20+ Free PMP EVM Practice Questions with Explanations

Similar documents
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Project Cost Management

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

An introduction to Earned Value Analysis

INSE 6230 Total Quality Project Management

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value Formulae

PROJECTS SCHEDULING AND COST CONTROLS

Using Earned Value Management for Improving Processes. By Cynthia K. West

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

IST 302 : Project Cost Management

Tracking Budgets and Schedules

Earned Value Management Guidelines

Introduction to earn value management in Civil Engineering

Project Cost Management

performance management system that is based on Earned Schedule Management.

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

AACE International Recommended Practice No. 86R 14

Chapter 7. (PMBOK Guide)

How To Manage A Project

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

Earned Value and Agile Reporting

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

700 Analysis and Reporting

Estimating Cost at Completion - Judgment & EV Information

COINS EVA Earned Value Analysis

Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )

Forecasting Project Schedule Completion by Using Earned Value Metrics

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

Brainstorm. What is Cost and Project Cost Management?

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

PROJECT COST MANAGEMENT

Project Control with ProTrack

CVR/IT Consulting LLC

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

Simple Earned Value (Using MS Project 2010)

PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS

A Gentle Introduction to Earned Value Management Systems

Earned Value Analysis Exercise

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

technical tips and tricks

Module 5 Cost Management PMP Exam Questions

EVM.01. Earned Value Analysis Why it Doesn't Work

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Project Cost Management

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Project Portfolio Earned Value Management Using Treemaps. University of Maryland, College Park, Maryland. 1 Introduction

CPM -100: Principles of Project Management

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

Project Management: Tracking Progress and Earned Value with MS Project 2003

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Metrics for Agile Projects:

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Agile Project Management Controls

The To Complete Performance Index

Predicting progress on your project

Certification Exam Objectives: PK0-003

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

Chapter 7: Project Cost Management. Munawar

Earned value method as a tool for project control

Earned-Value Benchmarks for Re-baselining Your Project

L10: Budgeting and Cost Control. Olivier de Weck

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM,

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Orange County Convention Center Orlando, Florida June 3-5, Using SAP PS Earned Value to Manage IT Projects Michael Kim

PMI Lexicon of Project Management Terms

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

What is the Health of my Project?

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

plans based on actual cost, schedule and technical progress of work [1, 9].

earned value management

(AA12) QUANTITATIVE METHODS FOR BUSINESS

Schedule Adherence a useful measure for project management

How to Use EVM to Maintain Quality in an Agile Environment. A National Asset for National Missions 1

Assessing Schedule Performance with Earned Value

DCMA DCMA-EA PAM October 2012

Tracking Software Development Progress with Earned Value and Use Case Point

Earned Schedule Leads to Improved Forecasting

Macroeconomics 2301 Potential questions and study guide for exam 2. Any 6 of these questions could be on your exam!

Appendix D Glossary Of Terms

Using Earned Value Management Concepts to Improve Commercial Project Performance

Transcription:

1 / 9 20+ Free PMP EVM Practice Questions with Explanations Earned Value Management (EVM) Calculation questions are usually regarded as one of the most difficult part of the PMP Exam. However, if PMP Aspirants can understand the EVM Calculation formulas correctly and master a few skills to tackle the EVM questions, these dreaded EVM questions would become lifesavers as nearly every PMP Aspirants can get all the EVM questions correct. Below you will find 20+ PMP EVM practice questions categorized by related skills to help you understand what you are required to know in order to correctly answer all the EVM questions that would appear on the PMP Exam. Try them and understand thoroughly how to tackle the questions through the explanations to each question. You too will be able to get all PMP EVM questions correct. Wish you PMP success! Note: the answer explanation to each question is directly under the question choices in the "grey box" you can either move the cursor over it or highlight it with the mouse to reveal the answer... EVM Graph Questions The EVM graph questions are one of the easiest questions to answer as you will only need to understand the meaning of the relative positions of the AC, PV and EV: AC vs PV: whether the project is under or over budget (AC > PV = over budget; AC ) EV vs PV: whether the project is ahead of or behind schedule (EV > PV = ahead of schedule; EV ) 1. With reference to the diagram below, it can be inferred that the project is currently:

2 / 9 1. ahead of schedule and under budget 2. ahead of schedule and over budget 3. behind schedule and under budget 4. behind schedule and over budget Solution: D As of today, AC > PV = over budget and EV, so the project is both "behind schedule and over budget". 2. With reference to the diagram below, it can be inferred that the project is currently:

3 / 9 1. ahead of schedule and under budget 2. ahead of schedule and over budget 3. behind schedule and under budget 4. behind schedule and over budget As of today, AC PV = over budget and EV > PV = ahead of schedule, so the project is "ahead of schedule and over budget". Definition of EVM Metrics These types of questions will test you on your understanding of the meaning of various EVM metrics: Planned Value (PV) how much work was scheduled to date Earned Value (EV) how much work was completed to date Actual Cost (AC) the amount of money spent so far Budget at Completion (BAC) the total budget for the project Estimate at Completion (EAC) the estimated total amount of money needed to be put into the project based on the information available as today Estimate to Completion (ETC) how much more do we need to put into the project to complete it

4 / 9 Variance at Completion (VAC) the difference between the estimated total cost and the original budget Cost Performance Index (CPI) ratio between EV and AC, to reflect whether the project work is under / on / over budget in relative terms Schedule Performance Index (SPI) ratio between EV and PV, to reflect whether the project work is ahead of / on / behind schedule in relative terms To Complete Performance Index (TCPI) the efficiency needed to finish the project on budget, it is the ratio between budgeted cost of work remaining and money remaining 1. If a project has a Schedule Performance Index (SPI) of 0.90, this means that: 1. 90% of the work planned to date has been completed 2. 90% of the work of the whole project has been completed 3. 90% of the budget planned to date has been spent 4. 90% of the project budget has been spent The Schedule Performance Index (SPI) represents the performance of the project in terms of schedule up to the moment. If it is smaller than 1, less than 100% of the scheduled work has been completed to date. 2. If a project has a Cost Performance Index (CPI) of 0.90, this means that: 1. 90% of the work planned to date has been completed 2. 90% of the budget planned to date has been spent 3. 111% of the budget planned to date has been spent 4. 111% of the project budget has been spent The Cost Performance Index (CPI) represents the performance of the project in terms of budget up to the moment. If it is smaller than 1, the project is currently over budget (i.e. has spent more than what has been planned). 3. If a project has a To Complete Performance Index (TCPI) of 0.90, this means that: 1. 90% of the work planned up to today has been completed 2. 90% of the budget planned up to today has been spent 3. the project can spend money at a rate 11% higher than planned and still meet the project budget 4. the project can spend money at a rate 10% lower than planned and still meet the project budget The To Complete Performance Index (TCPI) is the efficiency needed to finish the project on budget. If it is smaller than 1, that means that we have more money left on the budget than the remaining Planned Value (PV) to achieve. Therefore, in theory, we can spend more money yet can still finish the project on budget. (However, in reality, it is generally preferred to finish the project under budget. A TCPI smaller than 1 is a good sign that the project is going healthy.) 4. A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.80. The project is currently: 1. ahead of schedule and under budget 2. behind schedule and under budget 3. ahead of schedule and over budget 4. behind schedule and over budget Solution: D CPI and SPI, so the project is both "behind schedule and over budget".

5 / 9 5. According to EVM, which term below represents the outstanding amount of money required to finish the project? 1. Planned Value (PV) 2. Earned Value (EV) 3. Estimate to Complete (ETC) 4. Estimate at Completion (EAC) By definition, Estimate to Completion (ETC) is the amount of money we need to put into the project from today in order to complete it. 6. According to EVM, which term below represents the budgeted cost of the work to be completed to date? 1. Planned Value (PV) 2. Earned Value (EV) 3. Estimate to Complete (ETC) 4. Estimate at Completion (EAC) By definition, Planned Value (PV) is how much work was scheduled to date. Simple EVM Calculation Questions For these types of questions, you will simply need to recall the correct EVM calculation formulas and correctly substitute the values into the formulas to arrive at the correct answer. Please do make use of the on-screen calculator / physical calculator provided to do the calculation even if you are a Maths wizard. It is a pity to lose marks for careless calculation even if you have selected the correct formula. Also, most of such simple EVM calculation questions will supply more than enough information for you to use as a kind of distractor, it is a test of whether you can select the correct formulas as well as the correct values to substitute into the equation. SV = EV - PV CV = EV - AC SPI = EV/PV CPI = EV/AC VAC = EAC - BAC 1. A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)? 1. $200 2. $0 3. -$100 4. -$200 SV = EV - PV SV = $1000 - $800 = $200 Note that the Actual Cost (AC) is not used in the calculation.

6 / 9 2. A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Cost Variance (CV)? 1. $200 2. $0 3. -$100 4. -$200 CV = EV - AC CV = $1000 - $800 = $200 Note that the Planned Value (PV) is not used in the calculation. 3. A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Schedule Performance Index (SPI)? 1. 1.25 2. 0.80 3. 0.71 4. 1.40 The formula to be used to calculate SPI is: SPI = EV / PV SPI = $250 / $350 = 0.71 4. A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Cost Performance Index (CPI)? 1. 1.25 2. 0.80 3. 0.71 4. 1.40 The formula to be used to calculate CPI is: CPI = EV / AC CPI = $250 / $200 = 1.25 EVM Estimate At Completion (EAC) Questions Since there are multiple Estimate at Completion (EAC) formulas, PMP Aspirants should be able to get clues from the questions on which EAC formula to use: EAC = BAC/CPI If we believe the project will continue to spend at the same rate up to now (e.g. the delay is caused by reasons which is likely to continue) EAC = AC + (BAC-EV) If we believe that future expenditures will occur at the original forecasted amount (no more delays of the same kind in future) EAC = AC + [(BAC-EV)/(SPI*CPI)] If we believe that both current cost and current schedule performance will impact future cost performance

7 / 9 EAC = AC + New Estimate If we believe the original conditions and assumptions are wrong 1. For the project with original project budget $1000 and both the Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 1. Assuming the project will continue to spend money at the same rate, what is the Estimate At Completion (EAC) of the project? 1. $833 2. $933 3. $1,000 4. $1,033 As the project will continue to spend at the same current rate, the formula to be used would be: EAC = BAC/CPI EAC = $1000 / 1 = $1000 2. For the project with Earned Value (EV) = $350, Actual Cost (AC) = $400 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The original project budget is $1,000. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the Estimate At Completion (EAC) of the project? 1. $1,002 2. $1,102 3. $1,202 4. $1,302 As the project will be impacted by the current cost performance and current schedule performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)] EAC = $400 + [($1000 - $350) / (0.9 * 0.9)] = $780 3. For a project with Estimate at Completion (EAC) = $120,000 and Cost Performance Index (CPI) is 0.90. What is the Budget at Completion (BAC)? 1. $108,000 2. $118,000 3. $158,000 4. $208,000 As no information is given on the future performance of the project, we could safely assume that the project will spend at the same rate. So we will make use of the formula: EAC = BAC / CPI $120,000 = BAC / 0.90 BAC = $120,000 * 0.90 = $108,000 Wordy Calculation Questions Usually these questions will describe you are the project manager of a project which is X months into the schedule and X% of work has been completed so far along with lots of other information. The questions will span several lines. Then it will ask you to calculate some EVM metrics based on

8 / 9 the information provided. Also, the questions will not make use of EVM terms (like Planned Value, Actual Cost, Earned Value, etc.) but you can easily infer those values from the description provided. The key to answering wordy questions correctly is to read the questions carefully and extra useful information from the questions and write down PV, EV, AC, etc. while you are reading the questions. 1. You are the project manager of a housing project in which a total of 10 houses are to be build over 10 months (1 house per month). The total budget for the housing project is $1,000,000. The project is now at the end of the 6th month with 5 houses built and $500,000 spent. The project is behind schedule owing to a work strike for a month. The Cost Performance Index (CPI) for the project is: 1. 1.0 2. 0.9 3. 1.1 4. 1.2 The formula to be used to calculate CPI is: CPI = EV / AC CPI = $500,000 / $500,000 = 1.0 2. You are the project manager of a road paving project. A total of 10km of road is to be paved over a 5-month period. The total budget for the project is $10,000. The project is now at the end of the 3rd month with 4km of road paved and $8,000 spent. The Schedule Performance Index (SPI) for the project is: 1. 0.78 2. 0.98 3. 1.20 4. 1.33 Solution: D Since the road is assumed to be paved linearly, i.e. 2km of road per month. At the end of 3rd month, the PV should be $6,000 (for 6km of road). The formula to be used to calculate SPI is: SPI = EV / PV CPI = $8,000 / $6,000 = 1.33 Complicated EVM Calculation Questions These types of questions will required PMP Aspirants to make use of more than 1 PMP EVM formulas. These questions are considered the most difficult of all PMP EVM questions. Most PMP Aspirants not coming from a Science / Maths background would not even know which EVM formulas to pick, let alone arriving at the correct answer. But the good news is that these questions would seldom appear on the PMP Exam (for your reference: I got none in my PMP Exam). 1. For a project with Earned Value (EV) = $300, Actual Cost (AC) = $350 and Planned Value (PV) = $400. The overall project budget is $1,000. Assume that you will continue to spend at the same rate as you are currently spending. What is the Variance At Completion (VAC)?

Powered by TCPDF (www.tcpdf.org) 9 1. -$150 2. $150 3. -$167 4. $167 Solution: D As the project will continue to spend at the same current rate, the formula to be used would be: VAC = EAC - BAC EAC = BAC/CPI CPI = EV/AC VAC = BAC/(EV/AC) - BAC = $1000/($300/$350) - $1000 = $167 2. For the project with Earned Value (EV) = $300, Actual Cost (AC) = $250 and Planned Value (PV) = $300. The original project budget is $1000. Assuming the project will continue to spend money at the same rate, what is the Estimate At Completion (EAC) of the project? 1. $833 2. $933 3. $1,000 4. $1,033 As the project will continue to spend at the same current rate, the formula to be used would be: EAC = BAC/CPI CPI = EV/AC EAC = BAC/(EV/AC) = $1000 / ($300/$250) = $833 3. For the project with Earned Value (EV) = $350, Actual Cost (AC) = $300 and Planned Value (PV) = $400. The original project budget is $1,000. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the Estimate At Completion (EAC) of the project? 1. $837 2. $937 3. $987 4. $1,280 Solution: B As the project will be impacted by the current cost performance and current schedule performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)] SPI = EV / PV = $350 / $400 = 0.875 CPI = EV / AC = $350 / $300 = 1.167 EAC = BAC/(EV/AC) = $300 + [($1000 - $350) / (0.875 * 1.167)] = $937 / 9