XB YETS-2014-2015 PS-TT2 Indico 355427 EDMS 1448498
PS & TT2 Conditions During YETS Beam stop 15/12 @ 06:00 Switch off all equipment in a controlled manner All equipment switched off, but not consigné PS & TT2 remain in restricted access Christmas break: Access point in «Closed» mode 19/12/2014 19:00 to 05/01/2015 8:00 32nd meeting of the Facilities Operations Meeting - YETS organisation (R. Steerenberg) 2
CCC staffing during YETS 32nd meeting of the Facilities Operations Meeting - YETS organisation (R. Steerenberg) 3
CV activities for XMAS Circuits Stop Restart PS PS Central building Anneau 17/12/2014 06/01/2015 PS Main magnet 17/12/2014 13/01/2015 POPS 17/12/2014 13/01/2015 PS Chilled water Running (for the linac 2) Emptying the primary circuits and cleaning of the cooling towers Repairs / Bugs fixing Necessary maintenance (filters, belt, greasing, ) Works will be performed during the closure but not in the machines (no access needed) 35 th meeting of the Facilities Operations Meeting - CV activities for XMAS (S. Deleval) 4
IMPACT Activity Activity Title System Responsible 1 58191 Longitudinal Damper Cavity A - Acceleration MATTHIAS HAASE 2 58041 Inspection ligne de transfere L2 => Booster A - Acceleration CHRISTIAN MASTROSTEFANO 3 57824 YETS PS 10MHz cavity A - Acceleration VALENTIN DANIEL DESQUIENS 4 58873 Cavity 89 : reparation tuner & Cavity A - Acceleration VALENTIN DANIEL DESQUIENS 5 58975 Camera replacement PE.BTV16 B - Beam Instrumentation STEPHANE BURGER 6 58980 Replacement of the camera of F61.BTV01 B - Beam Instrumentation STEPHANE BURGER Replacement of the camera of FT16BTV.388 and 7 58976 FTA.BTV9003 B - Beam Instrumentation STEPHANE BURGER 8 58644 TT2 BPM maintenance B - Beam Instrumentation JEROEN BELLEMAN 9 58263 PS BPM maintenance B - Beam Instrumentation JEROEN BELLEMAN 10 58244 Maintenance DCCT (PS-TR34) B - Beam Instrumentation PATRICK ODIER 11 58234 Mesures transformateurs PS B - Beam Instrumentation FRANCO LENARDON 12 58107 Inspection of SEMgrids TT2 B - Beam Instrumentation MICHEL DURAFFOURG 13 58106 Inspection of SEMgrids ITH Line B - Beam Instrumentation MICHEL DURAFFOURG 14 57301 PS FWS FWS54, FWS65 exchange B - Beam Instrumentation WILLIAM ANDREAZZA 15 XXXXX Drain blockage between East and PS ring??? C - Civil Engineering RICHARD MORTON 16 58632 Câblage BPM ligne BTP YETS-PS-2014-2015 E - Electricity GEORGI MINCHEV GEORGIEV 17 58196 Test PR.DHZOC18 power circuit E - Electricity SIMON MATAGUEZ 18 57856 Cablage RF 25KV (entre Bat 355 et Bat 151) E - Electricity PATRICK LELONG 19 57842 Cablage FGC-ETHER (Bat 355 R-005/R-021) E - Electricity PATRICK LELONG 20 57416 Cablage RF entre Bat 353 et Bat 151 E - Electricity PATRICK LELONG 21 57359 Câblage PS-ECLOUD (SD98) E - Electricity PATRICK LELONG 22 56028 Test cable abimé sur porte YEPZ01.SWY=151 E - Electricity PATRICK LELONG 23 58190 demontage vanne TA reseau EG sur station 4 F - Fluids HASSANE SABRI 24 59046 PSR - Mesures Piliers vers MU's G - Survey and Geodesy TOBIAS DOBERS 25 58618 Scan machine PS (suite et fin!) G - Survey and Geodesy TOBIAS DOBERS 26 57762 Inspection LBS.BVT10 Handling Operations RICHARD SCRIVENS DOMINIQUE BODART / SYLVAIN 27 59037 Blindage chicane bat.151/350 ECR??? Handling Operations FUMEY 28 57965 Inspection de sécurité levage Hoisting Equipment LAURENT COLLY 29 57942 Inspection and maintenance crane PS Hoisting Equipment GILLES ROCHE Condition: Vacuum interventions during XB for FWS54, FWS65, and C80-89 in SS89. In order to ensure a good vacuum for the ion run, interventions are requested to take place in week 51 preferably as early as possible Activity Title System Responsible 29 589723 Visite pour mise a jour layout L - Layouts and assemblies JEAN-MICHEL LACROIX 30 58972 Visite pour mise a jour layout L - Layouts and assemblies JEAN-MICHEL LACROIX 31 58139 Verification septa SEH23/31 M - Magnetic Elements ANTOINE PROST 32 58137 Inspection visuelle Septa M - Magnetic Elements THIERRY MASSON 33 57419 Inspection of the magnets in LTB, LBE, LBS, BI and BTP M - Magnetic Elements ANTONY NEWBOROUGH 34 58726 PS&TT2 Evacuation plan to check P - Personnel safety SIMON MATAGUEZ 35 XXXXX 3 days of testing with the POPS R - Power converter FULVIO BOATINI 36 58733 Inspection de sécurité générale S - General Safety THIBAUT GILLES 37 57990 Inspection de sécurité générale S - General Safety THIBAUT GILLES 38 57584 Inspection and maintenance SFDIN-00265 détection incendie TT2 S - General Safety DENIS RAFFOURT 39 57583 Inspection and maintenance SESEV-00230 Evacuation TT2 S - General Safety DENIS RAFFOURT 40 57482 Inspection and maintenance SESEV-00229 Evacuation PS Ring S - General Safety DENIS RAFFOURT 41 57479 Inspection and maintenance SFDIN-00266 détection incendie PS S - General Safety DENIS RAFFOURT 42 57239 RP Survey & RP follow-up YETS-14-15 S - General Safety GERALD DUMONT 43 58256 Inspection and maintenance PS Beam Stopper + SLITS T - Targets and Dumps JEROME LENDARO 44 58254 Inspection and maintenance - PS Internal Dump T - Targets and Dumps JEROME LENDARO 45 58252 Inspection and maintenance - PS Beam Stopper T - Targets and Dumps JEROME LENDARO 46 58250 Inspection and maintenance PS RADMONs + Radfets + Batmons T - Targets and Dumps JEROME LENDARO 47 58099 Inspection and maintenance ventilation extraction POPS U - Ventilation HASSANE SABRI 48 58073 Inspection and maintenance ventilation +reseau EG+EC U - Ventilation HASSANE SABRI 49 58057 Inspection and maintenance ventilation LOCAL RF ET VIDE U - Ventilation HASSANE SABRI 50 58125 Inspection Visuelle VRJA + jauge penning V - Vacuum FRANCOIS PAUL BELLORINI 51 57343 Intervention BE-OP (CPS) Y - Access system FABRICE CHAPUIS 52 58812 Inspection and maintenance Access & Safety System Y - Access system DIDIER CHAPUIS 53 XXXXX Maintenance Lift AS-35 TT2 B.269 13H-15H 18/12/14 Y - Access system NICOLAS PEREZ 54 XXXXX Maintenance Lift AS-104 B.855 13H-15H 13/01/15 Y - Access system NICOLAS PEREZ 55 xxxx Maintenance Green Spaces Service Mathieu Emmanuel Fontaine 5
From 15/12 6.00 to 17/12 08.00 2 days of testing with the POPS But with 2 breaks: o EN/EL Test safety system(diesels). General power cut. 16/12/2014 Approx time 6.00 à 6.10 (10 mn) o RP Survey 16/12/2014 from 14.00 to 17.00 (3 hours) 32 hours after Beam Stop Restricted access to PS & TT2 allowed from 17/12 08.00 to 16/01 17.00 Test safety system (Diesels). BE/CO Controls Maintenance 05/01-07/01 Close PS & TT2 Ions to PS 6
Draft planning for discussion Beam off 06h00 POPS tests DECEMBER JANUARY Week 51 Week 2 Week 3 Week 4 15 16 17 18 19 5 6 7 8 9 12 13 14 15 16 19 20 21 22 23 * ** * PS Central building ring Cooling stations maintenance POPS Main magnet PS RP patrol (32h after beam stop) from 14.00 to 17.00 (3 hours) Test safety system (Diesels). (10 ' cut) PS FWS FWS54, FWS65 exchange Cavity 89 : reparation tuner & Cavity PS & TT2 Access closed Inspection and maintenance crane PS (payload needed) Cabling campaign Access maintenance and inspections (Access points not available) Ventilation maintenance and inspections detection incendie et evacuation Blindage chicane bat.151/350 ECR??? Maintenance Lift AS-35 TT2 B.269 13H-15H 18/12/14 Drain blockage between East and PS ring??? Bldg. 352 * Blind access needed ** Sector closed 7
Cabling campaign 16 58632 Câblage BPM ligne BTP YETS-PS-2014-2015 E - Electricity GEORGI MINCHEV GEORGIEV 17 58196 Test PR.DHZOC18 power circuit E - Electricity SIMON MATAGUEZ 18 57856 Cablage RF 25KV (entre Bat 355 et Bat 151) E - Electricity PATRICK LELONG 19 57842 Cablage FGC-ETHER (Bat 355 R-005/R-021) E - Electricity PATRICK LELONG 20 57416 Cablage RF entre Bat 353 et Bat 151 E - Electricity PATRICK LELONG 21 57359 Câblage PS-ECLOUD (SD98) E - Electricity PATRICK LELONG 22 56028 Test cable abimé sur porte YEPZ01.SWY=151 E - Electricity PATRICK LELONG HT test septa SEH23/31-15/12&16/12 RF Cavities test - 05/01-16/01 8
Shielding block CHICANE Bldg.151 project If ok shielding blocks will be removed week 2 (sector closed) Courtesy Dominique Bodart, Frederic Delsaux 9