Requirements on piling plan submission

Similar documents
Geotechnical Building Works (GBW) Submission Requirements

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

METHOD OF STATEMENT FOR STATIC LOADING TEST

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

A GUIDEBOOK TO THE CHANGES IN BUILDING CONTROL 2007/2008. Building and Construction Authority

Jack-in Piling Environmental Friendly Piling System

High Strain Dynamic Load Testing of Drilled Shafts

DESIGNING STRUCTURES IN EXPANSIVE CLAY

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

PILE TESTING SPECIFICATION

Design of pile foundations following Eurocode 7-Section 7

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

Foundation design to Eurocode 7

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Guide to Carrying Out Engineering Works within Road Structure Safety Zone and Engineering Activity on Land adjoining Public Streets

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

PILE FOUNDATIONS FM 5-134

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

Anirudhan I.V. Geotechnical Solutions, Chennai

Supplier ID: Local Office: GLASGOW 69 Buchanan Street Glasgow G1 3HL

VERTICAL MICROPILE LATERAL LOADING. Andy Baxter, P.G.

TECHNICAL NOTE: SI 01 SPECIFIC REQUIREMENTS FOR THE ACCREDITATION OF INSPECTION BODIES FOR SITE INVESTIGATION

Design and Construction of Auger Cast Piles

BUTE Department of Construction Management and Technology

ALLOWABLE LOADS ON A SINGLE PILE

KWANG SING ENGINEERING PTE LTD

Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

The information and materials contained in this disc are provided as is and as available.

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

Transmission Foundations. helical piles and guy anchors for transmission structures.

Pile test at the Shard London Bridge

Tunnelling & Underground. Specialists

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION

Table of Contents 16.1 GENERAL Overview Responsibilities

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

ATLAS RESISTANCE Pier Foundation Systems

INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES. Interpretations of the FTP

RECENT EXPERIENCES WITH BI-DIRECTIONAL STATIC LOAD TESTING

EN Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

Improvement in physical properties for ground treated with rapid impact compaction

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

EUROCODE 7 & POLISH PRACTICE

MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

An Automatic Kunzelstab Penetration Test

INSTRUCTIONS FOR USE

DIRECTIONAL DRILLING

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Site Auditing for Building Works. This practice note provides details of the strategy on auditing building works by the Buildings Department (BD).

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P

Step 11 Static Load Testing

vulcanhammer.net Visit our companion site

CEEN Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests

GUIDELINE FOR HAND HELD SHEAR VANE TEST

PDCA Driven-Pile Terms and Definitions

HOW TO DESIGN CONCRETE STRUCTURES Foundations

NATIONAL ANNEX TO STANDARD SFS-EN 1990 EUROCODE BASIS OF STRUCTURAL DESIGN

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

High Capacity Helical Piles Limited Access Projects

TBM CROSSING OF STATIONS

CALIBRATION OF EQUIPMENT FOR PILE LOAD TEST BY SAC-SINGLAS ACCREDITED LABORATORIES

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Design and Construction of Cantilevered Reinforced Concrete Structures

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

Driven Concrete Pile Foundation Monitoring With Embedded Data Collector System

LICENSING OF BUILDERS - Simplified Guide

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work

A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil

DYNAMIC TESTING OF MICROPILES. COMPARISON OF STATIC AND DYNAMIC TEST RESULTS

Piling Datasheets. Continuous flight auger (CFA) Driven Rotary

HUS-V Screw anchor. HUS-V Screw anchor. Basic loading data (for a single anchor) Mean ultimate resistance

FRANKIPILE. High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process

Laterally Loaded Piles

Dynamic Load Testing of Helical Piles

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Method Statement for Static Load Testing (Compression) for Micropiles

Technical Application Document. Hilti HIT-RE 500-SD

Federation of Piling Specialists Testing Datasheet No 1

NEGATIVE SKIN FRICTION AND SETTLEMENT OF PILES. Dr. Bengt H. Fellenius, P. Eng. University of Ottawa, Canada

Geotechnical Investigation Test Report

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Transcription:

Requirements on piling plan submission Under BC (Amendment) Act 2007 & Regulations 2008 Er Dr Yet Nai Song Building and Construction Authority 1

Types of piling submissions Barrettes Bored cast-in place piles Grouted micropiles 2

Types of piling submissions Driven piles Jacked-in piles 3

Objective To help Qualified Persons who prepare the piling plans to comply with requirements of BC (Amendment) Act 2007 & Regulations 2008 4

Overview 1. Submission checklist 2. BC Regulations 10(2) 3. SS CP4 : 2003 4. BCA / IES / ACES Advisory Note on Site investigation & Load test 5. Piling Annexes B, C, D 6. Good practices in design & construction 5

(1) Submission checklist 6

Submission checklist I. Piling plans endorsed by QP and AC II. III. IV. Design reports by QP and AC Declaration forms by QP and AC Site investigation report, endorsed & certified by a PE V. A plan showing the layout and location of the site, boundary line and neighbouring buildings VI. VII. Impact assessment report, where applicable (eg. for foundations located within influence zone of sensitive structures, like MRT or CST tunnels) Clearance letters, where applicable, from the relevant authority 7

Certifications by QP and AC on plans PE AC 8

Certifications by QP(geo) and AC(geo) on plans AC(geo) PE(geo) 9

10

Certification by PE for SI report 11

Plan to show Site Location Proposed Construction Site 12 Serangoon Road site Syed Alwi Rd Jalan Besar Desker Rd

An example of project close to sensitive structures Pile Raft for a 66-storey building CST tunnel MRT lines CST tunnel PUB drain MRT station 13

(2) Building Control Regulation 10(2) 14

Regulations 2003 Regulation 10(2) 15

Regulations 2008 Regulation 10(2) the location of piles and site investigation boreholes ; the estimated pile penetration depth for each design zone ; 16

Regulations 2008 Reg 10A(5) (Plans of foundation 30storeys) 17

Building Control Regulations 2008 Regulation 10(2) the location of piles and site investigation boreholes ; the estimated pile penetration depth for each design zone ; 18

(a) Pile type & material specification, pile joints, sectional details I. Do the plans show the pile types and material specification? II. Do the plans show pile size and pile details? III. Do the plans show the pile capacity? (i) allowable foundation capacity, before and after accounting for negative skin friction, (ii) allowable tension load, lateral load, where applicable. Items to be shown on piling plan 19

Pile capacity & Pile reinforcement Pile diameter Working load Pile reinforcement 20

Details of Pile reinforcement Anchorage length Lap length Sectional details Full depth cage /12m cage 21

Details of RC pile Pilecap connection details Joint details Sectional details 22

(b) Site investigation borehole I. Do the plans show location of site investigation boreholes? II. Is there any borehole within the footprint of each block? For buildings of 10-storeys or more III. Do number of boreholes exceed minimum? IV. Is depth of any borehole beyond proposed pile penetration depth? (see BCA/IES/ACES advisory note 2003) Items to be shown on piling plan 23

Site investigation boreholes (1) Footprint of tower block Total = 5 boreholes 24

Site investigation boreholes (2) Total = 10 boreholes 25

Site investigation boreholes (3) Total = 26 boreholes 26

(c) Pile depth & (d) Pile founding criteria I. Do the plans show pile design zones (based on site investigation information)? II. Do the plans show the following information? (i) pile founding criteria (eg. pile founding depth / minimum embedment into competent stratum / pile set criteria / magnitude of jack in load) (ii) a description of soil / rock for founding layer. Items to be shown on piling plan 27

Pile design zones based on boreholes 28

Example 1 Pile founding criteria (in hard soil) 29

Example 2 Pile founding criteria (in hard soil & rock) 30

Example 3 Pile founding criteria (pile set) 31

(e) Geotechnical parameters I. Do the plans contain unit shaft friction and unit pile base resistance used for pile design? II. Are soil strata / rock type given for the above? Items to be shown on piling plan 32

Unit shaft friction & base resistance used in pile design 33

(f) Negative skin friction I. Is there a design evaluation of the possibility of negative skin friction? (i.e. whether the soil is still undergoing consolidation at its final stress state?) II. Has negative skin friction been considered in the design? Items to be shown on piling plan 34

(g) Allowable settlements I. Are allowable total and differential foundation settlements shown on plan? II. Are these allowable foundation settlements consistent with the design calculation? 35

Sample variation of building settlement with time during superstructure erection 10 th 1.5mm 20 th 3.0mm 30 th 4.5mm 40 th 6.5mm 43 rd 8.0mm Settlement increases with building height. 36

(h) Vibration limits I. Are allowable vibration limits specified on the plan? 37

DIN 4150 : Part 3 Structural vibration in buildings Guideline on Limit of vibration Type 1 Type 2 Type 3 38

(i) Verification tests I. Do the plans contain the following information? II. III. IV. (i) number of tests, (ii) types of pile tests. Are types and number of tests provided complied with BCA/IES/ACES advisory note 2003? Is location of ultimate pile load test shown on plan, and correlated with borelog? Will the preliminary piles for the ultimate pile load test be instrumented, to verify the geotechnical parameters? (Applicable to piles where strain gauges could be installed along the pile, eg. bored piles, hollow spun pile) 39

2ULT + 5WLT + 9PDA Exceeded minimum! 40

Preliminary pile to be instrumented 41

A recap Items to be shown on piling plan a) Pile type & material specification, pile joints, sectional details b) Site investigation boreholes c) Estimated pile length for each design zone d) Minimum embedded depth into competent stratum e) Skin friction & End bearing for pile design f) Pile capacity before & after negative skin friction g) Allowable settlements h) Allowable vibration limits i) Pile load test & location 42

(3) SS CP4 : 2003 (Code of Practice for Foundations) 43

Code of Practice CP4 : 2003 44

Design for pile foundations [CP4 Clause 7.3.1] Every pile design has to satisfy 3 conditions: 1. Adequate safety factor against failure 2. Settlement of foundation under working load should not affect the serviceability of structure 3. Safety of nearby buildings should not be put at risk 45

I. Group settlement is greater than settlement of individual pile Pile Group Effect (CP4 Clause 7.3.4) II. Differential settlement between two pile groups < 1:500 46

An example where pile group effect is dominant with overlapping of stress bulbs of individual piles 300 nos 1.8m piles within 60mx60m footprint 47

Effect of lateral forces during basement excavation (CP4 Clause 7.4.5.3.2) If bored piles are subject to lateral forces, reinforcement should be adequately provided for bending moments. to full pile length or to where bending moment is negligible. 48

An example of effect of basement excavation on foundation piles 15m excav Marine clay Dwall GMP 4 struts 49

Foundation piles should be designed for the effect of basement excavation. Table 1 Pile Ecc and Maximum Forces at Final Stage of Excavation Pile Position from Max ecc Max N Max BM Max SF Dwall [m] [mm] [kn] [knm] [kn] Remarks L1 4 20 2029 615-595 in GMP L2 12 18 1782 488-346 in GMP L3 20 7 1753 229-372 in GMP R1 4 36 2340 820 1030 in GMP R2 12 30 3592-740 357 in GMP R3 20 24 3255-645 236 in GMP Foundation piles move by 36mm, and experience bending moment of 820 knm! 50

(4) BCA / IES / ACES Advisory note (for buildings of 10-storeys or more) 51

Requirements for Site Investigation to establish the soil strata and ground variation (a) Number of boreholes (b) Depth of boreholes Minimum requirement - 1 borehole per 300 m 2-1 borehole at 10 to 30m spacing - Minimum 3 boreholes - 5 metre into hard stratum with N>100-3 times pile diameters beyond pile founding level. 52

(1) Rockhead varies from RL 102m to RL88m (2) The quality of bedrock varies greatly. Min. 5m into hard stratum Example of soil profile for Bukit Timah Formatio 53

Example of soil profile for Jurong Formation Min. 3 pile diameters below intended pile founding level 54

Requirements for pile load tests Type of Load Test (a) Ultimate load test on preliminary pile (preferably instrumented) (b) Working load test (c) Non-destructive integrity test. (Note: This is for the purpose of quality control, and high-strain type should be used for bored piles) Pile Test Schedule 1 number or 0.5% of the total piles whichever is greater. 2 numbers or 1% of working piles installed or 1 for every 50 metres length of proposed building, whichever is greater. 2 numbers or 2% of working piles installed, whichever is greater. 55

Load measurement for pile load tests (CP4 Clause 7.5.5.2.1) Load should be measured by a calibrated load gauge & a calibrated pressure gauge 56

(5) Piling Annexes (for buildings of 10-storeys or more) 57

Piling Annex B Certificate of supervision of pile load test 58 QP(geo) Site supervisor Builder QP

Piling Annex C Interim certificate of supervision of piling works QP QP(geo) Builder Site supervisor 59

Piling Annex D Certificate for monitoring building settlement Signed by QP 60 Signed by QP(geo)

(6) Some good practices in pile design & construction 61

a) Reduce over-reliance on pile base resistance 1) Applying a minimum safety factor to skin friction, for bored piles, where soft toe may occur 62

a) Reduce over-reliance on pile base resistance 2) In erractic soil condition, eg limestone area 35m limestone 3-m thick cavity limestone 63

(b) Preliminary pile at borehole location Borehole Ultimate test pile 64

(c) Judicious location of strain gauges Taking into account : - change of soil layers - thickness - variability To aid interpretation eg. measurement of skin friction at various soil /rock layers 65

(d) Innovative Investigative preliminary pile CP4 Clause 7.5.4.1 Preliminary piles may be formed with voids at base or soft toes to determine ultimate shaft resistance 66

(e) Investigative preliminary piles installed using similar construction method as working production piles Wet hole method CP4 Clause 7.5.4.1 Dry hole method 67

(f) Proper transfer of load to Kentledge frame Use stiffener for effective transfer 68

g) Minimum distance between test pile & Kentledge leg Distance between Kentledge leg to surface of test pile 1.3 m (CP4 Clause 7.5.5.2.1) 69

(h) No preloading on piles before test 70

(i) Conduct working load test at location where it matters Pile Size Working Load Nos No. of Method of (mm) (kn) Load Test Test ASM - 135 0-1000 5800 147 0-1200 8400 99 1 Kentledge 1500 13200 115 2 Kentledge 1800 19000 159 3 Bi-Directional 2000 23500 96 1 Bi-Directional 2200 28500 88 1 Bi-Directional 2500 36800 62 1 Bi-Directional 2800 41600 22 1 Bi-Directional 3000 53000 16 0 - Total : 939 10 Examples : (1) Piles within the tower footprint (2) Piles carrying larger load 71

(j) No preselection of pile for working load test 72

(k) Keep rock/soil sample at site for verification 73

(l) Impose quality control measure at site 1) Pile bore stability 2) Pile base cleanliness 3) Tests on stabilizing fluids 74

(l) Impose quality control measures at site 4) Sufficient cooling time for weld to gain strength 75

(m) Check & verify obvious change in pile depth Eg: (1) Site investigation (2) Load tests 76

Recap of Some Good Practices a) Reduce over-reliance on pile base h) No preloading on piles before test resistance b) Preliminary pile at borehole location i) Conduct working load test at location where it matters c) Judicious location of strain gauges j) No preselection of pile for working d) Innovative preliminary pile load test e) Preliminary pile installed using same k) method as working piles Check & verify obvious change in pile depth f) Proper load transfer to Kentledge frame l) Keep soil/rock samples at site for g) Minimum distance between test pile & verification Kentledge leg m) Impose quality control at site 77

Summary 1. Requirements of piling plan submission under recent BC amendment Act and Regulations 2. Requirements for foundations of buildings more than 10-storeys 3. Good practices in design, load tests & construction 78

Concluding remark Standard Certification by QP on plans and calculations I... certify that they have been prepared in accordance with the provisions of the Building Control Regulations, the Building Control Act and any other written law pertaining to buildings and construction for the time being in force. QP who prepare plans and calculations for piling plans have to comply with the requirements of BC Act and regulations 79

THE END Thank you! 80