Railway Electric Power Feeding Systems



Similar documents
Opening of Tohoku Shinkansen Extension to Shin Aomori and Development of New Faster Carriages Overview of Series E5/E6 Shinichiro Tajima

Progress of Electric Railways in Japan

AN ANALYSIS OF THE EFFECT OF HIGH-SPEED RAILWAY ON INTER-REGIONAL MIGRATION AND TRAFFIC FLOW IN JAPAN

Power transformers. Special transformers Railway

A Design of DC/DC Converter of Photovoltaic Generation System for Streetcars

Kinetic energy recovery on railway systems with feedback to the grid

Shinkansen Investment before and after JNR Reform. Institute of Transportation Economics in Japan Fumio KUROSAKI, Ph.D.

ELEVATOR TRAVELING CABLE - DESIGN EVOLUTION

Estimation of electrical losses in Network Rail Electrification Systems

2012 San Francisco Colloquium

Product Data Bulletin

Current Status of Hokkaido Shinkansen

POWER TRANSMISSION FROM OFFSHORE WIND FARMS

DISCONNECTORS AND LOAD SWITCHES for railways

AMSC s Superconductor Cable Technologies for Electric Utilities

SIZING THE PRIMARY POWER SYSTEM FOR RESISTANCE WELDERS

Knowing the FACTS. FACTS that enhance power quality in rail feeder systems

Transformerless UPS systems and the 9900 By: John Steele, EIT Engineering Manager

Braking Systems. Railway Technology Today 7 (Edited by Kanji Wako) Izumi Hasegawa and Seigo Uchida. Technology. Early Brakes

International System Summary: JAPAN

1. The diagram below represents magnetic lines of force within a region of space.

Features and Economic and Social Effects of The Shinkansen

RAILWAY CATENARY SYSTEMS. Components and Systems for the Electrification of Railway Lines. ibemo

Introduction. Harmonics and IEEE 519 Page 1 of 19

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

Power Electronics. Prof. K. Gopakumar. Centre for Electronics Design and Technology. Indian Institute of Science, Bangalore.

What Is Regeneration?

Power Electronics Technologies for Railway Traction Systems

Globalization of Higher Education in Japan

SWITCH-MODE POWER SUPPLY CONTROLLER PULSE OUTPUT DC OUTPUT GROUND EXTERNAL FUNCTION SIMULATION ZERO CROSSING INPUT CONTROL EXTERNAL FUNCTION

Three-Phase Electric Power Distribution for Computer Data Centers

(lie Chicago, Milwaukee and St. Paul Railway

Inverter / Charger Installation General Operations and AC and DC Connections

FREQUENCY CONTROLLED AC MOTOR DRIVE

Agilent Technologies. Troubleshooting Three-Phase AC Motors with U1210 Series Handheld Clamp Meters. Application Note

EET272 Worksheet Week 9

Precision Miniature Load Cell. Models 8431, 8432 with Overload Protection

Electric Power Distribution

Power System Harmonics

The electrical energy produced at the gen

7. Reactive energy compensation

WIND TURBINE TECHNOLOGY

POWER FACTOR CORRECTION

Subminiature Load Cell Model 8417

4 SENSORS. Example. A force of 1 N is exerted on a PZT5A disc of diameter 10 mm and thickness 1 mm. The resulting mechanical stress is:

Network Standard Advice No. 1420C 9/6/2011

Improvements of Reliability of Micro Hydro Power Plants in Sri Lanka

HVDC-VSC: transmission technology of the future

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK

Public relations activities of Kansai Electric Safety Inspection Association concerning safe use of electricity

Survey of Harmonics Measurements in Electrical Distribution Systems

HARMONIC DISTORTION IN THE ELECTRIC SUPPLY SYSTEM

New Guided Urban Transit Systems in Japan

Electricity Disasters and Roles of Electrical Safety Inspection Associations in Japan

525-MVA Generator-motor and Thyristor Starter Put into Service at the Tokyo Electric Power Co., Inc. s Kannagawa Hydroelectric Power Station

2. A conductor of length 2m moves at 4m/s at 30 to a uniform magnetic field of 0.1T. Which one of the following gives the e.m.f. generated?

Circulating Current Relay. Type IRXm

Cable Solutions for Servo and Variable Frequency Drives (VFD)

Current Limiting Protector For Systems rated kV and continuous currents through 5000A.

Line Reactors and AC Drives

RC NETWORKS SALES GUIDE

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID

APPLICATION NOTE How to Deal with Electrical Noise and Interference in the Measuring Chain using a NEXUS

High Performance Railway Power

Electric Power Business. Electric Power-Related Business

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Power Supplies. 1.0 Power Supply Basics. Module

HIGH FREQUENCY TRANSFORMER WITH TRANSFORMER SWITCHOVER

Appendix 7. Conceptual Design of Electrification System. December 2010

Hyperlinks are Inactive

GenTech Practice Questions

Summary Report of Basic Survey on Wage Structure (starting salary)

CONTROLS DATA MANAGEMENT PROCESS AUTOMATION EUROCUBE. General purpose single phase thyristors and solid state relays Product data.

LOW COST MOTOR PROTECTION FILTERS FOR PWM DRIVE APPLICATIONS STOPS MOTOR DAMAGE

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE

Federal Wage System Job Grading Standards for Electric Power Controlling, Table of Contents

Motor Protection Voltage Unbalance and Single-Phasing

PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY

UrEDAS, URGENT EARTHQUAKE DETECTION AND ALARM SYSTEM, NOW AND FUTURE

HVDC Light, a tool for electric power transmission to distant loads

HERZ-Thermal Actuators

Engineering Education Programs at Bachelor Level. Accredited by JABEE Last updated: 27 December, 2012

Variable Frequency Drive Troubleshooting with U1610A/U1620A

TECHNICAL MEMORANDUM

KINETIC ENERGY RECOVERY SYSTEM BY MEANS OF FLYWHEEL ENERGY STORAGE

AS COMPETITION PAPER 2007 SOLUTIONS

DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS

The Intelligent AX1 Switchgear for Medium Voltage

How To Monitor Water Penetration In A Cable Screen

Contactless Power Transfer : Inductive charging of EV

Maintenance and Management of JR East Civil Engineering Structures

An extended EMC study of an electrical powertrain for transportation systems

Principles of Adjustable Frequency Drives

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO

Transformers. Special transformers Reactors products

Reyrolle Protection Devices. 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy

Aerial Fibre Optics. Complete One Stop Solution for Aerial Fibre Optics. OPGW Cable and Fittings for OPGW

Energy efficiency and fuel consumption of fuel cells powered test railway vehicle

Transcription:

echnology Technology Railway Technology Today 3 (Edited by Kanji Wako) Railway Electric Power Feeding Systems Yasu Oura, Yoshifumi Mochinaga, and Hiroki Nagasawa Introduction Electric power technology in the railway industry refers to the means of supplying good-quality electric power to the electric motors. It primarily consists of power conversion technology at sub-stations, feeding circuits for DC and AC feeding systems, and the structure, materials, measurement, and maintenance of the electric overhead lines. Power collection via the overhead line and pantograph, introduced nearly 100 years ago early in the history of electric railways, remains basically unchanged in physical appearance. However, technological developments during the past century have done much to greatly increase the current capacity, speed, and safety. Today, the capacity is more than sufficient to drive modern super high-speed trains. This article discusses all aspects of electric power supply systems for railways, ranging from the history of electrification of Japanese railways to today s sophisticated power supply facilities. It also compares them with their counterparts in other countries. World Railway Electrification Systems Table 1 shows various feeding systems around the world and the electrification distances. The history of electric railways dates back to 1835 when T. Davenport fabricated a model electric car powered by voltaic cells and put it on public exhibition. The first practical electric cars debuted in 1879 when a 150- dc, 2.2-kW, bipolar motor pulled three passenger cars at a maximum speed of 12 km/h at the Trades Exhibition in Berlin. In 1881, Siemens Halske built the world s first electric railway in Lichterfelde marking the first passenger electric railway. Electric operation is often preferred on railways with many long tunnels or on underground railways because the energy efficiency is higher than steam or diesel locomotives and does not involve onboard combustion. The high tractive force also makes electric operation suitable for lines running through hilly regions. As a consequence, electric train operation made remarkable progress. It started first with direct-current feeding systems capable of driving a DC motor directly and offering high tractive force and easy speed control. Although a 3000- dc feeding system is widely used in many other countries, some Japanese railways using DC rely on a 1500- dc system. The other alternating-current feeding system originated in Europe using a singlephase, commutator-type motor. Special low frequencies such as 25 Hz and 16.66 Hz were introduced in Austria, Germany, Table 1 DC System Type Japan 1 km % km % World (including Japan) Main Countries Less than 1,500 915 5 5,106 2 Germany, UK, Switzerland, USA 1,500 to 3,000 (Mostly 1,500 ) 3,000 or more (Mostly 3,000 ) 10,484 61 22,138 9 and other countries to minimize rectification failures. Later advances in silicon commutator technology paved the way for AC feeding systems using commercial frequencies in France and elsewhere. The 25-k system is used widely around the world while Japan relies on a 25 k system for shinkansen and a 20-k ac feeding system for conventional railways. (In this article, conventional means all JNR/ JR narrow-gauge lines, all non-jr railways, and the Akita and Yamagata shinkansen, which were converted to standard gauge from narrow gauge.) The three-phase, alternating-current feeding system is used with induction motors in Europe for railways with steep mountain grades, while a 600- system, featuring speed control by a power converter, is used in Japan for new urban transit systems. World Electric Railway Feeding Systems and Electrified Distances (1996) 78,276 33 France, Spain, Netherlands, Australia Russia, Poland, Italy, Spain, South Africa Singlephase 50 Hz Less than 20 k 245 0 France, USA AC 60 Hz 20 k 3,741 22 3,741 2 25 k 2,037 12 84,376 36 Russia, France, Romania, India, China 50 k 1,173 0 USA, Canada, South Africa 25 Hz 11 k to 13 k 1,469 1 USA, Austria, Norway 16.66 Hz 11 k 120 0 Switzerland 15 k 35,461 15 Germany, Sweden, Switzerland Three-phase AC 30 0 43 0 Switzerland, France Unknown 3,668 2 Kazakhstan 2, France Total 17,207 100 235,816 100 Notes: 1 Statistics include Japanese subways and AGTs. 2 Kazakhstan is 3,528 km (3,000 dc and 50 Hz 25 k ac) but details are not known. Sources: (1) Railway Electrical Engineering Association of Japan, vol.8, no.10, pp.3 5, Oct. 1997 (2) Ibid., vol.8, no.11, pp. 77 78 and pp. 81 83, Nov. 1997 48 Japan Railway & Transport Review 16 June 1998

Figure 1 History of Railway Electrification in Japan* History of Railway Electrification in Japan Commercial operation of electric railways in Japan dates back to 1895 when a 500- dc tram system was started in Kyoto. The first electric railway owned by the Japanese Government Railways began operation in 1906 between Ochanomizu and Nakano in Tokyo, which used to belong to Kobu Railways before being purchased by the government. The 600- dc system was later replaced by a 1200- dc system to prevent voltage drop. In 1922, it was replaced again by a 1500- dc system when the section between Yokohama and Kozu was electrified. The 1500- dc system is still used today by all DC electric railways in Japan. The postwar increase in transportation demand in Japan led to the introduction of more powerful electric locomotives around 1950. At that time, it was feared that the 1500- dc system had reached its limit, and a study was started on railway electrification based on commercialfrequency, single-phase alternating current. After a successful demonstration test on the Senzan Line, the first commercial operation using an electric locomotive started in 1957 on the Senzan and Hokuriku Lines, soon followed by a 20- k single-phase, alternating-current system using a step up or boosting transformer (BT) to minimize inductive interference in telecommunication lines. In 1964, the Tokaido began operations using the BT feeding system, marking the first high-speed train operation with a maximum speed of 210 km/h. However, it soon faced maintenance and other technical problems associated with the large collection current requiring complex anti-arcing designs. This led to a study of the auto transformer (AT) feeding system, which was introduced on the Yatsushiro-Nishi Kagoshima section of the Kagoshima Line in 1970, and on the Shin Osaka Okayama section of the Sanyo 0Electrification Ratio (%) Electrified Distance (km) 60 40 20 12,000 10,000 8,000 6,000 4,000 2,000 0 1906 1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 Year Note: * Including Japanese Government Railways, Japanese National Railways (JNR, from June 1949 to March 1987) and JRs, but excluding private railways in 1972. Today, the AT feeding system is the standard for all AC electric railways in Japan. Figure 1 shows the history of railway electrification in Japan from the era of the Japanese Government Railways until the present JRs. Figure 2 maps the various systems in Japan. Roughly speaking, the 1500- dc system is used on the conventional railways in Honshu (Kanto, Tokai, Kansai, and Chugoku districts) and Shikoku, while the 20-k ac system is mainly used in Hokkaido, northern Honshu (Tohoku and Hokuriku districts), and Kyushu. All shinkansen use the 25- k ac system. In contrast, most private railways rely on the 1500- dc system, while the 600- or 750- dc system is used by subways and some other railways. arious Feeding Systems From power station to railway sub-station The electric power generated by power stations is carried to electric railway substations by transmission lines. JR East has Electrified Distance AC, Conventional railways DC, Conventional railways JNR 10-year Financial Restructuring Plan 3rd Long Range Plan 2nd 5-year Plan 1st 5-year Plan Electrified distance Electrification ratio Conventional railways AC electrification 3,682.3 km Conventional railways DC electrification 6,215.0 km 2,036.5 km Conventional railways 9,897.3 km Electrification ratio 53.9% its own hydroelectric power station in Niigata Prefecture (on the Shinano River) as well as a thermal power station in Kawasaki City in Kanagawa Prefecture. These two power stations supply the railways in the Tokyo metropolitan area. In Japan, the receiving voltage at substations for direct-current electric railways is usually extra-high tension at 22, 66, or 77 k. This is converted to 1200 by a transformer, and then to direct current by a rectifier at the rated voltage of 1500 (no-load voltage of 1620 ). Subways and some private railways use 600 or 750 dc. The receiving voltage for alternating-current conventional electric railways is an extra-high voltage of 66, 77, 110, or 154 k. The shinkansen use receiving voltages of 77, 154, 220, or 275 k. The conventional railways use a feeding voltage of 20 k, and the shinkansen use singlephase at 25 k. Japan Railway & Transport Review 16 June 1998 49

Technology Figure 2 Map of Railway Electrification of JR Group in Japan Otaru Asahikawa Conventional Railways DC AC Akita Aomori Morioka Kushiro Muroran Hakodate Nishi Izumo Tottori Kinosaki Kanazawa Fukui Itoigawa Nagano Murakami Niigata Yamagata Fukushima Sendai Kokura Hakata Sasebo Oita Nagasaki Kumamoto Hiroshima Fukuyama Iyoshi Okayama Himeji Kyoto Shin-Osaka Tokushima Kochi Wakayama Nagahama Gifu Kofu Nagoya Shizuoka Kuroiso Utsunomiya Omiya Toride Tokyo Shingu Kagoshima Miyazaki Figure 3 Three-phase AC Transformer Rectifier Structure of a DC Feeding System 6-pulse Rectifier High-speed circuit breaker 3-phase AC Sectioning post 3-phase AC + + 1,500 dc 1,500 dc Electric car 12-pulse Rectifier Three-phase AC Transformer Rectifier Feeder Contact Rail DC feeding system A direct-current feeding system features a three-phase bridged silicon rectifier for conversion from alternating to direct current. Since the three-phase rectifier uses a 6-pulse system, it causes lower harmonics in the AC side and distortion in the voltage waveform, lowering the power quality. To reduce the harmonics, a more-modern rectifier design using a 12-pulse system featuring two sets of 6-pulse rectifying circuits, with AC input voltage phases 30 apart, connected in series or parallel, is used. Figure 3 is an example showing the structure of a DC feeding circuit connected to the nearest sub-station. Section and tie posts are sometimes used to prevent voltage drops on double tracks where substations are located far apart. In this case, the up and down tracks are connected by 50 Japan Railway & Transport Review 16 June 1998

a high-speed circuit breaker. The distance between sub-stations is about 5 km on metropolitan trunk lines and 10 km on other lines. Efforts are being made to introduce regenerative cars on DC electric railways in order to reduce the weight and save energy. They are designed to convert the kinetic energy into electric power during deceleration and return it to the overhead lines. However, the regenerated power would be wasted if there are no cars in the section to use it. This loss can be prevented by thyristor rectifiers, thyristor inverters, thyristor chopper resistors, or simultaneous up and down track feeding systems. Such devices are used on some sections; Figure 4 shows an example of a thyristor inverter. In this system, the motive power is supplied from a rectifier, and when the regenerative power exceeds the motive power requirement, the inverter is activated automatically to supply power to stations, etc. AC feeding system Since three-phase power from the power utility is converted to two single phases, to ensure that the current is as close as possible to the three lines of the threephase side, one separate phase is fed to each of the overhead up and down tracks. arious methods can be used to connect the feeding transformers. Today, the Scott connected transformer (Fig. 5) is used to receive extra-high tension, and the modified wood-bridge connected transformer (Fig. 6) is used to receive extra-high voltage, with the neutral point directly grounded. Figure 7 shows the composition of an AC feeding circuit. It includes feeding AC sub-stations, sectioning posts for feed sectioning, and sub-sectioning posts for limited sectioning, all located along the tracks. The feeding sub-stations feed the two single phases converted from the three-phase source by a feeding transformer in the opposite track directions, Figure 4 Transformer Figure 5 Rectifier Feed to overhead line (UW is 3-phase and TF is 1-phase) Figure 7 Power Regeneration by Thyristor Inverter Scott Connected Transformer U T Main phase transformer T Teaser transformer F (N) W F (N) U Figure 6 Structure of an AC Feeding System Feeding sub-station SS Three-phase AC Transformer Regenerative inverter Subsectioning post SSP : Circuit breaker : Air section 3-phase 6.6 k ac bus Harmonic filter O Earth Sectioning Subsectioning post SP post SSP Modified Wood-bridge Connected Transformer W T Distribution transformer Station facilities, etc. 1,500 dc Regenerative car A phase Feeding sub-station SS F ST T B phase F ST: Step up transformer Down track Up track : Disconnecting switch : Phase-to-phase changeover section Japan Railway & Transport Review 16 June 1998 51

Technology Table 2 Feeding system BT AT Coaxial Feeding oltages and Distances between Sub-stations of arious AC Feeder Systems in Japan Feeding voltage (k) Conventional railways 22 with a 90 phase offset. Table 2 shows the feeding voltages and the distances between sub-stations of various AC feeding systems in Japan. BT feeding system Figure 8 shows the composition of a BT feeding circuit. A BT is installed every 4 km on the contact to boost the return circuit current on the negative line. Distance between sub-stations (km) Conventional railways 30 to 50 44 60 90 to 110 20 to 60 30 10 This design minimizes the inductive interference on telecommunication lines because the current flows to the rail only in limited sections. In particular, when an electric car passes a BT section, a large arc is generated in the section, and a large load current can cause a very large arc that can damage the overhead line. Consequently, capacitors are often inserted serially in the negative feeder to compensate for the reactance and reduce the amount of current intercepted by the pantograph, thereby reducing arcing, and also helping to prevent voltage drop. AT feeding system In the AT feeding system, the feeding voltage of the sub-station is twice the voltage supplied to the electric car. An AT, at every 10 km along the track, cuts the voltage to the overhead-line voltage as necessary. This is very effective in reducing inductive interference in telecommunications lines. Figure 9 shows the composition of an AT feeding system, and the photograph below shows an external view of an AT designed for shinkansen. In Japan, the AT is designed with a turn ratio of 1:1 and the sub-station feeding voltage is twice the overhead-line voltage. This system is ideal for high-speed and largecapacity electric cars because there are no large voltage drops nor arcing sections. Figure 8 Sub-station I Structure of NF-based BT Feeding System BT section Boosting transformer (BT) Boosting I Electric car NF capacitor Negative feeder Contact Rail Coaxial cable feeding system As shown in Figure 10, the coaxial cable feeding system features a coaxial cable laid along the track. Every several kilometers, the inner conductor is connected to the contact and the outer conductor is connected to the rail. The cable itself is very expensive but the conductor Figure 9 Structure of AT Feeding System Sub-station AT 2 I/2 Auto transformer AT I AT Contact CPW Electric car Rail Feeder Protective External view of AT (60/30 k, 7500 ka) (RTRI) 52 Japan Railway & Transport Review 16 June 1998

Figure 10 Coaxial Cable Feeding System Overhead Line Systems Sub-station I Electric car layout is simple, making it ideal for use where space is limited. Japan is the only country that uses this system (the Tokyo sections of the Tohoku and Tokaido ). In comparison to the overhead line, the coaxial power cable has an extremely small round-trip impedance. Therefore, the load current is boosted in the coaxial power cable from the connection with the overhead line. This results in a rail current distribution similar to that of the AT feeding system, significantly reducing the inductive interference in telecommunication lines. I Coaxial power cable Contact Rail Negative feeder AC feeding system In an AC feeding system, faults are detected by a combination of a distance relay and an AC I-type fault selective relay (Figure 11). The distance relay monitors the overhead line impedance from the sub-station and recognizes an event as a fault when the impedance falls within a predetermined rectangle on the impedance plane. As with DC systems, the AC I-type fault selective relay detects the change in current. Furthermore, locators are used to mark fault points based on the current distribution, so any fault can be corrected promptly. Catenary system An electric railway takes its power for the electric motors, lights, air conditioning, etc., from the overhead line using the pantograph on the roof. The pantograph is in constant contact with the overhead line (contact ) located about 5 m above the rails, whether the train is moving or not. Therefore, the overhead line must always be located within the pantograph range, and the pantograph must always maintain contact with the overhead line to supply uninterrupted, good-quality power at all times. To meet these requirements, the overhead equipment is generally designed bearing the following in mind: Must have characteristics meeting train speed and current requirements Must be at uniform height above rail to optimize pantograph power collecting characteristics, so entire equipment must have uniform spring constant and bending rigidity Must have minimum vibration and Detecting Feeding Faults Figure 11 Protective Zone of AC Electric Railway Protective Relay Feeding circuit faults can be caused by electric car faults, overhead line faults, flying objects, and animals (birds, snakes, etc.). The high voltage causes a high fault current and, consequently, a protective relay is used to instantly detect any fault and trip a power circuit breaker. DC feeding system In a DC feeding system, typically, the current for the electric car increases smoothly, but a fault current always increases abruptly. A I-type fault selective relay at sub-stations is used to detect faults based on this difference. Reactance SS Impedance of contact line Distance relay SP Resistance SS: Sub-station SP: Sectioning post Thyristor controlling car Powering l relay PWM controlling car Powering Japan Railway & Transport Review 16 June 1998 53

Technology Figure 12 Overhead Lines of World High-Speed Railways 18.0 m 18.0 m 5.0 m 9.0 m 1.8 m 5.0 m 50 m 15 m 15 m 65.0 m German high-speed line 2 3.5 3.5 2 3.5 4.5 4.5 63 m 4.5 4.5 3.5 French TG Southeast 1 m 6.0 m 1.4 m 60 m 9.0 m French TG Atlantic Italian high-speed line Table 3 Comparison of Overhead Line Constants on Dedicated High-speed Lines Item Japan TG Southeast France TG Atlantic Germany Catenary type Heavy compound type Stitched and simple Simple Stitched and simple Twin stitched and simple Standard span [m] 50 63 (Stitched 15) 63 65 (Stitched 18) 60 (Stitched 14) Standard height [m] 5.0 4.95 4.95 5.3 4.85 System height [mm] 1,500 1,400 1,400 1,800 1,400 Wire grade Suspended Auxiliary suspended Contact St 180 mm 2 (1.450 kg/m) Cu 150 mm 2 (1.375 kg/m) Cu 170 mm 2 (1.511 kg/m) Bz 65 mm 2 (0.59 kg/m) Bz 65 mm 2 (0.59 kg/m) Bz11 70 mm 2 (0.63 kg/m) Bz 35 mm 2 Bz11 35 mm 2 (0.31 kg/m) CdCu 120 mm 2 Cu 150 mm 2 (1.33 kg/m) CuAg Ri 120 mm 2 (1.08 kg/m) Italy CdCu 153.7 mm 2 (1.42 kg/m) (0.30 kg/m) Contact line total density [kg/m] 4.34 1.65 1.92 1.71 2.77 2 Catenary tension Suspended [N] 24,500 14,000 14,000 15,000 18,400 Auxiliary suspended [N] CuAg 151.7 mm 2 (1.35 kg/m) 14,700 4,000 (Stitched ) 2,800 (Stitched ) 2,900 (Stitched ) Contact [N] 14,700 14,000 20,000 15,000 14,700 (Total tension) [N] (53,900) (28,000) (34,000) (30,000) (33,100 2) Wave propagation velocity of contact [km/h] β (train speed/ wave propagation velocity) 355 414 441 424 376 0.68, 0.76 (= 240, 270/355) 0.65 (= 270/414) 0.68 (= 300/441) 0.59 (=250/424) 0.66 (= 250/376) Pre-sag None 1/1,000 1/1,000 1/1,000 1/1,000 54 Japan Railway & Transport Review 16 June 1998

motion to ensure smooth pantograph passage during high-speed operation or strong winds Must have strength to withstand vibration, corrosion, heat, etc., while maintaining balance with reliability and operating life span Figure 12 compares the catenary equipment for high-speed trains in different countries. In Japan, compound catenary equipment consisting of three longitudinal s is used for shinkansen, while simple or stitched catenary equipment is used in Europe. The Italian high-speed line uses twin catenary equipment to supply the large current for the 3-k dc electrification. Table 3 compares the constants of these various catenary systems. Compound catenary systems feature less pantograph vertical motion and larger current capacity but require a larger number of components resulting in a more complex design. In Europe, pre-sag is often used to compensate for the large vertical motion of the pantograph in the simple catenary system. Pre-sag refers to a special design feature in which the height of the contact is lower at the centre of the span by an amount equal to around 1/1000 of the span. In real terms, generally, the contact height is 20 or 30 mm lower than the supports at the centre of the span, thereby suppressing the pantograph vertical motion. This design is effective for the overhead lines on the French and German high-speed lines which have a large amplitude, but is less effective for overhead lines with small amplitudes like the shinkansen and the Italian high-speed line. Lateral wave propagation The most critical constants for the mechanical performance of the overhead line are the weight and tension per unit length. The total tension is relative to the pushup force of the pantograph and is closely related to the vertical motion of the overhead line. It is 54 kn for shinkansen and Heavy compound overhead line of Tohoku (RTRI) Simple catenary equipment of Nagano-bound shinkansen (RTRI) 28 to 34 kn for the French and German systems. The Italian system has a total tension of 66 kn because it uses a twin catenary system with a larger size. The pantograph push-up force is roughly 70 to 80 N for Japan, 130 to 250 N for France and Germany, and 200 to 300 N for Italy. This means France and Germany have an overhead line amplitude about four times greater than that of Japan. Generally speaking, greater stability results from smaller overhead line amplitude. It also reduces the fault frequency and damage to components. The French and German systems seem to allow larger amplitudes at the cost of fewer pantographs. The square root of the ratio of the contact tension to the weight per unit length represents the velocity of the lateral wave propagating along the. This is the most important parameter in overhead line design. In railway technology, this velocity is called the wave propagation velocity and is recognized as the critical speed. Table 3 shows the wave propagation velocity and the ratio of the train speed to the wave propagation velocity (β). Simulation and experiments have verified that as the train speed approaches the wave propagation velocity, the overhead line amplitude and local bending increase, making it harder to maintain contact between the pantograph and overhead line. It is estimated that the resulting performance drop becomes apparent when the train speed exceeds 70% to 80% of the propagation velocity. At this speed, loss of contact with the line increases greatly, and in extreme cases, the overhead line itself can be destroyed. Consequently, the contact constant must be set so that the propagation velocity is significantly faster than the train speed. The propagation velocity can be increased by laying a lighter at a higher tension. In the case of a pure copper contact, after considering safety factors, the maximum achievable speed (neglecting wear) is around 500 km/h. Any further increase in the wave propagation velocity can only be achieved by using s with a higher tensile resistance per weight unit length. In Japan, s in use or under development include copper alloys, and other alloys, as well as compound s such as aluminium-clad steel, and copperclad steel s. In Table 3, the β values are all 0.7 or lower, indicating that all countries have selected values within the above-mentioned stable velocity range for train speeds. The photograph (above left) shows a heavy compound overhead line. The Naganobound (Takasaki Nagano section), which started operations in October Japan Railway & Transport Review 16 June 1998 55

Technology Figure 13 Figure 14 Tensionless Third Rail Arrangement Wall (tunnel, etc.) 6 m max. Overhead rigid conductor system and pantograph Protective plate Third rail (conducting steel rail) Insulator Overhead Rigid Conductor System 410 mm Running rails Insulator T-shaped mount Long ear Contact (RTRI) 1997, uses the simple catenary overhead equipment found commonly in Europe. This system was chosen for economy because the less-frequent train operation consumes only a small proportion of the current-carrying capacity. This shinkansen uses a 110-mm 2 copper-clad steel (Fig. 15b) with a tension of 20 kn to withstand the train operating speed of 260 km/h. This is the first simple catenary system for highspeed operation in Japan. Third-rail conductor In the third-rail conductor system, the collector is laid next to the rail to save space in restricted subways. This system dates back nearly 70 years to 1927 when it was first introduced on the Ginza Line of the Tokyo Rapid Transit Authority (TRTA). The voltage is 600 or 750. Figure 13 shows the structure. In Japanese subway systems, it is shielded at the top and on one side for safety; a flat shoe collects current directly from the top of the rail, which is supported by insulators every 2.5 to 5 m. This third rail system is limited to a maximum speed of around 70 km/h due primarily to the underground conditions in the Tokyo metropolitan area. However, experiments show it is capable of serving speeds exceeding 100 km/h. Overhead rigid conductor system The overhead rigid conductor system has been developed as an overhead line for direct links between subways and suburban railways. It features toughness and small space requirements (Fig. 14 and opposite photograph) and prevents broken s and other accidents, especially in the subway sections. The maximum speed has been limited to 90 km/h primarily due to the short distances between stations and frequent curves in the metropolitan subways. The system runs at a voltage of 1.5 k to allow direct connections to suburban railway systems. It has been used for nearly 40 years on the TRTA Hibiya Line. 56 Japan Railway & Transport Review 16 June 1998

Figure 15 Contact-Wire Cross Sections weight reduction is critical. Supports are often made of galvanized steel. High-quality, inexpensive porcelain insulators are common, but polymer insulators with excellent insulation characteristics have been introduced recently. Maintenance of Overhead Lines (a) Hard-drawn copper 3 mm 3 mm 3 mm Materials in Overhead Lines (b) Copper-clad steel (c) Aluminium-clad steel minium-clad steel. The messenger is often made of galvanized stranded-steel for economy and high mechanical strength. Harddrawn copper stranded s are also used in many sections requiring larger current capacity. Messenger fixtures require highstrength and corrosion-resistant materials, such as stainless steel and copper alloy. Aluminium alloy is preferred where Overhead line inspection cars The overhead line is a very long linear structure and, as such, is subject to sliding stress from the pantograph. It is also subject to a stress due to rain, wind, snow, ice, and other natural phenomena. Consequently, the overhead line is a potential source of accidents involving broken s due to corrosion and wear. Such accidents require many hours for repair, so maintenance is essential. Maintenance begins with accurate diagnosis of the present condition of the overhead line, often performed from a moving car. The shinkansen overhead lines are inspected every 10 days using Doctor Yellow, a seven-car electric facilities and track diagnostic system (JRTR 15, p. 43). Conventional lines use a two-car system. The measured items include the contact The overhead line equipment consists of the contact s, fixtures, and supports. The contact has a round cross section with grooves at the 2 and 10 o clock positions, used for hanging the from a fixture. Conventionally, contact s have been made of hard-drawn copper. Copper has very low electrical resistance and excellent corrosion resistance, making it an ideal material for contact s. To provide higher mechanical strength, soft copper is hard drawn into contact s. In Japan, contact s composed of copper with 0.3% tin are used widely to improve wear characteristics. Tunnel sections often use silver-copper alloy contact s for extra heat resistance with the aim of preventing broken s due to train fires. Recently, such copper-silver alloy contact s are being replaced by copper-tin alloy contact s. A recent addition to the shinkansen are copper-clad steel contact s designed to increase the tension for higherspeed operation. Figure 15 shows cross sections of the conventional type, and the two variations: copper-clad steel, and alu- External view of diagnostic car for electric facilities (RTRI) Japan Railway & Transport Review 16 June 1998 57

Technology height above rail, deviation, wear, acceleration of pantograph head, and contact loss. For shinkansen, the measured data are processed by a central computer and the results are sent to the relevant maintenance crews. Some items cannot be checked from a moving car. These include corrosion of the feeding s and loose screws, which are inspected manually during normal maintenance work. When lines need replacement, the work is performed using special cars. The above photograph shows a six-car system designed to replace shinkansen contact s. Automated diagnosis and repair is a recent topic for railway engineers and special efforts are being made to develop robots for this purpose. Contact replacement work car (RTRI) Robotics Overhead line systems require dangerous work at height. A self-powered feeding line robot with eddy current sensors has been developed and put into operation to locate cross-sectional area loss due to corrosion. Feeder line inspection robot (RTRI) Kanji Wako Mr Kanji Wako is Director in Charge of Research and Development at RTRI. He joined JNR in 1961 after graduating in engineering from Tohoku University. He is the supervising editor for this series on Railway Technology Today. Yasu Oura Mr Yasu Oura joined JNR in 1967 after graduating in electrical engineering from Shibaura Institute of Technology. He is Chief Manager of the Technological Development Department at the Railway Technical Research Institute, which he joined in 1987. Yoshifumi Mochinaga Dr Yoshifumi Mochinaga joined JNR in 1967. He graduated in electrical engineering from the Science University of Tokyo in 1980. He is a Manager in the Power Supply Technology Development Department at RTRI, which he joined in 1987. He obtained his doctorate in AC feeding systems from the Science University of Tokyo in 1994. Hiroki Nagasawa Dr Hiroki Nagasawa joined RTRI in 1972 after graduating in mechanical engineering from Tohoku University. He is engaged in development of current collection systems, especially overhead line materials. He obtained his Ph.D. in tribology from Tohoku University in 1996. 58 Japan Railway & Transport Review 16 June 1998