Industrial Involvement in the Construction of Synchrotron Light Sources



Similar documents
10 Project Costs and Schedule

Status Overview The Australian Synchrotron. Steven Banks Control Systems Group

Mechanical Operation and Maintenance Vacuum Group

Status of Radiation Safety System at

Reliability and Availability Aspects of. the IPHI Project

Solutions Manufacturing Performance

Frequency Map Experiments at the Advanced Light Source. David Robin Advanced Light Source

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I)

Damping Wigglers in PETRA III

Status of the SOLEIL project Commissioning from Linac to beamlines

FIVE PROJECTS OF HIGH RF POWER INPUT COUPLERS & WINDOWS FOR SRF ACCELERATORS*

SOLEIL Current Performances. And. Futur Developments

CLS Naming and Numbering Convention

Activities at the University of Frankfurt (IAP)

RF SYSTEM FOR VEPP-5 DAMPING RING

Shielding and Radiation Measurements at ESRF

Lecture VI Magnetic Design

OVERVIEW OF PROTON DRIVERS FOR NEUTRINO SUPER BEAMS AND NEUTRINO FACTORIES*

AUTOMATION OF OPERATIONS ON THE VEPP-4 CONTROL SYSTEM

The commissioning of the LHC: first the technical systems, then the commissioning with beam

source at CERN G.McMonagle AB/RF

The half cell of the storage ring SESAME looks like: Magnetic length =

THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK

Figure 1: Lattice drawing for the APS storage ring.

Status of the Diamond Storage Ring RF Systems. Morten Jensen on behalf of Diamond Storage Ring RF Group

Results: Low current ( ) Worst case: 800 MHz, GeV, 4 turns Energy oscillation amplitude 154 MeV, where

K O M A C. Beam Commissioning of 100-MeV KOMAC Linac. Korea Multi-purpose Accelerator Complex 양 성 자 가 속 기 연 구 센 터

Status And Future Plans. Mitsuyoshi Tanaka. AGS Department.Brookhaven National Laboratory* Upton NY 11973, USA INTRODUCTION

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN

The APS Machine Protection System (MPS) *

Institute of Accelerator Technologies of Ankara University and TARLA Facility

Catherine LeCocq, Robert Ruland. February, 2008

Linac RF Commissioning with the SNS HPRF Systems

THE TAIWAN LIGHT SOURCE AND SUPERCONDUCTING CAVITY

Ferroxcube. For more information on Product Status Definitions, see page Sep CBW625

Status of the HOM Damped Cavity for the Willy Wien Ring

The BESSY HOM Damped Cavity with Ferrite Absorbers. Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides

Brookhaven Magnet Division - Nuclear Physics Program Support Activities

Beam Energy (GeV) 2 Beam Current (ma) 400 Horizontal Emittance (nm)

FCC JGU WBS_v0034.xlsm

Systems, Inc. Energy Advanced

Zero Degree Extraction using an Electrostatic Separator

Cryogenic Current Comparator Status at GSI/FAIR -

LHC MACHINE PROTECTION

Monitoring and Controlling Particle Beams in Real Time

BEAM OPERATION OF THE PAL-XFEL INJECTOR TEST FACILITY

Data-analysis scheme and infrastructure at the X-ray free electron laser facility, SACLA

R&D Support Services. Ad Astra Rocket Company

The European X-ray Free-Electron Laser: A Truly European Project. Massimo Altarelli. massimo.altarelli@xfel.eu

Large Systems Commissioning

The STAR Project: Southern european Thomson source for Applied Research

THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES

HIGH CURRENT OPERATION OF THE ACSI TR30 CYCLOTRON

Digital vs. Analogue Control Systems

Undulators and wigglers for the new generation of synchrotron sources

Control System, general approach, integration with TANGO, and some User Interfaces

CLIC accelerator and detector

Maintenance & reliability management. H. Rozelot - Workshop Maintenance & Reliability SOLEIL- November 9 & 10

Covance Construction Management Staffing Plan Chandler, Arizona

Introduction. Magnet Coordinate System

Status of High Current Ion Sources. Daniela Leitner Lawrence Berkeley National Laboratory

High Power Tests of Beryllium Oxide Windows to the Lower Hybrid Current Drive Launcher in JET

ESRF Upgrade Phase II: le nuove opportunitá per le linee da magnete curvante


EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Laboratory for Particle Physics SUPERCONDUCTIVITY AND CRYOGENICS FOR FUTURE HIGH-ENERGY ACCELERATORS

Expression of Interest in providing design and manufacturing of detectors for the construction of the European X-ray Free Electron Laser Facility

INSTRUCTION FOR COMPLETING COMPETITIVE SOLICITATION ACKNOWLEDGEMENT FORMS

Cleaning Methods of SRF Power Couplers. Mircea Stirbet

Project X: A multi-mw Proton Source at Fermilab. Steve Holmes Extreme Beam Lecture Series

The ANKA Archiving System

Calculation of Eigenmodes in Superconducting Cavities

DEVELOPMENT ENGINEER *********************************************************************************

Standby Services or Reliance on Experts for Accelerator control?

Technical specification for the ALBA area radiation monitor network and detectors

How To Improve The Ganil Control System

Remote Monitoring and Control of Irradiation Experiments

PROJECT MANAGEMENT FRAMEWORK

Instructions for Setting the T560 Digital Delay Generator for the Target Delay

Proton Nuclear Magnetic Resonance Spectroscopy

Introductions: Dr. Stephen P. Schultz

Beam Instrumentation Group, CERN ACAS, Australian Collaboration for Accelerator Science 3. School of Physics, University of Melbourne 4

The Experiment Some nuclei have nuclear magnetic moments; just as importantly, some do not

FACET First Beam Commissioning. Jerry Yocky For the FACET commissioning team 21-May-2012 IPAC 2012, New Orleans, LA

Transcription:

Industrial Involvement in the Construction of Synchrotron Light Sources M.S. de Jong, Canadian Light Source Inc. European Particle Accelerator Conference 2004-07-07

Introduction Large demand for synchrotron light sources Completed in past few years: BESSY II, SLS, CLS, SPEAR III Under construction: DIAMOND, SOLEIL, SESAME, Australia, Spain, China Many newer sources are green field No major national laboratory for support Little pre-existing infrastructure Small design teams Little experience amongst team members Greater reliance on industrial involvement and support 2

CLS Example CLS Project approved on 1999 March 31 140.9 M $C to construct: 2.9 GeV booster and third-generation storage ring at least six beamlines Only 22 staff at the start of the project, including: 2 accelerator physicists 1 mechanical engineer 1 electrical engineer 4-person group for IT, controls, diagnostics 2 scientists Challenge: Complete facility in ~ five years Increase technical staff to ~60 Build organization for operations and future R & D Review industrial involvement through major CLS contracts Examine issues and challenges Determine lessons learned 3

CLS Facility 4

Status 1999 June 15 5

Major Contracts Project Services Canadian Light Source Inc. Not-for-profit corporation controlled by U. of Saskatchewan Permits independent policies and management Responsible for: Overall management and operation Liaison with users, 14 capital funding and 4 operating funding partners Technical design of accelerators, storage ring and beam lines License from Canadian Nuclear Safety Commission UMA Management Services Day-to-day project and construction management Design and Engineering of conventional facilities (building and services) Additional technical design and engineering support as needed Formed an effective joint project team 6

Major Contracts - Strategy For accelerator systems: Reduce detailed design as much as possible Proceed with design only far enough to ensure feasibility Functional and performance specifications only Retain responsibility for: Supervisory control Machine protection Personnel protection systems Suppliers to perform as much testing as possible For beamlines and insertion devices: Develop some beamline design capability Develop room-temperature ID design and construction capability 7

Major Contracts - Booster First major technical contract awarded to Danfysik CLS supplied nominal lattice design Used to validate cost estimates for storage ring Forced development of facility standards and guidelines Allowed CLS staff to focus on storage ring system design Turn-key System included: All magnets supplied, pre-aligned on girders All power supplies RF system Vacuum chambers Diagnostics Included installation supervision and commissioning assistance Supply excluded control system, vacuum pumps Awarded in 2000 January Installation complete in 2002 July Commissioning tests complete in 2002 September 8

Booster Extraction Area 9

Major Contracts - IT EDS Canada supplied: redundant network and server backbone for all data and communications including: Office, control and beamline networks (VLANs) Voice-over-IP telephones IT architecture: Guidelines and recommendations for future IT expansion Analysis of CLS IT requirements External Review Committee to monitor contract Valuable comments from expert reviewers Difficult contract scope Few CLS management processes had clear IT needs User requirements very difficult to determine so early in project 10

Major Contracts Magnets and Power Supplies Magnets Developed a magnet measurement laboratory Primarily to support ID development But supplies must measure all accelerator magnets Can be rechecked at CLS, if necessary Dipole magnets (TESLA) Measurements done in Barcelona Quadrupole and Sextupole magnets (Sigma-Phi) All magnets within specifications Power Supplies Programmable DC for storage ring magnets (IE Power) Pulsed supplies and magnets (Danfysik) 11

Storage Ring Sector 12

Major Contracts RF System Early decision to change to Superconducting RF Determined frequency (change to 500 MHz) Availability of cavity suppliers Cavity (ACCEL) Single cavity (+spare) based on 500 MHz Cornell design Includes cold valve box and instrumentation 300 kw RF Amplifier (Thales) Turn-key system: power supply, klystron, circulator and loads Cryoplant (Linde) >250 W cooling at 4.4 K CLS is first light source to use SRF storage ring acceleration! Operations support part of responsibility of two technicians CLS only provided waveguide and low-level RF control 13

Superconducting RF Cavity 14

Major Contracts - Vacuum Vacuum pumps and controllers (Varian) Single supply contract for the entire facility Negotiate standard prices for all procurement CLS supplies pumps and controllers to all contractors Storage ring vacuum chambers (FMB) Based on BESSY II and SLS design Installation by local construction contractors under CLS supervision 15

Major Contracts - Beamlines Insertion devices 4 designed and assembled in-house Two PPM, one hybrid in-vacuum SGU, one EPU Support structures by ADC (PPM+EPU) and RMP (SGU) Superconducting multi-pole wiggler (BINP) Front-ends based on APS design (Johnsen Ultravac) Seven beamlines 2 IR beamlines spectrometers (Bruker) and optical chicane (ADC) Five x-ray beamlines Two turn-key (IDT+Koizu, ACCEL) Two functional specification of components (Jobin-Yvon, Oxford Danfysik, and McPherson) One build-to-print (Johnsen Ultravac) based on ALS design 16

Issues and Challenges - 1 Project management view: scope, cost and schedule Scope: Need standard scope for technical specifications Availability of good sample technical specification important no bonus points for originality in specifications Need design standards and guidelines very early in project Difficult with new or inexperienced staff Desirable to have at least 3 bids Can determine scope of major tenders Cost: Importance of competitive bids Typically factor of two or more in price if 3 or more bids for designbuild tenders Restrictive tendering practices will increase cost Frequently used fixed price + incremental rates for most labour contracts Competent installation labour will challenge design team to keep ahead 17

Issues and Challenges - 2 Schedule: Most design-build contracts arrived late 10 major CLS accelerator contracts 8 deliveries were late by between 5 and 8 months Overall project schedule needs to allow for this possibility CLS targeted all contracted deliveries by end of 2002 Approximately ¼ to 1/3 of delay was due to CLS Delays CANNOT be used to justify other schedule slippage Control of scope and design changes essential Need engineering change control New staff often unfamiliar with process Used bonus-penalty contract for two smaller contracts - effective Communications (internal and external): Need good tracking of issues raised and their resolution Plan on 3 5 face-to-face meetings over contract duration Use weekly teleconference with email of issue-tracking form Difficult to reduce internal delays when contractor questions arise 18

2003 December SUCCESS: 10 ma Stored beam in C L S fill pattern 19

Conclusion Storage ring commissioning finished in 2004 May Approximately six months behind original schedule Cost over-run is approximately 0.05% Start Routine Operation in 2004 August I wish to acknowledge the huge contribution to our success by: All CLS suppliers and vendors for their commitment to high quality work University of Saskatchewan management and staff UMA Engineering All CLS staff 20