RAILROAD DAMAGE FROM THE OCTOBER 16, 1999 HECTOR MINE EARTHQUAKE



Similar documents
RAILROAD LIFELINE DAMAGE IN EARTHQUAKES

Performance-based Evaluation of the Seismic Response of Bridges with Foundations Designed to Uplift

Safe & Sound Bridge Terminology

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

RAILROAD ACCIDENT INVESTIGATION REPORT NO THE PENNSYLVANIA RAILROAD COMPANY WEST JEFFERSON, O. AUGUST 4, 1967 DEPARTMENT OF TRANSPORTATION

Informational Workshop Public Meeting Kanawha Falls Bridge Project

3.1 Historical Considerations

Bridge Type Selection

The unit costs are based on the trend line of the 3 low bids for the average quantity.

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

FLEXURAL PERFORMANCE REQUIREMENTS FOR PRESTRESSED CONCRETE TIES BY FACTORING * * *

Railway Track Design

2015 ODOT Bridge Design Conference May 12, DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

(1) Minami Nagamachi and Naka Nagamachi viaducts between Shiraishi Zao and Sendai Stations on the Tohoku Shinkansen line

Evaluation and Field Load Testing of Timber Railroad Bridge

WASHINGTON STATE s BRIDGE SEISMIC RETROFIT PROGRAM

EAST LYME HIGH SCHOOL

March 19, Ms. Jean McDonald CAP Management th Street, Suite 1010 Denver, Colorado 80202

BRIDGES ARE relatively expensive but often are

4 EFFECTS OF SURFACE FAULT RUPTURE ON INFRASTRUCTURE

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

REHABILITATION PACKAGE 1-a

IH-635 MANAGED LANES PROJECT, SEG. 3.2

Chapter. Earthquake Damage: Types, Process, Categories

How To Check For Scour At A Bridge

KCC Event Brief: 2014 La Habra Earthquake

Alternatives Presentation Meeting Middlebury WCRS(23)

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Architectural Condition Survey

PONTIS BRIDGE INSPECTION FIELD MANUAL FOR OKLAHOMA BRIDGES OKLAHOMA DEPARTMENT OF TRANSPORTATION BRIDGE DIVISION

ASSESSMENT AND PROPOSED STRUCTURAL REPAIR STRATEGIES FOR BRIDGE PIERS IN TAIWAN DAMAGED BY THE JI-JI EARTHQUAKE ABSTRACT

SMIP2000 Seminar Proceedings COSMOS VIRTUAL STRONG MOTION DATA CENTER. Ralph Archuleta

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

Magnitude 7.2 GUERRERO, MEXICO

Introduction to Seismology Spring 2008

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

SECTION 3 ONM & J STRUCTURAL ANALYSIS

Overhang Bracket Loading. Deck Issues: Design Perspective

How do scientists measure earthquakes?

Structural Failures Cost Lives and Time

21101 &?I I2 P 3: 2 I. kz COZY c:oi*;: iiss:en. DOCEET COEi1 f3.x..

Page & Turnbull imagining change in historic environments through design, research, and technology

CSXT Emergency Response for May 2010 Flood Repairs

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA

Rehabilitation of a 1985 Steel Moment- Frame Building

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

SEISMIC DESIGN OF HIGHWAY BRIDGES

US 51 Ohio River Bridge Engineering and Environmental Study

Department of Transportation, Rail Division Records Retention Schedule Effective Date: June 2003 Table of Contents. Rail Safety...

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

Detailing of Reinforcment in Concrete Structures

Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

Chapter 3. Track and Wheel Load Testing

Meeting the Challenge of Pipeline Emergency Repair

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

3. Observed Damage in Railway Viaducts

Residential Deck Safety, Construction, and Repair

fib Bulletin 39, Seismic bridge design and retrofit structural solutions: Colour figures

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Bridge Seismic Design, Retrofitting and Loss Assessment

THE 2004 SUMATRA EARTHQUAKE AND INDIAN OCEAN TSUNAMI: WHAT HAPPENED AND WHY

REQUEST FOR QUALIFICATIONS FROM FOUNDATION REPAIR CONTRACTORS BROOMFIELD DEPOT FOUNDATION REHABILITATION PROJECT

OVERVIEW OF TMH19: DRAFT STANDARD FOR THE VISUAL ASSESSMENT OF ROAD STRUCTURES

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

PRELIMINARY SEISMIC CONSIDERATIONS FOR PULASKI SKYWAY REHABILITATION PROJECT. Xiaohua H. Cheng 1

Technical Notes 3B - Brick Masonry Section Properties May 1993

EFFECTS ON NUMBER OF CABLES FOR MODAL ANALYSIS OF CABLE-STAYED BRIDGES

CHAPTER 8 CIVIL DESIGN

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

Numerical Modeling and Simulation of Extreme Flood Inundation to Assess Vulnerability of Transportation Infrastructure Assets

Chapter 3 Pre-Installation, Foundations and Piers

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL

Paving Capitalization Work Categories and Treatments

Office of Inspector General. Audit Report. Actions Taken in Advance of El Niño s Adverse Weather. Federal Railroad Administration

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA

SMIP05 Seminar Proceedings VISUALIZATION OF NONLINEAR SEISMIC BEHAVIOR OF THE INTERSTATE 5/14 NORTH CONNECTOR BRIDGE. Robert K.

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014

San Francisco Oakland Bay Bridge East Span Seismic Safety Project

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

The Original Carbon Fiber Reinforced Polymer System

DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job

Table of Contents. July

SEISMIC RETROFIT DESIGN CRITERIA

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

NUMERICAL ANALYSIS OF A HORIZONTALLY CURVED BRIDGE MODEL

Inspection, Maintenance, and Repair of PaCT Canadian Pacific Rogers Pass Tunnels British Columbia, Canada

3 Tappan Zee Bridge Rehabilitation Options

A COMPUTER ANALYSIS OF THE VINCENT THOMAS SUSPENSION BRIDGE

Guidelines for Earthquake Bracing Residential Water Heaters

Transcription:

RAILROAD DAMAGE FROM THE OCTOBER 16, 1999 HECTOR MINE EARTHQUAKE By: William G. Byers, P.E. Burlington Northern and Santa Fe Railway 4515 Kansas Avenue Kansas City, Kansas 66106 Phone (913) 551-4070 Fax (913) 551-4797

ABSTRACT On October 16, 1999 a magnitude 7.1 earthquake southwest of Ludlow, CA damaged the double track main line of the Burlington Northern and Santa Fe Railway. A westbound Amtrak passenger train, operating within 20 miles of the epicenter at the time of the earthquake, had 22 of its 24 cars derailed. Locomotive units were not derailed. Post earthquake serviceability inspections were completed in less than 8 hours after the event. Track damage included displacement of ballast from cribs and disturbances to track geometry. Bridge damage did not require removal of any bridges from service but six bridges required minor repairs. Track and bridge damage was all within 15 miles of the epicenter. Signal system operation was adversely affected over a greater length of route but not at significantly greater distances from the epicenter. KEY WORDS Earthquakes, Earthquake Damage, Derailments, Bridge Damage, Track Damage INTRODUCTION At 2:46:45 PDT, October 16, 1999 a shallow earthquake with a moment magnitude of 7.1 occurred southwest of Ludlow, CA. The epicenter location was initially reported as 34.503N 116.320W (1), later corrected to 34.59N 116.27W (2). The surface ruptured along a length of 45 km (28 miles) with right-lateral displacements as great as 2.8 to 4.7

meters (9 to 15 ft.) (2). The earthquake occurred on a steep surface dipping between 70 and 85 degrees and is described as a complex earthquake beginning with a tiny precursor followed by major events about 4 and 7 seconds after the onset (2). The optimal fault plane solution developed by seismologists with the U.S. Geological Survey, the Southern California Earthquake Center and the California Division of Mines and Geology (3) has a strike of N 29 o W, a dip of 77 o to the east, and a centroid depth of 13.5 km with pure right-lateral motion and moment of 10 26 Nm. Within the following 5 days, over 50 aftershocks with significant magnitudes had occurred. Aftershocks exceeding magnitude 5.0 occurred three times on October 16 and twice on October 20. The locations of railroads and seismograph stations in the vicinity of the earthquake and contours of peak ground acceleration are shown in Figure 1. RAILROAD INVOLVEMENT The double track main line of the Burlington Northern and Santa Fe Railway (BNSF) is in the vicinity of the fault rupture and was damaged by the earthquake. The Union Pacific Railroad (UP), which has a double track line in the area, but located over twice the distance from the epicenter and about 20 times the distance from the surface rupture, was not damaged. The shortest distance from the UP to the epicenter is slightly over 30 miles. The damaged portions of the BNSF are, with the exception of signal system damage, within 13 miles of the epicenter. The end of the surface rupture is slightly over 20 miles from the nearest point on the UP. The shortest distance between the surface rupture and the BNSF is about one mile.

EFFECTS ON RAILROAD OPERATIONS Post earthquake inspections to determine serviceability of the railroad were completed on the BNSF in less than 8 hours after the event. This included notification time for inspection personnel and travel time from their homes. More detailed inspections of bridges for specific repair planning were conducted the following day. Inspections were completed and normal operation restored on the UP in about 4 hours. The affected portion of the BNSF has automatic block signals and operation is double track, controlled by track warrants. Authorized speed is 79 mph for passenger trains and 55 mph for freight trains, except that freight trains satisfying certain specified requirements can be operated at 70 mph. Both tracks have 136 lb. continuous welded rail. Ties in the affected area are wood ties renewed in 1987, and 1993. A westbound Amtrak passenger train running on BNSF Track No. 1 (the north track) had cars derailed at MP 704.4 as a result of ground motions caused by the earthquake. Four passengers and one crew member received minor injuries. All cars remained coupled and upright and were re-railed or cleared by 2:10 PM (14:10 PDT). Track No. 2 (the south track) was opened to traffic at 2:35 PM (14:35 PDT) and Track No. 1 was returned to service at 11:15 PM (23:15 PDT), October 16, both at 25 mph. The initial 25 mph speed restriction was raised to 40 mph on October 21. All speed restrictions were removed on November 5.

TRACK, BRIDGE AND SIGNAL DAMAGE Track and bridge damage was limited to an area within 13 miles of the epicenter and within 9 miles of the surface rupture as shown in Figures 1 and 2. Signal system operation was adversely affected over a greater length of route and at greater distances from the epicenter. All damage was within 25 miles of the epicenter and within 15 miles of the surface rupture. Track damage included buckled track, other disturbances to track alignment and surface and displacement of ballast from cribs. Track alignment was disturbed at several locations near MP 702.2. Track at the end of Bridge No. 698.8, which was virtually skeletonized by displacement of ballast and/or vertical movement of the track, is shown in Figure 3. There were no pulled apart joints. Due to the short distances to the fault rupture, vertical accelerations may have made a significant contribution to track damage, including displacement of ballast from cribs and apparent upward displacement of ties relative to ballast on bridges. Data on bridges in the affected area, including type, distances from fault trace and from epicenter and estimated peak ground acceleration at each bridge are summarized in Table 1. Bridge damage, summarized in Table 2, was not extensive enough to require removal of any bridges from service but six bridges suffered minor damage, some of which required repair. One damaged bridge is located near the site of the derailment but

did not contribute to the derailment. The most prevalent damage was to unreinforced or lightly reinforced wing walls, primarily separations at cold joints, preexisting cracks or inadequately reinforced corners. Examples of the more severe damage are shown in Figures 4 and 5. One bridge, shown in Figures 6 and 7, with prestressed concrete slab spans and substructure built from precast concrete elements had damage concentrated at locations where the substructure elements were joined together. The substructure consisted of two column bents under each track, precast dump planks and columns supporting the dump planks beyond the ends of the caps. Individual spread footings were cast monolithically with the columns. The tops of the columns were grouted into 10 inch deep sockets in the 20 inch deep caps. Cracking originated in the relatively thin portion of the caps adjacent to the sockets. There was minor spalling where dump planks contacted precast columns. The surface under the bridge was paved for a roadway and erosion protection. The paving was cracked at the base of several columns. In the segment between the first and last damaged bridges, 13 bridges with independent spans under each track and 14 culverts were undamaged. All bridges, both damaged and undamaged, are ballast deck. For reference and comparison, damage to an abandoned concrete building located near the tracks in Ludlow is shown in Figure 8. Damage to highway bridges was reported to be less than in other Southern California earthquakes of comparable or lesser magnitude (4).

Signal problems included wrapped and broken wires and overturned relays. DERAILMENT The Amtrak passenger train, running at about 60 mph on Track No. 1 at the time of the earthquake, had 22 of the 24 cars and one wheel set each on the first and 14 th cars derailed at MP 704.4 as a result of ground motions caused by the earthquake. The engineer s observation of the track moving ahead of the train and the fact that none of the three locomotive units was derailed strongly indicate that the derailment was caused by ground movement under the train, not by earthquake damage to the track ahead of the train. Based on the locations of the epicenter and the surface rupture shown in Figure 2 of Reference (3) and in Figure 2 of this report, the derailment site is nearly in line with the surface rupture and probably on the hanging wall side of the fault. It is about 13 miles from the epicenter and only about 2 miles beyond the north end of the surface rupture. The derailment location would definitely have been subject to near-fault effects including a relatively long pulse of strong acceleration in the fault strike-normal direction. At this location, the angle between the track and the strike of the fault is not greater than 20 degrees. Other instances where trains or cars on tracks near to and making small angles with the fault rupture were derailed or overturned include the 1906 San Francisco and 1995 Kobe earthquakes.

A record of the accelerations obtained 4.5 miles from the fault rupture during the 1994 Northridge earthquake shows a large acceleration pulse in the strike-normal direction with a 0.3 second duration of near-maximum acceleration (5). A similar pulse would have resulted in strong lateral force of the rail against wheel flanges while the train, moving at about 60 mph, traveled between 20 and 30 feet. This distance greatly exceeds the 2 to 5 feet required for wheel climb. The fault involved in the Northridge earthquake is a blind thrust fault. A strike-normal velocity record containing a segment indicating nearly uniform high acceleration for a period in the order of one second is shown in Figure 2 of reference (5). It was obtained at the Lucerne station, located near the fault and about 30 miles from the epicenter, during the 1992 Landers earthquake on strike-slip faults. This pulse was caused by rupture propagation toward the station and was not observed at Joshua Tree near the epicenter (5). A similar relatively long pulse of strike-normal acceleration is highly probable at the derailment site, located approximately 12 miles from the epicenter and less than one mile from a line through the epicenter parallel to the trend of the surface rupture. At the Hector seismometer station, the east-west component of acceleration, the only component measured, was 0.3252g. The locations of this station and other nearby seismometer stations are shown in Figure 9 together with the components of acceleration and velocity at these stations. The Hector station is nearly twice as far from the fault rupture as the derailment site is. For an acceleration pulse duration similar to the Northridge pulse, sustained acceleration normal to the track at the derailment site is estimated to be in the 0.35g to 0.40g range which would produce lateral force to vertical

force (L/V) ratios of 0.7 to 0.8. Such L/V ratios are large enough to cause wheel climb on worn rail. The rail in Track No. 1 was laid in 1986 and had carried over 600 million gross tons at the time of the earthquake. The fact that the 14 th car had only one wheel set derailed indicates that the rail was not overturned under the first 13 cars although it was apparently overturned at some point behind the 14 th car, probably as a result of the derailment. Spectral accelerations at the natural frequencies of the cars could possibly be a contributing factor. Figure 10 shows values derived from 0.3 second, 1 second and 3 second pseudo-acceleration maps together with roll frequency ranges for equipment similar to the types derailed. Frequencies for loaded mail cars would probably be lower than for empty cars. Only the first five cars were passenger cars. SUMMARY A large (M=7.1), shallow, strike-slip earthquake derailed a passenger train operating within 2 miles of the fault rupture and caused minor damage to track and bridges within 13 miles of the epicenter and to signal equipment within 25 miles of the epicenter. Bridge damage occurred at joints between precast elements, inadequately reinforced corners of wing walls, cold joints and preexisting cracks. The derailment was probably caused by wheel climb produced by lateral forces resulting from the earthquake. The BNSF line was out of service for approximately 12 hours while the derailment was being cleared and operated with speed restrictions of 25 mph for 5 days and 40 mph for an

additional 13 days. The UP line, which was undamaged, was out of service about 4 hours for inspection. REFERENCES (1) USGS National Earthquake Information Center, QED Earthquake Bulletin, Updated: Tuesday, 1999 October 19 20:54 MDT (2) Person, Waverly J., Seismological Notes September-October 1999, Seismological Research Letters, Vol. 71, No. 5, September/October 2000, pp. 609-614 (3) Preliminary Report on the 16 October 1999 M 7.1 Hector Mine, California, Earthquake, Seismological Research Letters, Vol. 71, No. 1, January/February 2000, pp. 11-23 (4) Simek, Jaro and Murugesh, Ganapathy, Post Earthquake Investigation Team Report Performance of Bridges during the Hector Mine Earthquake of October 16, 1999, Caltrans Engineering Service Center, 1999, 54 pages. (5) Somerville, P. G., The characteristics and quantification of near fault ground motion, Proceedings of the NCEER Workshop on National Representation of Seismic Ground Motion fpr New and Existing Highway Facilities, May 29-30, San Francisco, California, National Center for Earthquake Engineering Research, Buffalo, NY, 1997

LIST OF TABLES Table 1. Bridge Data Table 2. Bridge Damage LIST OF FIGURES Figure 1. Railroads with measured and projected peak ground accelerations Figure 2. Fault trace and BNSF Railway track and bridges Figure 3. Disturbed ballast at BNSF Bridge No. 698.8 Figure 4. North side of BNSF Bridge No. 693.9 Figure 5. Wing wall break at preexisting crack and cold joint, Br. 698.1 Figure 6. General view of BNSF Bridge No. 701.4 Figure 7. Cracks and cap details BNSF Bridge No. 701.4 Figure 8. Damaged concrete building at Ludlow Figure 9. Seismometer stations and peak ground acceleration components Figure 10. Pseudo-acceleration in frequency range for derailed cars

Table 1. Bridge Data Bridge Distance in Miles from Aprox. Description Damage Number Epicenter Fault Trace PGA 693.1 9.9 9.3 0.27g Rail stringers on conc. pier & abuts. None 693.9 9.4 8.5 0.28g Prestr. conc. slabs on conc. pier & abuts. Minor 694.7 9.4 8.0 0.29g Steel deck girders on stone abuts. None Steel deck girders on conc. abuts. 695.6 9.1 7.1 0.30g Prestr. conc. on conc. pier & abuts. None Arch 9.0 6.2 0.31g Double 4x3.5 stone arch None Double 4x3.5 conc.arch 696.6 9.1 6.0 0.31g Prestr. conc. slabs on conc. pier & abuts. None Reinf. conc. slabs on conc. pier & abuts. 697.0 9.1 5.6 0.32g Reinf. conc. slabs on conc. pier & abuts. None 697.3 9.2 5.3 0.33g Prestr. conc. on H piles None 697.6 9.2 5.1 0.33g Prestr. conc. slabs on conc. abuts. None 697.9 9.3 4.8 0.34g Prestr. conc. slabs on conc. pier & abuts. None 698.1 9.4 4.6 0.34g Prestr. conc. slabs on conc. pier & abuts. Minor Reinf. conc. slabs on conc. pier & abuts. 698.8 9.6 4.1 0.36g Reinf. conc. slabs on conc. pier & abuts. Minor 699.2 10.0 3.8 0.36g Rail stringers on conc. piers & abuts. None 699.5 10.0 3.6 0.38g Timber stringers on conc. pier & abuts. Minor Reinf. conc. slabs on conc. pier & abuts. 700.8 10.3 2.2 0.38g Prestr. conc. slabs on conc. pier & abuts. None Reinf. conc. slabs on conc. pier & abuts. 701.4 10.2 1.7 0.38g Prestr. conc. slabs on precast conc. substr.* Minor 703.2 11.6 1.2 0.37g Prestr. conc. slabs on conc. pier & abuts. None 703.8 12.2 1.5 0.37g Rail stringers on conc. abuts. None Reinf. conc. slabs on conc. abuts. 703.9 12.3 1.6 0.36g Rail stringers on conc. abuts. None Reinf. conc. slabs on conc. abuts. 704.2 12.5 1.7 0.36g Rail stringers on conc. abuts. None Reinf. conc. slabs on conc. abuts. 704.5 12.8 1.9 0.36g Rail stringers on conc. abuts. Minor Reinf. conc. slabs on conc. abuts. 704.6 13.0 2.1 0.35g Rail stringers on conc. abuts. None Reinf. conc. slabs on conc. abuts. 704.9 13.2 2.4 0.35g Prestr. conc. slabs on conc. pier & abuts. None 705.3 13.5 2.7 0.35g Prestr. conc. slabs on conc. abuts. None Bridges 703.8 through 705.3 are beyond end of surface rupture * Precast substructure elements consist of integral column-footing units, caps and dump plank

Table 2. Bridge Damage Bridge Distance in Miles from Aprox. Damage Number Epicenter Fault Trace PGA 693.9 9.4 8.5 0.28g Wing walls on north side separated from abutments Connection between wing walls and parapet walls was not adequately reinforced. Similar wing walls on south side were undamaged. 698.1 9.4 4.6 0.34g Displacement at cold joints and other cracking in unreinfoced wing walls, spalled concrete around dowels between old and new concrete placed for modification. 698.8 9.6 4.1 0.36g Cracked wing walls, displaced ballast curb, concrete deck slabs separated, track and ballast disturbed, severe loss of ballast at end of bridge. 699.5 10.0 3.6 0.38g Appreciable damage to wing walls on south side. 701.4 10.2 1.7 0.38g Cracks in precast caps at sockets for precast columns, cracks in floor pavement where cast around columns, displacement of precast concrete wingwall dump planks and spalling of precast wingwall support posts. 704.5 12.8 1.9 0.36g Plain concrete extension to SE wing wall broken.