Recent NYSDOT Bridge Failure Investigations

Similar documents
STRUCTURAL FORENSIC INVESTIGATION REPORT

Overhang Bracket Loading. Deck Issues: Design Perspective

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

APPENDIX H DESIGN CRITERIA FOR NCHRP PROJECT NEW BRIDGE DESIGNS

Long-term serviceability of the structure Minimal maintenance requirements Economical construction Improved aesthetics and safety considerations

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

Index Series Prestressed Florida-I Beams (Rev. 07/12)

Optimum proportions for the design of suspension bridge

Engineering for Stability in Bridge Construction: A New Manual and Training Course by FHWA/NHI

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

ABSTRACT 1. INTRODUCTION 2. DESCRIPTION OF THE SEGMENTAL BEAM

A transverse strip of the deck is assumed to support the truck axle loads. Shear and fatigue of the reinforcement need not be investigated.

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1

Basics of Reinforced Concrete Design

bi directional loading). Prototype ten story

Design of reinforced concrete columns. Type of columns. Failure of reinforced concrete columns. Short column. Long column

Statics of Structural Supports

ASSESSMENT AND PROPOSED STRUCTURAL REPAIR STRATEGIES FOR BRIDGE PIERS IN TAIWAN DAMAGED BY THE JI-JI EARTHQUAKE ABSTRACT

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Objectives. Experimentally determine the yield strength, tensile strength, and modules of elasticity and ductility of given materials.

Structural Failures Cost Lives and Time

Behavior of High-Strength Concrete Rectangular Columns

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:

Joist. Reinforcement. Draft 12/7/02

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Weight Measurement Technology

AASHTOWare Bridge Design and Rating Training. STL8 Single Span Steel 3D Example (BrDR 6.6)

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

US 51 Ohio River Bridge Engineering and Environmental Study

TABLE OF CONTENTS. Roof Decks 172 B, BA, BV Deck N, NA Deck. Form Decks FD,.6 FDV Deck 1.0 FD, 1.0 FDV Deck 1.5 FD Deck 2.0 FD Deck 3.

Performance-based Evaluation of the Seismic Response of Bridges with Foundations Designed to Uplift

Detailing of Reinforcment in Concrete Structures

Prestressed Concrete I-Beam and TxGirder Haunch Design Guide

SEISMIC RETROFITTING STRATEGIES FOR BRIDGES IN MODERATE EARTHQUAKE REGIONS

Optimising plate girder design

Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges

(1) Minami Nagamachi and Naka Nagamachi viaducts between Shiraishi Zao and Sendai Stations on the Tohoku Shinkansen line

METHOD OF STATEMENT FOR STATIC LOADING TEST

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

Incorporating Innovative Materials for Seismic Resilient Bridge Columns

FOOTING DESIGN EXAMPLE

Snake River Bridge Load Test Addressing Bridge Management Issues WBES 2015 Reno, NV

Steel joists and joist girders are

6 RETROFITTING POST & PIER HOUSES

In-situ Load Testing to Evaluate New Repair Techniques

Quality and the Bridge Engineer

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

ETABS. Integrated Building Design Software. Concrete Shear Wall Design Manual. Computers and Structures, Inc. Berkeley, California, USA

Introduction to LRFD, Loads and Loads Distribution

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

INSTALLATION. General. Important Note. Design. Transport

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Rapid Short and Medium Span Bridge Construction Using Innovative. Precast Structural Systems

Preliminary steel concrete composite bridge design charts for Eurocodes

Reinforced Concrete Slab Design Using the Empirical Method

Structural Performance of Highway Bridges under Given Foundation Settlements

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

Chapter 3 Pre-Installation, Foundations and Piers

Residential Deck Safety, Construction, and Repair

EFFECTS ON NUMBER OF CABLES FOR MODAL ANALYSIS OF CABLE-STAYED BRIDGES

SEISMIC RETROFIT DESIGN CRITERIA

Quality Control and Quality Assurance Guide

[TECHNICAL REPORT I:]

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

LOAD TESTING FOR BRIDGE RATING: DEAN S MILL OVER HANNACROIS CREEK

Stability. Security. Integrity.

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Session 5D: Benefits of Live Load Testing and Finite Element Modeling in Rating Bridges

Numerical modelling of shear connection between concrete slab and sheeting deck

Investigation of the November 2, 2013 collapse of concrete beams at Fort Lauderdale-Hollywood Airport runway project

Type of Force 1 Axial (tension / compression) Shear. 3 Bending 4 Torsion 5 Images 6 Symbol (+ -)

System. Stability. Security. Integrity. 150 Helical Anchor

TXDOT ENGINEERING SOFTWARE SUPPORT INFORMATION. Prestressed Concrete Girder SUPERstructure Design and Analysis Program (PGSuper TM )

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

The Installation and Load Testing of Drilled Shafts

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

INTRODUCTION TO LIMIT STATES

III. Compression Members. Design of Steel Structures. Introduction. Compression Members (cont.)

SECTION 1 GENERAL REQUIREMENTS

Risk - Based Inspection Frequencies

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

This manual was produced using ComponentOne Doc-To-Help.

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

Retrofitting By Means Of Post Tensioning. Khaled Nahlawi 1

16. Beam-and-Slab Design

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED

SLAB DESIGN EXAMPLE. Deck Design (AASHTO LRFD 9.7.1) TYPICAL SECTION. County: Any Hwy: Any Design: BRG Date: 7/2010

Technical Notes 3B - Brick Masonry Section Properties May 1993

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

TECHNICAL NOTE. Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006 IBC. On Cold-Formed Steel Construction INTRODUCTION

U.S. Department of Labor Occupational Safety and Health Administration Directorate of Construction. April 2015

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

Underpinning Systems 14.1 FOUNDATION REPAIR. Helical Piles

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

How to Design Helical Piles per the 2009 International Building Code

Transcription:

Bridge Failures - Lessons learned Recent NYSDOT Bridge Failure Investigations George A. Christian, P.E. Director, Office of Structures New York State Dept. of Transportation Bridge Engineering Course University at Buffalo March 29, 2010

I-787 - Dunn Memorial Bridge Interchange Albany, NY partial collapse at pier 11- August 2005 I-787 Ramp NB to South Mall Expressway WB (BIN 109299A) 2

BIN 109299A 3

Structure Layout (looking east) 4

Overview of Failure 5

High Rocker Bearings 6

History of Misalignment of High Rocker Bearings at Pier 11 1987 Inspection Temp. @ 45 1999 Inspection Temp. @ 70 7

2003 Inspection Span 12 East Bearing Temp @ 45 F Lifted 0.25 ft.(3 in.) - Eccentricity = 3.4 in. 8

How did the bearings get misaligned? Superstructure Displacements: Survey of adjacent piers (w/ fixed bearings) Pier 10 displaced north 1.6 inches. Pier 12 displaced north 1.0 in (avg.) 1.7 inches on east side. History of Pier 13 joint Joints reset (vertical) in 1990 Joint was closed in 1990 Closed in 1995 thru present Longitudinal forces due to braking, centrifugal force 9

Condition of Rocker Bearings Susceptible to corrosion, debris when continually tilted Corrosion, debris prevents rocking back toward vertical Under rocker Pin corrosion Contact surfaces flatten or dish Result: Bearings become resistant to horizontal movement, especially back toward being plumb. Transfers longitudinal forces to substructure 10

Corrosion & Flattening 11

Frozen Pins 12

Rocker and Pintle Corrosion Span 11 Bearing 13

Pier 11 Height: 82.3 feet 13.9 x 6.44 at base 9 x 4 at top of stem Stem rebar: 46 - # 8 bars 14

Pier 11: Lack of Elastic Range Cracks 40 ft. up north face Rebounded 51/2 in. when released The pier failed in flexure 15

Comparison of Adjacent Piers PIER NO. HGT. BASE REINFORCING STEEL No.-Size Bars Area BEARINGS FIX OR EXP 9 67.47 131.4 x 71.2 42 - # 8 33.18 Fix - Exp 10 72.79 132.6 x 72.6 36 - #11 56.16 Fix 11 82.31 166.6 x 77.3 46 - # 8 36.34 Exp - Exp 12 83.38 155.3 x 77.6 42 #11 65.52 Fix 13 84.75 156.4 x 84.2 42 - #11 65.52 Exp - Exp 16

Pier 11 Design Check Designed per 1965 AASHO code Meets strength req. for code assumptions Allowable / Actual ratio = 0.98 =1.0 (OK) No provision for large flexural displacements Equivalent Column with 1% reinforcing. 17

Longitudinal Pier Cap Force [kips] Results of Pier Analysis Old Pier 11 (AC-12) 160 140 f c=9 210 120 100 80 60 40 20 0 0 5 10 15 20 Longitudinal Pier Cap Displacement [in.] Limited elastic range - yields at 5.5 deflection psi Cracking at 2.5 deflection No capacity increase beyond cracking 18

Forces Needed for Failure Thermal: limited by resistance of bearing Up to 0.58 x Dead Load if sliding assumed: approx. 200 kip from Span 12 only Limited range of movement Corrosion Build-up: Develops horizontal component of vertical dead, live load reactions Larger range of movement 19

Probable Failure Sequence Bearings tilted to north > 20 years ago Bearings begin to resist horizontal mov t. Superstructure longitudinal displacements began to move pier instead of Span 12 bearings Bearings resist movement moving back toward vertical Increased southward tipping of Span 12 and 11 bearings Instability point reached bearings tipped Forces (displacements) sustained to deflect pier 16 + in. (bearings tipping and spans falling on tipped bearings) 20

21

22

23

24

25

26

27

28

29

30

31

32

Underlying Cause of Failure 1. Rocker bearings becoming misaligned 2. Rocker bearing not functioning properly 3. Pier 11 was flexible in direction longitudinal to the bridge 4. Pier 11 stem was lightly reinforced, and not elastically ductile 1, 2 and 3 were required for failure to occur. 4 may have been required, but contributed to extent of failure 33

34

35

Follow up actions Reviewed all high rocker bearings with low inspection ratings (CR 3 or less) Inspected those overextended Preventive interim retrofits bolsters Technical Advisory: INSP 05-001 36

Follow up actions Bolsters installed as an extraordinary precautionary measures on 10 bridges Alerted other owners of bridges not under DOT s inspection jurisdiction Corrective action: Dunn Complex, bearing replacements 37

Marcy Pedestrian Bridge Collapse October 2002 Span = 171 ft. South Abutment Bracket Field Splice North Abutment

Acknowledgements Sponsored by New York State DOT P.I. Weidlinger Associates, Inc. Material testing and weld inspections by ATLSS Research Engineering Center, Lehigh University

Outline 1. Collapsed Bridge 2. Review of Bridge Design 3. Analysis of Bridge Failure 4. Demolition 5. Laboratory Testing 6. Conclusions 7. Recommendations 8. NYSDOT Actions 9. Applications Tub girders and beyond

6.3 ft (1.93 m) Tub Girder Cross Section 14.0 ft (4.27 m) 4.3 ft (1.3 m) Intermediate Diaphragm

Collapsed Bridge South Abutment Screed North Abutment

Collapsed Bridge Exp. Bearing South Abutment

Collapsed Bridge North Abutment Fixed Bearing

2. Review of Bridge Design Objective: Evaluate the adequacy of the bridge design

2.1 Design Codes NYS Standard Specifications for Highway Bridges with provisions in effect as of April 2000. AASHTO Standard Specifications for Highway Bridges, 16th Ed. LFD (1996) with 1997, 1998 & 1999 interim AASHTO Subsection 10.51 Composite Box Girders (LFD). This section pertains to the design of bridges of moderate length supported by two or more single cell composite box girders..

2.3 Finished Bridge Design assumption: Two I-girders Conclusions: The bridge, as designed, would have been sufficient to resist its design loads if it had survived its construction.

2.4 During Construction Top Flange Intermediate Diaphragm Failure Modes: b/t of top flange; Top flange buckling (between intermediate diaphragms) Global Torsional buckling

3. Analysis of Bridge Failure Objective: To find and prove the cause of failure

3.1 Deck Construction Facilities: C.L. Bridge Screed Operator Engine Form/Catwalk Web Concrete Drum West Tie-rod (4' apart) Hanger Angle Top Flange Metal Form Web Bottom Flange Bracket (3' apart) East

3.3 Elastomeric Bearings Top Steel Plate Bottom Steel Plate Elastomer Steel Plates Top Steel Plate Bottom Steel Plate Steel Pin Y k EC k k ES ES X Z a). Expansion Bearing Top Z k EC k FS Y F D Nonlinear Spring X k BRG =k ES +k PIN b). Fixed Bearing k PIN

94mm Force, N 3.4 Fixed Bearing Steel Pin Model 36 mm dia Applied Force 50000 40000 30000 20000 10000 Fixed Boundary Steel Plate 0 0 1 2 3 4 5 6 7 8 9 10 Deformation, mm Force-Deformation Curve

3.5 Global Model Top Flange Web Strut Diaphragm End Diaphragm Top Flange

Girder Rotation, Degree 3.6 Analysis Results North Abutment Concrete Screed SW+DL (rebar, form, etc.) Steel girder 0.0-1.0-2.0-3.0-4.0-5.0-6.0-7.0-8.0-9.0-10.0 As-designed (ideal) As-built 0.0 10.0 20.0 30.0 40.0 50.0 42' Concrete Pour Length, m 105' Y Rotation

3.7 Corrugated Metal Form Edge Screw Location Middle Screw Location Top Flange Form Thickness = 1.2 mm (3/64 in.)

3.9 Form Connection Model a Fixed Boundary F Weak Form: a=1/2" (12 mm) Fy = 40 ksi (275 MPa) Strong Form: a=3/4" (20 mm) Fy = 45 ksi (310 MPa)

Girder Rotation, Degree 3.11 Force-Rotation Curve Y As-designed (ideal), No form Rotation 0.0-1.0-2.0-3.0-4.0-5.0-6.0-7.0-8.0-9.0-10.0 As-built No form Weak form, as-built 42' 82' Strong form, as-built 95' 105' 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 Concrete Pour Length, m

4. Demolition Objectives Remove debris safely; Sample materials; Preserve evidence Cut Location Temp. Support

Objectives: 5. Laboratory Testing Verify Analysis Assumptions Check whether materials conform to contract specifications

Force, N 5.1 Form Connection Tests Gage 12 Steel PL 12000 10000 8000 6000 Lab Results Strong Form Model Screw Form Form connection test 4000 2000 0 Weak Form Model 0 2.5 5 7.5 10 12.5 15 17.5 20 22.5 25 Lateral Deformation, mm Force-Deformation Curve of Form Connections

Force, N 5.1 Form Connection Tests Gage 12 Steel PL 12000 10000 8000 6000 Lab Results Strong Form Model Screw Form Form connection test 4000 2000 0 Weak Form Model 0 2.5 5 7.5 10 12.5 15 17.5 20 22.5 25 Lateral Deformation, mm Force-Deformation Curve of Form Connections

5.2 Bearing Inspection a. Damaged Fixed Bearing Fixed Boundary b. Bearing Model

6. Conclusions The bridge failed in a global torsional mode; Stay-in-place forms greatly delayed the collapse, but were not strong enough to prevent it; Progressive failure of form connections that initiated the failure sequence The bridge would have buckled even if the two deck haunches were identical

7. Recommendations Clarify applicable codes; Add a new code provision that requires full length lateral bracing to be installed between top flanges unless proven unnecessary by analysis

8. NYSDOT Actions Reviewed similar ongoing projects in NYS. Required bracing systems for similar bridges in NYS (NYSDOT Blue Page ) Sought recommendations from AASHTO regarding code revisions.

AASHTO LRFD Specs. 3 rd Edition (2004) Art. 6.11: Provisions for single or multiple closed-box or tub girders Art. 6.7.5: Lateral Bracing 6.7.5.3: Top lateral bracing shall be provided between flanges of individual tub sections. The need for a full-length system shall be investigated If a full length lateral bracing system is not provided, the local stability of the top flanges and global stability of the individual tub sections shall be investigated for the assumed construction sequence

Lateral Torsional Stability of Open-tub girders 1/16 Top Plate Centroid @ +36.3 Shear Ctr. @ -36.0 Izz = 36 in^4 Iyy = 205,817 in^4 Centroid @ +37.3 Shear Ctr. @ -12.2 Izz = 114,870 in^4 Iyy = 212,572 in^4

Application to I-Girder Bridges

Application to I-Girder Bridges

Twin I-Girders: No bottom lateral bracing Iyy = 15,470 in^4 Izz = 472 in^4

Twin I-Girders: With bottom lateral bracing Centroid @ +19.96 Shear Ctr. @ -19.06 Izz = 472 in^4 Iyy = 296,426 in^4

Dead Load Factor Twin I-Girders: With bottom lateral bracing LTB with Non-linear Plate Model 2.5 2.0 1.5 1.0 0.5 0.0 6 0.0 20.0 40.0 60.0 80.0 Transverse Displacement at Midspan [in.]

Dead Load Factor Twin I-Girders: No bottom lateral bracing LTB with Non-linear Plate Model No Lateral Bracing 2.0 1.5 1.0 0.5 0.0 11 0.0 20.0 40.0 60.0 80.0 100.0 Transverse Displacement at Midspan [in.]

Twin I-Girder Behavior--summary More stable than open tub girder. Lateral or lateral-torsional behavior (vs. global torsional) Bottom lateral system effective for lateral resistance Consider top and bottom laterals for long, narrow spans No spec-ready equations for checking global behavior (Single Tubs or Twin-I systems)

Dealing with a bridge failure Expect your inspection program to come under scrutiny Expect safety of other bridges to be questioned Expect requests for data on failed bridge and other bridges Establish point of contact for all media questions. Make public info. Easily available

Dealing with a bridge failure Work with your lawyers, (but do not expect them to always have the same priorities). Establish protections for privileged material, e.g. ongoing investigations.

One Final Lesson The Paradox of Failure When it comes to bridge design, collapse is a most reliable teacher. Henry Petroski Success Through Failure; The Paradox of Design

Questions?