PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study



Similar documents
Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generation and Transmission Interconnection Process

Q140 Cluster Addendum

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

Emera Maine Proposed Potential Transmission Projects. Line Identification Line 75 - KR Sub. Estimated Cost $201,464 $0 $3,200,000

Control Number : Item Number : 9. Addendum StartPage: 0

Section 4: Integrating Public Policy Drivers

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

Updated SYSTEM IMPACT STUDY OF NEW ENGLAND AREA

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

COMMONWEALTH OF VIRGINIA LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF FINAL ORDER

TRANSMISSION ALTERNATIVES CONSIDERED

16 West Coast Regional Plan

BPA Network Open Season 2013 Cluster Study

Houston Region Import Capacity Project

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project

TDI's NYC Merchant CHPE Transmission Project with POI at Astoria (NYISO Queue #305) Deliverability Analysis

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

Deliverability Testing

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria

Section 4: Scheduling Philosophy & Tools

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Millennium Pipeline Company, LLC Response to New York State Energy Highway RFI

Rocky Mountain Power Transmission Five Year Study Findings Meeting

Memorandum. This memorandum requires Board action. Executive Summary

Potomac Electric Power Company 1900 Pennsylvania Ave., N.W. Washington, D.C

AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233

PJM Interconnection LLC Regional Transmission Organization (RTO)

SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner

AAPG 2011 Annual Convention & Exhibition April 10, 2011

IESO Supply Deliverability Guidelines

The Economic Impact of Dominion Capital Expenditure Projects

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION FEASIBILITY STUDY FOR PROPOSED XXXXXXXX GENERATION ON THE SIERRA BLANCA-FARMER 69 KV LINE

Pennsylvania Summer Reliability

SUMMARY OF CAPITAL EXPENDITURES

Load Dispatcher (Class Code 5223) Task List

PUBLIC SERVICE COMMISSION OF MARYLAND TEN-YEAR PLAN ( ) OF ELECTRIC COMPANIES IN MARYLAND

Tehachapi Renewable Transmission Project (TRTP)

HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS

Microgrid Building block for Smart Cities

Item 8: Houston Import RPG Project

BOUNDLESS ENERGY, LLC S RESPONSE TO THE REQUEST FOR INFORMATION BY THE NEW YORK ENERGY HIGHWAY

Transmission Related Station Power Use at Substations

DUKE ENERGY INDIANA. Preparation for Summer Presentation to Indiana Utility Regulatory Commission

NTTG Study Plan for the Public Policy Consideration Scenario

APPENDIX 7 TO LGIP INTERIM INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT

PJM LMP Market Overview

Economic Impact Analysis of PSE&G s Capital Expenditure Program

2015 Highlights. Operating Committee January 21, 2016

Electric Power 2005 in Chicago. Dr. Aiham Alsammarae Minister Of Electricity Iraq

FORM EIA-411 INSTRUCTIONS COORDINATED BULK POWER SUPPLY AND DEMAND PROGRAM REPORT

131 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING WAIVER. (Issued May 25, 2010)

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Generation Interconnection Facilities Study Report. For. PJM Generation Interconnection Request Queue Position R11. South River

345 kv Brazos Valley Connection Project FAQs

Kyrgyzstan: Power Generation & Transmission

ASSET MANAGEMENT STRATEGY Approved

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC.

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

Cyber Infrastructure for the Smart Grid

Preliminary Feasibility Assessment For. The Rio Tinto Alcan to BCH Transfer Limit of 460 MW. With 50% Series Compensation on Both KMO KIT lines

Comments of Louisiana Energy Users Group and Texas Industrial Energy Consumers. MISO South Market Congestion Planning Study. September 18, 2015

Sudbury to Hudson Transmission Reliability Project

ITP Evaluation Process Plan Cross-Tie Transmission Line

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South

Electrical System Studies

Chapter 7 - Appendix A

SPP Notification to Construct

E N G I N E E R I N G

2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference. July 1, 2014

Texas Demand Response Programs Cirro Energy Services an NRG Energy Company

Integrating Renewable Electricity on the Grid. A Report by the APS Panel on Public Affairs

PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013

Energy Storage Market Overview MADRI 3/3/2015 John Fernandes Policy & Market Development Manager

Updated: November 30, 2007 Date: 30-Nov-07 SUMMARY OF DISCOUNTED CASH FLOW CALCULATIONS EB Project # Exhibit B Tab 4 Schedule 4 page 1 of 5

Treasure Valley Electric Plan - Community Advisory Committee

Calculating the Business Case for Demand Response

TRANSMISSION BUSINESS PERFORMANCE

Fixed Income Investor Meeting

CITY AND COUNTY OF SAN FRANCISCO

Convergence of Wholesale And Retail Markets: The Texas Experience

Enabling End Users to see Real Time Price Signals and Manage their Own Electricity Costs via the PJM Demand Side Response Program Delaware DNREC

Operating Security Standards

Schedule 19 POWER PURCHASES FROM COGENERATION AND SMALL POWER PRODUCTION QUALIFYING FACILITIES

How To Operate The Williston Uvls

PJM Renewable Integration Study

TERMS AND CONDITIONS

Applicability and Eligibility

New York Independent System Operator (NYISO)

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations

D.3 South Minneapolis Electric Distribution Delivery System Long-Term Study

National Regulatory Conference May 20, The Role of Natural Gas in Electric Generation

Jason B. Keyes Keyes & Fox, LLP Kansas Solar Round Table Topeka, Kansas March 3, 2009

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions

Transcription:

PJM Merchant Transmission Request Queue #R75 Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study 413038v1a March 2007 PJM Interconnection 2007. All rights reserved.

Preface The intent of the feasibility study is to determine a plan, with ballpark cost and construction time estimates, to connect the subject merchant transmission upgrade to the PJM network at a location specified by the Interconnection Customer. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. All facilities required for interconnection of a merchant transmission upgrade must be designed to meet the technical specifications (on PJM web site) for the appropriate transmission owner. In some instances an interconnection customer may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection or merchant transmission upgrade, may also contribute to the need for the same network reinforcement. The possibility of sharing the reinforcement costs with other projects may be identified in the feasibility study, but the actual allocation will be deferred until the impact study is performed. The Feasibility Study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The project developer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study. PJM Interconnection 2007. All rights reserved.

General Reliant Energy Electric Solutions, LLC has proposed a project to upgrade the Mitchell Shepler Hill 138 kv circuit. The circuit is to be reconductored with 10.33 miles of 954 ACSR. The proposed in-service date for this merchant transmission project is January 1, 2008. This Merchant Transmission Feasibility Study assesses the practicality and cost of incorporating the transmission facility into the PJM system. This study was limited to short-circuit analyses as well as load flow analyses of probable contingencies. PJM has provided preliminary estimates of the type, scope, cost, and lead time for construction of facilities. If the interconnection customer elects to pursue the System Impact Study, a more comprehensive analysis will be performed. Attachment Facilities The proposed reconductored 138 kv transmission line will terminate at existing facilities. The total project cost is estimated to be $ 3,000,000 in 2007 dollars. This estimate does not include tax gross up. This project will require 26 months to complete from the date of receipt of a signed Construction Service Agreement (CSA). Delays could be based on weather, equipment lead-time, and availability of outages to perform the work. NETWORK UPGRADES The study indicates no network upgrades are needed for the project. PJM Interconnection 2007. All rights reserved. 3

Network Impacts Project #R75 was evaluated for compliance with reliability criteria for summer peak conditions in 2011. Potential network impacts were as follows: Generator Deliverability No problems were identified Multiple Facility Contingency No problems were identified Contribution to Previously Identified Overloads No significant contributions to previously overloaded facilities were identified New System Reinforcements None identified. Contribution to Previously Identified System Reinforcements None identified. Short Circuit No overdutied breakers were found. IDRs at Elrama 138 kv 0 MW The incremental MW-injection is limited by the Mitchell-Uninon J. 138 kv line for the tower outage of 138 kv lines Mitchell-Charleroi and Mitchell-Dry Run. PJM Interconnection 2007. All rights reserved. 4

Elrama (DL) * Approximately 4 miles 2 954 ACSR 2 954 ACSR * AP Mitchell Union Jct PJM Queue P56 Dry Run AP Reconductor Mitchell Shepler Hill Jct. 138 kv circuit. Smithton Shepler Hill Jct 138 kv Belmont Charleroi AP SOURCE CAD FILE REVIEWED APPROVED DATE Allegheny Power P L A N MITCHELL SHEPLER HILL JCT. RECONDUCTOR 138 kv LINE FOR RELIANT ENERGY ELECTRIC SOLUTIONS MERCHANT TRANSMISSION CHARLEROI SERVICE CENTER DRAWN CHKD SCALE AUTHORIZATION NS REV Figure 1 PJM Interconnection 2007. All rights reserved. 5