M.C.C.S.INTERNATIONAL

Similar documents
& Start-up Directory

TRANSNET PIPELINES. TPL 25 Tarlton Commissioning Plan

JOINT INTEGRITY MANAGEMENT SOLUTIONS

Assured Joint Integrity

Mechanical Installation

Lockout / Tagout Program

How To Manage A Project

NORSOK STANDARD COMMON REQUIREMENTS MECHANICAL COMPLETION AND COMMISSIONING

Standard Hydraulic Piping Flushing Procedure

The Pathway to ASME PCC Appendix A Compliance and why it s of Critical Importance

Unit LT01 Carry Out Routine Lift Truck Maintenance

Integrated Custom Systems

Backup Fuel Oil System Decommissioning & Restoration Plan

50t. Product training courses. 40t

Experience and Qualifications of PROCESS PLANTS CORPORATION

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

Engineering g Procurement. 02-Feb-2015

Energy Design Resources Commissioning Plan Outline Template

Float and Thermostatic Traps Series H, C and X

VENDOR PREQUALIFICATION QUESTIONNAIRE

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES

CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012)

PBX Series Quick Fit Connector Bimetallic Steam Traps

Training for Operations and Maintenance

Engineering Procurement Construction Quality Plan

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

Owner-User Pressure Equipment Integrity Management Requirements

2. Performance Test Schedule and Certificates. 2.1 Definitions

TfNSW Standard Requirements TSR T Technical Management

The advice. The expertise. Wherever you are.

Guidelines for a PROJECT EXECUTION PLAN

BPW32 DN15, DN20 and DN25 Balanced Pressure Wafer Steam Trap

Building Commissioning

Salof Companies Modularized Gas Liquefaction Plants

LOCKOUT/TAGOUT PROGRAM. Table of Contents

WEEKLY SAFETY MEETING All Euramax Subsidiaries LOCKOUT / TAGOUT. Safety Meeting Contents. Meeting Notice. Leaders Guide.

Roles and Responsibilities of Plant Commissioning, Hydrocarbon Introduction and Acceptance Test Run

Occupational Health Program Safety Training Series. Lockout/Tagout Safety Awareness Training

Our Know-How. Your Peace of Mind. Innovative Sealing and Gasket Solutions

Siemens Mechatronic Systems Certification Program (SMSCP)

4.4 Commissioning, Handover and Warranty

JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES

Section 10.9 STRUCTURAL STEEL AND MISCELLANEOUS METAL COMPONENTS

IMPORTANT SAFETY NOTICE

AWWA Butterfly Valve Operation and Maintenance Manual Series 511A & 510A 20 and Smaller

COMMISSIONING OF HVAC SYSTEMS

Electric Panel Pump Control System. Operation, Maintenance and Installation Manual

Generic CMMS Quality Assurance Plan

Tracking project deliverables through a standard definition of Project WBSs. Franco Concari Technip & VP IPMA Italy Luciano De Gaetano Technip Italy

Industrial Process Pump Safety Manual IMPORTANT SAFETY NOTICE

POWER & RENEWABLE ENERGY SERVICES

Erik Backström, High Voltage breakers, After Sales & Service High voltage SF 6 live tank circuit breakers After Sales & Service Training course

A Leading Provider of Engineering Information Management Solutions and Services. Facilitating multi-office, multi-contractor execution strategies

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook

Announcement on Providing Guarantee for the Subsidiary Company - Offshore Oil Engineering (Qingdao) Co., Ltd. by Offshore Oil Engineering Co., Ltd.

System Saver 318 Air Compressor for Mack E-Tech and ASET Engines

Construction Management Standards of Practice

Sample Company SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

KEPPEL GAS GAS SUPPLY HANDBOOK

SAFETY - LIFE SAVING RULES MECHANICAL ISOLATION CAT A-1 SOP #3

The cylinder head bolts tightening stages have been updated as listed in Table 1.

This instruction is valid for all ACD pump models shown on page 2

TABLE OF CONTENT

IKM Testing AS. - A brief selection of relevant services. Zero injuries an overall objective

POWER & RENEWABLE ENERGY SERVICES

Asset and Plant Lifecycle Management

Mechanical Engineering Technician- Plant Technician

THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING

2740 Whitten Rd Bldg 103 Memphis, TN Telephone

Manufacturing process

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)

Guidelines for the Acceptance of Manufacturer's Quality Assurance Systems for Welding Consumables

Energy Control Lockout/Tagout

INSTALLATION COMMISSIONING

VDOT GOVERNANCE DOCUMENT

Installation S19-220PT S19-220BPT. Wall-Mounted Eyewash with Plastic Bowl. Wall-Mounted Eyewash with Stainless Steel Bowl.

SMARTPLANT ENTERPRISE

Oil and Coolant Circulating Heating System. Model - OCSM

OPERATING and MAINTENANCE MANUAL SERIES 2700A CONTROL VALVE CONTENTS. INTRODUCTION...1 Scope...1 Description...1 Valve Identification...

U.S. Department of Energy CSP Program Review

Trouble Shooting. Pump

System Engineering Plan

Installation and Operational Qualification Protocol (Reference: SOP )

Section 100 Contractor Quality Control Program

Lockout - Tagout. Control of Hazardous Energy OSHA Standard

Hydraulic Safety Program


Designer Quality Control Plan Guidelines

SECTION STANDBY GENERATOR TESTING AND COMMISSIONING

INDEX 1.0 HEALTH, SAFETY & ENVIRONMENT 1.1 INTRODUCTION 1.2 OBJECTIVES 1.3 HEALTH, SAFETY & ENVIRONMENT STATEMENT 1.4 ENVIRONMENTAL STATEMENT

Operational Excellence Management System

Fire Sprinkler System Maintenance and Testing Page 1 MAINTENANCE AND TESTING OF FIRE SPRINKLER SYSTEMS

D. MCLAUGHLIN & SONS LTD QUALITY MANUAL

FLORIDA STATE COLLEGE AT JACKSONVILLE COLLEGE CREDIT COURSE OUTLINE. Automatic Transmissions and Transaxles

FAIRBANKS NIJHUIS FIRE PROTECTION. FIRE PUMP SETS & PUMP PACKAGES

Transcription:

M.C.C.S.INTERNATIONAL Mechanical Completion and Commissioning Services Ltd. Formed in 1994 To fill a niche market in the area of Mechanical Completion and Commissioning M.C.C.S. Worldwide Ltd. Formed 2000 in the UK M.C.C.S. Worldwide Sdn Bhd Formed 2001 Kuala Lumpur Malaysia and renamed to M.C.C.S. International Sdn Bhd 2007 Branch Offices in UK, Spain, Vietnam and Indonesia What makes M.C.C.S. unique? M.C.C.S. comprises a team of people who have specialised in this difficult area for several years. The principle spin off from this team approach is The Wheel is not Reinvented Maximise cost benefits M.C.C.S. involvement should be sought during the early planning and design phase of a project. Within schedule and under budget M.C.C.S. team has an enviable record of achieving its tasks within schedule and under budget.

MCCS PROFESSIONAL COMMISSIONING & MAINTENANCE SERVICES FOR EPCC / EPCIC OIL & GAS PROJECTS FEBRUARY.2015 BEHNAM

What is Pre-Commissioning? Pre-Commissioning: IT IS THE GROUP OF STATIC & DE-ENERGIZED VERIFICATIONS TO BE CARRIED OUT IN ORDER TO ENSURE THAT THE INSTALLATION ADHERE TO PROJECT ENGINEERING DOCUMENTS. Non-operating adjustments and cold alignment checks (such as testing without introducing process and auxiliary fluids prior to equipment energisation)

What is Commissioning? Commissioning: IT IS THE GROUP OF DYNAMIC & ENERGISED TESTS TO BE CARRIED OUT IN ORDER TO ENSURE THAT THE INSTALLATION IS READY FOR START-UP. Pre-startup, check-out, system adjustment, equipment and system activation to prepare system(s) and/or facilities for operation (by introducing auxiliary fluids and with equipment energisation)

What is Mechanical Completion? (MC) Construction is completed in accordance with drawings, specifications, vendor instructions, applicable codes and regulations and authority requirements. All inspection, checking and testing works are completed. System(s) and/or facilities are ready for pre-commissioning and commissioning (Note: Some Clients considered MC before pre-commissioning as a reference for Handover from Construction team to Commissioning Team & some Clients considered MC after pre-commissioning)

Project Systems breakdown to System & Sub-System This activity includes break-down of systems or areas into Sub-Systems/Work Packages by indicating limits and varying colour codes on design drawings such as Piping & Instrument Diagrams (P&ID s), Electrical Single Line Diagrams (SLD s), Instrument troubleshooting loop diagrams (TSLD s) and Telecoms Layout Drawings and other detailed design documents. Creating this breakdown will assist in establishing the Mechanical Completion Databases and allocation of Work Packages, Job Cards etc. The breakdown will also assist in establishing construction progress and will form the baseline for the Completion and Commissioning Databases and Handover of the plant to the Client.

What is punch list? From The Construction To The Routine Operation Three Punch List Priority Levels Should Be Considered: PL A: Item Considered As A Block Point For Commissioning Activity Of The Sub-system PL B: Item Considered As A Block Point For Start-up Activity Of The Sub-system PL C: Item Not Considered As A Block Point For Startup Activity, But Linked To A Contractual Performance From The Equipment And Milestone (For Example Partial Acceptance, Hand-over, etc.)

EPCC PROJECTS STAGES ENGINEERING STAGE (MCCS SUB-CONTRACTOR) PROCUREMENT STAGE (N/A) CONSTRUCTION STAGE (MCCS SUB-CONTRACTOR) COMMISSIONING STAGE (MCCS SUB-CONTRACTOR) WHAT WE CAN DO FOR ANY STAGE?

TECHNICAL PREPARATION & Basic Eng. Detailed Eng. Procurement EXECUTIVE PHASES E P Construction Pre-comm. - Preparation C Pre-comm. - Execution Commissioning - Preparation RFC By Sub System MECH COMP Comm. - Execution By Sub System RFSU C RFHO PUMA 3 SOFTWARE SUPPORT Equipment Population Pre-comm - Preparation Pre-comm. Execution STARTUP OPERATION & Maintenance Comm. - Preparation Punch List A Comm. - Execution Punch List B Punch list C

MCCS SERVICES FOR ENGINEERING STAGE TECHNICAL PREPARATION FOR; PRE-COMMISSIONING EXECUTION PHASE COMMISSIONING EXECUTION PHASE INCLUDED ALL CHECK LISTS, TEST SHEETS, PROCEDURES, PUNCH LIST DATA BASE, MASTER DATA BASE FOR ALL MAINTAINABLE TAG NUMBERS, RFC/RFSU/RFHO DOSSIERS CREATION BASED ON SYSTEM AND SUB-SYSTEM, etc.

MCCS SERVICES FOR ENGINEERING STAGE MCCS KEY SOURCES FOR SERVICES IN ENGINEERING STAGE ARE AS FOLLOW; PROFESSIONAL MULTIDISCIPLINE TEAM PROFESSIONAL SOFTWARE SUPPORT (PUMA 3) EVALUATE EXPERIENCE OF PREVIOUS SERVICES TO WORLD CLASS OIL & GAS MAIN CONTRACTORS

MCCS SERVICES FOR CONSTRUCTION STAGE FLANGE MANAGEMENT SERVICES DATA MANAGEMENT MANUAL BOLT TORQUE HYDRAULIC BOLT TORQUE HYDRAULIC BOLT TENSIONING FLANGE BREAKOUT / DISASSEMBLE

FLANGE MANAGEMENT SERVICES OVERVIEW FLANGE MANAGEMENT SERVICES SEQUENCES AS FOLLOW; PRE-ENGINEERING JOINT REGISTER PREPARATION OF WORK PACKS DATA SHEET DATA RECORDS JOINT COMPLETION CERTIFICATE (JCC) FLANGE PREPARATION AND INSPECTION INTERNAL LINE WALK FLANGE ALIGNMENT, SURFACE AND CLEANLINESS FASTENERS MATERIALS AND CLEANLINESS GASKET MATERIALS AND CLEANLINESS

FLANGE MANAGEMENT SERVICES OVERVIEW ENGINEERING TAGGING SYSTEM PREPARATION VERIFICATION OF FLANGES PRIOR TO ASSEMBLY ASSEMBLY BY COMPETENT PERSONNEL AND SUPERVISE BY MCCS INSPECTION CONDUCTED BY CLIENT QA/QC AND MCCS ALIGNMENT INSPECTION TIGHTENING MANUAL BOLT TORQUE HYDRAULIC BOLT TORQUE HYDRAULIC BOLT TENSIONING ** FLANGE BREAKOUT ** SYSTEM INSPECTION AND HANDOVER PRIOR TO FLANGE BREAKOUT ** DATA SHEET / DATA RECORDS / JOINT COMPLETION CERTIFICATE (JCC) ** VERIFY FLANGE DETAILS AND SPECIFICATION PROVIDED BY CLIENT ** REPAIR THE JOINT ** INSPECTION AND APPROVAL FROM CLIENT ** UPDATE JOINT REGISTER FINAL INSPECTION AND APPROVAL BY CLIENT ISSUANCE OF JOINT COMPLETION CERTIFICATE (JCC) WITHIN WORK PACKS UPDATE JOINT REGISTER

MCCS SERVICES FOR PRE- COMMISSIONING STAGE PHASE ACTIVITIES MILESTONE PRE-COMMISSIONING CONFORMITY CHECKS STATIC TESTING N2/He LEAK TESTING MECHANICAL COMPLETION (MC & RFC)

N2/He LEAK TESTING PROCESS PLANT IN ONSHORE & OFFSHORE

N2/He LEAK TESTING N2 / He Leak Testing Based On Specified Test Packages Step 1: Pre-Engineering/Engineering Provision of Mark-up P&ID Provision of System boundary / limit Provision of Isolation valve list/ Critical valve list (UVT, if required) Generation of test packs prior to submission for review Submission to Client/Main Contractor for Approval Amendments to be updated if any, in test packs, verified and pack/s must be resubmitted & reapproved following changes made Step 2: Onsite Preparation Application of Permit & Isolation Tagging. Rig up preparation work (Installation Tagging, Injection Point, OPP & Monitoring point)

N2/He LEAK TESTING Step 3: TRI-PARTY LINE WALK BEFORE TEST. (Final walk with client / Main Contractor For Confirmation of System readiness) Step 4: Introduction of N 2 He gas into system to 100% Test Pressure based on 90% of PSV Set point / Piping design pressure with quarter percentile stoppages, checking system/pressurization stability. Perform UVT (Client request) and Probing to Leak check for each joint

N2/He LEAK TESTING Step 5: REPORTING Leak Report Identification/Recording of leak points & rates tied in with related Marked-up P&IDs Verification of rectification order based on leak rates followed by given instruction (Clients) of system readiness for retest Step 6: Retest Re-test, following rectification of leaking joints in close accordance to working procedures Step 7: Test Completion Client/Main contractor Approval and Handover of related Test Package Dossier with complete sign off.

MCCS SERVICES FOR PRE- COMMISSIONING STAGE (MECHANICAL COMPLETION) PRE-COMMISSIONING EXECUTION (MULTIDISCIPLINE) Visual inspection of Equipment ( PG, Motors, Cables...).Quality of installation Compliance with Project Specifications, Safety rules, codes,... «Cold Testing» : Calibration of Instruments, Machinery alignement, Setting of safety valves,...(de-energised Tests) Pipes and Vessels N2/He Leak Testing (MCCS will follow approved Client/Company Procedures)

PRE-COMMISSIONING DOSSIER Compiled RFC Certificate One Dossier Per Sub- System

MCCS SERVICES FOR COMMISSIONING STAGE PHASE ACTIVITIES MILESTONE COMMISSIONING ENERGISATION DYNAMIC TESTS EQUIPMENT RUNNING-IN PRESTART-UP ACTIVITIES READY FOR START-UP (RFSU)

MCCS SERVICES FOR COMMISSIONING STAGE COMMISSIONING EXECUTION Electrical motors coupled runs, instrument loops test, electrical breakers operation... Running-in and on-line tests of plant utilities, and main process equipment in closed loop (wherever applicable) N2/He Final Leak Testing START-UP ASSISTANTE (MCCS Will Follow Procedures Approved By Client)

COMMISSIONING DOSSIER RFSU Dossier Index RFSU Certificate One Dossier Per Sub-System

MAINTENANCE SERVICES FOR PROCESS PLANTS IN ONSHORE & OFFSHORE WHAT WE NEED FOR MAINTENANCE SERVICES? 1) MULTI-DISCIPLINE PROFESSIONAL TEAM 2) SPECIAL & GENERAL TOOLS 3) PROFESSIONAL SOFTWARE FOR COMPUTRISED MAINTENANCE MANAGEMENT SYSTEM(CMMS)

MULTI-DISCIPLINE PROFESSIONAL TEAM COMMISSIONING TEAM IS BEST OPTION FOR MAINTENANCE SERVICES OF THE PLANT WHY MCCS IS BEST OPTION FOR MAINTENANCE? BECAUSE ALL DISCIPLINES (Elect., Inst., Telecom, Mechanical, Piping, etc.) HAVE STRONG BACKGROUND OF THE PLANT TECHNICAL DATA AS PER EXPERIENCE OF THE PLANT COMMISSIONING OPERATION

SPECIAL & GENERAL TOOLS MCCS IS PROFESSIONAL IN; SELECT AND PROVIDE THE APPROPRIATE TOOLS BASED ON TASK & EQUIPMENT TYPE FOR EACH DISCIPLINE: ELECTRICAL, INSTRUMENT, TELECOM, MECHANICAL

PROFESSIONAL SOFTWARE FOR COMPUTRISED MAINTENANCE MANAGEMENT SYSTEM(CMMS) WHY WE NEED TO SOFTWARE FOR THE MAINTENANCE? TO MANAGE TECHNICAL DOCUMENTS TO MANAGE SPARE PARTS TO MANAGE MAINTENANCE SCHEDULE DURING COMMISSIONING OPERATION MCCS WILL PROVIDE ALL OF THE DATA BASES AND WILL MANAGE UPLOADING OF THE TECHNICAL DATA FOR MAINTENANCE SERVICES. MCCS will support your projects for creation of pyramid data base for CMMS & EDMS. CMMS: Computrise Maintenance Management System EDMS: Electronic Document management System

THANKS FOR YOUR ATTENTION