RISK MANAGEMENT APPLIED TO TUNNELS



Similar documents
Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

TBM CROSSING OF STATIONS

Tunnelling & Underground. Specialists

Milan M5 metro extension the construction of Lotto station

(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT Nina Tveiten Norwegian National Rail Administration

How To Calculate Tunnel Longitudinal Structure

Investigation on the Effects of Twin Tunnel Excavations Beneath a Road Underpass

Numerical Analysis in the Design of Urban Tunnels. Numerical Analysis in the Design of Urban Tunnels

UNDER DRAINAGE AND FILTER DESIGN

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Subsidence due to peat decomposition in the Netherlands kinematic observations from radar interferometry

BUTE Department of Construction Management and Technology

Member Nation Report 2010 from Denmark.

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

AFTES POST-GRADUATE SPECIALISED MASTER S DEGREE TUNNELS AND UNDERGROUND STRUCTURES. from design to operation.

ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY

Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy

THE TRANSITION FROM OPEN PIT TO UNDERGROUND MINING: AN UNUSUAL SLOPE FAILURE MECHANISM AT PALABORA

Benchmarking Multi-Dimensional Large Strain Consolidation Analyses D. Priestley 1, M.D. Fredlund 2 and D. van Zyl 3

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

Embedded Rail Slab Track

EXPLAINING GROUNDWATER AND WATER WELLS

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

How To Design A Foundation

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Geotechnical Building Works (GBW) Submission Requirements

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Pro-Lift Steel Pile Foundation Repair

Emergency repair of Bridge B421

Groundwater Training Course SOPAC, April Electromagnetic (EM) Induction method for Groundwater Investigations

SOIL MECHANICS Assignment #4: Soil Permeability.

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Life after 30! Innovative investigation and repair of the Overvaal railway tunnel. r a i l w a y s a n d h a r b o u r s PROJECT TEAM

SECTION SHEETING, SHORING AND BRACING

DESIGN AND EXECUTIVE ASPECTS OF THE CONSTRUCTION OF THE LINE 1 OF THE NAPLES METRO

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

METHOD OF STATEMENT FOR STATIC LOADING TEST

A study on the causes of troubles in shield tunneling site with numerical analysis

Geothermal. . To reduce the CO 2 emissions a lot of effort is put in the development of large scale application of sustainable energy.

CIVL451. Soil Exploration and Characterization

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

A HYBRID GROUND DATA MODEL TO SUPPORT INTERACTION IN MECHANIZED TUNNELING

Design and Construction of Auger Cast Piles

DATA MANAGEMENT SYSTEM FOR TUNNELLING

Validation of methods for assessing tunnelling-induced settlements on piles

Liner system design for tailings impoundments and heap leach pads

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

Strategy and Analysis in Using NPV. How Positive NPV Arises

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

Membrane for tunnels and underground construction

GUIDELINE FOR HAND HELD SHEAR VANE TEST

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Know What Caused A Tunnel Collapse

Sample Project with SlurryTBM according to Anagnostou and Kovári

Washington ,

BOREHOLE SEALING IN A COAXIAL HEAT EXCHANGER BY BENTONITE TREATMENT

Effect of Sleeve Shrink-fit on Bearing Preload of a Machine Tool Spindle: Analysis using Finite Element Method

A GUIDEBOOK TO THE CHANGES IN BUILDING CONTROL 2007/2008. Building and Construction Authority

Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the

SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT RESOURCE REGULATION TRAINING MEMORANDUM

Numerical Simulation of CPT Tip Resistance in Layered Soil

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES

Determination of Thermal Conductivity of Coarse and Fine Sand Soils

SOME EXPERIENCE FROM THE SOFT GROUND TUNNELLING IN URBAN AREA

Reliability of Estimated Anchor Pullout Resistance. Yasser A. Hegazy, M. ASCE 1

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

Construction sites are dewatered for the following purposes:

MSE Wall Engineering A New Look at Contracting, Design, and Construction. Presented by: James M. Schmidt, P.E., P.Eng. 1 Daniel L. Harpstead, P.E.

Section Installation of pipe and casing for sanitary sewer by methods of augering.

General Manager of Geotechnical Department, CEO

State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

hs2 Ground A non-technical guide

Construction Dewatering and Ground Freezing

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

GOWANUS EXPRESSWAY TUNNEL PRIMER

CHAPTER 9 FEM MODELING OF SOIL-SHEET PILE WALL INTERACTION

Monobuckets and the competitiveness versus monopiles and jacket structures.

Integrated Tunnelling Data Management, Analysis and Visualization New IT Tools for Better Projects

Figure CPT Equipment

vulcanhammer.net This document downloaded from

EGYPTIAN CODES FOR DESIGN AND CONSTRUCTION OF BUILDINGS

DIRECTIONAL DRILLING

Open Access Numerical Analysis on Mutual Influences in Urban Subway Double-Hole Parallel Tunneling

SOUTH AFRICAN NATIONAL INSTITUTE OF ROCK MECHANICS CHAMBER OF MINES OF SOUTH AFRICA CERTIFICATE IN ROCK MECHANICS PART 4

EH-20 20m antenna. By VE3RGW

Design of diaphragm and sheet pile walls. D-Sheet Piling. User Manual

Methods for Land Reclamation using Soft Soil and Waste

A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES

Transcription:

RISK MANAGEMENT APPLIED TO TUNNELS J. Brinkman Deltares, Delft, The Netherlands e-mail: hans.brinkman@deltares.nl GeoQ All tunnel projects require some sort of solid foundation, but ground conditions bring some degree of uncertainty to every tunnel project. Dealing properly with uncertainty over ground conditions can make the difference between the commercial success and failure of a tunnel project. With margins in the construction industry at historic lows, and with costs of failing to accurately predict ground conditions becoming increasingly high, the importance of proper management of the variety of groundrelated risk is paramount. Risk management has demonstrated its value in many industries, but the full lessons of that experience has not yet fully reached all aspects of civil engineering. In particular, the importance of individuals and their own awareness of risks and how to manage them has often been overlooked. Martin van Staveren has written a new kind of book on ground risk management, the GeoQ concept. Based on many years of professional experience and proven risk management techniques. Figure 1 GeoQ Tunnelling in the Netherlands All the work that is done in the field of soil deformations due to shield tunnelling in the Netherlands can be put in a risk management perspective. In early nineties, the bandwidth for prediction and controlling tunnelling was far too large to start tunnelling in the sensitive ancient inner cities of the Netherlands. Figure 2 Reduction of risk due to soil deformations as a function of time

Figure3 Research on soil deformation in relation to Dutch shield tunnel project One can say that to narrow this bandwidth a risk management process started by the visit of a Dutch delegation Japan in 1991. In 2002, the bandwidth was narrowed to such an extent that tunnelling the North-South Metro Line in the sensitive ancient city centre of Amsterdam is feasible. In this process, the innovation circle tool has been applied. Figure 4 Innovation circle for grouting Two examples of the innovation circle are presented in this presentation: for grouting and for face stability. Furthermore a brief overview on soil deformation research in the Netherlands in relation to the different tunnelling projects is given. Finally, a general overview is given for the present Dutch situation; this is an interpretation of design procedures of the different projects from a risk management point of view. The groene hart tunnel case The Groene Hart tunnel is a 7190 m long, 14.9 m diameter shield tunnel, part of the high-speed railway link between Amsterdam and Paris. The risk management in the initiative, the preliminary design, contract, final design and construction phase is presented. At the end of the initiative phase a (very expensive) bored tunnel was chosen under the Green Hart, this was a political decision no technician had foreseen. Starting the preliminary design the tunnel project was based on risk management control. Some of boom, structural integrity, integrity of the Green Hart and time. For all these items, special research was initiated to the first air shaft knowledge to be able to manage the risks to an acceptable level. To make use of the international knowledge and experience in the field of shield tunnelling a D&C contract was chosen. As planning was tight in advance of the contracting phase a symposium was held to inform the market about

the tunnel project and all of the key risk items. Also during the contracting phase, the full risk dossier was shared. This resulted in a very competitive innovative winning design that was taking care of all key risk items. During the detailed design phase and the construction phase, the client and the contractor only discussed the key risk items in an open constructive way. Figure 5 The lanching shaft of the Groene Hart tunnel with at the bottom side the first air shaft Figure 6 The full scale tunnel lining test facility with 3 full rings 2 probabilistic analysis of the soil deformations. As a client should not interfere in the details how a contractor runs the TBM the Project organisation HSL-zuid has chosen not to demand an extensive monitoring program. To minimise the risk of delays due to large instabilities in loose sands layers and to ensure a well embedded lining it was chosen to restrict the surface settlements to 10-25 mm. The idea was that small settlements are only possible with good face stability and a good grouting. The result would be a limited chance on instabilities (calamities) and a good filled tail void. The goal of project organisation HSL-zuid for this probabilistic analysis was to get an insight in the variations of the surface settlements to be expected during normal tunnelling operations and to detect critical sections. Based on the geology and depth of the tunnel the 7160 m length was divided into 15

sections. For each section series of FEM analyses where made. The stiffness and strength of individual soil layers and the pore water pressures and the unit weight of the soil were varied in the FEM computations. These variations where based on the 5% upper and lower limit results of the geo-statistical analysis of the extensive soil investigation. In the analysis the grout and slurry pressures where also varied. The basis of this analysis was the design of the contractor Bouygues-Koop with his proposed grout and slurry pressures. The results of these FEM analysis where combined to a mean, 5% upper and 5% lower bound prediction of the settlements. Further, an analysis was made on the minimum and maximum face pressure based on analytical methods to detect critical sections. A long critical section was detected in a deep polder. The critical mechanism was the propagation of tunneling induced excess pore water pressures in the confined aquifer resulting in a loss of vertical stability of the overlaying aquitard in the polder consisting of very soft organic clay. For this a detailed analysis was made and during tunnelling the results of this analysis where verified by measurements. Then it was chosen to take extensive mitigation measures to ensure the vertical stability of the soft organic clay layer during tunneling. Figure 7 The geological profile of the Groene Hart tunnel and the settlement prediction band and measurements Souterrain case The Souterrain in The Hague, also known as the Tramtunnel combines a Light Rail Line underneath the busiest pedestrian shopping area in the centre of the city with a large number of parking facilities. At its deepest point the Souterrain has three different levels: 2 floors with parking facilities and below those the double Light Rail Line at the 3rd level. The Souterrain contains two Rail Stations, one at Grote Markt and one at Spui. The length of the tunnel is 1250 m and its maximum depth is 13m. During the construction cost nearly tripled here the main lesson learned are discussed February 1998 a leak developed in the jetgrout arch in part 16 of the Kalvermarkt section of the Souterrain. Sand erosion from outside the tunnel lead to sinkholes at ground surface. To stop flow of water and sand towards the tunnel and to prevent damage

Figure 8 Section of the Souterrain with a Jetgrout arch Figure 9 Section of the Souterrain with a Soft-gel injection layer Construction stopped for approximately two years. When, after a two year standstill, construction started again in July 2000 it had become apparent that the deep wells in station Spui had lost much of their capacity to de-water the soil contained between the diaphragm walls and the deep gel layer. Circumstances called for interaction between measurements and construction phasing. The original design approach aimed to minimise construction costs by taking into account the variable width and depth of the tunnel over its length. By using different construction techniques depending on local depth and width of the tunnel, an optimized construction scheme was defined. The lessons learned where: 1. minimize the amount construction types as transitions always significantly increase the risk profile 2. make an in-depth what-if scenario analysis, especially if a system is optimized to its extreme. In the end, the use of the Observational Method (OM) led to the successful completion of Station Spui. The combination of the new monitoring with existing measurements led to changes in the construction sequence, reducing settlements below adjacent buildings. This was helped by a changed, more flexible and adaptive organisation of the project. The late implementation of OM was hindered by the original optimised, but relatively inflexible, design. References Aartsen R.J. Shield Tunneling under the Green Heart. Soft soil and excess pore pressures Challenges and solutions. Tunneling and soil improvements The 5th Japan the Netherlands Tunnelling Seminar, Delft 2005 Bezuijen A. Model experiments using foam, simulating the drilling with an EPB shield, GeoDelft report CO-51010. 2000

Bezuijen, A. & Brassinga E., Blow-out pressures measured in a centrifuge model and in the field Proc. Int. Symp. on Modern Tunneling Science and Techn. Kyoto 2001. Bezuijen, A, Pruiksma, P. & Meerten, H. van. Pore pressures in front of tunnel, measurements, calculations and consequences for stability of tunnel face Proc. Int. Symp. on Modern Tunneling Science and Techn. Kyoto 2001. Bezuijen A., Talmon A.M., Kaalberg F.J. and Plugge R. Field measurements on grout pressures during tunnelling Proc. 4 th Int. Sym. on Geotechnical Aspects of Underground Construction in Soft ground, Toulouse 2002 Bezuijen A. The influence of soil permeability on the properties of a foam mixture in a TBM Proc. 4th Int. Sym. On Geotechnical Aspects of Underground Construction in Soft ground, Toulouse 2002 Brinkman J. Managing soil deformations due to tunnelling in the Netherlands. The 4th Japan the Netherlands Tunnelling Seminar, Delft 2002 Brinkman J. Learning tunnelling in The Netherlands. Proc. 1 st China-Japan-The Netherlands Tunnel Seminar, Shanghai, 2006 Jovanovic P.S. Chances offered by Risk Management Control on Design Build. Tunnelling Projects Transportation Research Board, AM82, Washington 2002 Luger H.J. Use of OM at the Souterrain, the Hague, Geotechnet Case study 6, Delft 2005 Staveren M.T.H. Uncertainty and Ground Conditions: A Risk Management Approach. Elsevier Publishers 2006