Repair of a Hull 15 m below the Waterline



Similar documents
Rudder and Rudder Horn Repair on the Bulk Freighter Sophia D

UNDERWATER MAINTENANCE AND REPAIR IN LIEU OF DRY DOCKING. USS MIDWAY Museum Installation of Hull Suction and Discharge Blank Patches

Field Welding Inspection Guide

Part B Repair Quality Standard for Existing Ships

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/ Stud Welding

FIELD ACCEPTANCE OF FIELD WELDING GUIDE

11. NONDESTRUCTIVE TESTING

Structural welding is a process by which the parts that are to be connected are heated and

TABLE OF CONTENT

Oil and Gas Pipeline Design, Maintenance and Repair

Part 0 - Classification and Surveys Classification and Surveys I

TITANIUM FABRICATION CORP.

Chapter 5 - Aircraft Welding

WORD DEFINITION WORD (NATIONAL LANGUAGE)

Part A Shipbuilding and Remedial Quality Standard for New Construction PART A - SHIPBUILDING AND REMEDIAL QUALITY STANDARDS FOR NEW CONSTRUCTION

SECTION GROUND WATER STORAGE TANKS

Job Ready Assessment Blueprint. Welding. Test Code: 4172 / Version: 01. Copyright All Rights Reserved.

Itemized RAI Responses

CHAPTER 13 LOAD HOOKS

CLASSIFICATION NOTES

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

VLCC Structural Design - Past, Present and Future

Thickness measurement and close-up survey guidance

A Beginners Guide to Flux Cored Arc Welding

Part A Shipbuilding and Remedial Quality Standard for New Construction PART A - SHIPBUILDING AND REMEDIAL QUALITY STANDARDS FOR NEW CONSTRUCTION

INDIAN STANDARDS (BIS) ON WELDING

M/V Eleranta IMO Water Ballast Tank Inspection Report. China Shipping International Shipyard Co. Ltd (CSIS), Changxing Island, Shanghai

Simple Damage Control Aboard

GK Packing System Welding Instructions

SAMPLE TEST QUESTIONS STEAMFITTER/PIPEFITTER - ITA WEBSITE

Use of Steel Grades for Various Hull Members - Ships of 90 m in Length and Above

Essentials Welding QA/QC Plan Sample

Pressure vessel basics for all engineers

ASK THE EXPERT: Burner Troubleshooting Information & Maintenance

Structural Steel Welding

QUALIFICATION OF PROCEDURE AND WELDER. (19 February 2014)

FRAME DOOR OPENING, DOOR AND SIDE PANEL OUTER

Duplex Stainless Steel Fabrication. Gary M. Carinci TMR Stainless Consultant for International Molybdenum Association

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

How To Repair A Steel Pier With A Watertight Frame

Specification of the cooling- water-piping for SESAME Storage Ring and the Radio-Frequency System

3.3 Welding and welded connections

SECTION COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

Gasoline Engines and Water Intrusion

Crevice Corrosion on Stainless Steel Propeller Shafts

QUALITY & TECHNICAL CERTIFICATIONS

Welding Codes and How They're Used (DOD) (ANSI). (AWS), (ASME) (API). not American Welding Society AWS D1.1 AWS D1.2 AWS D1.3 AWS D1.4 AWS D1.

Welding Procedure Guide

U.S.S. TEXAS (BB-35)

PMCap Local Thin Area Repair and Restoration Component. for Pressure Retaining Items

Welding of Boilers, Pressure Vessels and Pressure Piping

ASTM A860/A860M-09 Standard Specification for Wrought High Strength. Ferritic Steel Butt Welding Fittings. 1. Scope :- 2. Reference Documents :-

IHSS-N1 WELDED HONEYCOMB CORE SPECIFICATION. Generated: Sergiy Papyshev Engineering. Approved: Don Prysi Manufacturing. Approved: Merzuk Ramic Quality

Corrosion protection of crude oil cargo tanks new IMO regulations

MARC5001A Employ tools, equipment and materials in a shipboard context

A.1 Obligations and reporting of the gaining Society. Plans to be Submitted by the Owner to the Gaining Society

WELDING TECHNOLOGY DEGREES AND CERTIFICATES. Welding Technology Degree. Shielded Metal Arc Plate and Pipe (270 hours) Certificate

APPLICATION COMPETENCY FIELD

Section VIII, Div. 1 (Rules for Construction of Pressure Vessels).

FABRICATION AND TESTING OF OFFSHORE STRUCTURES

DNVGL-OS-C401 Edition July 2015

Vehicle Restraint Installation Manual

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1078

North Carolina FFA Association Agricultural Mechanics Career Development Event

Embedded Parts Introduction - Anchors

COASTAL BEND COLLEGE WELDING SYLLABUS (Revise 11/13) Intermediate Shielded Metal Arc Welding (SMAW)

STANDARD SPECIFICATION SECTION STEEL PIPE, FUSION-BONDED EPOXY LINED AND COATED

Nondestructive Testing: Why, When, What and How?

Evaluating Protective Coatings for Ballast Tanks

IN-SERVICE REPAIRS TO LEAKING ABOVE GROUND STORAGE TANK ROOFS

Wastewater Capital Projects Management Standard Construction Specification

TARIFF CODE and updates standard

Application of Welding Standards in Hong Kong. S. K. Babu Laboratory Manager - Foundation Techniques Ltd

Intershield 300 The industry benchmark in corrosion protection

James M. Pleasants Company

FedEx s Fire Suppression System

SECTION 3 SANITARY SEWER DESIGN

Stena S ,200 DWT Product/Chemical Tanker CONQUEST CONQUEROR CONCORD CONCEPT CONSUL CONTEST

DESIGN PROCEDURE JOINT CONFIGURATION

BASIC PRINCIPLES OF WELDING

725-R-599 PIPE LINING. (Revised ) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

Issue of the Guidelines on Prevention of Water Seepage in New Buildings

Apprenticeship Training Standard. Welder. Trade Code: 456A. Development Date: October 2007

D1.8 Seismic Supplement Welding Manual. A General Overview of AWS D1.8 Welding Code - Seismic Supplement

SPECIFICATION FOR PIPEWORK WELDING, INSPECTION, SUPPORTING AND TESTING

Apprenticeship and Industry Training

FIELD WELDER QUALIFICATION PROCESS

Guidelines for Securing by Welding of Chain Cable Studs in Service Guidance for Anchoring Equipment in Service

Avoiding Burning Through: Control the Inside Surface Temperature, Not the Pressure

Transcription:

Repair of a Hull 15 m below the Waterline Fig. 1 This 189 m vessel required an underwater repair after it had its hull pierced sufficiently enough to let seawater enter its water ballast tank. Since circumstances prevented the vessel from entering dry dock, the repairs had to be completed while it was afloat BY UWE ASCHEMEIER AND KEVIN PETERS UWE W. ASCHEMEIER (uwe@miamidiver.com) is the sr. welding engineer for the SubSea Solutions Alliance. KEVIN S. PETERS (kevin@miamidiver.com) is the president of Miami Diver LLC, a member of the SubSea Solutions Alliance. Accidents seem to happen at the most inconvenient times, so it is important to know who to turn to when they happen. When a 50,000-ton product tanker ended up with a hull breach while taking on cargo in a loading facility in Venezuela, the owner turned to Miami Diver LLC, a founding member of the Subsea Solutions Alliance, a global network of specialized underwater ship repair contractors that also includes Parker Diving Service LLC and Trident BV. The following is a chronological review of the events, from the accident, through damage review until the successful repair of the vessel. The Tanker The vessel is a 50,000 MT ice-classed product tanker (Fig. 1), built in 2009. The 183-m-long double-hull ship is classed by DNV and RINA. In the area of the damage, the hull is constructed from 13.5- mm-thick higher tensile steel AH36. The Accident In May 2012, the tanker was loading jet fuel in a tanker port in Venezuela. During the loading operation at the terminal, the tanker sank deeper into the water with every ton of cargo being 32

pumped into the tanks. Nobody knew that a submerged obstacle, most likely in the form of a broken pile, was hidden below the waterline, invisible to the officers and crew of the vessel. While increasing her draft through the increasing weight of the cargo, the submerged piling finally pierced its way through the hull of the vessel, allowing the ingress of seawater into the portside water ballast wing tank. Damage Assessment Despite the damage, the tanker left Venezuela and sailed to Aruba in the Caribbean Sea, where an initial evaluation of the damage was performed by a local dive company. After the assessment, the owner of the tanker contacted the Miami Diver office in Curaçao. The damage proved to be severe (Fig. 2), preventing the vessel from sailing to its destination. Class would only allow the vessel to continue the journey if the hull breach was fixed permanently. Since the vessel was fully loaded, dry-docking was out of the question. The repairs needed to be performed with the vessel afloat. It was discussed with the owner and class to sail to Curaçao and perform the repairs with the vessel at berth in the clear waters of the sheltered Caracas Bay. Miami Diver s engineering department developed a detailed repair procedure that was submitted and agreed to by the owner and class, suggesting a no condition once the repair was completed. Attending the Vessel With the arrival of the vessel in Curaçao, a team of divers, welders, and the welding engineer were deployed from Miami, Long Beach, and Curaçao to attend the vessel. The initial inspection dive revealed an approximate 400-500- mm hole in the hull of the vessel and deformed hull plating in the vicinity of the hull breach. In addition to the aforementioned damages, the bilge keel and grounding bar were also found to be damaged Fig. 3. The bilge keel and grounding bar had to be trimmed back to allow for the installation of the cofferdam and the insert plate. The trimmed bilge keel and grounding bar were mechanically profiled to match the original form. Templating, Engineering, and Building the Cofferdam To allow the repair work to be performed under dry conditions, a cofferdam was engineered by Miami Diver. To ensure that the cofferdam would be large enough to enclose the area of the deformed hull, divers laid out the area the cofferdam needed to cover and communicated the measurements to the engineering department. Since the damage was in the turn of the bilge, the transition between the flat bottom and sidewall of the ship, divers templated the contour of the area to be Fig. 2 Damage to the hull viewed from the outside. WELDING JOURNAL 33

Fig. 3 Schematic of the vessel showing where the hull was pierced and bilge keel damage. enclosed by the cofferdam. The area covered by the cofferdam needed to be large enough to cover the deformation in the hull caused by the impact. Based on information and sketches provided by the divers, the cofferdam was modeled to meet the required 4-times safe working load at 14 m depth. Complete built drawings were produced to ensure the cofferdam was built in accordance to the modeling profile. The cofferdam was built from 8-mm ASTM A36 steel in the facilities in Curaçao Fig. 4. Preparing the Insert Plate The deformed and breached shell plate section needed to be removed and replaced with a rectangular insert plate, approximately 2185 1422 mm in size, with the corners prepared with classrequired radii. The insert plate, fabricated from 15- mm-thick EH36 class-approved steel was cut to size, prepared for welding with an approximate 37.5-deg bevel and rolled to Fig. 4 The cofferdam under construction. match the curvature of the hull. The preparation of the insert plate was performed locally in Curaçao. The track with customized ceramic backing tiles develop by Miami Diver was fitted around the peripheral edge of the insert. Lifting lugs were welded onto the rec- 34

Fig. 5 Diver welder welding a lifting lug to the hull. WELDING JOURNAL 35

Fig. 6 Grinding performed to prepare the joint for welding. Fig. 7 Insert plate being installed. tangular insert plate to allow for easier handling. After preparation of the insert plate was completed, the plate was placed into the cofferdam. Installing the Cofferdam The cofferdam was fitted with a closed-cell foam gasket material around the outer perimeter. It was centered and installed over the breach and deformation, overlapping the weld zone 500 mm, to shield the welding area and heataffected zone. Weld fixtures were wet welded to the ship hull (Fig. 5) by diver welders to hold the cofferdam in place. After installation, the cofferdam was dewatered and checked for leaks prior to cutting and welding work to be performed from the inside. Removing the Damaged Shell Plate Section from the Inside The damaged section of the hull plating was removed by oxyfuel cutting from inside the cofferdam. The edges of the cut area (future weld joint) were ground smooth and beveled (Fig. 6) to approximately 37.5 deg. The corners were prepared with a 100 mm (4 in.) radii. Preparing the Weld Joint To allow unrestricted access for removal of the damaged hull section and installation of the new insert plate, frames needed to be cropped and/or temporarily removed. The welds between the web frames and hull were carefully removed by gouging the weld. In the area Fig. 8 Welding the root from inside the cofferdam. 36

Fig. 9 Large and small inserts as they appeared from the water side. of the intersection between the web of the frame and weld joint of the insert plate, weld access holes were removed from the web member, sufficient in size to allow unrestricted access to the weld joint to be welded and tested. Installing the New Shell Plating After preparation of the weld joint, the insert plate was pulled tight against the outside of the shell plating with a consistent root opening of about 10 mm. The plate was secured in place with weld fixtures Fig. 7. Prior to welding the insert plate, the previously cropped and/or removed frame members were reinstalled and tack welded into place. The preheat temperature of 80 C was controlled through heat-indicating crayons. Root Opening with Ceramic Backing Ceramic Inclusion While welding the root, welders experienced a popping of the ceramic backing resulting in undesirable rejectable inclusions in the root of the weld. It appeared that the ceramic was emerged in the seawater for too long, picking up moisture that could not be released through preheating. It was discussed with the owner and surveyors to cut a 510-660-mm manhole into the center of the insert plate, backgouge the root pass from the insert plate to remove all inclusions, and reweld the root from inside the cofferdam. The manhole was welded on ceramic backing. Both classification societies DNV and RINA agreed to the proposal. After completion of the weld between the insert plate and hull, the manhole was cut in the center of the insert plate to gain access to the root side of the original joint. The root pass was removed by carbon arc gouging, followed by cleaning the joint by grinding and rewelding the root with the SMAW process (Fig. 8) in the overhead position. Welding the Root from Inside the Cofferdam After welding was completed, visual and ultrasound inspection was performed on the weld between the insert plate and hull plating. The weld did not reveal rejectable indications. Reinstalling the Manhole Cut Out The weld joint of the insert plate for the manhole was prepared and welded on ceramic backing. It was subject to visual and ultrasound inspection after completion. The welds passed without rejectable indications Fig. 9. All temporary removed frames were reinstalled with weld sizes matching the original weld sizes. Welding Underwater Wet Welding Underwater wet welding was only performed to attach installation aids for the cofferdam, which were removed after completion of the work. All underwater wet welding was based on AWS D3.6:1998 Class A welding procedure qualifications (WPQ), employing the wet shielded metal arc welding process with Hydroweld FS electrodes. All welds were executed as multilayer fillet welds in T- and lap joints. WELDING JOURNAL 37

Fig. 10 Divers removing the cofferdam. Top Side Welding Top side welding was performed as a permanent repair in the dry. Top side welding was performed in accordance with the class-approved welding procedure specification (WPS), employing the flux cored arc welding process (FCAW) under a shielding gas consisting of 75% argon and 25% CO 2 and shielded metal arc welding (SMAW) process with class-approved E7018 low-hydrogen electrodes. Complete joint penetration welds were either welded on nonconsumable ceramic backing or backgouging the root and rewelding the root side of the joint. Removing the Cofferdam After removal of the cofferdam (Fig. 10), previously welded installation aids were removed and any weld metal remaining on the hull was ground flush. Underwater magnetic particle (MT) testing was performed on the ship hull where installation aids for the cofferdam were removed. Corrosion Protection After welding was completed and the welds passed nondestructive examination, corrosion protection in the form of Hycote 151, an underwater, two-component, polyamine-cured epoxy coating, was applied over the welds, areas adjacent to the welds, and areas where the corrosion protection had been removed or burned off during welding. This assisted in the protection and reduction of metal wastage in those areas due to immersion in saltwater by providing a permanent anticorrosive protection. Preparation of the coating of the internal paint system was performed by the vessel s crew. 38