TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE

Size: px
Start display at page:

Download "TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE"

Transcription

1 TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE Reynaldo Cantu, Pervez Jameel, Susan Kelly Brown and Caldwell 9011 Mountain Ridge Drive, Suite 100 Austin, TX ABSTRACT For over a decade, an existing 42-inch wastewater interceptor has plagued the Austin Water Utility (Utility) with higher than usual maintenance demands. Located in the Walnut Creek flow line, this interceptor is partially exposed with manholes rising several feet above the creek bed due to years of erosion. The interceptor suffers from external erosion and is victim to debris floating down the creek during rain events. On two separate occasions, the Utility designed a new parallel interceptor to replace the existing one only to have the project halted by the public and local home owners association. The environmental concerns, coupled with stream bank erosion and stabilization issues, made this project a heated debate for City residents. To further aggravate the situation, in 1999 the Utility was put under an Administrative Order by the U.S. Environmental Protection Agency (EPA) to eliminate sanitary sewer overflows in their wastewater conveyance system by December 31, This project utilizes trenchless technology coupled with traditional construction methods to develop a variety of solutions - and ultimately the best solution for the project. It was imperative to keep the public impacts to a minimum and have the project substantially complete by the mandated date of the EPA s Administrative Order. The fast tract schedule mandated work in double shifts for at least a portion of the project and did not leave much time for changed or unforeseen conditions. Because of these specific project conditions, it was important to assure that the element of risk on the project was kept to a minimum and shared by the Utility and the Contractor. In order achieve this several items were incorporated into the project, and are listed below: 1. Differing Site Conditions Clause 2. Geotechnical Baseline Report 3. Disputes Review Board 4. Escrow Bid Documents 5. Pre-Construction Survey 6. Noise Abatement 7. Monitoring Ground Movement A win-win for the Utility and the residents, this project won acceptance from the residents, minimized impacts to the community and the environment, and eliminated land acquisition requirements. The project began construction in June of 2004 and the tunneling operation was 5467

2 complete in November of In January of 2006 the City Manager received a letter from a resident of the Little Walnut Creek Community stating the following: Where s the new sewer line we ve been promised? The City promised us the line down Northeast With the tunnel mining operation complete two months prior to the resident s letter, it was clear that the resident was unaware that the construction for the sewer line down Northeast Drive had already been completed. Clearly a sign that impacts to the community were kept to a minimum. The project reached substantial completion in July of 2006 well within the projects fast track schedule. The project is ultimately a success with neighborhood acceptance and minimal impact to the community and the environment. KEYWORDS Trenchless Technology, Public Acceptance, Dispute Review Board INTRODUCTION Due to the simple laws of physics, wastewater collection systems flow by gravity to sewer basin creeks and rivers. Over time the soils and soft rock formations along the creek beds erode and shift and wastewater collection systems become exposed or misaligned and damaged. The Austin Water Utility (Utility) is no stranger to this phenomenon with what they commonly referred to as the Little Walnut Creek Interceptor. 5468

3 This existing 42-inch wastewater interceptor has plagued the Utility with higher than usual maintenance demands for over a decade. Located in Walnut Creek, this interceptor is partially exposed with manholes rising several feet above the flow line of the creek due to years of stream bed erosion. Several of the interceptor s manholes have been damaged over time due to high velocities carrying debris down the creek during storm events. Put into service in the 1960s the interceptor has also reached capacity and with infiltration and inflow, struggles to keep up during rain events. To remedy the capacity issue the Utility designed a relief sewer in the creek bed on at least two individual occasions in the past. These two designs met significant opposition from the public and the local home owners association and were never constructed. The Little Walnut Creek bed has shown a significant amount of erosion over the past several decades and if left un-stabilized the creek will continue to erode at a rate of two feet per year. Residents and business owners along the creek are concerned Figure 1 Little Walnut Creek Interceptor that further disturbance would only accelerate the erosion of the creek bed and compromise the stability of the river banks. Additionally due to the exposed nature of the existing interceptor, residents have been subject to several sanitary sewer overflows and argue that an additional interceptor in the creek will only amplify the problem. The environmental concerns, coupled with the stream bank erosion and stabilization issues, have made this project a heated debate for City residents. To further aggravate the situation; in 1999 the Utility was put under an Administrative Order by the U.S. Environmental Protection Agency (EPA) to eliminate sanitary sewer overflows in their wastewater conveyance system by December 31, It was now imperative that the Utility find a solution for the Little Walnut Creek Interceptor. The primary goals of the project were to augment the capacity of over 15,000 linear feet of the existing 42-inch interceptor, achieve public acceptance, and meet the terms of the Administrative Order. For this project to be a success an alignment needed to be selected that would protect the environment, minimize public impact and meet the Administrative Order deadline. This project utilizes trenchless technology coupled with traditional construction methods to develop a variety of solutions - and ultimately the best solution for the project. This paper will 5469

4 discuss the challenges of the alignment selection, design and construction phases and how solutions were put in to place to meet these challenges. ALIGNMENT SELECTION With environmental impacts and public acceptance as two of the major drivers on this project, the construction methods considered for this interceptor were primarily trenchless. Using trenchless technology such as tunneling or boring would eliminate community concerns for accelerating stream bed erosion, disturbing environmental wet lands or impacting the neighborhood. With trenchless technology as a viable option, the next hurdle was to select an alignment that was geotechnically favorable to trenchless construction methods, and would satisfy the needs of the Utility and appease the public. Within the first two months of the project, a detailed feasibility study was completed to clearly define the design parameters and determine the best route selection as it relates to: Hydraulic capacity Permitting Sufficient amount of cover Land or easement acquisition Constructability Construction cost Geotechnical characteristics Impacts to the community Environmental issues Scheduling Long term operation and maintenance requirements In the feasibility study six alignments were ultimately identified; however, three of the alignments were dismissed early on due to high risk in constructability, prohibitive costs, environmental constraints, excessive land acquisition, and/or public opposition. The remaining three alignments were investigated in greater detail and are described below: Green This alignment paralleled the existing interceptor in the creek. It required a drop structure at the tie in point to the existing interceptor on the upstream end and required land acquisition of several properties. Purple This alignment meandered within the creek and the road right-ofway (approximately 50/50) and had one aerial creek crossing. This alignment also required a drop structure at the tie in point to the existing interceptor on the upstream end and required the land acquisition of several properties. 5470

5 Figure 2 Proposed Project s 5471

6 Red - This alignment was completely within street right-of-way with the exception of two properties, one of which was owned by the City. This alignment was slightly longer than the others; however, there was no need for a drop structure and land acquisition was very minimal. Once the three alignments were verified to meet the above criteria, the criteria were rated against each other using specified evaluation criteria and a decision matrix. The evaluation criteria were divided into 6 main categories, including: 1. Schedule 2. Public impacts 3. Environmental impacts 4. Land acquisition 5. Constructability 6. Cost A weighting factor was assigned to each category, and the sum of all of the categories weighted factors equaled 100 percent. Categories with greater importance were assigned a higher percentage of the weighting factor. Each of the alignment alternatives were then rated under each category on a scale of 1 to 3 with 1 being the better or preferred choice. These ratings were then incorporated into the comparison matrix for an overall rating of each alternative. Each of the evaluation categories and the alternative ratings are defined below. Schedule - Weighting Factor 20% The milestones of this project which impact the schedule are the design, bid, land acquisition and construction phases. The amount of time required for the design and bid phase is the same for each of the alignment alternatives. However the land acquisition and construction phases are different for each of the alternatives. For example, the Red will take longer to construct due to the fact that it is longer in length, and the Green and Purple s will take longer to reach the construction phase due to the larger number of property owners involved with land acquisitions. Since land acquisitions are rated as a separate category of evaluation criterion in the comparison matrix, it is not necessary to rate the alternatives with respect to land acquisitions under the schedule category. Therefore this category rated each alternative with respect to the construction schedule only. The estimated time for the construction phase for each of the alignment alternatives and their ratings are shown below. 5472

7 Table 1 Construction Duration Construction Duration 1 Rating Green 17 months 1 Purple 19 months 3 Red 18 months 2 1. Rating 1 through 3, 1 being the preferred rating Due to the importance of this project to be complete by the Environmental Protection Agency s Administrative Order deadline, the weighting factor for this evaluation criteria was assigned a higher weight of 20 percent in the comparison matrix. Public Impacts - Weighting Factor 10% The Utility strives to keep impacts to the public a minimum on all of their projects. The Little Walnut Creek residents are a particularly active group and have opposed and overruled two previous plans for wastewater improvements within their creek which runs through the center of their subdivision. The criteria used to rate public impact addresses short term impacts which occur during the construction phase and long term impacts after the project is complete. These criteria and the alternatives ratings are listed below: Short Term Public Impacts (during construction) Easement Acquisition Easements needed to be acquired from residential, commercial and park properties. The Green required easements from 30 properties, the Purple required easements from 7 properties and the Red required easements from 2 properties. Acquiring Residential Properties The Green and Purple s ran between two residential properties. A drop structure was also required at this location which would significantly impact the residential properties and possibly render these properties unacceptable for residential housing. Construction Adjacent to Occupied Properties During construction, residents or businesses adjacent to work shafts or open cuts construction will be inconvenienced by noise, dust, and traffic caused by construction activities. Each alignment has construction adjacent to occupied properties. Truck Hauling Routes Truck hauling routes will be necessary to haul tunnel excavation spoils and bring in pipe and other supplies needed for construction. The Red had the more direct route to U.S., Highway 183 however all alternatives would impact the residents to some degree. 5473

8 Long Term Public Impacts (after construction is completed) Above Ground Improvements Each alignment will require access shafts for maintenance. The Green and Purple s will also need a drop structure in the creek at the upstream end of the project. Visual Aesthetics The local community is very concerned about the conditions and appearance of their creek. The Green and Purple s will require a drop shaft and 500 lf of open cut construction within the limits of the creek which will require streambed stabilization. Additionally, the Purple will have an aerial creek crossing in the northern portion of the alignment. Odor The drop structure required for the Green and Purple s may emit odors and may require an odor control facility. Description of Impact Table 2 Public Impact Ratings Green Purple Red Short Term Public Impacts Easement acquisition (30) (7) (2) Acquiring residential property Construction adjacent to occupied properties Truck Hauling Routes Above Ground Improvements Long Term Public Impacts Visual Aesthetics Odor Control 1 Rating Rating 1 through 3, 1 being the preferred rating It would be impossible to construct any of the alternatives without impacting the public to some extent, therefore, the weighting factor for this evaluation criterion was assigned a lower weight of 10 percent in the comparison matrix. Environmental Impacts - Weighting Factor 10% As noted in the Public Impacts section above, the City of Austin continues to strive to keep impacts to the environment to a minimum on all of their projects. The primary area of environmental concern on this project is construction within the creek bed during which, a proactive erosion, sedimentation and dewatering program must be in place. Additionally streambed stabilization will be required to protect the improvements within the creek bed from future erosion and scouring caused by natural creek flow. The Green and Purple s have approximately 800 lf of open cut construction within the creek bed located at the upstream portion of the project. Therefore they received a lower rating than the Red under this criteria as shown below. 5474

9 Table 3 Environmental Impacts 1 Rating Green 3 Purple 3 Red 1 1. Rating 1 through 3, 1 being the preferred rating Environmental impacts are present in all of the alternatives to some extent, therefore, the weighting factor for this evaluation criterion was assigned a lower weight of 10 percent in the comparison matrix. Land acquisition Weighting Factor 30% Easement acquisition for temporary and permanent easements will be required for all three of the alternatives. Any easement, regardless of its size, requires the same documentation and level of effort from the City s Real-Estate department and the property owners. As previously mentioned in this report, this project must be completed by September 2007 in order to be in compliance with the Environmental Protection Agency s Administrative Order. A concern is the easement acquisition process would hold up the construction phase of the project. The number of properties that require easements for each alignment alternative and their rating under this criteria is shown below. Table 4 Land Acquisition Number of Properties 1 Rating Green 30 3 Purple 7 2 Red Rating 1 through 3, 1 being the preferred rating Due to the importance of this project to be complete by the Environmental Protection Agency s Administrative Order deadline of September 2007, the weighting factor for this evaluation criterion was assigned a higher weight of 30 percent in the comparison matrix. Constructability Weighting Factor 10% Each alignment alternative consists of similar lengths of open cut and tunneling construction and each of the alternatives can be tunneled with the same tunneling methods. The constructability of these alternatives is impacted by several items. These items include tunneling under creek crossings with minimal cover, tunneling through mixed face conditions tunneling under or close 5475

10 to developed property, and construction of a hydraulic drop structure on a creek embankment. The Green and Purple s share many of the items above however the Red does not have to address these issues and is the preferred route under these rating criteria. Table 5 - Constructability Tunneling Under Creek Tunneling Through Mixed Face Soil Conditions Tunneling with minimal cover Tunneling Close to Developed Property 1 Rating Green 3 Purple 2 Red 1 1. Rating 1 through 3, 1 being the preferred rating Constructability issues are present in all of the alternatives to some extent, therefore the weighting factor for this evaluation criterion was assigned a lower weight of 10 percent in the comparison matrix. Cost Weighting Factor 10% The cost estimates for each proposed alignment alternatives were for comparison purposes only because subsurface investigations were not performed for each alignment alternative. Should actual subsurface conditions vary from those assumed in this evaluation, construction costs would also vary. The cost estimates include labor, equipment, equipment operation, materials, supplies, subcontractors, mobilization and demobilization. Table 6 Construction Cost Cost 1 Rating Green $17,050,000 1 Purple $17,107,800 2 Red $18,326, Rating 1 through 3, 1 being the preferred rating Cost varies amongst the alternatives by a minimal 7%, therefore, this evaluation criterion was assigned a lower importance weighting factor of 10 percent. Comparison Matrix The table below compares the three alignment alternatives using the above described evaluation criteria. As noted above, the evaluation criteria were divided into 6 main categories, which are 5476

11 shown in the comparison matrix as items 1 through 6. Each of these categories has been assigned a weighting factor, the sum of which totals 100%. Each alignment alternative was rated under each category from 1 through 3 with 1 being the preferred or best alternative under the evaluation category. The total or overall rating of each alignment is summarized at the bottom of the matrix. Evaluation Criteria Total Weight % Table 7 Comparison Matrix Green Purple Red 1 Rating Total 1 Rating Total 1 Rating Total Schedule Public Impacts Environmental Impacts Land Acquisition Constructability Cost Total Overall Rating Rating 1 through 3 with 1 being the preferred rating The Red was the recommended alignment, and it was ultimately chosen. With the proposed project alignment accepted by the community the next challenge was to design and construct the project successfully and on time. DESIGN CONSIDERATIONS During the design phase several important components of the design required special attention. One of the major characteristics attributing to the project challenges was the limited access along the route. The project had a 10,000 linear foot span within the right-of-way of a residential road (Northeast Drive) that had virtually no points of access. Additionally the right-of-way had several curves requiring negotiation during construction. This limited access meant that the project would have to be constructed in one continuous run with no intermediate shaft. Other key characteristics included the hydraulics of the sewer line with respect to odor, corrosion and erosion, and an extensive geotechnical investigation. Construction Methods A combination of trenchless technology and conventional construction methods were used on this project. Tunneling applications were evaluated for the installation of pipelines, where the alignments are deep or the ground surface cannot be disturbed due to existing improvements or environmental constraints. The tunneling methods evaluated for this project were road header, tunnel boring machine, and microtunnel boring machine. The road header constructs a horseshoe shaped tunnel by means of excavation, while the tunnel boring and microtunnel boring machines construct a circular tunnel by means of boring. Each of these methods has advantages and disadvantages related to tunneling capabilities, procurement and mobilization, and rate of tunneling progress. The table below summarizes the key points for each tunneling method. 5477

12 Tunneling Method Construction Method Procurement Set-Up & Breakdown of Operation Manipulation of Bends on Rate of Tunneling Per Shift Road Header Excavation 1 month 1 week Yes (any) 25 feet Tunnel Boring Machine Microtunnel Boring Machine Boring 3 to 7 months 1 month Boring 1 month 1 week per 1,000 linear feet of construction Yes 350 R max No, must have bore pit to make bend 75 feet 35 feet The chosen alignment consisted of approximately 5,000 linear feet of pipeline in undeveloped property owned by the City, and 10,000 linear feet of pipeline along residential streets within City right-of-way. The alignment located on City property was relatively shallow, and on both constructability and environmental standpoint lent itself to traditional open cut construction methods. The alignment located within the street right-of-way was over 140-feet deep in some locations; had curves that needed to be negotiated; and the need for any intermediate shafts would have required land acquisition with possible condemnation, significant impact to the community, and public opposition. Due to these constraints, the Tunnel Boring Machine (TBM) was the chosen method of construction within the street right-of-way with the use of the road header excavator in the more shallow areas consisting of non-cohesive soils, which typically do not lend themselves to TBM construction methods. Hydraulics, Odor and Corrosion Figure 3 Tunnel Boring Machine During the design phase, special attention was paid to the capacity of the proposed tunnel and the existing upstream and downstream flows. It was observed that the upstream flow was supercritical and the downstream flow was subcritical. In order to eliminate a hydraulic jump, which may cause odor and corrosion problems in the future, the new tunnel diameter and slope were selected to maintain a flow at normal depth at the transition of supercritical to subcritical 5478

13 flow. Additionally, conduits were specified in the junction structures in the event that future odor control would be needed. Once the carrier pipe size was determined, the actual TBM size was selected. In determining the size it was important to take into account that the tunnel would have no intermediate shaft within its 10,000 linear foot alignment; therefore, larger ventilation ducting and power and ventilation booster stations would be required. Geotechnical Investigations Since this project was such a political issue to the residents and under the Administrative Order s fast track schedule, it was important to take special measures during the design to minimize risk and eliminate causes for construction delays. For this reason, an aggressive geotechnical investigation was performed, which included over 30 soil borings ranging in depth from 50 to 150 feet and two inclined borings used to identify possible fault locations. These borings were on display for the contractors to view during the bidding phase. The location of the tunnel starter shaft was dictated by the ground conditions. It was the desire to launch the TBM in solid rock not mixed face soil conditions; therefore, several borings were taken at the starter shaft location to identify where and at what depth the transition from non-cohesive soil to rock took place. As the ultimate location of the starter tunnel did have some mixed face properties in the vicinity of the crown of the tunnel, ground modifications through the use of surface grouting were also specified. CONSTRUCTION AND KEEPING THE PEACE The project was located in a very developed and active residential community with several schools, churches and businesses in the area. It was important for the Utility to keep the public impacts to a minimum and have the project substantially complete by the mandated date of the EPA s Administrative Order. The fast track schedule mandated work in double shifts for at least a portion of the project and did not leave much time for changed or unforeseen conditions. Because of these specific project conditions, it was important to assure the element of risk on the project was kept to a minimum and shared by the Utility and the Contractor. In order to do this, several items were incorporated into the project. These are listed below and are described in more detail on the following pages. 8. Differing Site Conditions Clause 9. Geotechnical Baseline Report 10. Disputes Review Board 11. Escrow Bid Documents 12. Pre-Construction Survey 13. Noise Abatement 14. Monitoring Ground Movement Differing Site Conditions Clause To keep the peace between the residents, the Contractor and the Utility, all parties must accept the basic philosophy of risk sharing. The contract must begin with a complete and accurate set of plans, specifications and contact documents. On this project site conditions were specific to 5479

14 the underground. Even with the new and advanced geotechnical study and exploration methods it remains difficult to foresee all conditions that will be encountered in underground construction projects. It is for this reason that a provision for Differing Site Conditions was included in the contract documents. To back up this provision, the contract provided for an equitable price and time adjustment so if differing site conditions were encountered they could be easily resolved. The standard Federal clause for Differing Site Conditions states: DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before the conditions are disturbed, notify the [Contracting Officer, Owner, Engineer] in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this contract. The [Contracting Officer, Owner, Engineer] shall promptly investigate the conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor s cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the contract modified in writing accordingly. (b) No claim of the Contractor under this clause shall be allowed unless the Contractor has given the notice required in (a) above; provided, however, the time prescribed therefore, may be extended by the (Government, Owner). (c) No claim by the Contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract. Geotechnical Baseline Report The Geotechnical Baseline Report (GBR) sets forth the geotechnical engineers interpretations regarding anticipated conditions for the site and construction. The GBR is typically made part of the contract documents by reference and establishes the baseline for all anticipated conditions on the site. The incorporation of the GBR generally promotes a cooperative climate since the emphasis is on openness and truthfulness and, if conditions differ from the baseline report, the Contractor can typically demonstrate the financial impact. Additionally the GBR when prepared properly enhances the Contractor s opportunity to be innovative. By having information on anticipated ground behavior, the Contractor can better estimate the impacts of using innovative construction methods at his own cost. Dispute Review Board The Dispute Review Board (DRB) provides a forum that fosters cooperation between the owner and the contractor and provides a means of resolving disputes fairly and quickly. The DRB is made up of three board members who are considered experts in the construction methods of the project. The DRB is selected immediately after contract award. A member is selected by the Contractor and by the Utility. These two Board members then select a third member for the 5480

15 Board who is the lead board member. The Board met at the construction site on a quarterly basis throughout the duration of the project. The role of the board was to provide an independent assessment of any disputes and recommendations for solutions. The Board s recommendations are not binding; however, the knowledge of an experienced and impartial party is very respected by both parties. On this project, there were no disputes or need for any Board recommendations. Escrow Bid Documents Escrow Bid Documents included all quantity take-offs, calculations, price quotes and other information that the contractor used to develop his bid. Typically in a bid the three highest bidders are requested to submit their escrow bid document in a sealed envelope. The documents are considered the property of the contractor and are to be stored in the care of a third party and returned to the contractor at project completion. If during construction there is a dispute over cost or pricing, the escrow bid documents can be opened to assist in finalizing the pricing dispute. The documents can be opened only in the presence of the designated representatives from the Utility and the Contractor. In addition to enhance the effectiveness and improve realization of the contract goals, the following three specific concepts were also added to protect the Contractor: Pre-Construction Survey With the tunneling to take place under a developed residential neighborhood, several of the residents were concerned that ground movement may occur and possibly cause damage to their property foundations. To protect the contractor and prevent a wrongful claim, the Contractor was required to produce an audio/video recording of the entire construction route and any other adjacent areas that may be impacted by construction operations. The video was required to digitally show time and date of the recording and was to capture the address of the areas being filmed or other landmarks to provide orientation of video location. Noise Abatement The starter shaft for the tunneling operation was located adjacent to an apartment complex. Concerns about noise and the need for double shift operations called for a plan to monitor and abate the noise. The contract documents included a line item for noise monitoring and abatement which required the contractor to meet City Noise Ordinances during the execution of his work. The work included continual monitoring of noise at the property line and the use of portable sound barriers to mitigate the noise. Monitoring Ground Movement Prior to the commencement of construction, ground monitoring systems were installed by the Contractor at strategic locations along the project. The purpose of the ground monitoring systems was to determine ground behavior for comparison with design assumptions and to provide a timely warning for the implementation of remedial measures in order to prevent possible damage to structures and utilities. Four types of monitoring devices were installed, 5481

16 surface settlement markers, subsurface shallow settlement indicators, multiple position borehole extensometers and inclinometers. The combination of these devices measured any settlement, heave, or lateral movements in the ground and assisted in serving as a baseline of ground conditions prior to the commencement of construction. CONCLUSION The project began construction in June of 2004 and the tunneling operation was complete in November of In January of 2006 the City Manager received a letter from a resident of the Little Walnut Creek Community stating the following: Where s the new sewer line we ve been promised? The City promised us the line down Northeast With the tunnel mining operation complete two months prior to the resident s letter, it was clear the resident was unaware the construction for the sewer line down Northeast Drive had already been completed. Clearly a sign that impacts to the community were kept to a minimum. The project reached substantial completion in July of 2006 well within the projects fast track schedule. The project is ultimately a success with neighborhood acceptance and minimal impact to the community and the environment. The chosen alignment, which pushed the envelope for construction methods with the elimination of an intermediate shaft, prevented the need for extensive land acquisition, and made the project schedule a feasible one to maintain. During the design phase a thorough and comprehensive feasibility study and design approach eliminated risk and any unforeseen conditions which typically haunt fast track or challenging projects. During the construction phase, the proactive use of partnering and a Dispute Review Board kept the project on track and ultimately made it a win-win for the residents, the EPA and the Utility. 5482

Dewatering - Time and Cost Relief by way of Trenchless Construction

Dewatering - Time and Cost Relief by way of Trenchless Construction North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,

More information

Emerging Technologies in Wastewater Collection Systems

Emerging Technologies in Wastewater Collection Systems Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

Rehabilitation or Replacement? That Is The Question

Rehabilitation or Replacement? That Is The Question Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

Technical Memorandum Cost Criteria for 2010 System Capacity Plan

Technical Memorandum Cost Criteria for 2010 System Capacity Plan 2010 SASD SEWER SYSTEM CAPACITY PLAN UPDATE Technical Memorandum Cost Criteria for 2010 System Capacity Plan PREPARED BY: My Huynh DATE: September 13, 2011 REVIEWED BY: Sonny Lunde INTRODUCTION This Technical

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

San Antonio, TX July 28, 2011

San Antonio, TX July 28, 2011 Rehabilitation of a Deteriorated 60 RCP Wastewater Interceptor Using Competing Trenchless Technologies Bruce Cole, PE Corey Anderson, EIT TAWWA/WEAT Summer Seminar San Antonio, TX July 28, 2011 Wendy Martinez,

More information

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued

More information

SECTION 7 UNDERDRAIN SERVICE

SECTION 7 UNDERDRAIN SERVICE SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations

More information

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598 Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**

More information

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT 2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT Open channel flow is defined as flow in any channel where the liquid flows with a free surface. Open channel flow is not under pressure; gravity is the

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013. Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013 Rationale Underground infrastructure may be at risk from valley, streambank

More information

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE 1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,

More information

Type of Sewer Systems. Solomon Seyoum

Type of Sewer Systems. Solomon Seyoum Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

Sanitary Sewer Overflow (SSO) Incident Report Form

Sanitary Sewer Overflow (SSO) Incident Report Form Submit completed form to EHS. Date of SSO spill: Sanitary Sewer Overflow (SSO) Incident Report Form Identify the SSO category (check one): Category 1 SSO Spills of any volume that reach surface water Category

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

SECTION 3 SANITARY SEWER DESIGN

SECTION 3 SANITARY SEWER DESIGN SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Beacon Hill Sewer District Standard Specifications

Beacon Hill Sewer District Standard Specifications Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

Homeowner s Guide to Drainage

Homeowner s Guide to Drainage Homeowner s Guide to Drainage a scottsdale homeowner s guide to drainage produced by the city of scottsdale s stormwater management division Transportation Department TABLE OF CONTENTS Introduction 2 Drainage

More information

Linear Schedules for Tunnel Projects

Linear Schedules for Tunnel Projects Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear

More information

CHAPTER 3 STORM DRAINAGE SYSTEMS

CHAPTER 3 STORM DRAINAGE SYSTEMS CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

Alternatives Presentation Meeting Middlebury WCRS(23)

Alternatives Presentation Meeting Middlebury WCRS(23) Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College

More information

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein

More information

CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES

CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper C-4-04 CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES Brad Jenson

More information

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR ABSTRACT Phil Hubbard, P.E., HRSD Paul Wilson, P.E., Brown and Caldwell* Mark Harber, P.E., Brown and Caldwell *301 Bendix Road, Suite 400 Virginia

More information

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity United States Environmental Protection Agency Collection Systems Technology Fact Sheet Sewers, Conventional Gravity DESCRIPTION Sewers are hydraulic conveyance structures that carry wastewater to a treatment

More information

CONSTRUCTION PERMIT REQUIREMENTS

CONSTRUCTION PERMIT REQUIREMENTS CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department

More information

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are

More information

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience

Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience Robert W. Carr 1 * and Stuart G. Walesh 2 1 Water Resources Modeling, LLC, 4144 S. Lipton Ave,

More information

City of Hilshire Village Pine Creek Ln Reconstruction

City of Hilshire Village Pine Creek Ln Reconstruction City of Hilshire Village Pine Creek Ln Reconstruction OVERVIEW The City will be soliciting bids for the Pine Creek Reconstruction Project with construction scheduled to begin in January 2015. This project

More information

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 The Montgomery County Dept. of Environmental Protection, in cooperation with the Dept. of Permitting Services and the Washington

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY

DEPARTMENT OF ENVIRONMENTAL QUALITY PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0

More information

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting? Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting

More information

DRAFT Public Outreach Document for What s an SSMP?

DRAFT Public Outreach Document for What s an SSMP? DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials

More information

FY15 Gravity Sewer and Manhole Rehabilitation

FY15 Gravity Sewer and Manhole Rehabilitation Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE

More information

Wastewater Collection Practice Test #3 Page 1 of 15

Wastewater Collection Practice Test #3 Page 1 of 15 Wastewater Collection Practice Test #3 Page 1 of 15 1) A 54 in. storm sewer flowing half full, at a velocity of 1.35 Ft./sec., will discharge how much flow into a creek in MGD? 13.85 MGD 10.73 MGD 1.85

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities

Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities This document summarizes and provides explanation for the purpose and intent of major recommended

More information

How To Check For Scour At A Bridge

How To Check For Scour At A Bridge Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway

More information

McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C.

McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C. McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C. 111 Wheatfield Drive, Suite 1 Milford, Pennsylvania 18337 (570) 296-2765 fax: (570) 296-2767 e-mail: mhepa@mhepc.com RICHARD D. McGOEY, P.E. (NY &

More information

M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to

M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to M E M O R A N D U M DATE: August 7, 2015 TO: FROM: SUBJECT: Metropolitan Wastewater Management Commission (MWMC) Matt Stouder, MWMC General Manager Capacity Management, Operations, and Maintenance (CMOM)

More information

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 1/12/2007 1 Briefing Purpose Provide update on Wastewater Collection Activities

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

Tunnelling & Underground. Specialists

Tunnelling & Underground. Specialists Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering

More information

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

More information

Specifications for Residential Property Owners Connection to New Public Sewer

Specifications for Residential Property Owners Connection to New Public Sewer Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the

More information

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water United States Office of Water EPA 916-F-01-032 Environmental Protection (4606) July 2001 Agency Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows

More information

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R CCTV PIPE INSPECTION AND EVALUATION For RUNWAY 17L-35R At ST. PETERSBURG CLEARWATER INTERNATIONAL AIRPORT February 2011 CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R ST. PETERSBURG CLEARWATER INTERNATIONAL

More information

Repair or Replacement - Band-Aids vs. Surgery

Repair or Replacement - Band-Aids vs. Surgery Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing

More information

Sanitary Sewer Master Plan

Sanitary Sewer Master Plan , Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY

More information

Review of Footing Drain Disconnection Projects

Review of Footing Drain Disconnection Projects Wastewater Master Plan DWSD Project No. CS-1314 Review of Footing Drain Disconnection Projects Technical Memorandum Original Date: August 8 2002 Revision Date: September 2003 Author: CDM Table of Contents

More information

Trenching and Excavation Safety

Trenching and Excavation Safety 1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking

More information

AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy

AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy The City of Kitchener, Ontario, Canada, was in a dilemma. After repeated breakdowns

More information

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans APPENDIX IV Version: February 2, 2015 Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans Please fill in all blanks and please reference the plan sheets/pages where the information may

More information

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels Estimation of Adjacent Building During Drilling of Urban Tunnels Shahram Pourakbar 1, Mohammad Azadi 2, Bujang B. K. Huat 1, Afshin Asadi 1 1 Department of Civil Engineering, University Putra Malaysia

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

Unauthorized Discharges and Sanitary Sewer Overflows

Unauthorized Discharges and Sanitary Sewer Overflows TCEQ REGULATORY GUIDANCE Field Operations Support Division RG-395 Revised April 2011 Unauthorized Discharges and Sanitary Sewer Overflows What does this document cover? The Texas Commission on Environmental

More information

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner SHORT FORM PRIME CONTRACT BETWEEN OWNER & CONTRACTOR This Agreement ( Contract ) is made this day of, 20, between ( Contractor ) and ( Owner ) at The work described in Section 1 below shall be performed

More information

NEVADA IRRIGATION DISTRICT DEVELOPER REQUIREMENTS FOR TREATED WATER SYSTEM EXTENSIONS GENERAL

NEVADA IRRIGATION DISTRICT DEVELOPER REQUIREMENTS FOR TREATED WATER SYSTEM EXTENSIONS GENERAL NEVADA IRRIGATION DISTRICT DEVELOPER REQUIREMENTS FOR TREATED WATER SYSTEM EXTENSIONS GENERAL An owner requesting treated water service to lands which do not otherwise have service available must comply

More information

Cost Estimating Procedures for Raw Sewage Overflow Control Program

Cost Estimating Procedures for Raw Sewage Overflow Control Program Raw Sewage Overflow Control Program April 23, 2004 Raw Sewage Overflow Control Program City of Indianapolis Department of Public Works Table of Contents Section Page 1.0 Introduction... 1 2.0 General Project

More information

Technical Specifications For Sewing Enveilment Plans

Technical Specifications For Sewing Enveilment Plans Appendix B Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN CONVEYANCE PIPELINES Version 2.0 April 2014 Table of Contents Section 1 General Information... 1 Section 2 Gravity and Pressure

More information

Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts

Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts Outline Update on Soapstone Emergency Response Provide project background Provide project purpose & need Present proposed

More information

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall CHELTENHAM TOWNSHIP SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall 1 SANITARY SEWER UPDATE 1. Overview a. The Problem b. Pennsylvania Department of Environmental Protection

More information

PART 5 : WASTEWATER DRAINAGE

PART 5 : WASTEWATER DRAINAGE Authorised by : City Waters Unit Manager Page 1 of 15 PART 5 : WASTEWATER DRAINAGE 5.1 INTRODUCTION This Manual sets out the basic design principles for drainage of wastewater. While some construction

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...

More information

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the

More information

COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary

COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary CITY OF LAKEWOOD COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary MAY 2006 storage conveyance treatment performance Prepared for: City of Lakewood, Ohio Prepared by: Metcalf & Eddy of Ohio,

More information

ADVERTISEMENT FOR BIDDERS

ADVERTISEMENT FOR BIDDERS ADVERTISEMENT FOR BIDDERS Sealed Bids will be received by the City of Lookout Mountain, Georgia, 1214 Lulu Lake Road, Lookout Mountain, Georgia 30103, Attention: Brad Haven, City Manager until: for the

More information

Minimum Design Criteria for the permitting of Gravity Sewers

Minimum Design Criteria for the permitting of Gravity Sewers Minimum Design Criteria for the permitting of Gravity Sewers Adopted by the Division of Water Quality on February 12, 1996 Updated to 15A NCAC 2T Regulations on March 2008 1,400 copies of this document

More information

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued) BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset

More information

SUMP PUMP. City of Ann Arbor & C O L L E C T I O N S Y S T E M G L O S S A R Y

SUMP PUMP. City of Ann Arbor & C O L L E C T I O N S Y S T E M G L O S S A R Y Foundation A foundation is the bottom part of a building. It s the element that anchors the building to the ground and transmits the building s gravity load directly to the earth. Water damage weakens

More information