San Francisco Oakland Bay Bridge SELF-ANCHORED SUSPENSION (SAS) SPAN



Similar documents
San Francisco Oakland Bay Bridge East Span Seismic Safety Project

STATEMENT OF WORK (SOW) On-Call Certified Welding Inspections and Nondestructive Testing

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

DENVER MODEL 30 X 30 SPECIFICATIONS

CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES

METHOD OF STATEMENT FOR STATIC LOADING TEST

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Acceptance Codes APPENDIX - A. Acceptance Criteria

ABOUT CWB CERTIFICATION/ QUALIFICATION The work CWB does on behalf of our clients can be divided into five main categories:

Safe & Sound Bridge Terminology

Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

COLORADO MODEL. 35 x 65 SPECIFICATIONS

Engineered Material Handling. Overhead Bridge Cranes and Gantry Cranes

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

Value Engineering vs. Alternate Designs in Bridge Bidding

Owner Controlled Insurance Program (OCIP) Overview

SECTION PRECAST CONCRETE STRUCTURES

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL. AC172 February 2015 (Effective April 1, 2015)

Virginia Approach Spans

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059

High Strain Dynamic Load Testing of Drilled Shafts

WSDOT Bridge Elements

TARIFF CODE and updates standard

ATLANTA MODEL SPECIFICATIONS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

US 51 Ohio River Bridge Engineering and Environmental Study

Embedded Parts Introduction - Anchors

Hamilton Form Company, Ltd Custom Designs, Flexible Solutions

COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP

[BARLINES MANUAL OF STANDARD PRACTICE (PHILS)] Chapter One METRIC (SI), PNS BAR SIZES STANDARDS AND OTHER CRITERION

Welded Fabric. The CARES Guide to Reinforcing Steels Part 5. Installation of welded fabric on a major contract. 1.0 Introduction

Chapter 3 Pre-Installation, Foundations and Piers

Contractor s Statement of Responsibility for Seismic-Force-Resisting Systems This form is to be filled out by the contractor.

High Capacity Helical Piles Limited Access Projects

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

SECTION 1 GENERAL REQUIREMENTS

Mechanical Installation

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

SECTION GUARDRAILS

Residential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

1 Barlines Rebar Detailing Standards in the Philippines

9. QUALITY CONTROL/QUALITY ASSURANCE

Quality Assurance Manual. QAM-2013-Rev2

HIGH TENSION CABLE BARRIER

SECTION STORM DRAINAGE SYSTEM

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

The ACR : Advanced Design Features for a Short Construction Schedule

U.S. Department of Labor Occupational Safety and Health Administration Directorate of Construction. April 2015

Chaudière Crossing Bridge Rehabilitation

1.2 Advantages and Types of Prestressing

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

Residential Deck Safety, Construction, and Repair

Scope of EN Clarification Document

Essentials Welding QA/QC Plan Sample

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Buildings Construction Procurement Strategy

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

WELDING INSPECTION REPORT

Optimum proportions for the design of suspension bridge

2. Division 05 Structural Steel Framing for steel framework requirements

Uncovered Decks & Porches

Evaluating. A Case Study

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

Truss. are both simple and A Matsuo Example continuous trusses. The

Designed and Engineered to Perform

Hunter College school of Social Work Thesis Proposal

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

PART 1 GENERAL 1.1 SECTION INCLUDES

ACCREDITATION CRITERIA FOR INSPECTION PROGRAMS FOR MANUFACTURERS OF METAL BUILDING SYSTEMS AC472

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

Quality Management System

TOP RUNNING SINGLE GIRDER BRIDGE CRANE

Detailing of Reinforcment in Concrete Structures

SERIES NG 1800 STRUCTURAL STEELWORK

SECTION 15 AIR RELEASE VALVE ASSEMBLIES General

MATTHEW L. SAMS. Curriculum Vitae. General Building Contractor, State of California License #796054

SECTION WINDOW WASHING SYSTEMS

Quality Control and Quality Assurance Guide

Measuring the Condition of Prestressed Concrete Cylinder Pipe

Quality and the Bridge Engineer

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

What is Seismic Retrofitting?

Fabrication of Reinforcement

COMPANY ESTIMATOR BID DAY PHONE NO.

B.TECH. (AEROSPACE ENGINEERING) PROGRAMME (BTAE) Term-End Examination December, 2011 BAS-010 : MACHINE DESIGN

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

Technical Assignment 2 TABLE OF CONTENTS

Transcription:

San Francisco Oakland Bay Bridge SELF-ANCHORED SUSPENSION (SAS) SPAN

San Francisco Oakland Bay Bridge SELF-ANCHORED SUSPENSION (SAS) SPAN 2 Project Overview Conventional Vs SAS Bridge SFOBB SAS Features International Fabrication Temporary Bridge Shear Leg Crane Concrete Works Quality Program Audits Quality Plans Mock-ups and Pre-qualifications NCR Processing In-process Tests and Inspections Weld Tracking

3 Project Overview

4 October 17, 1989

5 Current East Span

Replacement Span 150 Year Service Life 1400 Year Earthquake 6

Self-Anchored Suspension (SAS) SAS West Span YBI Transition West Approach BID AMT $1.41B First Working Date May 18, 2006 Estimated Completion Date Spring 2013 7 San Francisco-Oakland Bay Bridge (SFOBB)

Existing 8 View Driving West to San Francisco

9 Bicycle/Pedestrian Facility

Summary Project Schedule Project General Bridge Deck Temporary Towers/Trusses Removal T1 Tower Cable System W2 Cap Beam E2 Cross Beam Mechanical\Electrical 10

11 Conventional Vs SAS

Conventional Suspension Bridge Two towers Two Main cables anchored to land Deck sections lifted in-place 12

Self-Anchored Suspension Need to build a bridge to build the bridge Bridge deck acts as compression member Transfer of deck loads to cable is last structural operation performed 13

14 SAS Features

SFOBB SAS Tower Height = 160 m Deck Length =625 m Superstructure = 43,603,000 kg 15

16 T-1 Tower Layout

17 One Tower (4 Legs) Seismic Shear Link Beams

18 Orthotropic Deck and Crossbeam

Cable Installation Asymmetrical single tower One continuous main cable Bridge decks super-elevated and curved Load transfer not in free hanging position Final structural analysis will be as-built analysis Cable Wraps Around Roadway 19 Single Cable Concept

Zinc Oxide / Zinc Dust Paste 127 Wire PWS Strand with Grease Application of Individual Wire Elastic Noxide Primer and Paint Cable is made up of 137 PPWS 5.4mm Zinc Galvanized Wire Composition of SAS Cable S-Wire Wrapping 17,400 Wire Main Suspension Cable 20

SAS Saddle Location (Total 6) (1) Tower Saddle (2) Deviation Saddles (2) Splay Saddles (1) Jacking Saddle 21

West Deviation and Jacking Saddles at W2 Hinge K Jacking Saddle Status Developing pattern for E line segment 2 Molding saddle for E line segment 1 Deviation Saddle 22

23 Hinge K

24 E2 Bearing and Shear Key

25 Tower Bolted Splice Details

Bolting ASTM A490M bolts with Dacromet coating A490 bolts rarely used on bridges Coatings not allowed by current standard No rotational capacity criteria for metric Bolting in confined space 26

27 International Fabrication

SAS - International Fabrication Effort Fabrication Process Suspender Cables-Kiswire Bearings- Hochang Machinery Industries Shear Key- Hochang Machinery Industries Pipe Beams-Oregon Iron Works Washington Minnesota Shanghai Korea Japan Saddles-Japan Steel Works So. Calif Misc Steel-D.S Brown & Westmont Industries PWS Cables-Shanghai Pujiang Cable Co Tower Fabrication - ZPMC Orthotropic Box Girder Sections - ZPMC Bikepath - ZPMC 28

Superstructure Fabricator - ZPMC Changxing Island Facility Shanghai, P R China 29 New Tower Fabrication Shop

30 Tower

Orthotropic Box Girder Submerged Arc Welding Gantry 31 U-Rib Bending Machine

Orthotropic Box Girder OBG Lift Assembly 32 OBG Lifts Lined Up

33 Delivery of OBG and Tower Lifts

Saddle Fabrication JAPAN STEEL WORKS 34 Casting West Deviation Saddle

Saddle Fabrication Types: 35 Machining West Deviation Saddle

Shanghai Pujiang Cable Co., Ltd. PWS Cable Taping PWS Cable Assembly 36

Goodwin Steel Castings Mock-up Casting Pattern Shop 37

Stoke-on-Trent, UK Cable Bands Xitang, PRC PWS Cable 38

39 Temporary Bridge

Temporary Works Facts 6,500 Mtons of Piling consisting of 48 x 1-1/4 and 42 x 1-1/2 4,300 Mtons for Towers 5,500 Mtons Truss Material 2,124 Mtons of Driving Frames 1 2 3 4 5 6 7 8 9 10 11 12 13 14 40 W2 A B C D F G T1 H E2

41 Temporary Tower Foundations

42 Temporary Bridge

43 Shear Leg Crane

Shear Leg Crane and Barge Lifting Capacity: 1700 Mtons Boom Length: 100 Meters Self Erecting Boom 44

45 Shear Leg Crane

46 Concrete Works

E2 Crossbeam W2 Cap Beam

48 W2 Cap Beam Details Elevation

49 Cable Tie-down Details

W-2 Cap Beam Facts 2,300 cubic meters conventional concrete 4,500 cubic meters selfconsolidating concrete (8,700PSI) 1,000 tons of rebar Dimensions: 55 W x 225 L x 22 D 50

51 Pier E2 Details

E-2 Cross Beam Facts 2,000 cubic meters selfconsolidating concrete (8,700PSI) 650 tons of rebar Dimensions: 15 W x 200 L x 20 D 52

53 Quality Program

54 Facility Audits

Audits (40 performed to-date) Extensive in-depth facility audits Audit checklist from lessons learned Paperwork approval (English only) before audit Facility audit American standards Verify capability and control/traceability though out the process Extensive international travel Some doing work for Caltrans on other projects do not receive a pass for the SAS Extends to lower tier subcontractors Cannot start ANY work until passing an audit Financial penalties for failing an audit 55

56 Quality Programs

QUALITY PLANS (14 approved to-date) CONTRACT DOES NOT REQUIRE ONE COMPREHENSIVE ABFJV QC PROGRAM/MANUAL SPECIFIC CONTRACT QUALITY PROGRAM REQUIREMENTS SEVERAL QC MANAGERS SEVERAL QC PLANS OTHER FABRICATION SPECIFIC PLANS (i.e., THERMAL CONTROL PLAN, PRECAST FENDERS, BEARING LUBRICANT, CABLE BAND SLIP, etc.) 57

58

Mock-Ups and Prequalification 59

Completed ABF Tower Mock-Ups

61 Electroslag Weld trials

U-Rib Bending Demonstration 1 2 3 62

Cable Compaction Cable Band Slip Test 63

W-2 Cap Beam Integrated Shop Drawings 1. Prepared Using Navisworks Program by ABFJV Personnel (Michael Lewis) 2. Modeling of Approximately 30,000 Elements which includes: a. Reinforcing Steel b. Post Tensioning Ducts c. Embeds d. High Strength Rods for Main Hinge & Deviation Saddles 3. Resolved 30,000 conflicts which was almost one conflict per every element modeled 64

65 W-2 Cap Beam Integrated Shop Drawings

66 Reinforcing Mechanical Coupler Pre-qualifications

W-2 Cap Beam SCC Pour Mock-up 67 Formwork for Mass Concrete Demonstration Pour Spread Test Performed During Self Consolidating Concrete Pour Mock-up

68 NCR Processing

NCR Processing Transition from serial letters with attachments to on-line document control process Lesson Learned Technology is not the process. There need to be buy-in and commitments from all parties to make the system work 69

Creation of a Non-Conformance Report in PDF format

The NCR is transmitted to the Contractor

Quick search and status of all the Non-Conformance Reports and Non-Conformance Proposed Resolution reports

73

74 In-Process Tests and Inspections

In-Process Tests and Inspections Coordination of inspection and testing activities Numerous sub-consultant contracts Domestic and international Coordination with Caltrans 75

In-Process Tests and Inspections Welding Quality Control Procedure Qualifications Welding Quality Control Plan Only AISC Category 3 facilities can selfperform welding NDT & inspection Daily Reports 76

77 Welding QC Plan

78

AMERICAN BRIDGE/FLUOR SFOBB BRIDGE PROJECT QUALITY ASSURANCE SOFTWARE WELDLINKPRO

80

Designed by Built by

Introduction Web based Quality tool developed using Microsoft s ASP.NET and C# programming language. Designed to be utilized by Fabricator, Contractor and Owner specifically to document the fabrication of the San Francisco Bay Bridge Project. Real time reporting of inspections and repairs before, during and after welding by use of hand held devices and wireless network. Material traceability through the use of bar code technology and Material Data Log. 82

Introduction (continued) Accountability of welders through tracking repair rates by welder, process, position, joint configuration and cause. Insures all required inspections and repairs have been completed in advance of shipment. Provides access via the world wide web to unlimited personnel to view the real time inspection and repair status. 83

Industries Bridge Aerospace Nuclear Hydroelectric Marine Military Construction 84

Highlights Material traceability Weld joint tracking Welder performance tracking Weekly Welding Report Documentation Benefits Contact information 85

Material traceability Material traceability is accomplished by use of bar code technology and/or traditional means of tracking items such as heat number and grade. Material information is compiled and stored on the Material Data Log as well as the Weld Data Log. Filtering allows the user to search by any desired combination of fields. 86

Material traceability (continued) Material lists can be downloaded offsite for material on hand payments. Consolidated material list between parties. Individual plate traceability. Check sample verification PDF material test report 87

88

89

Highlights Material traceability Weld joint tracking Welder performance tracking Weekly Welding Report Documentation Benefits Contact information 90

Weld Data Log A centralized location for each weld joint on the project. Created prior to weld joint fit up. Outlines the required nondestructive testing. Outlines the required in process inspections per the contract requirements. Provides material traceability used to construct the weld. Works in conjunction with weld maps. 91

Weld Data Log (continued) Insures proper acceptance criteria is applied. Eliminates costly re inspections 92

93

Weld Data Log (continued) All inspection and repair reports are created via links from this central location. Captured data populates the weld reject log and daily production. Insures the correct acceptance criteria is applied during inspections. Eliminates the need for manual creation of reports reducing reporting errors. 94

95

Weld Data Log (continued) History of all repairs associated to the weld Provides the positive proof all required inspections and repairs have been completed. Supports the creation of the weekly welding report. Supports and captures revisions to repair reports such as critical weld repairs. May be utilized during the review of the weekly welding report 96

97

Highlights Material traceability Weld joint tracking Welder performance Weekly Welding Report Documentation Benefits Contact information 98

Welder Performance Welder performance is captured on the Weld Reject Log. Filtering allows the user to search by any desired combination of fields. Utilized for trend analysis of weld repairs. Provides real time total reject percentages project wide by any filterable field. 99

Welder Performance (continued) Inspector Welder Repair type Weld identification Location in the structure Position Process Joint type Repair length Repair depth Repair width Repair percent Cause 100

101

Highlights Material traceability Weld joint tracking Welder performance tracking Weekly Welding Report Documentation Benefits Contact information 102

Weekly Welding Report Weekly Welding Report is Compiled electronically following completion of tasks outlined on the Weld Data Log. Following review by the Quality Control Manager the Weekly Welding Report is submitted electronically to the Engineer for approval. During review by the Engineer the database may be available to verify current status of inspections and repairs. 103

Weekly Welding Report (continued) Weekly Welding Report includes: NDE reports Critical Weld Repair Reports Weld Repair Reports Heat Straightening Reports Nonconformance Reports Weld Reject Log Daily Production report 104

105

Highlights Material traceability Weld joint tracking Welder performance tracking Weekly Welding Report Documentation Benefits Contact information 106

Documentation Records can be viewed electronically or printed. Final acceptance of components is obtained by producing a Data Acceptance Packet. Data Acceptance Packets are compiled after completing a query and are produced in PDF format. 107

Documentation 108 Data Acceptance Packet include the following Nondestructive Testing Reports Weld Repair Reports Post Weld Repair NDE Reports Weld Map Weld Data Log Material Test Report In process inspections as required

Highlights Material traceability Weld joint tracking Welder performance tracking Weekly Welding Report Documentation Benefits Contact information 109

Benefits 110 Real time wireless accurate and consistent reporting of inspection and repair results. Electronic submittal process reduces the approval time and personnel. Increased level of traceability of material, inspections and repairs result in decreased time and involvement by the customer before, during and after fabrication including shipment. Eliminates costly re-inspections of previously inspected and accepted welds and components.

Benefits (continued) Shared information between all parties at all locations through the use of web based application. Onsite reporting increases floor coverage and decreases office time. Increased level of accountability of welders and inspectors. 111 Localization (bilingual) Eliminate redundant tracking by multiple parties.

Benefits (continued) Reduced exposure for omitted and duplicate reports. Customer satisfaction by providing access to the database during the review and approval of the Weekly Welding Report. Reduce costly repairs through trend analysis May be implemented project wide Paperless submittal process Electronic report correlation and PDF printing 112

Summary 113 Designed for the Total Quality Management approach this unique tool will greatly enhance traditional Quality Control and Quality Assurance reporting and documentation. Web based application opens the door for cooperation between Fabricator, Contractor and Owner. Increases accountability for welders, inspectors and reviewers. Captures valuable data that can be utilized to establish controls to reduce or eliminate defects. Provides complete material traceability from beginning to end.

Highlights Material traceability Weld joint tracking Welder performance tracking Weekly Welding Report Documentation Benefits Contact information 114

Contact information Inspectech Corporation 8550 W Charleston Blvd #102-148 Las Vegas, Nevada 89117 503-550-9918 www.inspectechconsulting.com Further product information on WeldLinkPro can be found at the following website www.weldlinkpro.com 115 Copyright 2006-2008 Inspectech Corporation All Rights Reserved.