First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche, R. Ledru, R.Sterenberg, P. Sollander EDMS 1520642
Outline 1. Terminology 2. LHC Electrical network topology 3. LHC Systems classification 4. Daily average consumption @ 7 TeV and 13 TeV 5. Consumption variation between 7 TeV and 13 TeV 6. Comparison between consumption @ 7 TeV, 13 TeV and LHC design values 7. Active power profile during two runs @ 13 TeV 8. Active power profile during a 13 TeV Ramp-down and a Ramp-up 9. Summary of steady state and peak active powers 10. Conclusion
Terminology Average power [P avg ]: is the mean value of the power consumption during the interval of interest (in our case at least 24 hours, weekly, monthly) Steady state power [P steady ]: Is the mean value of the power during an interval in which the system state variables are considered to be constant (in our case the duration of the: injection, stable beam, TS, etc ) Peak power [p peak ]: the maximum instantaneous power during an interval of interest (in our case: peak during magnets ramp-up) Installed power [P inst ]: the sum of the rated power of the supplied electrical equipment (example on CV) Power profile: is the time evolution of the power acquired through the fastest achievable sampling rate
LHC - Electrical network topology Machine network Radial supply from 66 kv network 66 kv distribution to points LHC 1, 2, 4, 6 and 8 Point LHC 5 feed from point LHC 6 at 18 kv level To Meyrin MEH59 Tunnel loop (also known as LHC General Services loop) 18 kv network installed in the tunnel and coming to surface on all 8 LHC points Feed from point 1 Operated in closed loop mode Included in the autotransfer system Admissible apparent power 30 MVA To Meyrin ME9
LHC - Systems classification Classification given according to rules defined for EN-EL web energy application Systems Cooling: pumping station, cooling towers, air conditioning, etc,.. Ventilation: tunnel ventilation, chillers, air conditioning, etc Cryogenics: Compressors and cooling stations Magnets and converters: Power converters supplying warm and superconducting magnets Radio Frequency: cavities in point 4, Experiences: CMS, ATLAS, ALICE, LHCb General services: Loads not included in the other systems as : F1, F2, F3, F4-400V sockets distribution, UPS systems, 48 V systems, fire and ODH detection, elevators, cranes,.. Loads to be covered by auto transfer in case of internal of external power outage
Daily average consumption @ 7 TeV and 13 TeV P AVG-14-days-june(2012) = 60.8 MW P AVG-14-days-june(2015) = 67.8 MW = + 7 MW (+12%) Note: 21 MW for the LHC experiences are not included
Daily average consumption @ 7 TeV and 13 TeV 1 TS 2 TS Notes: 1 Probable additional load on the LHC loop by EL operation (TBC) 2 Probable additional power request in SM18 (TBC) Analysis: Major contribution to daily power variation is done by magnets and power converters. Probably directly related to the number of ramp-up and ramp down of magnets and the number of hours of operation of the warm magnets Average daily power consumption during TS is between 48 and 52 MW RF + magnets and converters OFF Cryo decrease of consumption All other systems remains constant
Power consumption variation between 7 TeV and 13 TeV Comparison done on the first 14 days of June (2015 minus 2012) Comparison of the systems daily average power consumption variation: +15 to +20 % for the cryogenics +25 to +60 % for magnets and power converters +10 to +12 % for cooling -20 to +15 % for ventilation -15 to +5 % for radio frequency -10 to +30 % for general services
Comparison between average consumption @ 7 TeV, 13 TeV and LHC design values System LHC design report - 2004 (table 7.1) [MW] EN-EL survey March 2011 (EDMS 1153902) [MW] LHC design 14 TeV (FCC meeting,24 November 2014) [MW] Nov-2012 7 TeV (FCC meeting, 24 November 2014) [MW] June 2012 7 TeV [MW] June 2015 13 TeV [MW] Duration of measurement Not applicable Not applicable Not applicable One month 14 days 14 days Data acquisition Not applicable Not applicable Not applicable 10 min average power Stored only if +/- 10% variation compared to last point acquired Copy of data presented on 24 th of November 2014 1min sampling rate 100 kw power variation 1min sampling rate 100 kw power variation Magnets and power converters 18.8 17.4 20 3 3.1 4.7 Cryogenics 48.8 35.0 35 32 30.1 35.9 Cooling 23.7 33.2 20 6 6.2 6.8 Ventilation (32.8 winter) 14 4 3.8 3.6 Radio Frequency 17.9 7.2 18 7 6.6 6.3 General Services 13.6 Included in other systems 20 13 11.0 10.5 Experiments 21.8 23.2 22 21 21 21 Other machine 1.92 Not identified 2.5 0 0 0 Total [MW] 155.6 116.0 151.5 86 81.8 88.8 Estimates / Survey Measurements
Active power profile during LHC run @ 13 TeV The period considered goes from the 13 June (16h30) to 14 June (17h16) P peak = 83 MW 1 1 P steady 6.5 TeV = 70 MW P AVG 68 MW (dotted line) P steady 450 GeV = 63 MW 1 Power variations to be further investigated. Could be real or due to data processing mistakes
Active power profile during a Ramp-down and a Ramp-up Ramp-down and Ramp-up snapshot Physics Dump Ramp down @ injection injection Ramp up Tune squeeze adjust Physics 2 1 P peak = 82 MW P steady 6.5 TeV = 70 MW 3 P AVG = 68 MW (dotted line) P steady 450 GeV = 63 MW 1 Beam energy ramp up. Power increase mainly due to power converters 2 Power start to decrease before start of ramp-down. 3 Transitory period during ramp-down.
Summary of steady state and peak active powers Description Name June 2012 7 TeV [MW] June 2015 13 TeV [MW] Steady state at 450 GeV (injection) P steady 450 GeV Data not retrievable 63 Steady state at 13 TeV P steady 6.5 TeV Data not retrievable 70 Steady state during TS P steady TS 49 50 Peak active power during a LHC run P peak Data not retrievable 81 21 MW for the experiences are not counted and shall be added whenever applicable (i.e. not during TS) Deviation on measured data will be determined by additional measurements Steady state and peak consumptions under nominal LHC operational conditions are the key values for electrical network dimensioning, redoundancy layouts and optimization of network operation (i.e. systems outage in case of reduced power availability)
Conclusion DAQ system for LHC power consumption is now operational and tuned to acquire the maximum data points achievable Data for daily average consumption are sufficient to estimate LHC energy consumption and costs Dimensioning of the FCC network infrastructure require to study more in detail the steady states and peak power consumptions of LHC Definition of individual systems installed power vs. systems operational processes are necessary to define simultaneity factors and power profiles
Thank you for your attention
Annexes
Example: Cooling and ventilation Comparison of power consumption @ 7 TeV, 13 TeV and announced values System Nov-2012 7 TeV June 2012 7 TeV June 2015 13 TeV Cooling 6 6.2 6.8 Ventilation 4 3.8 3.6 Total [MW] 10 10.0 10.4 Cooling and ventilation power needs are stable during LHC operation @ 13 TeV Announced values diverge from measured values Need to use a common terminology (average, peak, steady state, etc )
Power consumption for LHC cooling and ventilation (MW) Installed Power Sum of equipment rated power Cooling 23 Ventilation 52 Total 75 Required power Accounting for back up Cooling 18 Ventilation 39 Total 57 Peak consumption (I) Running LHC in winter conditions Cooling 12 Ventilation 26 Total 38 Peak consumption (II) LHC stopped in winter conditions Cooling 9 Ventilation 25 Total 34 Peak consumption (III) Running LHC in summer conditions Cooling 13 Ventilation 18 Total 31 Average peak consumption over the year Cooling 10 Ventilation 20 Total 30 G. Peon FCC I&O meeting 25.02.2015 17
Systems - Installed active power System Installed active power [MW] Notes Magnets and power converters 39.4 Max taken from LHC design report - 2004 Cryogenics 48.4 Max taken from LHC design report - 2004 Cooling 23 Provided by system owner Ventilation 52 Provided by system owner Radio Frequency 17.9 Max taken from LHC design report - 2004 General Services 13.6 Max taken from LHC design report - 2004 Experiments 21.8 Max taken from LHC design report - 2004 Other machine 1.92 Max taken from LHC design report - 2004 Total [MW] 218.0 Network - Available active power System Installed active power [MW] Notes LHC - 1 36 1 x 66 kv transformer rating Meyrin load (20 MW) LHC - 2 60.8 2 x 66 kv transformer rating LHC - 4 30.4 1 x 66 kv transformer rating LHC - 6 30.4 1 x 66 kv transformer rating LHC - 8 30.4 1 x 66 kv transformer rating LHC loop 21.8 Limited by loop ampacity Total [MW] 209.8
Impact of TI2 and TI8 on LHC active power profile (1)
Impact of TI2 and TI8 on LHC active power profile (2)