MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC. BASIC ASSUMPTIONS

Similar documents
ASME/ANSI B Cast Iron Pipe Flanges and Flanged Fittings ASME/ANSI B Malleable Iron Threaded Fittings ASME/ANSI B16.

SAMPLE TEST QUESTIONS STEAMFITTER/PIPEFITTER - ITA WEBSITE

SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

SECTION PIPE HANGERS AND SUPPORTS

SERIES ASM NEOPRENE/EPMD FLANGED SINGLE SPHERE CONNECTOR CONNECTORS. Pressures to 225 PSIG (15.51 barg) Temperatures to 230ºF (110ºC)

STEAM AND CONDENSATE PIPING AND PUMPS DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL Purpose:

CAST IRON THE BASICS. Heatline - Cast Iron Radiators SMOOTH FLAT FILE TO REMOVE ANY SWARF. ONE TIME. ASSEMBLY. JOINTS SHOULD BE TIGHTENED.

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

PIPES AND TUBES FOR HVAC PIPING AND EQUIPMENT

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

Hose Clamps & Fittings

WATER SERVICE 2

Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING

Copper and Copper Alloy Tube, Pipe and Fittings

NCCER Progress Blvd., Alachua, FL Tel: (888) Task Number Item Date(s) Recorded By

Pipe threads for tubes and fittings where pressure-tight joints are not made on the threads. (requires PTFE sealing tape or liquid sealant).

LS 2540 SEWER LATERALS AND INSPECTION TEES

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

TRANS-05, Torque Tube Removal, Rebuilding, and Installation

Front axle components, overview

Installation and Operating Instructions Installation Instructions for SS EPE-316L Series

SECTION GUARDRAILS

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

TABLE OF CONTENT

High Strain Dynamic Load Testing of Drilled Shafts

Application Guide. Compensators Hose Assemblies Expansion Joints FLEX-WELD INCORPORATED FLEX-WELD.COM. Manufactured By:

SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

Float and Thermostatic Traps Series H, C and X

Caps STANDARD WEIGHT Inches / Pounds

I N S T A L L A T I O N I N S T R U C T I O N S F O R T H E H i l k o i l Energy S aving Hot Water Kit

Style 07 Zero Flex Rigid Coupling. Style 75 Flexible Coupling. Style 77 Flexible Coupling 11. Description

Mechanical Joint Restraints

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Cover Page page 1. Table of Contents page 2. Section 1 Introduction page 3. Section 2 Variable Air Volume System Components page 4

FIX TURE CARRI ERS. 140(a) MPB-2011-USA

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Mechanical Services Standard Specification Compressed Air Systems. May For ROYAL HOLLOWAY UNIVERSITY OF LONDON

Plumbing Lesson Five: Pipe Fittings and Parts. Student Handouts

The Augustus Group Products Projects and Engineering Consulting. ASME BOILER AND PRESSURE VESSEL CODE Mike Looram

Machine Moving. By Norm Berls

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

Constantemp Double Wall Low pressure steam-water Heater F-340LDW,F-640LDW, F-940LDW and F-1240LDW

INDIAN STANDARDS (BIS) ON WELDING

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SECTION ALUMINUM HANDRAIL AND RAILING SYSTEMS WITH DECORATIVE METAL PANEL INFILLS

PARTS CATALOG RPPCR01111_Front_Backcx.indd 1 RPPCR01111_Front_Backcx.indd 1 11/21/11 1:41 PM 11/21/11 1:41 PM

Chapter 5 - Aircraft Welding

TEXAS A&M CENTRAL ACADEMIC BUILDIING & PATRIOT S CASA SUBMITTAL Pre-Insulated Piping

These features have made Lo Torc valves the choice of high pressure plug value users, worldwide:

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

Power Cube Open Source Ecology Page 1. Power Cube. Version 4

A. This Section includes the following for soil, waste, and vent piping inside the building:

General Guidelines for Repairing Buried PE Potable Water Pressure Pipes

CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION

TYPE E Main Valve Sizes 3 /8 through 12

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

MÁQUINAS AGRÍCOLAS JACTO S.A. EDITION

All work shall comply with applicable codes and ordinances. Work shall comply with the BOCA National Plumbing Code, latest edition.

Watts Pure Water Systems

DOUBLE CONTAINMENT DESIGN & INSTALLATION GUIDE

Installation Instructions

SECTION POLYVINYL CHLORIDE (PVC) PIPE

INSTALL INSTRUCTIONS KK-C-HVAC-1 HVAC UNIT CHEVROLET/GMC VANS FOR

with installation dynafact boost GAUGE this manual is for use with systems

Course available 24/7 for up to six months from the date of purchase or until completion

INSTRUCTIONS AND PARTS LIST FOR MODEL 70H & 75H HAND-OPERATED HYDRAULIC PRESS

Wastewater Capital Projects Management Standard Construction Specification

CALCULATION & DRAFTING STANDARDS MANUAL PROCEDURE: C&D 515 Bill of Materials Standard REV 0.0 5/6/04

Copper Meter Resetters

Select Radiators Installation Guide

GEET Fuel Processor Plans

Hot, Warm and Cold Mineral Water Cooler [Models Cool18, Cool25, Cool36, Cool50, Cool75, Cool100]

Rental Services Temporary Cooling - Flexible Water Hose

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

Chief S21M PARTS MANUAL Chief Automotive Technologies

SECTION DUCTILE IRON PIPE AND FITTINGS

Overview PARTS LIST. B. Lever mounting base C. Flush handle assembly D. Grey/Blue float stop E. Grey float (Full Flush) F. Flush valve washer

Fuel Tank Pickup Modifications-Dmax

Fire Hydrant Troubleshooting

WHAT YOU DON T KNOW ABOUT ACCUMULATORS CAN KILL YOU!

Important: Please read these instructions carefully and completely before starting the installation. TITAN Fuel Tanks

VOYAGER 570G. 744A Sprayer Control

GAS DISTRIBUTION PRODUCTS STEEL SERVICE TEES

Spare Parts Program. Parts, Consumables & Accessories superproductsllc.com

Pump Skid Fabrication for Magnetic Coupling. Rick Soltis Chief Mechanic City of Bedford

SECTION DUCTILE IRON PIPE AND FITTINGS

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

2. Division 05 Structural Steel Framing for steel framework requirements

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

Installation Instructions

Installation Instructions S

Heating, Ventilation and Air Conditioning

SECTION DUCTILE-IRON PIPE AND FITTINGS

Mechanical Installation

ELECTRICAL SAFETY Information Bulletin

3", 4", 6" & 8" Model H Series Alarm Check Valve Installation and Maintenance Guide

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Transcription:

A labor unit for purposes of this website, is expressed in terms of manhours to install a unit of material (such as a foot of pipe), an individual item (such as a fitting or valve), or perform a specific task (such as welding a joint). In developing the labor units set forth on this website, MCAA reviewed the many elements that make up installation labor. They are: Receiving Unloading Stockpiling Distribution Handling and erection Fitting and joining Pressure testing There are two basic approaches to laboring piping systems in the WebLEM. The traditional method is called the Component Method, and it is based on using labor units that represent all activities necessary for the installation of one component (such as a 90 elbow or a tee). For piping, the unit is in manhours per foot and for components such as fittings, the unit is represented by each. The Component Method Expressed Simply is: Base Labor + Handling and Erection + Joining + Hydrostatic Testing = Manhours Per Unit. The second method, developed and published by MCAA in 2013, is called the Work Activity Method. Labor units in the Work Activity Method are simply manhours per activity. In this method each activity has a different labor unit, so the labor to make a joint is separate from the labor to handle and erect the item as is the testing labor for the item. Because the basis for these two laboring methods is so different, estimators need to take extreme caution if they intend to use a combination of the two methods within the same estimate. The two methods are not designed to be combined, instead they are designed to give the contractor a choice at the system take-off level. Once an estimator has chosen one particular method, it s advisable that he (she) stick with that method for the entire estimate. Regardless of the method you choose, each and every item in your estimate requires manhours. In the development of this website, MCAA took extreme care to assure the proper relationships of the labor units to each other across the full scope of sizes and pressures for various materials and joining methods. Each labor unit has been derived from an empirical formula and proven over many years to be accurate and consistent.

The following conditions are assumed to exist: if conditions other than those listed below are encountered, correction factors must be applied to the units contained herein. SEE SECTION ON CORRECTION FACTORS FOR SOME OF THESE CONSIDERATIONS. All work is to be installed in 1 st, 2 nd or 3 rd floor, or 1 st or 2 nd Basement. Material stockpile is to be within two hundred (200) feet of work areas. Material is to be put in place at ten (10) feet or less above floor. (Except thirteen (13) feet for hanger rod and inserts, beam clamps, etc.) All work is to be performed off a reasonably hard and level surface. All work is done by experienced mechanics knowledgeable in the materials installed. Average working conditions and productivity exist. That material handling for inside work is as follows: 1. 0-250 lbs. Material handled by hand by two men; use of chain falls or similar tools. 2. 251-1,000 lbs. Material handled by use of a Roustabout; cannon carrier, chain falls, etc. to move and put material in place. 3. 1,001-10,000 lbs.- Material handled by small rig, lift jacks, rollers, etc. to move and install into place (personnel to operate equipment not included). Thread joints are to be made on a pipe machine. Material handling in wide-open spaces as follows: 1. Pipe distribution directly from delivery truck by stringing along route of pipe. 2. Material handling by power equipment. (Personnel to operate equipment not included). There has been no attempt to establish criteria for Union Jurisdiction on any of the items contained in this manual by placing them in a particular section of the manual. Labor is for productive hours only. Add for Non-Productive labor. Labor is based on field assembly (Any savings resulting from shop fabrication would have to be reflected when applying your labor productivity factors). For shop fabrication versus field installation breakdown, the WebLEM Committee recommends using a split of 16% for fabrication shop handling and 84% for field handling and installation. These numbers are based on data gathered and are intended to represent average conditions. Each contractor's actual split may be different based on their respective fabrication shop material flow and the specific job site conditions. Spool pieces are a fabricated item, purchased and delivered ready for installation. Special consideration shall be given to in-line items such as flow meters, control valves and expansion joints as it relates to testing and flushing procedures. In most cases the contractor cannot test or flush through these items and dummy spool pieces may need to be installed and then

removed. Labor related to the installation and removal of the dummy spool pieces is not included in the WebLEM as part of the labor units for the specialty item. All material and equipment on a project requires labor for installation. It is absolutely essential to read the footnotes at the bottom of each table! The following items pertain only to the Component Method of estimating: 1. Gaskets and bolts and the handling thereof are included in flange man-hours. 2. Labor hours for the installation of the coupling are included in the piping system. 3. Couplings have been labored in the fitting section to be used for joining non-standard lengths of pipe. For example; cutting 20 lengths of copper tubing to fit into an elevator would require an additional coupling during installation. 4. When fittings are installed back to back, a correction factor should be applied to compensate for the reduction in the number of fitting joints. 5. In threaded systems, if an item contains both female and male joints, only the female joint is considered in the calculation of the labor unit. Example: Black Malleable Iron 90 Elbow has two joints used in the calculation. A Street 90 Elbow however only has one joint used in the calculation. 6. Labor to install rubber gaskets such as used in cast iron service weight or XH fittings are included in the fitting and pipe labor units. The following items pertain only to the Work Activity Method of estimating. This method of estimating requires that every single activity to fabricate and install a spool be considered for a complete estimate of the labor hours: 1. Pipe, Fitting, Flange, Nipple and Valve Handling: These tables contain the labor for handling the item and for installation of that item and these tables are required. 2. Pipe Cut and Bevel. If the material is carbon steel, there is a table with the cut and bevel combined into one operation. Other alloys require both a cut and bevel from separate tables. 3. TIG Root: Use this table if a TIG root is required. 4. Inert Gas Purge: Use this table if an inert gas purge is required. 5. Preheat: Use this tables if preheat is required. 6. Joints: Use these tables to establish the labor hours for the buttweld, socket weld, thread, or groove joints. 7. Stress Relieving: Use these tables if stress relieving or post weld heat treat is required. 8. Bolt Up: These tables are used for ALL flanged joints. 9. In-Line Specialty Items: These tables contain handling and installation labor for all In- Line Specialty item. The joints associated with each specialty item are not included and must be accounted for separately. 10. Hydro-testing: The hydro-test tables are for flanged ends or plain/beveled ends to install and remove blanks during the hydro-testing process. Each table also contains additional labor hours per foot of pipe run to establish the hours required for filling, testing and draining the run of pipe. Make sure you add the additional hydro-testing hours as shown in these tables. 11. There are other activities to consider such as drilling holes, fillet welds, layout and flame cutting of plate and machining the inside of pipe of fittings (counter-boring). Use these tables if required.

Labor units for pipe, valves, fittings, etc do not include labor for the installation of hangers. See the hanger section for applicable labor units.

The Labor Units DO NOT include the items listed below regardless if used in the Component Method or Work Activity Method: 1. De-Watering 2. Chemical and Mechanical Pipe Cleaning 3. De-greasing 4. Performance or other special testing 5. Non-Destructive testing of welds or any other weld testing 6. Chill rings 7. Temporary operations (operation of equipment or systems for benefit of others such as temporary heat) 8. Boiler cleaning, boilout 9. Flushing and draining of systems 10. Refilling and venting of systems 11. Traps shipped with blanks, floats and/or thermostatic elements shipped separately 12. Labor for forming and/or pouring thrust blocks or installing tie rods 13. Instructions to operating personnel 14. Operational tests 15. Balancing and adjusting systems 16. Start up procedures 17. Valve charts and tags 18. Equipment and System identification 19. Shop drawings (such as sleeve and insert drawings) 20. As built drawings 21. Installation of floor & ceiling escutcheons 22. Caulking of sleeves 23. Reconditioning and cleaning of owner equipment and material 24. Cleanups 25. Special torque requirements 26. Non-productive supervision 27. Excavation and backfill 28. Shoring and tamping 29. Labor to perform X-ray quality welding The Labor Units DO NOT include the items listed below if used in the Component Method: 1. Preheating and/or stress relieving 2. Inert gas purge IT IS ABSOLUTELY ESSENTIAL THAT FULL CONSIDERATION BE GIVEN TO THE FOOTNOTES AND SPECIAL CONDITIONS LISTED ON THE VARIOUS PAGES OF THIS MANUAL.