles. The microtunneling plan made provisions for an intermediate jacking station (IJS) that was going to be installed if and when about 70 to 80 percent of the system capacity was reached. In lieu of installing the IJS prematurely, the contractor elected to embark on an aggressive lubrication regime in their endeavor to bring the jacking forces back Paper MA-T

9 in line with what they had predicted. The first aggressive lubrication injection occurred around 250 feet (76 m) (see Figure 8). The lubrication quantities were increased from an average of less than 100 gallons/foot/day (g/f/d) (~375 liters/foot/day) to about 400 g/f/d (~1,515 l/ft/d) over a three-day period. During this three-day period, an average of one casing segment per day was advanced. As shown on the jacking force plot in Figure 8, there was an immediate reversal in jacking forces following this aggressive lubrication regime. After this initial reduction in jacking forces, the lubrication quantity was increased to about 100 g/f/d (378 l/f/d) for the next five pipe segments. However, the jacking forces gradually increased over those five pipe segments such that the jacking forces were again approaching the previous trend line. This prompted the contractor to again embark on another aggressive lubrication regime in which 350 g/f/d (1,325 l/f/d) of lubrication were injected for the subsequent four pipe segments. The jacking force plot in Figure 8 shows a marked reduction in jacking forces such that the jacking forces were now in line with the contractor s projected jacking force plot. The contractor continued to inject copious amounts of lubrication at an average rate of about 200 g/f/d (~760 l/f/d) over the remainder of the microtunnel drive. By doing so, Michels was able to maintain the jacking forces at or below the predicted jacking force plot. Microtunneling through the porous limestone also took its toll on the microtunnel equipment. As would be expected, mining through the limestone coral rock proved to be quite abrasive. The limestone coral is naturally sharp, and it maintains that attribute when mined. The mining process produced an abundance of rock chips that were typically in the size range of 0.5 to 1 inch (13 to 25 mm). Over time, the abrasive rock took its toll on the components of the slurry transport system. Some hoses were eaten through, but the booster pumps appeared to take the brunt of the abrasion. Impellers were worn down, and in a couple of instances the impeller housing was worn through (see Figure 10). Figure 10. Abrasion of the impeller housing (left) and impeller (right). Ric-Man Construction hired Super Excavators Inc. as the microtunneling contractor for the second drive from South Pointe Park to the Water Shaft. Super Excavators benefited from the experience gained in mining the first microtunnel. The microtunnel boring machine was required to be outfitted with new flexible hoses to ensure used worn hoses would not be exposed to the abrasive limestone. Before arriving on-site, Super Excavators voluntarily went through and refurbished the slurry pumps earmarked for the project including spare pumps. In addition, Ric- Man Construction required Super Excavator to install an automatic lubrication system that was controlled from the surface to provide a more effective means of delivering lubrication to the annular space. The effectiveness of the automatic system bears out in the jacking force plot (shown in Figure 11), which closely follows the predicted jacking forces. 6 STAKEHOLDER ISSUES Both the Fisher Island and Miami Beach launch shafts were located in an exclusive area of South Florida. As mentioned earlier, Fisher Island is an island with multimillion dollar residences and is only accessible by ferry or boat. The island is mainly occupied during the winter months when residents, who predominantly live in the Paper MA-T

10 northern states, spend their days golfing and boating to get away from the cold weather. These stakeholders did not want to be bothered by the noise and vibration of heavy equipment involved with construction. Figure 11. Jacking force records for the South Pointe Park to Water Shaft microtunnel drive. The stakeholders in the area of Miami Beach launch shaft are a part of the South of Fifth Neighborhood Association (SOFNA). Association members include ultra-luxury condos, restaurants such as the famous Joe s Stone Crab and Smith & Wollensky, as well as other high-profile commercial interests. These stakeholders were very concerned with the noise, vibration, work hours, and traffic interruptions that could result from the project. The Apogee Condominium is a recently constructed, 22-story, ultra-luxury condo with many famous residents including Hollywood stars and professional sports icons. The condominium was located less than 200 feet from the launch shaft. Noise and vibration monitoring as well as working hours and maintenance of traffic were the primary concerns of the residents of the building. The concerns of the stakeholders for Miami Beach were addressed by accommodating the residents requests for limited working hours and work days during the November and December/January Holiday periods. In addition, noise and vibration monitoring equipment was installed near both the Fisher Island and Miami Beach work areas. This equipment reports longitudinal, transverse, and vertical vibration levels in inches per second (in./s), as well as sound in decibels (db), as depicted in Figure 12. Noise and vibration readings were transmitted via text message to select construction and management personnel, and weekly continuous monitoring reports were transmitted to MDWASD. Action plans to mediate a spike in vibration or sound were developed should any readings exceed background levels. 7 SUMMARY This project had to prevail over difficulties and challenges from the outset, starting with the alignment selection all the way through construction. The design had to overcome an alignment that presented numerous challenges, especially the selection of the Water Shaft to retrieve the microtunnel boring machine and to make the tie-in connection. The design also had to overcome the challenge of adding a second drive back to the Miami Beach Paper MA-T

11 mainland to bypass the existing PCCP force main that was deemed to be at the point of imminent failure. Likewise, construction proceeded under extremely challenging circumstances and in difficult and unforgiving ground conditions. The horizontal and vertical alignments were restricted by easements, severe limits were imposed on access to Fisher Island, an unprecedented Water Shaft was required for the force main tie-in and two microtunnel boring machine retrievals, and land-based shafts had to be shoe horned into confined and restricted working space on Fisher Island and at South Pointe Park. And in the end, the porous limestone ground conditions presented their own set of challenges for construction of the shaft and the cased microtunnel. Figure 12. Noise and vibration monitoring data and equipment Several microtunneling challenges that were overcome stand out. First, an aggressive and vigilant lubrication program was necessary for mining through the Fort Thompson Formation to minimize rapid increases in jacking forces. Absent such a program, the contractor would have been at the mercy of ground conditions that are very unforgiving. Second, the abrasiveness of the mined ground brings to light the importance of having new flexible hosing and new or refurbished fixed components on the return side of the slurry transport system. This included refurbishing slurry pumps, especially those housed behind the microtunnel machine or in-line booster pumps. Despite all of the challenges and difficult ground conditions that presented themselves, the steel casing for the two microtunnel drives was successfully completed. The fiberglass carrier pipe was installed and backfilled. And the new deeper force main between Miami Beach and Fisher Island is in service as the Port s dredging project begins. 8 REFERENCES AECOM Contract No. W-924 Volume 2, Book 1, Water Main Microtunnel Geotechnical Baseline Report, October, 64pp. Boyce, G., S. Mancini, C. Camp, R. Zavitz, O. Castro, and E. Vega Miami-Dade s Water Main Government Cut Replacement Project. In Proceedings of North American No-Dig 2013, NASTT, March, Paper MA Jacobs Associates Daily Inspection Reports for Microtunneling Beneath Government Cut Channel. Miami- Dade 54-inch Force Main Replacement Government Cut. Jacobs Associates Daily Inspection Reports for Microtunneling Between South Pointe Park and Over-Water Shaft. Miami-Dade 54-inch Force Main Replacement Government Cut. Pure Technologies Letter Report to MDWASD titled Miami Beach to Virginia Key PipeDiver Government Cut Results Preliminary Condition Assessment of PCCP. December 19. Paper MA-T

Miami-Dade s Water Main Government Cut Replacement Project

Miami-Dade s Water Main Government Cut Replacement Project North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 Paper MA-T2-02 Miami-Dade s Water Main Government Cut Replacement Project Glenn

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

WINTER 2014. Wastewater Master Plan for Cartagena HORIZONS. water environment solutions. The. Averting Damage to Vital Infrastructure

WINTER 2014. Wastewater Master Plan for Cartagena HORIZONS. water environment solutions. The. Averting Damage to Vital Infrastructure WINTER 2014 2 Trenchless 6 Analyzing 8 Protecting Assets 13 Underwater Shrinking from Climate Change Construction Demand Ramifi cations Wastewater Master Plan for Cartagena HORIZONS water environment solutions

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR ABSTRACT Phil Hubbard, P.E., HRSD Paul Wilson, P.E., Brown and Caldwell* Mark Harber, P.E., Brown and Caldwell *301 Bendix Road, Suite 400 Virginia

More information

Meeting the Challenge of Pipeline Emergency Repair

Meeting the Challenge of Pipeline Emergency Repair Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider

More information

Tunnelling & Underground. Specialists

Tunnelling & Underground. Specialists Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598 Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF

More information

MEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525

MEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 To: From: Date: Subject: Mr. Thomas Gibson, City of St. Petersburg Jeffrey D. Malyszek, PE and Deborah C.

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057 Lecturer: Jim Cahill 29 th November 2011 TABLE OF CONTENTS SUMMARY 1 MAIN BODY SECTION

More information

Annular Space Grouting of Slipline Products

Annular Space Grouting of Slipline Products Annular Space Grouting of Slipline Products by David Gellings(, M.APWA & John Jurgens(, M.WWCPA Traditional methods of using neat cement slurries, (Portland cement and water, cement with fly ash or cement

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

Dewatering - Time and Cost Relief by way of Trenchless Construction

Dewatering - Time and Cost Relief by way of Trenchless Construction North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,

More information

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).

More information

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

Nutrient Reduction by Use of Industrial Deep Injection Wells, Miami-Dade County, Florida

Nutrient Reduction by Use of Industrial Deep Injection Wells, Miami-Dade County, Florida GWPC September 27, 2015 Nutrient Reduction by Use of Industrial Deep Injection Wells, Miami-Dade County, Florida Virginia Walsh, PhD, P.G. Miami-Dade Water and Sewer Department Ed Rectenwald, P.G. MWH

More information

Moving Small Mountains Vesuvius Dam Rehab

Moving Small Mountains Vesuvius Dam Rehab Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority

More information

Rehabilitation or Replacement? That Is The Question

Rehabilitation or Replacement? That Is The Question Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

ABSTRACT INTRODUCTION

ABSTRACT INTRODUCTION DELIVERING VALUE ON THE PORT OF MIAMI TUNNEL PROJECT LOUIS BRAIS, PE AND JEFFREY PLANT, MBA, P.ENG., PMP, CVS ABSTRACT The Port of Miami Tunnel [POMT] Project is an excellent example of the value-for-money

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering. ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical

More information

Flowtite Jacking Pipe

Flowtite Jacking Pipe U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe

More information

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses They also give the community a built-in re-entry system for future monitoring and repair. BY BRETT HANES According to

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration

More information

Member Nation Report 2010 from Denmark.

Member Nation Report 2010 from Denmark. Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City

More information

Applications of Integrated Vessel-based LiDAR, Multibeam Bathymetry, and Geophysical Surveys for Geohazard Assessments and Site Characterization

Applications of Integrated Vessel-based LiDAR, Multibeam Bathymetry, and Geophysical Surveys for Geohazard Assessments and Site Characterization Applications of Integrated Vessel-based LiDAR, Multibeam Bathymetry, and Geophysical Surveys for Geohazard Assessments and Site Characterization James Fisher Engineering Geologist Todd Mitchell Survey

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Luis Aguiar Miami-Dade Water & Sewer Department Anna Pridmore, PhD Structural Technologies PROJECT BACKGROUND Miami-Dade Water & Sewer Department

More information

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

Failing Coastal Wood Infrastructure on the Great Lakes

Failing Coastal Wood Infrastructure on the Great Lakes University of Wisconsin Sea Grant Institute Contact Gene Clark grclark@aqua.wisc.edu 715-392-3246 Failing Coastal Wood Infrastructure on the Great Lakes Gene Clark/UW Sea Grant Institute Introduction Many

More information

TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE

TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE Reynaldo Cantu, Pervez Jameel, Susan Kelly Brown and Caldwell 9011 Mountain Ridge Drive, Suite 100 Austin, TX 78759 ABSTRACT

More information

Chapter 9 Remedial Measures

Chapter 9 Remedial Measures [This is an annotated version of a chapter from the US Army Corps of Engineers book, Foundations in Expansive Soils. This book is in the public domain. This document is consists of an abbreviated and annotated

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

How to Design and Build a Fence/G traverse Bridge or Graffiti Project Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River

More information

AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate

AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate AGENDA ITEM C9 DATE: February 2, 2015 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles Carden, Chief Operating Officer South Pasco Transmission Main Condition Assessment Services with Pure Technologies

More information

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

Repair or Replacement - Band-Aids vs. Surgery

Repair or Replacement - Band-Aids vs. Surgery Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel

Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel OAWWA 73 rd Annual Conference Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel By Jason DeLaet, P.E. Supervising Engineer Greater Cincinnati Water Works & Michael J. Livermore

More information

HARBOR INFRASTRUCTURE INVENTORIES Port Austin Harbor, Michigan

HARBOR INFRASTRUCTURE INVENTORIES Port Austin Harbor, Michigan HARBOR INFRASTRUCTURE INVENTORIES Port Austin Harbor, Michigan Harbor Location: Port Austin Harbor is located at the tip of the thumb of Michigan, about 80 miles northeast of Saginaw, MI Authority: Rivers

More information

X Planning X Quality X Maintenance & Operations

X Planning X Quality X Maintenance & Operations Delaware Department of Transportation Division of Transportation Solutions Design Guidance Memorandum Memorandum Number 1-20 Revised 1. Road Design Manual 2. Bridge Design Manual 3. Utilities Design Manual

More information

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

2010-2011 Contractor of the Year

2010-2011 Contractor of the Year U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United

More information

Jackson Gulch Outlet Canal Rehabilitation Project

Jackson Gulch Outlet Canal Rehabilitation Project Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County

More information

Emerging Technologies in Wastewater Collection Systems

Emerging Technologies in Wastewater Collection Systems Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation

More information

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES WATER & SEWER REHAB TECHNOLOGIES NORTH VANCOUVER PIPE BURST REQUIRES CAREFUL PLANNING Close proximity to storage silos, poor ground conditions and clogged storm sewer pipe puts trenchless contractor to

More information

C O N S U L T A N T S RESUME

C O N S U L T A N T S RESUME C O N S U L T A N T S RESUME Ed Bove, P.E. SUMMARY OF EXPERIENCE Mr. Bove possesses 28 years experience in the civil engineering field. He has been involved with investigation, design, analysis, and quality

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

Specifications for Residential Property Owners Connection to New Public Sewer

Specifications for Residential Property Owners Connection to New Public Sewer Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the

More information

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,

More information

BROOKS BRIDGE WATERLINE REHABILITATION

BROOKS BRIDGE WATERLINE REHABILITATION The North American Society (NASTT) and the International Society for Trenchless Technology (ISTT) International No-Dig Show 2009 Toronto, Ontario Canada March 29 April 3, 2009 Paper C-3-02 BROOKS BRIDGE

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

The International Workshop on Micropiles, 2007

The International Workshop on Micropiles, 2007 MICROPILE FOUNDATION REPAIR AND UNDERPINNING, ARTS AND SCIENCE MUSEUM, UNIVERSITY OF PUERTO RICO, MAYAGUEZ Presented at: International Society of Micropiles (ISM) The International Workshop on Micropiles,

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major

More information

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

Technical Memorandum Cost Criteria for 2010 System Capacity Plan

Technical Memorandum Cost Criteria for 2010 System Capacity Plan 2010 SASD SEWER SYSTEM CAPACITY PLAN UPDATE Technical Memorandum Cost Criteria for 2010 System Capacity Plan PREPARED BY: My Huynh DATE: September 13, 2011 REVIEWED BY: Sonny Lunde INTRODUCTION This Technical

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM Stadium Reconstruction EIR Appendices \ AECOM Technical Services, Inc 401 West A Street Suite 1200 San Diego, CA 92101 www.aecom.com 619-610-7600 tel 619-610-7601

More information

Force Main Condition Assessment: New Technologies & Case Studies

Force Main Condition Assessment: New Technologies & Case Studies Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the

More information

Rachel Silverstein, Ph.D. Executive Director and Waterkeeper

Rachel Silverstein, Ph.D. Executive Director and Waterkeeper Dredging-Related Sediment Impacts on Coral Reefs near the Port of Miami Channel Rachel Silverstein, Ph.D. Executive Director and Waterkeeper As the Panama canal undergoes an expansion, shallow ports along

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

Installation of Large Diameter Buried Pipes

Installation of Large Diameter Buried Pipes Installation of Large Diameter Buried Pipes Sullivan (Sully) Curran P. E., Executive Director I. Introduction and Scope There is an ongoing need to provide designers, specifiers, engineers, consultants

More information

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN 3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary

More information

REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY IN NEWPORT, RHODE ISLAND

REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY IN NEWPORT, RHODE ISLAND North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper A-5-04 REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY

More information