Core Scheduling Papers: #6 Schedule Levels Major Projects



Similar documents
Spec. Standard: 11/27/ Revision: 11/27/06

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

Project Time Management

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

DCMA 14-Point Assessment Metrics

Demonstrate and apply knowledge of project management in

PMP Exam Preparation Answer Key

Time Management. Herb Pollard III

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Project management. Objectives. Topics covered. Organizing, planning and scheduling software projects DISCUSSION

Project success depends on

Project Plan Version 0.0

Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised )

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

IMCPM04 Project Scheduling and Cost Control. Course Outline

A collection of Safran Project report samples for project professionals

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Project Management Certificate (IT Professionals)

Certified Project Management Professional VS-1079

Project Management Using Earned Value

SECTION COST LOADED CRITICAL PATH SCHEDULE

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Project Time Management an essential element to project success

Project management. Organizing, planning and scheduling software projects. Objectives. Chapter 3. Chapter 3 Project Management. Learning Objective

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.

Develop Project Charter. Develop Project Management Plan

MICROSOFT OFFICE PROJECT - SYLLABUS

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

EXHIBIT 2-2-C PROGRESS SCHEDULES

The Project Planning Process Group

Project Management Fact Sheet:

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction Why Do We Need Schedules?...

How To Manage A Project

Project Management Concepts and Strategies

Project Management Professional (Certified by PMI)

CRITICAL PATH METHOD (CPM) SCHEDULES

Introduction to IT Project Management

Project Management Dr. James A. Bednar

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

Software Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics

MODEL SCHEDULING SPECIFICATION

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Introduction to Project Management

Project Planning and Scheduling

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

How to Plan, Design & Implement A Bad Schedule Lessons Learned: The Scheduler as Generalist

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

Project management. Organizing, planning and scheduling software projects

PROJECT RISK MANAGEMENT

NFSA Project Management Guidelines

NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services

No man is wise enough by himself. -Plautus

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

An Investigation on the Impact of Laddering Technique in Project plan: a Case of Road Construction

Chapter 2: Project Time Management

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management

Organizing, planning and scheduling software projects

Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

Project Management Concepts

Certificate In Project Management (CIPM)

Systems Analysis and Design

Project Management Guidelines

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management

Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Project Management Guidelines

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18

PROJECT MANAGEMENT FRAMEWORK

Head, Office of Project Management Oversight

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

The 10 Knowledge Areas & ITTOs

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

Schedule Compression

Earned Value Management Best Practices

Developing Critical Path Method Scheduling (CPM)

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule

Work Breakdown Structure (WBS)

Step by Step Project Planning

PROJECT PLAN FOR. Project Name Here

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC. Abstract. About PRINCE2

Project management Project Management

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

WORK PROGRAM GUIDELINES

Application of MS Project Software for Time and Cost Management in Real Estate Construction

TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS

PMI Lexicon of Project Management Terms

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA

Transcription:

Schedule Levels Major Projects Level 1 Schedule Executive Summary, also called a Project Master Schedule (PMS). This is a major milestone type of schedule; usually only one page, it highlights major project activities, milestones, and key deliverables for the whole project. It is used to summarise the project schedule in reports and other documents when a more detailed schedule is not required. Frequently developed by the client as part of its initial feasibility studies for the project and then maintained by the contractor; may be used to assist in the decision making process (go/no-go, prioritization and determining the criticality of projects). Can be used to integrate multiple contractors / multiple project schedules into an overall program schedule. Audiences for this schedule Level include, but are not limited to client, senior executives and general managers. If included with a bid and/or the Contract, demonstrates conformance to contractual and other milestones. Level 2 Schedule Management Summary, also called a Summary Master Schedule (SMS). Maintained as a summarisation of the Level 3 Project Coordination Schedule(s). It depicts the overall project broken down into its major components by area and is used for higher-level management reporting. Frequently developed by the client as part of its commitment planning for the project and then maintained by the contractor. Can be used to integrate multiple contractors / multiple project schedules for the overall control of a program. It will include the Level 1 information expanded to show activities by area or major item of capital equipment. Should demonstrate the driving path for structures and major process systems at the CSI Division Level (e.g., Earthwork, Foundations, Framing, Enclosure, MEP Services and Process Equipment), based on the project method statement. Audiences for this type of schedule include, but are not limited to general managers, sponsors, and program or project managers. Level 3 Schedule Project Coordination Schedule (PCS) also called a Publication Schedule. Initially developed as an integrated CPM overview of the project, the Level 3 schedule is then maintained as an integrated rollup or summary of the Level 4 schedule activities for reporting status to senior management and to report monthly status to major clients, etc. The schedule consists of a set of integrated Level 4 schedules based on Critical Path Methodology (CPM) and is developed with detailed input from the project management team. Usually developed by the main contractor as part of its tendering process for the project or by the project team during the initial phases of planning. The Level 3 schedule spans the whole of the project and is used to support the monthly report. It includes all major milestones, major elements of design, engineering, procurement, construction, testing, commissioning and/or start-up. If the Level 4 schedules are primarily developed by trade/sub-contractors, during the initial phases of the project the Level 3 schedule provides the schedule framework and constraints used by the subcontractors to develop their tenders. During the execution phase of the project this schedule defines the overall critical path and is the primary coordination tool for the overall project. Audiences for this type of schedule include, but are not limited to program or project managers, CMs or owner s representatives, superintendents, and general foremen. Level 4 Schedule Execution Schedule, also called a Project Working Level Schedule. Level 4 is the detailed working level schedule, where each schedule is an expansion of part of a Level 3 schedule, and is established within the integrated project schedule. This is the key working level CPM schedule displaying the activities to be accomplished by the project workforce and is required for every project. The dates generated by the schedule activities represent the anticipated start and completion of work required to complete the project. If there is no Level 3 schedule, activities in future months/years may be summary in nature but still provide approximate start and completion dates for major pieces of work (this is called rolling wave scheduling ). Developed by the contractor, subcontractor (trade contractor), or the project team prior to commencing 1 www.mosaicprojects.com.au

work on the project execution, or work in a phase or area of the project. The Level 4 schedule may be for the whole of the project or a part of the project depending on the size of the project and complexity of the work. A critical factor is keeping each Level 4 schedule to a sensible size that can be easily managed, updated, validated, etc. Level 4 schedules may be for major sections of the work or for discrete processes such as a Design Schedule, Procurement schedule and/or a Commissioning Schedule. Generally, the Level 4 schedule represents the area of authority of a section manager or engineer, so one manager is responsible for all of the work in the schedule. Activities are generally over a week in duration (depending on the nature of the project) and should be resource loaded at least in the near term and include detailed crew movements and other means and methods to ensure viability. Where used, short term look ahead are produced from this level; typically Three Week Look-ahead schedules are updated every two weeks. Audiences for this type of schedule include but are not limited to project managers, superintendents, and general foremen. Level 5 Schedule Detail Schedule. The further breakdown of the activities of a Level 4 Schedule. A short term schedule used to map out the detailed tasks needed to coordinate day to day work in a specific areas. Level 5 schedules are developed by workforce supervisors to plan and coordinate their work at the detail level; Workarounds and critical areas can be exploded here. Typically Bar Charts (Gantt Charts), the schedules are replaced every 1, 2 or 4 weeks depending on the complexity of the work, typically schedules extend for 1 or 2 weeks beyond the date when the replacement is due (eg a weekly schedule will extend for 2 weeks and be updated/replaced each week), this encourages continuity of working. Audiences for this type of schedule include but are not limited to superintendents, team leaders, crew leaders, general foremen, foremen and sub-foremen. Notes: 1. This document is consistent with The Practice Standard for Scheduling 1 and published information from Bechtel Corporation and Fluor Corporation standards. 2. Schedules are typically developed from the top down, but are then maintained from Level 4 up. Level 5 schedules are temporary documents based on the Look-ahead schedule and used to coordinate work in an area. 3. Where available, the WBS is used as a basis for the development of the schedule structure. 4. Level 1 and 2 schedules are normally developed as part of the pre-feasibility studies to determine the viability of the project. a. Frequently developed as milestone charts or simple Bar Charts they outline the strategy and objectives of the overall project or program. b. Only Mega projects will have a fully maintained Level 1 and Level 2 schedule. Smaller project typically only have a Level 2 schedule. c. These schedules are maintained for reporting purposes as roll ups of data from the working level schedules (Either Level 3 or Level 4). They may be stand alone documents or integrated into a lower level schedule and extracted as a report. 5. The Level 3 schedule is initially developed as a high level CPM overview of the project. If the project is relatively small, the Level 3 schedule is expanded into a Level 4 schedule for coordinating the execution of the works. On larger projects with multiple Level 4 schedules the Level 3 schedule is maintained as the project s overall, integrated CPM schedule. 1 PMI. (2007). The Practice Standard for Scheduling. Project Management Institute, Newtown Square, PA. For more information see: http://www.mosaicprojects.com.au/planning.html#core_papers 2 www.mosaicprojects.com.au

6. Every project requires a Level 4 schedule for day to day coordination of the project s work. However, the overall size of this schedule needs to be manageable and focused on the work in one management area. The Level 3 schedule becomes critical for the overall coordination of the project as soon as more than one Level 4 schedule is in use. 7. The advances in project scheduling tools allow a high degree of integration and interconnection between individual schedules. It is quite feasible to maintain one computer file that produces the Level 1, 2 and 3 reports. Similarly the Level 3 schedule can be directly linked to the Level 4 schedules (although integration is not recommended due to the size of the files the computer can handle the records, but people have difficulty understanding the data). 8. The degree of granularity designed into a Level 4 schedule will depend on the nature of the project and the intended update cycle the guidelines included above are of general application only, see: A Guide to Scheduling Good Practice - http://www.mosaicprojects.com.au/planning.html 9. There are diverse views on the optimum maximum size for a Level 4 working schedule. Our recommendation is to aim for less than 1000 tasks per schedule (ideally 500 to 600) for several reasons: a. The schedule needs to be capable of being printed and viewed as a whole. b. The schedule needs to be easily understood by the responsible manager and the cause and effect of changes need to be both seeable and understandable by the team members using the schedule. c. The number of tasks a skilled scheduler can understand is not relevant, the important criteria is communication to, and understanding by, the project team leaders, etc. d. Most scheduling tools allow linking to external project files so having a number of Level 4 schedules will not degrade the overall integrity of the project schedule. 10. Level 3 and Level 4 schedules should be developed as CPM (Critical Path Method) networks: a. For guidance on developing an effective CPM schedule see: A Guide to Scheduling Good Practice - http://www.mosaicprojects.com.au/planning.html b. To understand the importance of using a CPM network see: Dynamic Scheduling - http://www.mosaicprojects.com.au/planning.html#core_papers c. To appreciate the role of a scheduler see: The Roles and Attributes of a Scheduler at http://www.mosaicprojects.com.au/pdf/attributes_of_a_scheduler.pdf 11. Schedule Density. 3 www.mosaicprojects.com.au

The concept of schedule density is not dissimilar to rolling wave planning. The concept is based on the idea that it is practically impossible to fully detail a schedule for a complex project at day 1 too many factors are unknown or still to be developed. The advice is to plan the overall project at low density, expand the work for the next 9 months to medium density and plan the next 3 months at high density 2. Low density activities may be several moths in duration. Medium density activities are no longer than 2 months and focused on one type of work in one specific location. High density activities are fully resourced, with a planned duration no longer than the schedule update period and with specific workers allocated. The expansion of information between levels for a construction activity may be: Schedule density and schedule levels Low density activities are used for Level 2 schedules (generally extracted from Level 3). Low and medium density activities would be used for the Level 3 schedule, with medium density activities focused in the next 12 months and low density beyond. Most of a Level 4 schedule would be medium density, expanded to high density for the next 3 to 5 months. If the Level 4 schedule extends over several years, low density activities are appropriate for future years. All Level 5 schedule activities would be high density. 12. Key References: a. AACE International. (2010). AACE International recommended practice No. 37R-06 Schedule levels of detail - As applied in engineering, procurement and construction. Retrieved from http://www.aacei.org/resources/rp/ b. Guide to Good Practice in the Management of Time in Complex Projects, published by CIOB, UK: http://www.mosaicprojects.com.au/books.html#ciob_guide 2 For more on Schedule Density see: Guide to Good Practice in the Management of Time in Complex Projects, published by CIOB, UK: http://www.mosaicprojects.com.au/books.html#ciob_guide or WP1016: www.mosaicprojects.com.au/whitepapers/wp1016_schedule_density.pdf 4 www.mosaicprojects.com.au

c. Guide to the forensic scheduling body of knowledge Part I. Ponce de Leon, G., Jentzen, G., Fredlund, D., Field, D. & Spittler, P. (2010). Published Ann Arbor: PMA Consultants LLC. This paper is a core reference in our PMI-SP and PTMC credential courses. For more information on these courses see: http://www.mosaicprojects.com.au/training-planning_one-on-one.html The papers in this series: - A Guide to Scheduling Good Practice: http://www.mosaicprojects.com.au/pdf/good_scheduling_practice.pdf - Attributes of a Scheduler: http://www.mosaicprojects.com.au/pdf/attributes_of_a_scheduler.pdf - Dynamic Scheduling: http://www.mosaicprojects.com.au/pdf/dynamic_scheduling.pdf - Links, Lags & Ladders: http://www.mosaicprojects.com.au/pdf/links_lags_ladders.pdf - Schedule Float: http://www.mosaicprojects.com.au/pdf/schedule_float.pdf - Schedule Levels: http://www.mosaicprojects.com.au/pdf/schedule_levels.pdf - Schedule Calculations: http://www.mosaicprojects.com.au/pdf/schedule_calculations.pdf Additional information; see Mosaic s Scheduling Home page at: http://www.mosaicprojects.com.au/planning.html 5 www.mosaicprojects.com.au