SURFACE REMEDIATION AND MANAGEMENT OVERVIEW



Similar documents
Establishing an Ambient Air Quality Monitoring Program During the Giant Mine Remediation

Giant Mine Working Group 12 February 2015 Meeting Summary DRAFT

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

FINAL PLAN OF REMEDIAL ACTION

Helen Mercury Mine EE/CA OPINION OF PROBABLE COST

Mine Plan of Operations Reclamation Bond Checklist

Site Description and History

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

Storm Drain Inlet Protection

SECTION SELECTIVE DEMOLITION

A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems.

1. Page 1, Incoming Soil Materials, Testing Frequency :

Environmental Construction Operations Plan (ECO Plan) Framework

Contaminants of Concern Exposure Pathways

Health Consultation MID-AMERICA TANNING COMPANY SERGEANT BLUFF, WOODBURY COUNTY, IOWA EPA FACILITY ID: IAD FEBRUARY 17, 2005

SE-10 STORM DRAIN INLET PROTECTION. Objectives

UPDATE ON MANAGEMENT OF LEGACY ENVIRONMENTAL ISSUES IN GHANA

Proposed Terms of Reference for EIA studies

Monitoring Program Waste

Preventing Storm Water Pollution: What We Can Do

Environmental guidelines for preparation of an Environment Management Plan

Prattsville Berm Removal Project. 1.0 Project Location

Introduction to Lockheed West Seattle. Working Together. Site Background. Lockheed West Seattle Superfund Site

GUIDELINE FOR MUNICIPAL MANAGEMENT PRACTICES FOR STREET SWEEPINGS & CATCH BASIN CLEANINGS

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

Case Study: Habitat Restoration

Emergency Spillways (Sediment basins)

ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Storm Drain Inlet Protection

Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. CIVL 1112 Detention Ponds - Part 1 1/12

Title 27A. Environment and Natural Resources Chapter 1 - Oklahoma Environmental Quality Act Article III - Jurisdiction of Environmental Agencies

National Environmental Policy Act and Permitting Services for the Mining Industry

Plan Requirement Guidance for Quartz Mining Projects

Vehicle Tracking Control (VTC)

The Wismut Rehabilitation Project: Present State, Outlook and Lessons Learned

KITSAULT MINE PROJECT ENVIRONMENTAL ASSESSMENT. Section Summary of Commitments

CHAPTER 4 ALTERNATIVES COMPARISON

Storm Water Management Requirements for Construction Projects Less than One Acre

SECTION TEMPORARY ENVIRONMENTAL CONTROLS

Risk-Based Decision Making for Site Cleanup

Environmental Guidelines for Preparation of an Environmental Management Plan

Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury

SECTION EARTH MOVING

Florida Department of Environmental Protection

WORK BREAKDOWN STRUCTURE FOR A TYPICAL MINE

Carson River Mercury Superfund Site Management Strategies and Goals. May 2011

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials

INFORMATION SHEET ORDER NO. R XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY

Q 4/17/13: Thank you for your quick response to our dated April 10, In looking over your comments, we have a few clarifying remarks.

SOIL AND GROUNDWATER MANAGEMENT PLAN For Site Located at 420 South Avenue Rochester, New York NYSDEC Spill No PREPARED FOR: PREPARED BY:

Remediation Weekly Activity Summary Report Ameren LaSalle Former MGP - Soil Removal Action

NPDES Industrial Stormwater Inspection Worksheet

CCR Fugitive Dust Control Plan CPS Energy Calaveras Power Station San Antonio, Texas

MBJ Environmental Programmes

5. Environmental Analysis

Wyckoff/Eagle Harbor Site Bainbridge Island, Washington

Swamp Area Passive Treatment System Kettle Creek Watershed, Clinton County, PA

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents

Draft ABCA : USEPA 2015 Brownfields Cleanup Grant Application for Former Hudepohl Brewery Site by Port of Greater Cincinnati Development Authority

Draft Construction Work Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Outlet stabilization structure

Preventing Basement Flooding

PRESS RELEASE CANADIAN ZINC RECEIVES ENVIRONMENTAL APPROVAL. Review Board approves proposed Prairie Creek Mine

Package Treatment Plant Policy and Procedure

Remediation Weekly Activity Summary Report Ameren LaSalle Former MGP - Soil Removal Action

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

SECTION 5. Sediment Control Measures

1200 United Boulevard

SECTION 202. REMOVAL Of ROADWAYS AND BUILDINGS

consulting engineers and scientists

6.0 EVALUATION OF ALTERNATIVES

SECTION SITE PREPARATION

SPILL PREVENTION PLAN

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE ENVIRONMENTAL, HEALTH, AND SAFETY

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

Ontario Mining Act Fact Sheet Mine Closure Plans Your Right to Know!

Construction Site Inspection Checklist for OHC By making use of some simple Best Management Practices (BMPs) a construction site operator can

This Food Safety Plan was developed in New York as an example for growers. Each grower must develop their own plan which fits their operation.

Concrete Waste Management

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION

Getting Started - More Information:

This Chapter was compiled by GCS (2014) as part of the EMP Consolidation for MP 30/5/1/2/2/133MR and remains pertinent.

D R A F T. Best Management Practices Plan (Surface Water, Sediment & Erosion Control) West Carleton Environmental Centre. May 2014

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

Temporary Batch Plants

4. Environmental Impacts Assessment and Remediation Targets

ENVIRONMENTAL REVIEW SCREENING QUESTIONS

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations

Transcription:

SURFACE REMEDIATION AND MANAGEMENT OVERVIEW Giant Mine Remediation Project Environmental Assessment Public Hearings September 10-14, 2012 Adrian Paradis (AANDC) Mike Nahir (AANDC) Bruce Halbert (Technical Advisor) Rudy Schmidtke (Technical Advisor) 1 John Hull (Technical Advisor)

2 SURFACE REMEDIATION WILL IMPROVE: Baker Creek Open Pits Existing Tailings Contaminated Soils Debris and Demolition Air Quality

BAKER CREEK Assessments to date show there will be improved water quality in Baker Creek. 3

Reduce flood risk: REMEDIATION OBJECTIVES Flow through site without spill to underground; increase physical stability of creek Current criteria are 500-year flood flow event, with 2 m anchor ice, plus 1 m freeboard Minimize groundwater seepage to the underground Maintain a low flow channel for fish passage and habitat Enhance/restore fish habitat in Baker Creek Measures to result in positive change to flow regime & habitat 4

EXISTING AND HISTORICAL ALIGNMENTS N 5

HYDROLOGY 6

HYDROLOGY Baker Creek Flood Regime Return Period (years) Estimated Flood Discharge (m 3 /s) 2 1.7 10 5.4 50 10.8 100 13.8 200 17.3 500 25.0 Probable Maximum Flood ~200 Spring 1991, at 8.45 m 3 /s - greatest recorded flow (since 1968) Mean annual flow - about 6.8 million m 3 Anchor ice formation observed in recent years, particularly in Winter 2010-11. 7

CHANNEL DESIGN 3H:1V Bank 6 m 1 m 8

CHANNEL DESIGN 2H:1V in Soil 3H:1V Bank 6 m 1 m 0.5H:1V in Rock 32 m 9

CHANNEL DESIGN 2 m Anchor Ice Accumulation 2H:1V in Soil 3H:1V Bank 6 m 1 m 0.5H:1V in Rock 32 m 10

CHANNEL DESIGN 2 m Anchor Ice Accumulation 1:500 year Flood Flow 2H:1V in Soil 3H:1V Bank 6 m 1 m 0.5H:1V in Rock 32 m 11

CHANNEL DESIGN 2 m Anchor Ice Accumulation 1:500 year Flood Flow 1 m Freeboard 2H:1V in Soil 3H:1V Bank 6 m 1 m 0.5H:1V in Rock 32 m 12

CHANNEL DESIGN 2 m Anchor Ice Accumulation 1:500 year Flood Flow 1 m Freeboard 2H:1V in Soil 3H:1V Bank 6 m 1 m 0.5H:1V in Rock 32 m Channel geometry and materials are based on local geomorphology investigation 13

REMEDIATION ELIMINATES FLOOD RISK 14

REMEDIATION ELIMINATES FLOOD RISK Reach 3 Design option: Divert creek to west in deep cut around a bedrock outcrop, approximately 100 m to 250 m west of C1 Pit. 15

BAKER CREEK SEDIMENT STUDY Review sediments in creek to determine extent of contaminated sediments and tailings in creek: to provide input for DFO, EC to provide data to make informed decisions. Decision on creek remediation requires input from DFO and other parties before moving forward. 16

PROJECT INTERACTION GNWT Highway realignment does not interfere with Baker Creek. 17

BAKER CREEK REMEDIATION ACTIVITIES WILL: Increase physical stability. Reduce flood risk to mine. Consider stakeholder input to Baker Creek options. 18

OPEN PITS Remediation activities will improve public safety. 19

OPEN PIT LOCATIONS 20

OPEN PIT RISK REMEDIATION PLAN Minimizing risk to: public health and safety by restricting access to pits; the environment; and sensitive and critical infrastructure near pits. Accomplished by standard Canadian practices: Limiting or restricting public access to the open pits Fencing and/or berms Placement of appropriate signage Backfilling of specific open pits, or portions thereof where necessary, to enhance longer term stability and manage drainage and assist the freeze program. Capping openings to surface. 21

OPEN PIT REMEDIATION WILL: Increase public safety Restrict public access Freeze contaminated soil in B-1 pit 22

TAILINGS WILL BE COVERED 23

SITE PLAN 24

REMEDIATION WILL: Isolate tailings from contact with humans and wildlife. Allow potential future uses of the areas and these uses would be discussed with stakeholders. Use borrow sources on site. Address historic foreshore tailings. 25

26 POTENTIAL BORROW SOURCES ON SITE, LIMITING IMPACT OF PROJECT TO MINE LEASE AREA

27 TAILINGS COVER Vegetative growth layer developed from on site borrow Coarse layer constructed from rock from on-site quarries Tailings surface will be re-graded prior to placing cover Clayey silt or silty clay Vegetation Support Layer Coarse gravel or crushed rock Coarse Layer Tailings Tailings

EROSION PROTECTION TO FORESHORE TAILINGS 28

TAILINGS REMEDIATION WILL Isolate tailings from direct contact by humans and wildlife. Make area available for other uses the end-use to be determined with input from stakeholders (e.g. YKDFN, GNWT, City) 29

30 CONTAMINATED SOILS AND MINE WASTE ROCK Allows for future uses of the site which will be discussed with stakeholders.

31 GNWT INDUSTRIAL STANDARD Remediate overall site to GNNT industrial standards Backfill soils into frozen zone in B1 Pit Improve quality of the site surface conditions

12 6 7 1 11 4 5 10 1 Mill Area 2 West of Central Pond & TRP 4* West of Settling Ponds 5 Propane Tank Farm 6 Town Site 7 Town Site Road 8 Yellowknife Bay 9 Adjacent to North Pond 10 Northwest Sites 11 West Sites 12 Southwest Sites * Area 4 is a combination of Areas 3, 4 & 13 8 2 9 32

REDUCED FOOTPRINT 33

OPPORTUNITIES FOR RE-USE OF MATERIAL Incorporate as fill to support Tailings Containment Area (TCA) cover. Place in B1 Pit. Use as intermediate cover in landfill. 34

REMEDIATION WILL Remove contaminated soil and waste rock with arsenic above the GNWT industrial standard (up to 2m depth). Cover any remaining contaminated soil greater than 2m depth. Resulting arsenic levels on surface will be low enough to support: industrial uses everywhere other uses in most places. 35

DEMOLITION OF MINE INFRASTRUCTURE Engage interested parties to preserve historic buildings where possible Recover hazardous building materials located in structures and underground Demolish all structures and utility lines with no future use Decontaminate materials prior to disposal offsite or in on-site landfill Collect all surface debris ELIMINATES SITE HAZARDS 36

MANAGING WASTE Construction of a waste disposal facility (on site landfill) Onsite disposal of all non-hazardous and asbestos materials Re-use mine waste rock for intermediate fill Water treatment plant sludge disposal in dedicated cell Roaster complex and other arsenic trioxide wastes will be placed in frozen block in B1 pit and underground. DITCH CAP DITCH BERM 37

N ELIMINATE PHYSICAL HAZARDS IN SCATTERED AREAS 23 identified surface debris areas Akaitcho TRP and ETP C - Shaft Townsite B - Shaft A - Shaft 38

NON-HAZARDOUS WASTE MAJORITY OF SURFACE DEBRIS Summary of Waste Generated during Building Deconstruction (m 3 ) 70,000 66,530 60,000 50,000 40,000 30,000 20,000 10,000 7,890 0 Non-Hazardous Waste 220 Petroleum Products 3,170 Asbestos Containing Materials 110 Chemicals, PCBs, Mercury 1,560 1,250 Lead and Leachable Lead Paint Mineral Process Waste Arsenic Impacted Wastes 39

ON AND OFF SITE WASTE MANAGEMENT Waste Type Non-hazardous Asbestos Semi Processed Ores from Crusher, Conveyor and Mill Buildings PCB/Chemicals/Petroleum Products Leachable Lead Painted Materials Arsenic Trioxide Dust New Water Treatment Plant Sludge Location On-Site - Engineered Landfill, Central Pond On-Site - Engineered Landfill On-Site Tailings Pond Off-Site - Approved Facility Off-Site - Approved Facility Frozen Block On-Site landfill 40

CURRENT DESIGN CONCEPT FOR LANDFILL N Central Pond Waste Disposal Location 41

ROASTER COMPLEX DEMOLITION - PROTECT HUMAN HEALTH AND SAFETY Risks Exposed arsenic trioxide in flues and loose asbestos Observed movement in flue support columns Corrosion and openings in roaster building Planning Specifications under development to be ready to mitigate the risks 42

HIGH RISK ROASTER COMPLEX ACCELERATED DEMOLITION 43

DEMOLISHING MINE INFRASTRUCTURE WILL: Eliminate physical and chemical risks. Increase public safety. Result in no adverse impacts through longterm management of demolition wastes. 44

AIR QUALITY ASSESSMENT 45

IMPROVEMENTS TO AIR QUALITY Air quality after remediation improved and sources of tailings dust eliminated. Main effects on Air Quality will occur during remediation phase (short-term). Mitigative measures in place. 46

AIR QUALITY ASSESSMENT Detailed assessment on Project effects on Air Quality was undertaken using CALPUFF/CALMET modelling package. Assessment of air quality included multiple sources: remediation activities occurring at the same time at several locations; plus Jackfish Power Plant operating at 18 MW output year round (3 MW for GMRP; 15 MW for City). 47

SOURCES IN AIR QUALITY ASSESSMENT Wind-blown dust from tailings B1 Pit backfilling Freeze pipe drilling Capping of tailings Roaster demolition & soil clean up Misc. earthworks Power generation (off-site) 48

EMISSION SOURCES Haul truck & equipment movement Material handling Windblown dust to air Haul truck & equipment tailpipe exhaust Jackfish Power Plant to air TSP, PM 10, PM 2.5, As NOx, SO 2, PM 2.5 49

PUBLIC EXPOSURE ON/OFF SITE Model was run in hourly time steps using meteorological data from 2007. Model was run: with six discrete Off-site Receptor locations; and for hikers on the existing Ingraham Trail alignment through the Giant Mine site. Predicted contaminant levels were compared to Ambient Air Quality Criteria (AAQC). 50

OFF-SITE RECEPTOR LOCATIONS 51

FINDINGS AT OFF-SITE RECEPTORS Low compared to Canadian guidelines No exceedances of Ambient Air Quality Criteria (AAQC) were predicted for TSP, PM 10, As, and SO 2 at any of the receptor locations. Very low probability of exceeding the one-hour NO 2 and 24-hour PM 2.5 AAQC at the R6 (Niven Lake) receptor location only at the maximum rate of power output from Jackfish Power Plant of 18 MW. At the typical operating rate of 12 MW of the Jackfish Power Plant, no exceedances of AAQC were predicted at any of the receptor locations. 52

MONITORING AND MITIGATION GNWT has provided GMRP modelling results to the NWT Power Corporation and are discussing options to mitigate potential exceedances and if necessary, monitoring Mitigation measures, such as reducing power requirements for the GMRP, can be implemented during peak power demand periods 53

HIKER EXPOSURE ALONG INGRAHAM TRAIL 54

FINDINGS FOR HIKER ON INGRAHAM TRAIL Low compared to published guidance in the open literature: PM 2.5 exposure predicted to fall consistently below the incremental exposure criterion; Very low probability of exceeding the Arsenic exposure criterion for non-carcinogenic effects under high wind conditions; and can be mitigated by suspension of remediation activities, as per normal practice Arsenic exposure consistently below the carcinogenic benchmark under all modeled conditions. 55

AIR QUALITY MONITORING Air quality monitoring of TSP and metals has been in place at the Giant Mine since 2004. Ambient air quality monitoring is also performed by the GNWT in Yellowknife. The existing air quality monitoring program will be modified and incorporated into an Air Quality Environmental Management Plan (EMP) prior to remediation. Air Quality EMP will identify action levels that trigger additional management actions, if required. Site-wide air quality monitoring will be continued until surface remediation activities are complete and for three years thereafter. 56

PROPOSED AIR QUALITY MONITORING STATIONS 57

AIR QUALITY DURING REMEDIATION ACTIVITIES Pose minimal risks to the public in the Yellowknife study area (off site) Pose minimal risks to members of the public while hiking or biking on Ingraham Trail (on site) AIR QUALITY POST REMEDIATION Air quality will be improved by eliminating dust from tailings and other sources 58