RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd



Similar documents
RIIO-T1 business plan submission London Tuesday 6 September 2011

Interaction between business context and an appropriate WACC for ESBN

The Implementation of the RIIO Framework

National Grid Electricity Transmission s RIIO-T1 business plan overview

SP Energy Networks Business Plan

Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE

Glossary of terms: RIIO-T1 and GD1 review

Decision letter on the regulatory asset lives for electricity distribution assets

Debt in depth: the cost of debt in regulatory determinations

Dear Colleague, Summary

RIIO T1 Business Plan Update January 2012

National Grid Gas Transmission s RIIO-T1 business plan overview

We hope all the questions are understandable, If you have any difficulties please

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

RIIO-T1 & RIIO-GD1: UNCERTAINTY ISSUES

SP Transmission RIIO-T1 Business Plan

Caithness-Moray Needs Case Consultation

A Trip to RIIO in Your Future? Great Britain s latest innovation in grid regulation. By Peter Fox-Penner, Dan Harris, and Serena Hesmondhalgh

National Grid Gas plc Annual Report and Accounts 2015/16. Company number

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

ANNEX 27: CORPORATE GOVERNANCE, COMPLIANCE AND DATA ASSURANCE BUSINESS PLAN ANNEX

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

Transmission Price Control Review: Updated Proposals and Smithers & Co. Ltd.: Report on the Cost of Capital. Response to consultation

Data Communications Company (DCC) price control guidance: process and procedures

RULE DETERMINATION Rule Proponents

Electricity Market Reform:


PR18 working paper Working paper 3: Initial views on the regulatory framework for Network Rail s system operator function

Report on the EMR Delivery Body s performance of its functions in relation to the Capacity Market

The Levy Control Framework

Consultation on United Utilities statement of risks, strengths and weaknesses 2015/16 Our annual performance reporting

PROJECT MANAGEMENT FRAMEWORK

NETWORK OUTPUT MEASURES CONSULTATION

Decision on our methodology for assessing the equity market return for the purpose of setting RIIO-ED1 price controls

UNSOLICITED PROPOSALS

Ofgem guidance on the determination of disputes for use of system or connection to energy networks

Value for Money Assessment Guidance: Capital Programmes and Projects

Name Telephone Mike Wilks

Offshore Transmission: Guidance for Cost Assessment Guidance Document

Project Assessment Framework Establish service capability

Innovation in Electricity Networks

Information Requirements: Business Plan. Trinidad & Tobago Electricity Commission

This document outlines Wales & West Utilities Business Plan for the next regulatory period from

Private Health Insurance Ombudsman

Water Charges Plan Decision Paper (Executive Summary)

The Transport Business Cases

Service Price Control Proposal

UTILITY REGULATOR WATER. Water & Sewerage Services Price Control

UK Power Networks Business plan (2015 to 2023) Executive summary

REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

The Low Carbon Transition & the Challenge for Distribution Grids 19 September 2013

PRELIMINARY DECISION CitiPower distribution determination

RII0-GD1. Business Plan

Draft Integration Scheme for the Ayrshire Parties 18 December 2014

Consultation on changes to Feed-in Tariff accreditation

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

Review of the Approach to Capital Investments

A new electricity market for Northern Ireland and Ireland from Integrated Single Electricity Market (I-SEM)

Reorganising central government. Synergy reporting for Mergers and Acquisitions

Thames Tideway Tunnel Cost of capital

Smart metering A REPORT PREPARED FOR CENTRICA. October Frontier Economics Ltd, London.

Synergies and Conflicts of Interest arising from the Great Britain System Operator delivering Electricity Market Reform

National Grid plc Results for the year ended 31 March 2011

SUBMISSION ON THE AER'S DRAFT DISTRIBUTION DETERMINATION , APPENDIX P: DEBT RAISING COSTS

Proposed debt assignment protocol for prepayment customers. A consultation document

TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

15 April 2011 Re: Expansion of the Victorian Energy Efficiency Target

Annex A Feed-in Tariff with Contracts for Difference: Operational Framework

Network Rail Infrastructure Projects Joint Relationship Management Plan

Energy Procurement Practice Guide

From our review of the experience at PR14 we have identified five key lessons for the next price review. These are summarised in Figure 1 below.

Project Management Guidebook

Accessing finance. Developing a business case for your resource efficiency projects

Reforming the business energy efficiency tax landscape

Accessing finance. Developing a business case for your resource efficiency projects

National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares

Below are our responses to the questions included in Appendix 4 of the consultation document.

Government response: EMR consultation on industry code and licence modifications

Customers and Other Interested Parties Direct Dial:

Electricity settlement reform moving to halfhourly

Appendix 5 Oadby and Wigston Borough Council: HRA self-financing business plan model

Financeability and financing the asset base a discussion paper

Minutes of a Meeting of the Gas and Electricity Markets Authority. Ofgem, London SW1P 3GE

Wholesale power market liquidity: consultation on a Secure and Promote licence condition

RIIO Game or business as usual? in association with

1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) /02/2014 Chris Ong All Reformatting of initial version

Equality Process & Procedure in the Human Rights Act, First Steps

Financial Settlement Strategy

Consultation document Helping users of HMRC s Basic PAYE Tools undertake automatic enrolment calculations

Monitoring Highways England The monitoring framework

RELEVANCE OF MARGIN BASED APPROACH

SEPA's New Legal Rules and Regulations in South East Scotland

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS No. [XXXX]

LATE ITEM REPORTS BY OFFICERS

Annual EMR Compliance Report. National Grid Electricity Transmission plc

Manchester City Council

Commission s Proposals on Distribution Use of System Revenue Requirement and Tariff Structure 1 October September 2007

Contract and Vendor Management Guide

NEW CABLE? - Understanding the cost to connect renewable generation in Orkney

Transcription:

To generators, shippers, suppliers, network companies, consumers and their representatives, the sustainable development community, investors and other interested parties Promoting choice and value for all gas and electricity customers Our ref: 07/12 Direct Dial: 020 7901 7165 Email: hannah.nixon@ofgem.gov.uk Date: 23 January 2012 Dear colleague RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd The next transmission price control (RIIO-T1) is the first price control 1 to be conducted under our new RIIO (Revenue = Incentives + Innovation + Outputs) model. The price control is due to run from 1 April 2013 to 31 March 2021. The objective of RIIO is to encourage network companies to play a full role in the delivery of a sustainable energy sector, and to do so in a way that delivers value for money for existing and future consumers. This letter sets out the Authority s decision that the business plans of SP Transmission Ltd (SPTL) and Scottish Hydro Electric Transmission Ltd (SHETL) are of sufficient quality to be consulted upon through fast-tracking Initial Proposals with a view to reaching early settlement of their price controls, ie that their business plans are suitable for fasttracking. It provides a high-level summary of our assessment of the companies business plans. It also sets out the key components of their plans that will form our Initial Proposals for their price controls. Our decision to fast-track SPTL s and SHETL s plans, subject to consultation, reflects the significant improvement in the plans in both cases since their initial submission in July 2011, and the value that the plans provide to consumers and wider stakeholders. As set out in our October letter 2, in RIIO-T1 we have provided for greater iteration between the first business plan submission and our fast-track decision than we intend in the future, including in RIIO-GD1 and RIIO-ED1. As network companies learn what is expected from them under RIIO, for example in terms of a more joined up assessment, testing different options and employing long-term thinking across the whole plan, we do not consider there will be a requirement for significant iteration as the quality of the initial submissions should be higher. Importantly, this does not mean that we are lowering the bar for a company to be fast-tracked in RIIO-T1. SPTL and SHETL have published revised versions of their RIIO-T1 business plans. These will be available at the following links: 1 We are currently in the process of setting price controls for the gas distribution companies RIIO-GD1 but that process is being taking forward on a separate timetable. 2 Initial assessment of RIIO-T1 business plans and proportionate treatment http://www.ofgem.gov.uk/networks/trans/pricecontrols/riio-t1/conres/documents1/busplanletter.pdf

SPTL http://www.spenergynetworks.co.uk/publicinformation/stakeholder_riio.asp SHETL http://www.ssepd.co.uk/projects/transmissionpricecontrolreview/ We intend to publish our consultation on Initial Proposals for both SPTL and SHETL on 6 February, and will seek views from stakeholders at that point. In the meantime, if you would like to discuss any aspect of this letter, please contact Grant McEachran on 0141 331 6008 or by e-mailing grant.mceachran@ofgem.gov.uk. Background Under the RIIO process, network companies are required to take into account the needs and views of stakeholders in order to submit to us well-justified business plans. We are taking a proportionate approach to our scrutiny of companies plans, i.e. the level of our regulatory scrutiny varies according to the quality of plans. Companies that submit very high quality plans will be able to agree price controls early, i.e. achieving fast-tracking. In March 2011, we set out our Strategy Decision for RIIO-T1. 3 This set out decisions on the key aspects of the regulatory framework. It also set out what we expected to see in a welljustified business plan and the criteria against which we would assess such a plan. We used five broad criteria to assess the plans: Process: has the company followed a robust process? Outputs: does the plan deliver the required outputs? Resources (efficient expenditure): are the costs of delivering the outputs efficient? Resources (efficient financial costs): are the proposed financing arrangements efficient? Uncertainty/risk: how well does the plan deal with uncertainty and risk? We received the transmission owners (TOs) RIIO-T1 business plans at the end of July 2011. Our assessment in October concluded that none of the plans was suitable for fasttracking in their existing format. However, we also took into consideration that this was the first time any company had submitted a business plan under the RIIO framework and that the scale of the outstanding issues for SPTL and SHETL may allow them to resolve these in a timeframe consistent with fast-tracking. On this basis we retained SPTL and SHETL in the fast-tracking process. Our assessment outlined the issues SPTL and SHETL would need to address in order for us potentially to develop Initial Proposals in early 2012. We considered that the outstanding issues for National Grid Electricity Transmission plc (NGET) and National Grid Gas Transmission plc (NGG) were not resolvable in this timeframe. Consequently, NGET and NGG reverted to the non-fast-tracking process. SPTL and SHETL s revised business plans Following the publication of our initial assessment of the companies plans both SPTL and SHETL have undertaken a significant amount of further work to revise their plans. Both have undertaken more work in key areas, provided further supporting information and carried out further stakeholder engagement. Both companies have submitted revised versions of their business plans. Our updated assessment is based on all of the information provided to us as part of this process. It is also informed by responses to our October business plan assessment and views received from the Consumer Challenge Group (CCG) 4. 3 Decision on strategy for the next transmission price control: RIIO-T1 Ofgem, 31 March 2011 Ref:46/11 http://www.ofgem.gov.uk/networks/trans/pricecontrols/riio-t1/conres/documents1/t1decision.pdf 4 The CCG comprises consumer and environmental experts acting as a critical friend to Ofgem in the RIIO-T1 and RIIO-GD1 processes. 2 of 6

Assessment of revised business plans This section summarises our updated assessment of each of SPTL s and SHETL s revised business plans. This covers the five criteria we used in the initial assessment. SPTL and SHETL have taken different approaches to their business plans. In taking a decision on fasttracking we have therefore assessed each plan as a package. We are satisfied that both packages as a whole provide value for money to both existing and future consumers and demonstrate how they will meet the challenges associated with facilitating the move to a low carbon economy. SP Transmission Ltd (SPTL) In relation to its process SPTL has addressed our key concerns. It has undertaken further stakeholder engagement and increased its stakeholder database. It has also provided information in relation to omissions from the key content in its July business plan. SPTL has made changes to a number of its output and incentive parameters which provide better value to customers. In particular, it has changed its proposals in relation to the primary outputs for reliability and connections which bring it into line with the positions set out in our Strategy Decision document. It has provided more information in relation to its processes for developing a network availability policy and customer satisfaction survey. It has also provided more information on their environmental outputs and recognises there is room to refine these further. The area where SPTL has made most progress since October is in relation to its justification around cost efficiency. It has provided a wide range of additional material including evidence of the robustness of its processes to ensure efficiency, shown that a large proportion of its cost base is subject to competitive tenders and provided additional information to demonstrate how it will deliver its plan. SPTL s unit costs are comfortably within our consultants range. SPTL has revised elements of its financial proposals. It has reduced its cost of equity assumption, increased notional gearing and introduced a fixed rate of totex capitalisation. SPTL has made revisions to its approach to dealing with risk and uncertainty. It has proposed volume drivers that are tightly defined both in terms of scope and unit costs and set out a similarly well defined mechanism for wider works. Scottish Hydro Electric Transmission Ltd (SHETL) In relation to its process SHETL has undertaken further stakeholder engagement and increased its stakeholder database. It has also provided information in relation to omissions from the key content in their July business plan. SHETL has made changes to a number of its output and incentive parameters. Several of these, including its environmental outputs, network availability policy and customer satisfaction, will be strengthened by further detail in the coming months. SHETL has provided more information and revised plans in relation to both its costs and risk and uncertainty to address our concerns that its July plan transferred a disproportionate risk onto consumers. SHETL has made substantial changes to its financial package since the July plan, bringing it in line with our policies and ranges. Among the key changes it has made are applying straight line depreciation to new assets, with a 16-year transition; reducing the assumed cost of equity from 8.25% over the first four years of the RIIO-T1 period and 7.5% thereafter to 7% throughout the RIIO-T1 period; increasing notional gearing from 50% in the first four years of the RIIO-T1 period and 55% thereafter to 55% throughout the RIIO- 3 of 6

T1 period; removing the uplift to the cost of debt index; and applying a fixed totex capitalisation rate. Decision on fast-tracking and proportionate treatment SPTL SPTL has addressed the key outstanding issues we had with their July business plan. In a wide range of areas it has provided more detail and in a number of areas it has changed its proposals. We note there are areas where SPTL could improve and we are outlining below some areas in relation to stakeholder engagement and outputs where we expect further work to be undertaken. Overall we consider the package put forward by SPTL provides good value for consumers. On this basis, we are putting forward SPTL s business plan for fast-tracking and intend to publish Initial Proposals shortly. SHETL SHETL has made significant progress in addressing the outstanding issues we had with its July business plan. It has provided more detail in various areas of the plan and put forward innovative proposals in a number of areas. Most notably SHETL has proposed significant changes to its financial package. As with SPTL there are areas where SHETL could improve. We outline below some areas in relation to stakeholder engagement and outputs where we expect further work to be undertaken. Overall we consider the package put forward by SHETL provides good value for consumers. On this basis, we are putting forward SHETL s business plan for fast-tracking and intend to publish Initial Proposals shortly. Summary of SPTL and SHETL s business plans The fast-tracking Initial Proposals for SPTL and SHETL will be developed and published shortly, based on the information set out in their business plans. The key elements of those plans are summarised in Table 1 below. 4 of 6

Table 1: Summary of SPTL and SHETL s business plans Area SPTL SHETL Outputs Complete range of RIIO outputs including baseline deliverables and the strength of the financial incentives Complete range of RIIO outputs including baseline deliverables and the strength of the financial incentives Environmental strategy Expenditure (nominal prices) Baseline capex Capex subject to uncertainty mechanisms Controllable Opex Financial parameters Cost of equity (post-tax real) Notional gearing Cost of debt (pre-tax real) Depreciation profile Some areas of best practice in its environmental outputs i.e. baseline for SF 6 emissions and commitment to mitigation measures for visual amenity 1.8bn 0.7bn (SPTL best view) 0.3bn Some areas of best practice in its environmental outputs i.e. transmission losses and a visual amenity statement 1.1bn 4.0bn (SHETL best view) 0.4bn 7% 7% 55% 55% Indexed using 10 year simple trailing average Straight line: 20 years on existing assets, 45 years on new assets Indexed with bespoke weightings tracking Totex profile Straight line: 20 years on existing assets, 45 years on new assets one price control period two price control periods Asset life transition Totex capitalisation rate 90% 90% Efficiency incentive rate 50% 50% Uncertainty mechanisms Including, but not limited to, Including, but not limited to, a volume driver for volume drivers for generation connections, a generation connections, within-period revenue within-period revenue determination for specified determinations for specified large overhead line large wider reinforcement replacement projects and projects including where wider reinforcement works. possible costs associated with visual amenity. Innovation Set out an innovation strategy and requested an Innovation Allowance of 0.75% Set out an innovation strategy and requested an innovation allowance of 1% and a reprofiling of the allowance over the period. SPTL and SHETL s proposals are set out in more detail in their revised business plans which are published on their websites. Areas for further work While we consider both SPTL and SHETL s plans are suitable to be put forward for fasttracking we recognise there are areas for further work in both plans. Under RIIO, we expect significant changes from network companies in terms of the way they operate and engage with consumers. While both companies have made considerable strides forward over the last year, there is inevitably more that they could do. 5 of 6

The areas where we will be expecting both SPTL and SHETL to undertake further work are: Environmental strategy While both plans set out baselines for some of the environmental outputs required in the RIIO-T1 strategy, both have further work to do to firm up the performance levels they will deliver across all of the environmental outputs. We expect the companies to provide more detail on their processes to finalise the outstanding areas to inform our decisions on Final Proposals. Stakeholder engagement We note the significant progress both companies have made in this area and welcome their commitments to do more going forward. Network availability and customer satisfaction These are areas where all of the TOs continue to work together to further develop the outputs. We expect that work to continue over the coming months to ensure the new arrangements are in place for the start of RIIO-T1. Both companies requested network innovation allowances of greater than the minimum which was provided for in the March strategy document. Having reviewed the companies innovation strategies, we do not consider that either company has yet provided sufficient justification for their proposed allowance. However, if either company considers that they can justify a higher level of allowance then they may put forward further evidence. We will consider that evidence, alongside any consultation feedback, in setting the Final Proposals. Next steps In light of our assessment we will consult on Initial Proposals for SPTL and SHETL. We intend to publish those proposals along with further detail on our assessment of the revised plans on 6 February 2012. We will provide a six week consultation period and will require responses by 19 March. We will set out our final decision on fast-tracking and, if appropriate, Final Proposals for one or both companies in April 2012. If, in light of feedback to our Initial Proposals, we decide not to fast-track SPTL and/or SHETL then they will revert to the non fast-track process. Alongside our Initial Proposals we also intend to consult on additional financial incentives to sharpen the environmental considerations demonstrated by the transmission companies throughout the RIIO-T1 period. We had set out our intention to consult in this area in our March 2011 Strategy Decision document. The proposal set out in this document would apply to NGET as well as SPTL and SHETL. We will also publish our Final Proposals in this area in April 2012. NGET and NGG are required to resubmit their business plans by 5 March 2012. We will consult on Initial Proposals for NGET and NGG in July 2012. Yours sincerely Hannah Nixon Acting Senior Partner, Smarter Grids and Governance: Transmission 6 of 6