Centre, Bandar Tasik Selatan, Kuala Lumpur, Malaysia.

Similar documents
Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

BEARING CAPACITY AND SETTLEMENT RESPONSE OF RAFT FOUNDATION ON SAND USING STANDARD PENETRATION TEST METHOD

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

STRUCTURAL DAMAGE OF A 5-STOREY BUILDING: DIFFERENTIAL SETTLEMENT DUE TO CONSTRUCTION OF AN ADJACENT BUILDING OR BECAUSE OF CONSTRUCTION DEFECTS?

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

The design of foundations for high-rise buildings

CE 366 SETTLEMENT (Problems & Solutions)

CHAPTER 9 FEM MODELING OF SOIL-SHEET PILE WALL INTERACTION

How To Model A Shallow Foundation

PILE FOUNDATIONS FM 5-134

Validation of methods for assessing tunnelling-induced settlements on piles

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

A case study of large screw pile groups behaviour

13. AN INTRODUCTION TO FOUNDATION ENGINEERING

ENCE 4610 Foundation Analysis and Design

ESTIMATION OF UNDRAINED SETTLEMENT OF SHALLOW FOUNDATIONS ON LONDON CLAY

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

vulcanhammer.net This document downloaded from

Ground improvement using the vibro-stone column technique

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION

Optimum proportions for the design of suspension bridge

Improvement in physical properties for ground treated with rapid impact compaction

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Load and Resistance Factor Geotechnical Design Code Development in Canada. by Gordon A. Fenton Dalhousie University, Halifax, Canada

Dynamic Load Testing of Helical Piles

Formwork for Concrete

NEGATIVE SKIN FRICTION AND SETTLEMENT OF PILES. Dr. Bengt H. Fellenius, P. Eng. University of Ottawa, Canada

GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design

Module 7 (Lecture 24 to 28) RETAINING WALLS

CPTic_CSM8. A spreadsheet tool for identifying soil types and layering from CPTU data using the I c method. USER S MANUAL. J. A.

Embedded Retaining Wall Design Engineering or Paradox?

The assessment of the risk of damage to buildings due to tunnelling and excavations AN HISTORICAL PERSPECTIVE

MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS

4.3 Results Drained Conditions Undrained Conditions References Data Files Undrained Analysis of

PDCA Driven-Pile Terms and Definitions

Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P

16. Beam-and-Slab Design

INTRODUCTION TO SOIL MODULI. Jean-Louis BRIAUD 1

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

CH. 2 LOADS ON BUILDINGS

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

NUMERICAL MODELLING OF PIEZOCONE PENETRATION IN CLAY

Compression load testing straw bale walls. Peter Walker Dept. Architecture & Civil Engineering University of Bath Bath BA2 7AY.

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

When to Use Immediate Settlement in Settle 3D

ATLAS RESISTANCE Pier Foundation Systems

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Technical Notes 3B - Brick Masonry Section Properties May 1993

HOW TO DESIGN CONCRETE STRUCTURES Foundations

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

ALLOWABLE LOADS ON A SINGLE PILE

A Theoretical Solution for Consolidation Rates of Stone Column-Reinforced Foundations Accounting for Smear and Well Resistance Effects

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

VERTICAL STRESS INCREASES IN SOIL TYPES OF LOADING. Point Loads (P) Line Loads (q/unit length) Examples: - Posts. Examples: - Railroad track

Simplifying design and construction. Alan Tovey, Director The Basement Information Centre

Jack-in Piling Environmental Friendly Piling System

DESIGN AND CONSTRUCTION CONSIDERATIONS FOR DEEP EXCAVATION.

Embankment Consolidation

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

How To Calculate Tunnel Longitudinal Structure

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Design Manual to BS8110

Practice of rapid load testing in Japan

SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE

Structural Analysis. EUROCODE 2 Background and Applications

EUROCODE 7 & POLISH PRACTICE

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

Seismic Risk Prioritization of RC Public Buildings

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

DESIGN SPECIFICATIONS FOR HIGHWAY BRIDGES PART V SEISMIC DESIGN

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

A N Beal EARTH RETAINING STRUCTURES - worked examples 1

Structural Design of Multi-story Residential Building for in Salem, India

Laterally Loaded Piles

GUIDELINE FOR HAND HELD SHEAR VANE TEST

Field tests using an instrumented model pipe pile in sand

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Vibration mitigation for metro line on soft clay

Settlement of Shallow Circular Foundations with Structural Skirts Resting on Sand. ÉeôdG Y I~æà ùÿg á«fé ûf G ±Gƒ G e á«ë ùdg ájôfg~dg ~YGƒ dg hõf

Soil Mechanics. Outline. Shear Strength of Soils. Shear Failure Soil Strength. Laboratory Shear Strength Test. Stress Path Pore Pressure Parameters

EN Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

Effect of Sleeve Shrink-fit on Bearing Preload of a Machine Tool Spindle: Analysis using Finite Element Method

MECHANICS OF SOLIDS - BEAMS TUTORIAL 1 STRESSES IN BEAMS DUE TO BENDING. On completion of this tutorial you should be able to do the following.

Seismic performance evaluation of an existing school building in Turkey

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

By D. P. StewarP and M. F. Randolph z

CONSOLIDATION

Transcription:

Methodology for Design of Piled Raft for Five-Storeys Buildings on Very Soft Clay Tan, Y.C. 1, Cheah, S.W. 1 and Taha, M.R. 2 Abstract Conventional piled foundation is usually designed for buildings to provide adequate load carrying capacity and to limit the overall settlement and hence control differential settlement within tolerable limits. Piles are often installed into competent stratum or to set. However, this solution generally only addresses the short-term problem associated with soft clay as pile capacity is also significantly reduced due to negative skin friction. This often reduces the cost-effectiveness of such conventional solution. In this paper, design methodologies of a floating piled raft foundation system for medium rise building (5-storey) on soft clay are discussed. The design objective is to control the differential settlement at the onset rather than only limiting the overall settlement. The foundation of medium rise building is designed using skin-friction piles of different length. The design also considers the interaction between piled raft and soil in order to produce an optimum design which satisfies both serviceability and ultimate limit states. The design methodologies and monitoring results of the successfully implemented buildings are also presented in the paper. 1.0 Introduction The medium rise building is located at a residential and commercial development of about 1200 acres at Bukit Tinggi, Klang, Malaysia which comprises of terrace houses, semi-detached houses, bungalows, apartments, commercial units, and other amenities. This development is constructed over soft silty clay, termed as Klang Clay (Tan et al., 2004a). The conventional design approach and construction of buildings over deep deposit of highly compressible soft clay is often associated with problems such as 1 Gue and Partners Sdn Bhd, Kuala Lumpur, Malaysia, 39-5 Jalan 3/146, The Metro Centre, Bandar Tasik Selatan, 500 Kuala Lumpur, Malaysia. e-mail: gnp@gueandpartners.com.my 2 Professor, Dept. of Civil & Structural Eng., University Kebangsaan Malaysia, Bangi, Malaysia, e-mail: dmrt@eng.ukm.my 1

excessive differential settlement, negative skin friction and bearing capacity failure. Piles are introduced to address the issue of bearing capacity and excessive differential settlement. The piles are often installed into competent stratum or to set in order to limit the differential settlement by reducing the overall settlement of the structure. However, this solution only addresses short-term problem associated with soft clay as pile capacity is significantly reduced due to negative skin friction. This often reduces the cost-effectiveness of such conventional solutions especially if the depth of the compressible layer is significant. Tan et al. (2004b) have presented a design methodology for low-rise buildings (less than 3-storey high) on very soft clay using settlement reducing piles. In this paper, a design methodology for floating piled raft foundations for 5-storey apartments is presented together with a discussion on the results of settlement monitoring on the completed buildings. 2.0 Subsoil Condition The alluvial deposits at the site generally consist of very soft at the top to firm silty CLAY layer up to a depth of 25 to 30m with the presence of intermediate sandy layers. The silty CLAY stratum is generally underlain by silty SAND. Klang Clay can be divided into two distinct layers at a depth of 15m. The details of Klang Clay are presented in the paper by Tan et al. (2004a). 3.0 Design Approach for Platform Earthworks Design approaches for foundation of the apartments on very soft soils are integrated with ground treatment design for the earthworks so that both designs are technically compatible and efficient. In this project, both temporary surcharging and preloading techniques are adopted to control long-term settlement of the subsoil under the loads from the fill and buildings. Asaoka s method (Asaoka, 1978) was adopted to determine the degree of consolidation. After the subsoil had consolidated to the required degree of consolidation, the temporary earth fills were removed and followed by the foundation works. 4.0 Design Methodology for Foundation of 5-Storey Apartments 4.1 Design concept and methodology Differential settlement control approach has been adopted for foundation of 5-storey apartment where the settlement reducing piles are introduced at the concentrated load area or large settlement area to control the differential settlement but not necessarily reducing the average total settlement significantly. Horikoshi and Randolph (1998) suggested that for uniformly loaded raft, piles distributed over the central 16-25% of the raft area is sufficient to produce an optimum design and for piled raft subjected to non-uniform vertical loads, the use of piles with varying length would give the most optimum design (Reul and Randolph, 2

2004). However, these recommendations have yet to be explored for medium rise buildings with concentrated column loads on very soft clay. Poulos (2001) suggested that in order to provide an optimum piled raft foundation design, the following aspects shall be considered and checked: - (a) Ultimate load capacity of piled raft for vertical, lateral and moment loadings (b) Maximum settlement (c) Differential settlement (d) Raft moments and shears for the structural design of the raft (e) Pile loads and moments for the structural design of the piles 4.2 Structural column loadings Generally, the column loads of the 5-storey apartments are highest at the columns and ranges from about kn to 750kN. The line load from the brick wall is 9 kn/m (4.5 inch thick brick wall) and the uniform live load acting on the ground floor raft is 2.7 kn/m 2 (1.5 kn/m 2 live load + 1.2 kn/m 2 floor finishing) as per recommended values given by BS6399: Part 1: 1996. The main design criterion for the 5-storey apartments is to limit the differential settlement and relative angular distortion to 1/350 (Skempton and MacDonald, 1956) to prevent cracking in walls and partitions. Figure 1. Typical cross-section of strip-raft for low cost apartments. Completed 5-storey Apartments BLOCK D UNIT PANGSAPURI 5 TINGKAT BLOCK B UNIT PANGSAPURI 5 TINGKAT Soft compressible layer ( 25 to 30 m) Piles with varying length (18m, 21m BLOCK C Monitored Block UNIT PANGSAPURI 5 TINGKAT Stiff layer Figure 2. Schematic of piled raft system with varying pile lengths superimposed on completed low cost apartments. Figure 3. Site layout plan for low cost apartment. 3

4.3 Foundation system of 5-Storey apartments The foundation system adopted for the low cost apartments consists of 200mm x 200mm reinforced concrete (RC) square piles of lengths varying from 18m to 24m interconnected with 350mm x 0mm strips and 300mm thick raft. Fig. 1 shows a typical section of the strip-raft foundation system and Fig. 2 shows schematic view of the foundation system superimposed onto the completed low cost apartments. A total of 504 piles consisting of 284 piles of 18m length, 1 piles of 21m length and piles of 24m length spread over the whole building layout is adopted. This represents pile spacing/pile size (s/d p ) ratio of approximately 10 and total pile length (nl p ) of 9912m. The locations of the strips are adjusted during detailed design to ensure the strips are available beneath all the columns (i.e. concentrated loads) for optimum structural design. 4.4 Foundation analysis and design Two major cases were considered in the detailed analysis for the foundation of 5- storey apartment, i.e.: - a) Case 1: Pile-soil-structure interaction b) Case 2: Overall settlement behaviour Case 1 takes into consideration of the pile-soil-structure (foundation raft) interaction in order to determine the stresses distribution and deformation and settlement of the piles and raft. The modelling of pile-soil-structure interaction can be carried out using 3-dimensional finite element method (FEM) software (e.g. PLAXIS 3-D Foundation). However, due to the computation limit, the available FEM software for engineering usage at this stage can only account for simple piled raft problems with small numbers of piles at reasonable time and computer resources but not for complicated piled raft problems with irregular loadings pattern and large numbers of piles. Therefore, an iterative approach using combination of 2-dimensional FEM software (e.g. SAFE) to compute the structural stresses induced in the raft foundation and elastic pile interaction software (e.g. PIGLET/PIGEON) to compute the pile-soil-pile interaction has been adopted to reduce the required computation time. Since the foundation system of the 5-storey apartment consists piles of varying lengths, therefore, the solutions of Randolph and Wroth (1979) which was derived for piles of uniform length and adopted in the software PIGLET (which only allows single pile length as input) is no longer applicable for the current design. Hence, the original equation proposed by Randolph and Wroth (1979) is revisited by the Authors to derive a solution for piles with varying pile length. The solution for pile interaction proposed by Randolph and Wroth (1979) is based on the solution for single pile (Randolph and Wroth, 1978) and extended for pile groups based on the principle of superposition. A stiffness matrix relating load, P t and settlement, w t is then obtained with the pile length incorporated into the matrix as a constant. The method is based on the superposition of individual pile displacement fields, considering the average behaviour down the pile shafts separately from that beneath the level of the pile bases. For cases with different pile lengths, the interaction of the pile bases at different levels is very complicated and its effect to 4

shear stress along the pile shaft unknown. However, for the current application in soft ground, the pile capacity is derived primarily from shaft/skin friction with very little end-bearing contribution. Therefore, the original equation proposed by Randolph and Wroth (1979) can be rewritten with pile length as variable where every single pile in the group can be assigned different values of pile length. This concept has been incorporated in the software, Pile Group Analysis Using Elastic or Non-linear Soil Behaviour, PIGEON (Chow and Cheah, 2003). Fig. 3 shows the site layout plan for the 5-storey apartments. In this layout, as the apartments are located close to each other, the pile-soil-pile interaction of the adjacent blocks have also been considered in the foundation analysis instead of considering the pile-soil-pile interaction within the individual block only. As Case 1 only addresses the short term behaviour of the piled raft foundation, therefore, an additional case, namely Case 2 is required to address the long term behaviour of the piled raft foundation which considers the overall settlement behaviour (immediate and consolidation settlement) of the piled raft foundation system in order to predict the settlement profile for structural design. The settlement analysis is carried out based on Terzaghi s 1-dimensional consolidation theory. The stresses in the subsoil induced by adjacent blocks of buildings have been taken into consideration in the settlement analysis. Appropriate adjustments were made to the pressure imposed on the subsoil due to distribution of the superstructure load by the piles using the concept of equivalent raft. The settlement profiles obtained are then used to determine the spring stiffness or Winkler s modulus in the 2-dimensional FEM software to generate the overall stresses on the foundation raft due to the settlement profile. CSM02 CSM05 CSM10 CSM14 CSM13 25m CSM01 CSM04 CSM06 CSM07 CSM09 CSM11 CSM03 m CSM08 CSM12 Legend: 18m Piles 21m Piles 24m Piles Figure 4. Locations of column settlement markers. (Plan View) 5.0 Settlement Monitoring A total of 14 precise settlement markers were installed at ground floor columns of the structure as shown in Fig. 4 to monitor the performance of the foundation system. Monitoring works were carried out starting from September 2003 when construction works had reached the 3rd floor to October 2004 when the building has been 5

completed for more than nine months. Settlement points CSM01, CSM03, CSM04 and CSM08 were damaged and the values were extrapolated from the trend of available earlier readings. 0 200 300 400 0 10 20 0 10 20 0 10 0 200 300 400 0 10 30 40 50 Legend: - CSM01 CSM02 CSM03 CSM04 CSM05 CSM06 CSM07 CSM08 CSM09 CSM10 CSM11 CSM12 CSM13 CSM14 30 40 50 20 30 40 50 Legend: - Max Differential Settlement Raft Average Settlement Legend: - Raft Average Settlement Max Differential Settlement 0 200 300 400 Days 20 30 40 50 0 200 300 400 Days Figure 5. Settlement monitoring results Figure 6. Raft average settlement and maximum differential settlement Legend: Legend: - - Predicted Analyzed Measured β = 1/8274 CSM03 C L CSM08 β = 1/3515 CSM12 C L Legend: Legend: - - Analyzed Predicted Measured β = 1/1831 β = 1/2987 β = 1/3107 CSM01 CSM07 CSM04 CSM11-30 -20-10 0 10 20 30 Distance (m) Settlement profile across CSM03, CSM08 and CSM12-30 -20-10 0 10 20 30 Distance (m) Settlement profile across CSM01, CSM04, CSM07 and CSM11 Legend: Legend: - - Analyzed Predicted Measured C L β = 1/4291 CSM09 β = 1/5086 CSM13 Legend: Legend: - - Predicted Measured Measured Predicted β = 1/23 CSM02 C L CSM14 β = 1/2269 CSM06 CSM05 β = 1/17594 CSM10-30 -20-10 0 10 20 30 Distance (m) Settlement profile across CSM06, CSM09, and CSM13-30 -20-10 0 10 20 30 Distance (m) Settlement profile across CSM02, CSM05, CSM010 and CSM14 Fig. 7 Settlement profile across settlement markers 6

The measured settlement monitoring results of the 14 settlement markers are presented in Fig. 5 while the average settlement and maximum differential settlement are shown in Fig.6. The maximum differential settlement stabilised at about 27mm for the last two monitoring measurement while the average building settlement does not stabilised due to consolidation settlement. Fig. 7 shows both the measured and predicted (from Case1) cross-sectional settlement profile of the apartments at the edge and centre of the apartment. The relative maximum local angular distortion recorded is 1/685 (between CSM11- CSM12). The monitoring results also show that the apartment experiences tilting towards the adjacent blocks (towards left and top side of the apartment) as shown in Fig. 8 due to the stress influence from adjacent blocks. Figure 8. Measured Settlement Contour (Measurement No. 8 at 391 days) The monitoring results show relatively smaller settlement at the edge of the building also indicate that further improvement and refinement by shortening piles or totally omitting piles at the edge of the apartment can be explored. A reduction of stiffness at the building edge may lead to a more economical design and improved raft performance as differential settlement can be reduced. This is consistent with the findings of Reul and Randolph (2004) who suggested that for a raft under uniform loading or core-edge loading, the differential settlements can be most efficiently reduced by installation of piles only under the central area of the raft. However, careful considerations of structural and total settlement requirements shall be evaluated before further optimization are carried out especially for buildings on very soft ground where bearing capacity is also of major concern. 6.0 Conclusion An iterative design approach for piled raft foundation for 5-storey apartments using settlement reducing piles of varying length in soft ground is presented. The foundation system consists of piled raft with varying pile lengths with longer piles in the central portion of the building and progressively shorter piles toward the edge. The detailed design of the foundation system involved pile-soil-structure interaction analysis of the piled raft foundation (Case 1) in order to determine the 7

load distribution and local settlement of the piles. The overall settlement behaviour of the piled raft foundation system (Case 2) has also been incorporated in the design. The influence of adjacent blocks has to be taken into consideration in the piled raft foundation design as confirmed by the monitoring results. References British Standard Institution. 1996. BS6399: Part 1: 1996: Code of practice for dead and imposed loads. Horikoshi, K. and Randolph, M.F. 1998. A contribution to optimum design of piled rafts. Geotechnique, 48(3), 301-317. Randolph, M.F. and Wroth, C.P. 1978. Analysis of deformation of vertically loaded piles. Journal of the Geotechnical Engineering Division. Proc. of the ASCE, 104, GT12, 1465-1488. Randolph, M.F. and Wroth, C.P. 1979. An analysis of the vertical deformation of pile groups. Geotechnique, 29(4), 423-439. Reul, O. and Randolph, M.F. 2004. Design Strategies for Piled Rafts Subjected to Nonuniform Vertical Loading. Journal of Geotechnical and Geoenvironmental Engineering, 130(1), 1-13. Skempton, A.W. and MacDonald, D.H. 1956. The allowable settlement of buildings. Proceedings Institution Civil Engineers, 3(5), 727-784. Poulos, H. G. 2001. Pile raft foundations: design and applications. Geotechnique 51, No. 2, 95-113. Tan, Y.C., Gue, S.S., Ng, H.B. and Lee, P.T. 2004a. Some geotechnical properties of Klang Clay. Proceedings Malaysian Geotechnical Conference, 179-185, Kuala Lumpur. Tan, Y.C., Chow, C. M. and Gue, S.S. 2004b. Piled raft with short piles for low-rise buildings on very soft clay. Proceedings 15th SEAGC, Bangkok, Thailand, 171-176. 8