SUPPLEMENTAL REBUTTAL TESTIMONY OF ROBERT SPARKS ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

Similar documents
California s Energy Future

Memorandum. This memorandum requires Board action. Executive Summary

Intentionally left blank

SECTION 5.15 ELECTRICITY AND NATURAL GAS

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Quail Brush Power Plant is Wrong Approach for San Diego - Local Solar Is the Right Solution. Bill Powers, P.E. Powers Engineering September 21, 2012

NTTG Study Plan for the Public Policy Consideration Scenario

DECISION AUTHORIZING LONG-TERM PROCUREMENT FOR LOCAL CAPACITY REQUIREMENTS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

Section 1: Executive Summary

Meeting California s Electricity Needs Without San Onofre or Diablo Canyon Nuclear Power Plants

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Four Corners) Scheduling. Operating Procedure

EE and Reliability: SCE s LCR RFO and Preferred Resources Pilot. ACEEE Energy Efficiency as a Resource National Conference Mohammed Aliuddin

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria

Electrical System Studies

148 FERC 61,009 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Distributed PV the road California is already on. Public Interest Environmental Law Conference Bill Powers, P.E., Powers Engineering March 5, 2011

Tehachapi Wind Energy Storage Project (TSP)

2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference. July 1, 2014

June 24, Notice of Proposed Construction Project Pursuant to General Order 131-D, Weymouth 66/4 kv Substation Project

TRANSMISSION MAINTENANCE COORDINATION COMMITTEE (TMCC) MINUTES January 16, 2014 Meeting from ISO Headquarters Folsom, California

Tehachapi Renewable Transmission Project (TRTP)

4.5 TRANSPORTATION - YEAR 2025 TRAFFIC CONDITIONS WITH PROPOSED TIMP ESTIMATION OF TRIP REDUCTIONS WITH TIMP TRANSIT AND TDM PROGRAMS

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

RELIABILITY PLANNING CRITERIA

PREPARED DIRECT TESTIMONY OF MICHAEL R. WOODRUFF ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

TRANSMISSION CONTROL AGREEMENT APPENDIX A. Facilities and Entitlements

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions. Electric Grid Operations

Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations

Commission Staff Report

CITY AND COUNTY OF SAN FRANCISCO

August 27, 2007 Advice Letter 2146-E. Advice Letter 2146-E is effective August 31, Thank you for your time.

California s Electricity Market. Overview

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

IESO Supply Deliverability Guidelines

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions August 10, Electric Grid Operations

Full Network Model Scope for FNM DB2015Q4

About Southern California Edison

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

Generation and Transmission Interconnection Process

Integration of Renewable Resources

Background City Code Requirements Business License Tax Rates and Revenue

SAN DIEGO DISTRIBUTED SOLAR PHOTOVOLTAICS IMPACT STUDY. Final Report

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions June 4, Electric Grid Operations

Recent Developments in US-Mexico Electricity Trade: A Tale of Two Borders

SPECIFICATION COG-2007

ENERGY AWARD HIGHLIGHTS

AIS Power Reliability

Emera Maine Proposed Potential Transmission Projects. Line Identification Line 75 - KR Sub. Estimated Cost $201,464 $0 $3,200,000

DISCUSSION CALENDAR AGENDA ITEM NO. 11 BOARD OF DIRECTORS MEETING February 27, 2014

Aliso Canyon Gas-Electric Coordination. Issue Paper

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

Panel 2 Opening Statement

Cross-Tie Transmission Line. Ravikanth Varanasi Principal Transmission Planner

Load Dispatcher (Class Code 5223) Task List

Treasure Valley Electric Plan - Community Advisory Committee

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

NERC Cyber Security Standards

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

PJM Merchant Transmission Request. Queue #R75. Mitchell Shepler Hill 138 Kv Feasibility / System Impact Study

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project

Merchant Generation Site Selection On the AEP Transmission System

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014

Instructions for use:

Midwest Reliability Organization Procedure For NERC PRC-012

March 14, Subject: Southern California Edison 2014 Annual Progress Report

Applicability and Eligibility

16 West Coast Regional Plan

Proceedings of the 38th Hawaii International Conference on System Sciences

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

IEPR Lead Commissioner Workshop Electricity Infrastructure Issues in California

Aliso Canyon Gas-Electric Coordination. Straw Proposal

PG&E s Distribution Resource Plan

How To Reduce Energy Use

Network Consulting for Power Grid Optimization

Northport - Norwalk Harbor Cable (NNC) Tie line

3.0 Project Description

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014

Typical Data Requirements Data Required for Power System Evaluation

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

How To Operate The Williston Uvls

Capital Action Plan Status Thru Dec 2015

Microgrids. EEI TDM Meeting Charleston, South Carolina October 7, Neal Bartek Smart Grid Projects Manager

Flexible Capacity Planning for Renewable Integration CEF Topical White Paper Jeremy Hargreaves, Elaine Hart, Ryan Jones, Arne Olson E3

This document should be reviewed at least every two years.

132 FERC 61,083 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING AND INSTITUTING SECTION 206 PROCEEDING

Appendix F. DRECP Energy Development Assumptions and the BLM LUPA

Business Requirements Specification

Item 8: Houston Import RPG Project

5/27/2015. Overview of Energy Storage Value Propositions and Business Cases. Utility Cost-Function: Foundation of Energy Storage Economics.

TERMS AND CONDITIONS

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

Transcription:

Application No.: 1-0-00 Exhibit No.: Witness: Robert Sparks In the Matter of the Application of San Diego Gas & Electric Company (U90E) for a Certificate of Public Convenience and Necessity for the South Orange County Reliability Enhancement Project. Application 1-0-00 SUPPLEMENTAL REBUTTAL TESTIMONY OF ROBERT SPARKS ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

1 7 8 9 10 11 1 1 1 1 1 17 18 19 0 1 Q. What is your name and by whom are you employed? A. My name is Robert Sparks. I am employed by the California Independent System Operator Corporation (CAISO), 0 Outcropping Way, Folsom, California as Manager, Regional Transmission. Q. Have you previously provided testimony in this proceeding? A. Yes, I provided direct testimony in this proceeding served on May, 01 and rebuttal testimony on June, 01. My educational and professional background is provided in my direct testimony. Q. What is the purpose of this testimony? A. The purpose of my testimony is to present the CAISO s analysis of Alternative J to the South Orange County Reliability Enhancement (SOCRE) project proposed in the Recirculated Draft Environmental Impact Report (RDEIR). In summary, Alternative J as proposed is infeasible because it relies on a non-standard substation design that is not consistent with industry standards. If Alternative J was reconfigured to a standard substation design, the alternative would fail to meet the reliability concerns and objectives identified by the CAISO and it would exacerbate other identified reliability concerns in the Southern California Electric Company (SCE) service area. Q. Please provide an overview of Alternative J to the SOCRE project as included in the RDEIR. A. Alternative J is a 0 kilovolt (kv) loop in from the Southern California Edison Company (SCE) 0 kv system to the Trabuco Substation. This alternative was suggested during public review process for the Draft EIR and the DEIR includes it 1

1 7 8 9 10 11 1 1 1 1 1 17 18 19 0 1 as the environmentally superior alternative. Alternative J would upgrade the SDG&E owned Trabuco Substation from 18/1 kv to 0/18/1 kv and interconnect it to the SCE owned 0 kv transmission line between the San Onofre to Santiago substations. Under Alternative J, the DEIR proposes a non-standard substation design as an additional source for the South Orange County 18 kv transmission system. Q. Does the CAISO have any concerns regarding the non-standard substation design at the Trabuco Substation as proposed in Alternative J? A. Yes. As described in Section 7 of Chapter of SDG&E s Second Supplemental Testimony, this substation design is infeasible because it provides insufficient space to construct the 0/18/1 kv Trabuco Substation in accordance with IEEE, industry and SDG&E standards for safety and reliability. A standard substation design would also loop the SONGS-Santiago line into Trabuco substation designed in a breaker-and-a-half bus configuration. 1 As proposed, the new SONGS-Trabuco and the Santiago-Trabuco 0 kv transmission circuits would directly connect to the Trabuco bus without a circuit breaker protecting the substation facilities and circuits. Under this arrangement, San Diego would need to de-energize the two new circuits to perform maintenance at the Trabuco Substation. In the event of a bus fault, line fault, or breaker failure in the SONGS, Santiago, or Trabuco substation, the entire Trabuco Substation and the two circuits would be shut down. This substation configuration would unduly limit operational 1 ORA s proposed Trabuco Alternative reflected this substation design, and the CAISO previously commented on ORA s proposal in its June, 01 rebuttal testimony.

1 7 8 9 10 11 1 1 1 1 1 17 18 flexibility and lead to more frequent reductions of transmission capability on the major transmission path between the Los Angeles Basin and the San Diego systems. Q. If Alternative J was modified to meet industry standards, would the CAISO have any other concerns with this alternative? A. Yes. Even if Alternative J was modified to meet industry standards for substation design, the alternative still must be rejected because it fails to address all identified reliability concerns and objectives that the project is intended to address. Q. The RDEIR indicates that Alternative J would ensure that each of the CAISO identified Category C (N-1-1) violations would be avoided through the 10-year planning horizon. Is this statement correct? A. If the Trabuco Substation is designed to meet industry standards, as discussed above, its system performance would be problematic similar to other proposed alternatives that parallel the SCE 0-kV system with the SDG&E s South Orange County (SOC) 18 kv system. As described in the direct testimony of Neil Millar on behalf of the CAISO, any alternative paralleling SCE 0-kV system with the SDG&E s SOC 18 kv system would materially impact the transmission path between SCE's LA Basin and the San Diego area. Table 1, included in Appendix A to this testimony, demonstrates the negative effects on transfer See the previously submitted direct testimony of the CAISO regarding the Draft Environmental Impact Report Alternatives C1, C and D as well as my rebuttal testimony addressing the Trabuco and Pico alternatives proposed by ORA and Forest Residents Opposing New Transmission Lines (Frontlines).

1 7 8 9 10 11 1 1 1 1 1 17 18 19 capability that this would have on the major transmission corridor between San Diego and Los Angeles for various NERC Category P and P7 contingencies. As indicated in Line 1 of Table 1, the CAISO identified thermal overload issues on the single 0/18 kv transformer at the Trabuco substation proposed in Alternative J. Q. Does Alternative J cause additional reliability concerns on the SCE transmission system? A. Yes. The CAISO 01-01 transmission planning process identified thermal overload and potential transient voltage instability concerns on SCE s adjacent Ellis-Santiago and Ellis-Johanna 0 kv lines and the Johanna/Santiago/Ellis substations for various NERC Category P contingencies. Based on the CAISO s preliminary studies, these concerns could be addressed by implementing 107 megawatts (MW) of preferred resources and energy storage as mitigation. Regardless of the bus configuration design at the Trabuco substation, Alternative J would contribute to the severity of these identified thermal overloads by shifting SOC load that is currently supplied by the Talega /18 kv substation to the Trabuco 0/18 kv substation. This will exacerbate to the need to upgrade the SCE owned Ellis-Santiago and Ellis-Johanna 0 kv lines or increase the need for additional generation or storage resources. Please note that NERC recently changed its contingency naming methodology. New Category P and P7 contingencies would have previously been considered Category C or N-1-1 and C or N- contingencies under the prior naming convention. See ID #SDGE-T-OP1 in Table 1. Formerly known as Category C or N-1-1 contingencies.

1 7 8 9 10 11 1 1 1 1 1 17 18 19 0 1 The CAISO modeled the relative impacts of the SOCRE Project, and Alternative J with an industry standard Trabuco Substation configuration. Tables through provide the results in detail. Table identifies thermal overloads for both of the alternatives based on the 01-01 summer peak base case without any mitigation by additional preferred resources and energy storage. As can be seen, overloading occurs in the SCE system under all alternatives, but the SOCRE Project reduces the magnitude of the overload in each case. Tables and illustrate the effect of the two alternatives in the summer peak base case and the California Energy Commission s high load scenario with mitigation by additional preferred resources and energy storage. As can be seen, the SOCRE project reduces loading on the identified lines in every scenario. This analysis indicates that Alternative J will cause additional loading in the SCE system which must be mitigated through either incremental resource additions or additional transmission system improvements. Figures AA-1 and AA- show the one-line diagram for the SOCRE project and Alternative J including the SCE system in the vicinity. Because Alternative J is electrically closer to the SCE owned Ellis-Santiago and Ellis-Johanna 0 kv lines, it exacerbates overload concerns compared to the SOCRE Project. Q. If the Commission approves Alternative J to the SOCRE Project, what additional improvements would be necessary to address all the CAISO identified reliability concerns? A. In order to meet industry safety and reliability standards, mitigate the negative impact on transfer capability in the major transmission corridor between San Diego

1 7 8 9 10 11 1 1 1 1 1 17 18 19 0 1 and Los Angeles and avoid the potential negative impact on the SCE system, the following system improvements would be required: modification to Alternative J to meet industry standards for substation design; elimination of aged Bank #0 and # transformers at Talega Substation and standardization of the 0/18/9 kv Talega substation; addition of a second 0/18 kv transformer at Trabuco Substation; upgrade of TL18A of the Talega-San Mateo- Laguna Niguel threeterminal-line from Talega Tap to Laguna Niguel; upgrade of TL18A of the Talega-San Mateo-Pico three-terminal-line from Talega to Talega Tap; upgrade of TL181 from Pico to Capistrano; upgrade of TL18 from Talega to Pico; reconfiguration of the Trabuco-Capistrano-Pico-Laguna Niguel 18 kv system; and an increase of ampacity ratings of the SCE owned Ellis-Santiago 0 kv transmission circuit by replacing terminal equipment at Ellis/Santiago substations and an increase of clearance on transmission spans along the circuit. an increase of ampacity ratings of the SCE owned Ellis-Johanna 0 kv transmission circuit by replacing terminal equipment at Ellis/Johanna substations and an increase of clearance on transmission spans along the circuit.

1 7 8 9 10 11 1 1 1 The cost of modification to Alternative J to meet industry standards for substation design alone is estimated by SDG&E to cost $18 million to $ million, which far exceeds the cost estimate for the SOCRE project. Q. Please summarize your testimony. A. The Commission should reject Alternative J presented in the RDEIR for a number of reasons. First, it does not meet industry standards for a substation. Even if Alternative J is configured to meet industry standards for substation design, it will not address all the reliability concerns and objectives that the project is intended to meet. More specifically, Alternative J will negatively impact the transfer capability of transmission corridor between San Diego and Los Angeles and increase identified thermal overloading concerns on the SCE system. Based on these findings, Alternative J is not a reasonable alternative to the SOCRE Project. Q. Does this conclude your testimony? A. Yes. 1 1 17 18 SDG&E s Second Supplemental Testimony, p. 7, line 8. 7

Table 1 Thermal Overloads in the SDGE SOC System - Based on 00 Off-Peak Case (1800 MW Northbound Flow via the SONGS Path) SOCREP VS Alternative J ID Overloaded Facility Contingency Category Description Thermal Loading (% over applicable rating) SOCREP Alternative J SDGE- T-OP1 8 TRABUCO 0 80 TRABUCO 18 1 L_0010_Line S.ONOFRE 0.0 to TRABUCO 0.0 Ckt 1 and L_008_Line S.ONOFRE 0.0 to SANTIAGO 0.0 Ckt 1 P (N-1-1) P7 (N-)* NA 11 SDGE- T-OP 11 CAPSTRNO 18 PICO 18 1 L_0010_Line S.ONOFRE 0.0 to TRABUCO 0.0 Ckt 1 and L_008_Line S.ONOFRE 0.0 to SANTIAGO 0.0 Ckt 1 P (N-1-1) P7 (N-)* NA 99 SDGE- T-OP 80 TALEGA 18 8 TA TAP 18 1 L_0010_Line S.ONOFRE 0.0 to TRABUCO 0.0 Ckt 1 and L_7008_Line TALEGA 18.0 to PICO 18.0 Ckt 1 P (N-1-1) NA 98 SDGE- T-OP 8 TA TAP 18 PICO 18 1 L_0010_Line S.ONOFRE 0.0 to TRABUCO 0.0 Ckt 1 and L_7008_Line TALEGA 18.0 to PICO 18.0 Ckt 1 P (N-1-1) NA 97 SDGE- T-OP 81 LAGNA NL TAP 18 9 LAGNA NL 18 1 L_0010_Line S.ONOFRE 0.0 to TRABUCO 0.0 Ckt 1 and L_700_Line CAPSTRNO 18.0 to PICO 18.0 Ckt 1 P (N-1-1) NA 97 SDGE- T-OP 80 TALEGA 18 PICO 18 1 L_0010_Line S.ONOFRE 0.0 to TRABUCO 0.0 Ckt 1 and Tap_9001_Line TALEGA- TAP-PICO-SANMATEO 18.0 1 P (N-1-1) NA 9 Note: * Category P7 or N- contingency is credible assuming the RDEIR Trabuco Alternative was modified to meet industry standards 8

Table Thermal Overloads in the SCE System - Based on CAISO 01~1 TPP 0 Summer Peak Base Case without mitigation SOCREP VS Alternative J ID Overloaded Facility Contingency Category Description Thermal Loading (% over applicable rating) SOCREP Alternative J SCE- T-B1 0 ELLIS 0 1 SANTIAGO 0 1 L_00_Line ELLIS 0.0 to JOHANNA 0.0 Ckt 1 and L_0001 MIGUEL-ECO ck 1 P (N-1-1) 10 108 SCE- T-B 0 ELLIS 0 1 SANTIAGO 0 1 L_00_Line ELLIS 0.0 to JOHANNA 0.0 Ckt 1 and L_000 ECO-IMPRLVLY ck 1 P (N-1-1) 10 107 SCE- T-B L_00_Line ELLIS 0.0 to SANTIAGO 0.0 Ckt 1 and L_0001 MIGUEL-ECO ck 1 P (N-1-1) 10 10 SCE- T-B L_00_Line ELLIS 0.0 to SANTIAGO 0.0 Ckt 1 and L_000 ECO-IMPRLVLY ck 1 P (N-1-1) 101 10 SCE- T-B L_0001 MIGUEL-ECO ck 1 and L_000_OCOTILLO - SUNCREST ck 1 P (N-1-1) 99 101 SCE- T-B L_000 ECO-IMPRLVLY ck 1 and L_000_OCOTILLO - SUNCREST ck 1 P (N-1-1) 97 99 SCE- T-B7 L_0001 MIGUEL-ECO ck 1 and L_000_IMPRLVLY - OCOTILLO ck 1 P (N-1-1) 97 99 9

Table Thermal Overloads in the SCE System - Based on CAISO 01~1 TPP 0 Summer Peak Base Case with mitigation SOCREP VS Alternative J ID Overloaded Facility Contingency Category Description Thermal Loading (% over applicable rating) SOCREP Alternative J B-M1 0 ELLIS 0 1 SANTIAGO 0 1 L_00_Line ELLIS 0.0 to JOHANNA 0.0 Ckt 1 and L_0001 MIGUEL-ECO ck 1 P (N-1-1) 9 9 B-M 0 ELLIS 0 1 SANTIAGO 0 1 L_00_Line ELLIS 0.0 to JOHANNA 0.0 Ckt 1 and L_000 ECO-IMPRLVLY ck 1 P (N-1-1) 91 9 B-M L_00_Line ELLIS 0.0 to SANTIAGO 0.0 Ckt 1 and L_0001 MIGUEL-ECO ck 1 P (N-1-1) 88 90 B-M L_00_Line ELLIS 0.0 to SANTIAGO 0.0 Ckt 1 and L_000 ECO-IMPRLVLY ck 1 P (N-1-1) 87 89 B-M L_0001 MIGUEL-ECO ck 1 and L_000_OCOTILLO - SUNCREST ck 1 P (N-1-1) 87 89 B-M L_000 ECO-IMPRLVLY ck 1 and L_000_OCOTILLO - SUNCREST ck 1 P (N-1-1) 8 88 B-M7 L_0001 MIGUEL-ECO ck 1 and L_000_IMPRLVLY - OCOTILLO ck 1 P (N-1-1) 8 88 10

Table Thermal Overloads in the SCE System - Based on CAISO 01~1 TPP CEC's 0 High Load Scenario with mitigation SOCREP VS Alternative J ID Overloaded Facility Contingency Category Description Thermal Loading (% over applicable rating) SOCREP Alternative J S-M1 0 ELLIS 0 1 SANTIAGO 0 1 L_00_Line ELLIS 0.0 to JOHANNA 0.0 Ckt 1 and L_0001 MIGUEL-ECO ck 1 P (N-1-1) 10 10 S-M 0 ELLIS 0 1 SANTIAGO 0 1 L_00_Line ELLIS 0.0 to JOHANNA 0.0 Ckt 1 and L_000 ECO-IMPRLVLY ck 1 P (N-1-1) 101 10 S-M L_00_Line ELLIS 0.0 to SANTIAGO 0.0 Ckt 1 and L_0001 MIGUEL-ECO ck 1 P (N-1-1) 97 99 S-M L_00_Line ELLIS 0.0 to SANTIAGO 0.0 Ckt 1 and L_000 ECO-IMPRLVLY ck 1 P (N-1-1) 9 98 S-M L_0001 MIGUEL-ECO ck 1 and L_000_OCOTILLO - SUNCREST ck 1 P (N-1-1) 9 9 S-M L_000 ECO-IMPRLVLY ck 1 and L_000_OCOTILLO - SUNCREST ck 1 P (N-1-1) 9 9 S-M7 L_0001 MIGUEL-ECO ck 1 and L_000_IMPRLVLY - OCOTILLO ck 1 P (N-1-1) 9 9 11

Figure AA-1 SDG&E 0/00 kv System with the SOCRE Project Del Amo Barre Lewis kv Chino (SCE) Legend kv line & bus Alamitos Ellis 0 kv Serrano (SCE) 0/0 kv line&bus transformer Huntington Beach Villa Park phase shifter Johanna Santiago (SCE) Viejo (SCE) line tap line with overload concerned Capistrano the SOCRE Project boundary line Talega SONGS (SCE) Encina 0 kv San Luis Rey Escondido Palomar ~ Potential overload concern on SCE s Ellis-Santiago and Ellis- Johanna 0 kv lines for various overlapping outages in SCE and SDGE (P) Penasquitos Sycamore Mission Suncrest Oldtown TL000 North Gila Silvergate South Bay kv Ocotillo TL000 TL000 APS Otaymesa ~ Plant Pio Pico Plant ~ Otaymesa Miguel kv TL0001 ECO TL000 Imperial Valley kv TDM Plant RPS & Others Plants ~ IID Tijuana (CENACE) La Rosita (CENACE) 1

Figure AA- SDG&E 0/00 kv System with the RDEIT Trabuco Alternative Del Amo Barre Lewis kv Chino (SCE) Legend kv line & bus Alamitos Ellis 0 kv Serrano (SCE) 0/0 kv line&bus transformer Huntington Beach Villa Park phase shifter Johanna Santiago (SCE) Trabuco Viejo (SCE) RDEIR Trabuco Alternative is electrically closer to the concerned facilities in SCE comparing to the SOCREP line tap line with overload concerned boundary line Talega SONGS (SCE) Encina 0 kv San Luis Rey Escondido Palomar ~ Potential overload concern on SCE s Ellis-Santiago and Ellis- Johanna 0 kv lines for various overlapping outages in SCE and SDGE (P) Penasquitos Sycamore Mission Suncrest Oldtown TL000 North Gila Silvergate South Bay kv Ocotillo TL000 TL000 APS Otaymesa ~ Plant Pio Pico Plant ~ Otaymesa Miguel kv TL0001 ECO TL000 Imperial Valley kv TDM Plant RPS & Others Plants ~ IID Tijuana (CENACE) La Rosita (CENACE) 1

APPENDIX A The CAISO used assumptions consistent with the 01-01 transmission plan process in conducting additional analysis on the SOCRE project and the RDEIR Alternative J, which are shown in Table A- 1 and Table A- and can be summarized as follows: Updated load forecast by California Energy Commission (CEC); Updated Once-Through Cooled (OTC) generation retirement schedule; CEC/Commission Long-Term Procurement Process (LTPP) forecasts and authorization, including energy efficiency, Demand Response, Distributed Generation, Energy Storage, and conventional gas fired resources; A total of 107 MW in NQC of Preferred Resource and Energy Storage are assumed to be implemented as mitigation to address reliability concerns in LA Basin and SDGE; Load forecast and generation resources assumptions Table A-1 summarizes the 1-in-10 load forecast and generation resource in the South Orange County area assumed in the CAISO 01-01 0 Summer Peak base cases. For comparison purpose, similar load forecast and generation resource in the CAISO 01~01 TPP 0 Summer Peak base case are also listed in the table. The MW of net load in the 0 Summer Peak case is 1.% higher than the net peak load in the 0 Summer Peak cases on which the CAISO original and the rebuttal testimonies provided in A.1-0-00 were based. Table A-1. Load and Resources Assumptions in the SDGE's South Orange County Area CAISO 01~01 TPP VS CAISO 01~01 TPP Unit 01~01 TPP: 0 Peak 01~01 TPP: 0 Peak Load 1-in-10 Forecast coincident peak MW 89. 0. AAEE MW -0.9-1.78 Demand Response (DR) MW - -11 Load Distributed Reduction Generation (DG) MW -7. 0 Energy Storage (ES) MW -.1 0 Subtotal MW -. -.8 Net Peak Load in SOC MW Landfill Generation MW (in NQC).. 1

Table A-. Load Forecast and Additional Preferred Resources Used as Mitigation in SCE and SDGE 1-in-10 load in LA Basin and SDGE, 1-in- in other areas Unit SCE SDGE Base Case High Load Scenario Base Case High Load Scenario Load Forecast MW 8 9 80 170 Energy Efficiency (AAEE) MW -18-18 -01-01 Net Load MW 708 80 9 79 Track 1 and Conventional Gas Fired MW (in NQC) 18 800 Preferred Resources and Energy Storage that are used as mitigation to address reliability concerns in LA Basin and SDGE in the 01~01 TPP CPUC Authorized Preferred Resource and Energy storage in LA Basin and SDGE Existing repurposed Demand Response RPS Portfolio Distributed Generation Additional Energy Storage based on CPUC D1-10-00 Subtotal of MW in NQC MW 01 100 MW 11 17 MW 0 MW 0 97 MW 188 18 1