Use of arched cables for fixation of empty underground tanks against underground-waterinduced

Similar documents
MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Optimum proportions for the design of suspension bridge

Statics of Structural Supports

Chapter 2 Basis of design and materials

SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

DESIGNING STRUCTURES IN EXPANSIVE CLAY

MECHANICS OF SOLIDS - BEAMS TUTORIAL 1 STRESSES IN BEAMS DUE TO BENDING. On completion of this tutorial you should be able to do the following.

Numerical modelling of shear connection between concrete slab and sheeting deck

General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and guards.

SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

METHOD OF STATEMENT FOR STATIC LOADING TEST

INTRODUCTION TO BEAMS

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Seismic Analysis and Design of Steel Liquid Storage Tanks

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

1.2 Advantages and Types of Prestressing

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

METHODS FOR ACHIEVEMENT UNIFORM STRESSES DISTRIBUTION UNDER THE FOUNDATION

Page 1 of Sven Alexander Last revised SB-Produksjon STATICAL CALCULATIONS FOR BCC 250

ENGINEERING MECHANICS STATIC

Lecture 4. Case Study of 16 th C Church in Old Goa

Copyright 2011 Casa Software Ltd. Centre of Mass

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

6 RETROFITTING POST & PIER HOUSES

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

Approximate Analysis of Statically Indeterminate Structures

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

EN Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

Problem 1: Computation of Reactions. Problem 2: Computation of Reactions. Problem 3: Computation of Reactions

Chapter 8. Flexural Analysis of T-Beams

Detailing of Reinforcment in Concrete Structures

Page & Turnbull imagining change in historic environments through design, research, and technology

Guidelines for the Design of Post-Tensioned Floors

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA

Technical handbook Panel Anchoring System

Pro-Lift Steel Pile Foundation Repair

Design of pile foundations following Eurocode 7-Section 7

oil liquid water water liquid Answer, Key Homework 2 David McIntyre 1

IMPROVING THE STRUT AND TIE METHOD BY INCLUDING THE CONCRETE SOFTENING EFFECT

When showing forces on diagrams, it is important to show the directions in which they act as well as their magnitudes.

Technical Notes 3B - Brick Masonry Section Properties May 1993

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

Stresses in Beam (Basic Topics)

Structural Axial, Shear and Bending Moments

Design and Construction of Cantilevered Reinforced Concrete Structures

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

Excerpts from the Canadian National Building Code (NBC)

Step 11 Static Load Testing

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

9.3 Two-way Slabs (Part I)

Module 7 (Lecture 24 to 28) RETAINING WALLS

EVALUATION OF SEISMIC RESPONSE - FACULTY OF LAND RECLAMATION AND ENVIRONMENTAL ENGINEERING -BUCHAREST

Chapter 8. Shear Force and Bending Moment Diagrams for Uniformly Distributed Loads.

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

In-situ Load Testing to Evaluate New Repair Techniques

8.2 Elastic Strain Energy

p atmospheric Statics : Pressure Hydrostatic Pressure: linear change in pressure with depth Measure depth, h, from free surface Pressure Head p gh

Designed and Engineered to Perform

Physics 1114: Unit 6 Homework: Answers

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

NPCA Buoyancy White Paper

EFFECT OF GEOGRID REINFORCEMENT ON LOAD CARRYING CAPACITY OF A COARSE SAND BED

Experiment 3 Pipe Friction

Design of diaphragm and sheet pile walls. D-Sheet Piling. User Manual

How To Calculate Tunnel Longitudinal Structure

Installation guide for the SafeLine type anchorage device. Tested in compliance with EN 795: No.: SE-...

SEISMIC RETROFITTING OF STRUCTURES

Time- Cost Benefit Analysis for Anchor Type Foundation in Transmission Towers

Recitation #5. Understanding Shear Force and Bending Moment Diagrams

PROVA DINAMICA SU PALI IN ALTERNATIVA ALLA PROVA STATICA. Pile Dynamic Load test as alternative to Static Load test

5. Forces and Motion-I. Force is an interaction that causes the acceleration of a body. A vector quantity.

PILE FOUNDATIONS FM 5-134

Map Patterns and Finding the Strike and Dip from a Mapped Outcrop of a Planar Surface

System. Stability. Security. Integrity. 150 Helical Anchor

Lighthouse Engineering, L.L.C.

Section 16: Neutral Axis and Parallel Axis Theorem 16-1

Retrofitting By Means Of Post Tensioning. Khaled Nahlawi 1

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

A N Beal EARTH RETAINING STRUCTURES - worked examples 1

AP Physics - Chapter 8 Practice Test

HOUSE BUILDING DIGEST

ANALYSIS FOR BEHAVIOR AND ULTIMATE STRENGTH OF CONCRETE CORBELS WITH HYBRID REINFORCEMENT

When the fluid velocity is zero, called the hydrostatic condition, the pressure variation is due only to the weight of the fluid.

16. Beam-and-Slab Design

CE 366 SETTLEMENT (Problems & Solutions)

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

Chapter. Earthquake Damage: Types, Process, Categories

Physics 125 Practice Exam #3 Chapters 6-7 Professor Siegel

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Transcription:

Journal of Civil Engineering (IEB), 36 () (008) 79-86 Use of arched cables for fixation of empty underground tanks against underground-waterinduced floatation Ala a M. Darwish Department of Building & Construction University of Technology, Baghdad, Iraq Received 9 January 008 Abstract An empty underground storage tank, constructed within the fluctuating rise and fall of the underground water level, can be mobilized by an uplifting pressure equal to the weight of the displaced water minus the self weight of the tank. This research presents the detail of a suggested method to use Arched Cables to fix empty rectangular reinforced concrete tanks against any floatation caused by the uplifting pressure which might be generated by the rise of the underground water level. The equations required to design such system was demonstrated to show the application of the suggested procedure. Finally, it can be concluded that: the suggested arched cable, which is placed through a parabolic profile duct embedded in the concrete of the tank walls and anchored from its both sides by earth anchorages, has the ability of countering the uniformly distributed uplifting pressure by exerting a linear equivalent downward uniformly distributed force resulting in a more practical and economical solution to maintain empty tanks in their positions. 008 Institution of Engineers, Bangladesh. All rights reserved. Keywords: Underground tanks, floatation of a tank, fixation of a tank, lifting up pressure, arched cables. 1. Introduction Due to many aspects, a lot of storage tanks are constructed totally or partially underground. In some areas, like Iraq where this study was done, underground water level fluctuates very close to the ground surface, i.e. less than 0.5m. In such circumstances, there will be a huge uplifting pressure tending to float an empty tank in a way similar to a ship in a sea. The magnitude of the uplifting pressure is equal to the weight of the displaced water minus the self weight of the tank. Of course this is a well known critical design case,

80 A.M. Darwish / Journal of Civil Engineering (IEB), 36 () (008) 79-86 which always has been taken into consideration by structural engineers (Westbrook 1984). The solution, some times, is done by increasing the weight of the tank to be greater than the weight of the displaced water. But for large size storage tanks this solution is not practical due to the increasing amount of the uplifting pressure. In such cases a raft foundation supported by several piles may be required. Even with this structural solution piles will be subjected to tension forces, as shown in Fig. 1. For a typical interior pile supporting an underground reinforced concrete tank with the following properties, 10m depth, 0.5m thick walls, and m on centre of piles, it is easy to calculate that: this interior pile will support a compression of 460kN, when the tank is filled with water and the ground water level falls below its floor, while it must be prepared to resist a pulling up tensile force of 300kN, when the tank is empty and the ground water level rises to its maximum. In spite of the high cost of constructing pile foundations, it has many defects, which can be listed as follows: Piles penetrating into a stratum having a confined hydrostatic head will be subjected to uplift, possibly sufficient to raise them from their end bearing. Seepage around piles in unwatered excavations may reduce skin friction to less than hydrostatic uplift (Chellis 199). Even if the piles will not be raised or lifted up, they will be subjected to a repetitive high tensile stresses. These tensile stresses may be greater than the pile s concrete tensile strength. Then, cracks near the pile heads can occur. Crack formation across the entire cross section of a pile head will lead to an increasing tendency for corrosion of its reinforcing steel.

A.M. Darwish / Journal of Civil Engineering (IEB), 36 () (008) 79-86 81 Usually, sub-soil can support an underground tank without using any piles, because it was overburden by the weight of the excavated soil which is normally greater than the weight of the filled tank. But if the tank becomes empty, during the rise of the underground water level, such soil even if it is hard as the rocky soil can do nothing to resist the tank floatation. From the structural point of view, tension forces in piles will vary between interior piles and exterior ones. This variation will increase the complication of the design process. While in the following suggested solution all the piles will be eliminated. According to the above brief introduction mentioned above, the author feels that the current structural solutions to the problem of rectangular underground tanks floatation are not very satisfactory. In the present study a suggested solution for the mentioned problem will be presented. The suggestion includes the use of high tensile steel cables instead of piled foundations to stabilize underground empty tanks against floatation. These cables with their defined profiles and end anchorages have the ability to counter floatation forces in an active and economical manner.. Definition of the arched cable system A typical storage tank is shown in Fig.. It consists of floor, roof, and four side walls. For any rectangular tank there are two long walls and the other two walls are short. Uplifting pressure due to the displaced underground water is a uniformly distributed upward pressure applied to the tank floor. If the two long walls of the tank can be fixed in their positions, and this is the aim of this research, then the design of the tank floor will be similar to a one way slab subjected to an upward uniform load. A parabolic duct is required to be constructed inside the concrete of each of the long tank walls, as shown in Fig.. The path of each duct must pass through the wall two bottom corners and rise to a given height in the middle of the wall according to a parabolic equation (will be given later). A high tensile steel cable is required to pass through each duct taking its parabolic shape. Each of the two cable ends has to be well anchored to a soil anchorage. The anchorage has to be able to resist all the calculated

8 A.M. Darwish / Journal of Civil Engineering (IEB), 36 () (008) 79-86 vertical and horizontal forces or in other words to sustain the cable pulling out tensile forces. In this case, the adoption of four soil anchors, one under each tank corner, will eliminate the need for any pile leading to an acceptable escape from the mentioned problems that might be arise when pile foundations are used. This system looks like an arch but actually it is just a cable, for this reason it is called the arched cable system. The system has the ability of exerting a downward uniformly distributed linear force subjected perpendicularly along each of the long tank walls. Each tank requires two arched cables to be fixed in its original place. 3. Govermimg equations of geometry & structural action of arched cables According to the mathematical procedures used to derive the governing equations of the geometry and the structural action of arches and suspension cables (Wang 196, Ramamrutham 1988 and Thomas-1974). The shape, length, reactions, tensile force and loading of arched cables can be derived as follows; 3.1 Vertical reaction V The arched cable is not like other structural systems. It might have no end reactions if the tank floor slab is not subjected to any uplifting pressure. Moreover, it has no end reactions even due to its self weight. But if it is activated by a floating uplifting pressure, subjected to the tank floor slab, then there will be a great deal of end reactions. Figure 3 shows an arched cable a, b. This cable is exerting a uniformly distributed stabilizing downward force w per unit run on the horizontal span l, so it will be subjected to a tension force T. Point c which is situated along the cable path is representing its highest point with respect to its end anchorages a, b. This maximum height is denoted by the symbol h. The vertical end reaction V at each anchorage is calculated according to the following equation; wl V = + (1)

A.M. Darwish / Journal of Civil Engineering (IEB), 36 () (008) 79-86 83 3. Horizontal end reaction H H = wl 8h Directed away from tank center () 3.3 Maximum Tension Tmax. Maximum tension (Tmax) = Resultant reaction at a or b wl l T max. = 1+ 16h (3) The tension force along the cable varies from its maximum at the cable ends to its minimum at point c. This is because of the elimination of the vertical component at point c. 3.4 Shape of the arched cable Let the coordinate of any point p of the cable be (x, y) with respect to c, as shown in Fig.5. Let us consider the equilibrium of the part pc. The forces keeping the point p in equilibrium are the following: i. External load (wx) acting perpendicularly upwards. ii. Tension (To) = H acting horizontally at c. iii. Tension (T) at (p) acting along the tangent at p. Let ө be the inclination of the tangent at p with the horizontal. Resolving the forces on this part vertically and horizontally we get: With either support as origin, the equation to the parabolic cable is: 4hx( l x) y = l (4)

84 A.M. Darwish / Journal of Civil Engineering (IEB), 36 () (008) 79-86 3.5 Actual length of the arched cable L The actual length of the curved cable passing through the tank wall can be calculated by the following equation. L = l + 8 h 3l (5) In practice an additional extra length is required to link the cable with its end soil anchorages. 4. Example To illustrate the use of the suggested arched cable system, a simplified reinforced concrete rectangular storage tank is shown in Fig.5. Its external dimensions of (0 8 10) m, and its roof, floor and wall thicknesses (0.5) m are all assumed to simulate the required procedure. Also, the highest underground water level is assumed to reach up to 0.5m below natural ground surface. Volume of concrete = (0 10 8)-(19 9 7) = 403m 3 Weight of concrete =403 5 = 10075kN Weight of displaced water = 0 8 9.5 10 = 1500kN Net uplifting force = 1500-10075 = 515kN Net uplifting pressure = 515/ (0 8) = 3kN/m Net uniform uplifting linear force/ long wall = 3 4 = 18 kn/m

A.M. Darwish / Journal of Civil Engineering (IEB), 36 () (008) 79-86 85 Adapting a cable type 1/13 having the following properties (Westbrook-1984): Strand diameter = 10.5mm Cable diameter = 5mm Strand c/s area = 94.mm Cable c/s area =1130mm Ultimate load =1980kN Initial force = 1380kN = 138Ton Vertical reaction V = wl/=18 0/ =180kN Horizontal reaction H = wl/8h = (18 0)/(8 5) = 64Kn Maximum cable tension force T max T max = V + H = (180) + (64) = 181kN T max = (181kN) < T all (1380kN) O.K. Cable Length L The actual curved length of the cable (extra length is required for End anchorages) is calculated as follows: 8h 8 5 L = l + = 0 + = 1. 7m 3L 3 0 Profile of the arched cable The cable has to comply with the parabolic path of the duct. To calculate the coordinates of any point along this path, the following calculations show the coordinates of points at 1, 5 and 10m from the bottom corner of the tank long wall; The parabolic equation of the arched cable is: y = 4hx( l x) l = 4 5 x(0 x) 400 = 0x x 0 x = x 0 at x = 1m from left corner 1 y 1 = 1 = 0.95m 0 5 y 5 = 5 = 3.75m 0 100 y 10 = 10 = 5m 0 * Note: it is required (by the same way) to calculate the coordinates of the cable each 0.5m, in order to make it easy to fix the duct and the cable during construction.

86 A.M. Darwish / Journal of Civil Engineering (IEB), 36 () (008) 79-86 5. Conclusions Conclusions have been drawn based on an approved theoretical solution for a practical case, as follows: An empty underground rectangular storage tank, constructed in an area of high underground water level, will be subjected to an increasing amount of lifting pressure directly proportional to the volume of the displaced water. Such tanks can be mobilized from its original positions due to the huge floating pressure. To fix such tanks, it is suggested in this paper that the use of two earth anchored curved profile cables in a system called the arched cable system. The parabolic geometry of each cable can exert a uniform downward force on each of the two long walls of the tank. The amount of the linear downward force can be well calculated to counter the uniform uplifting pressure which is trying to float the tank. By applying the arched cable system to an underground rectangular tank, it can be assured that the tank will remain stable and safe in its place. Using the suggested system can eliminate the use of the current disputed pile foundations. References Chellis, R.D. (199), Foundation Engineering, McGraw-HILL Book Company, USA. George, B., Thomas, J. R. (1974), Calculus & Analytical Geometry, 4th Edition, Addison- India. Ramamrutham, S. (1988), Theory of Structures, Hindustan, Offset Press, New Delhi, Wang, C.K., (196), Statically Indeterminate Structures, McGraw-Hill International Book Company, Tokyo, Japan. Wesley Publishing Company, California, U.S.A. Westbrook, R. (1984), Structural Engineering Design in Practice, 1st ed, Longman Inc., New York, USA.