How To Know What Caused A Tunnel Collapse
|
|
|
- Winfred Nash
- 5 years ago
- Views:
Transcription
1 An unusual tunnel collapse, the Hull Wastewater Transfer Tunnel Australian Tunnelling Society Wednesday, 26th March, 2014 Steve Macklin Principal Tunnel Engineer/ Engineering Geologist, GHD Melbourne
2 References: Chamley et al (2000) North America Tunneling Conference, Boston June Published AUA News September Caiden, Chamley & Covil (2005) RETC Proceedings, 2005 BTS Informal Discussion at the ICE, November 2001, Tunnels & Tunnelling, March 2002 Machon & Stevens (2004) - Proc. Institution of Civil Engineers, GE3 Grose & Benton (2005) Proc. Institution of Civil Engineers, GE4 Various (2006) - Discussion: Proc. Institution of Civil Engineers, GE2 Munks, Chamley & Eddie (2004) Proc. North American Tunnelling 2004 Brown (2004) - Proc. Institution of Civil Engineers, GE3 Tunnels & Tunnelling March 2002
3 The project The failure The investigation Possible causes Remediation Implications for the insurance industry Lessons learned Questions An unusual tunnel collapse, the Hull Wastewater Transfer Tunnel
4 The project 10.6km tunnels 10No. Shafts 7.5m to 12.5m int. diam. 2No. Jet grout maintenance blocks 6No. De-watering & comp. air stops 3.6m ID lining: 6No. Trapezoidal Segments, 1m long, 250mm thick Segments cast vertically location 50M contract to construct a 10.6km long tunnel for Yorkshire Water's 200M Humbercare sewage collection and processing scheme.
5 The project Medium dense silty, fine to medium alluvial SAND (non-tidal aquifer) 2. Firm to stiff and friable PEATY CLAY/SILT, with fragments of timber, aquitard, k h 400k v 3. Upper alluvial SILTY FINE SAND grading down to GRAVELLY SAND to SANDY GRAVEL 4. Soft to firm to stiff thinly LAMINATED CLAY (aquiclude, k h 10k v ) 5. Dense fine AEOLIAN SAND 6. glacial SAND AND GRAVEL (tidal aquifer) HOLOCENE PLEISTOCENE
6 The project The failure The investigation Possible causes Construction News, 14 September 2000 Remediation Implications for the insurance industry Lessons learned Questions. All tunnels leak to some extent, but when I was told of the enormity of this situation I couldn't understand what could have gone wrong
7 Failure sequence: The failure 19:00 R2403 2L/min leak right knee 23:30 7L/min 00:30 black organic smelling water, leaking around circle joint 01:30 sand filling invert, rings buckling 02:20 invert heaving, re-bolting attempted 02:45 manrider derailed and abandoned 03:00 segments crazing and spalling 03:30 tunnel abandoned 04:00 water main burst, ground cracking, shaft sinking 07:30 tunnel inspected, filled with fine sand 60m diameter depression - maximum 2.6m settlement the volume of the settlement depression was about 2600m 3 - tunnel filled with fine sand/silt approx. 200m either side of shaft
8 The project The failure The investigation Possible causes Grose & Benton, 2005 Remediation Implications for the insurance industry Lessons learned Questions The investigation into the cause of the collapse demanded.. urgent answers. Clearly, future tunnelling, and the previously constructed tunnel, were at risk until conclusions were available regarding the cause
9 The investigation So why did an apparently stable, grouted-up lining fail weeks after construction? Was it: Something in the ground conditions (e.g. peat compressibility, mobile sands)? Hydrogeological effects (e.g. damming, tidal fluctuations in water pressure)? A design flaw (e.g. segment capacity, shear pad failure, gasket bypassed)? Construction problems (e.g. ring damage during shaft entry, removal of circle joint bolts, annulus grouting, shaft disturbance)?
10 The investigation A comprehensive investigation was undertaken, this included: New ground investigations including: 22 BHs, 71 CPTs, PM tests Triaxials, Rowe Cells, oedometer, Pollen & species analysis, C 14 dating (Uni Hull) and LOI (in peat); Atterbergs; PSD; SEM (aeolian sand); dispersivity (laminated clay); water chemistry; Centrifuge (Cambridge Univ. Eng. Dept.); Hydro (piezo, 2No. Pump tests, tracer Uni Sheffield) lining design checks 2D and 3D FEA modelling of possible failure mechanisms Witness statements to reconstruct sequence of events Examination of available construction records
11 The investigations Centrifuge tests limited by modelling simplifications required, however confirmed: Tunnel buoyancy caused longitudinal deformation relative to fixity at the shaft softening/ disturbance of soil local to the shaft Circle joint opening If laminated clay in invert stays intact NO FAILURE But if fine single size SAND gains access FAILURE
12 The project The failure The investigation Possible causes Remediation Grose & Benton, 2005 Implications for the insurance industry Lessons learned Questions A relatively unusual feature of the collapse was that there was no immediately obvious cause.. usually the blame is attributed to some design or construction aspect or.. adverse ground conditions. but in this case all seemed satisfactory
13 Possible causes Consequence of longitudinal movement: top hat incident? shear pads failure? Nib crushed gasket bypassed?
14 Possible causes Highly mobile fine sand silt in: In Holocene alluvium laminated clay Aeolian sands Previous problems: Hull Tidal Surge barrier (Fleming et al 1980 and McMillan, 1984) Shaft tremmie problems with trapped silt sludge (T4) Problems with ground anchor holes piping Possible glacial disturbance providing water path in laminated clay The peat/organic clay: Disturbance and softening during shaft construction? Loss of confinement due to buoyancy, compression? leakage & consolidation at the early stages? Groundwater pressure: Failure at HIGH TIDE damming by tunnel 2bar in lower aquifer but... Upper aquifer no tidal response so lower pressure
15 The project The failure The investigation Possible causes Brown, 2004 Remediation Implications for the insurance industry Lessons learned Questions. The use of liquid nitrogen to create a stable environment in which to rebuild the tunnel was a technically challenging option. Cost and programme implications were significant
16 Remediation 40m 75m W2 W1 E1 E2 E3 Re-mining using AGF to form 1.5m ice-walls around tunnel
17 The project The failure The investigation Possible causes Remediation Implications for the insurance industry Lessons learned Questions Underwriters reluctant to Insure Tunnel Projects without adoption of Joint Code of Practice please provide your views and comments June 2003, from AON, KCRC s Insurance Brokers (Jesudason HKIE, download March 2014)
18 Insurance implications Chamley et al (2000): The Construction All Risks (CAR) insurance policy covered both client and contractor - protected against the damage repair costs. ACCELERATION INSURANCE addressed the measures necessary to get the construction back on track to meet the completion date. Where the CAR policy does not cover the remedial works and programme mitigation costs, the COST OVER-RUN INSURANCE limited the clients financial liability. Client saw little impact and the anticipated outturn cost was within the original estimate.
19 Insurance implications Munich Re - Wannick (2006) BTS closed face tunnelling report on Hull and Portsmouth collapses May 2002 BTS ABI JCOP published September International Tunnelling Insurance Group (ITIG) by 2005
20 The project The failure The investigation Possible causes Covil et al (2005) Remediation Implications for the insurance industry Lessons learned Questions four key risks during construction are safety (life and economic), cost, time and quality. These can all be identified, assessed, valued, mitigated and then apportioned to the appropriate project stakeholder
21 Lessons learned Carry out detailed geo-hazard risk assessments and risk management processes early (e.g. identifying previous issues with the mobile sands ) Keep on top of TBM data logging never know when you need the data note the Closed Face working party (2002) recommendations (4.2) Ensure annular grouting and take a zero tolerance to leaks Smooth transition from rigid shaft to flexible tunnel design for permanent bolts or some other means Are shear pads (for build accuracy) a good idea? Distance between EPDM gasket and extrados? Segment design and casting adequate cover and joint quality Monitoring (e.g. ground movement, water pressures) in critical locations - difficult around a working shaft but this is a key risk area Design for sufficient redundancy / robustness avoid false economies
22 The project The failure The investigation Possible causes Grose & Bentley (2005)_Discussion Remediation Implications for the insurance industry Lessons learned Questions buoyancy and tidal variations caused repeated cyclic movement of the tunnel even with a fully grouted annulus. This. may have created both a path for the sand to travel towards the tunnel and compromised the gasket.
23
Impacts of Tunnelling on Ground and Groundwater and Control Measures Part 1: Estimation Methods
Impacts of Tunnelling on Ground and Groundwater and Control Measures Part 1: Estimation Methods Steve Macklin Principal Engineering Geologist GHD Melbourne 1. Introduction, scope of Part 1 2. Terminology
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering
Washington 98102-3699, [email protected]
LESSONS LEARNED FROM A STONE COLUMN TEST PROGRAM IN GLACIAL DEPOSITS Barry S. Chen 1, P.E., Member, Geo-Institute and Michael J. Bailey 2, P.E., Member, Geo-Institute ABSTRACT A stone column test program
BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM
BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
Coxwell Sanitary Trunk Sewer Emergency Repair: By-pass Sewer Tunnel Construction Final Report
STAFF REPORT ACTION REQUIRED Coxwell Sanitary Trunk Sewer Emergency Repair: By-pass Sewer Tunnel Construction Final Report Date: July 28, 2014 To: From: Public Works and Infrastructure Committee General
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located
Soils, Foundations & Moisture Control
Soils, Foundations & Moisture Control Soil The top loose layer mineral and/or organic material on the surface of the Earth that serves as a natural medium for the growth of plants and support for the foundations
Construction sites are dewatered for the following purposes:
9. DEWATERING CONTROL OF GROUNDWATER Construction of buildings, powerhouses, dams, locks and many other structures requires excavation below the water table into water-bearing soils. Such excavations require
Site Investigation. Some unsung heroes of Civil Engineering. buried right under your feet. 4. Need good knowledge of the soil conditions
This is an attempt to create a stand alone self learning module on site investigation. Fasten your seat belts. Sit back, relax and enjoy. 1 2 Site Investigation Some unsung heroes of Civil Engineering
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
COST AND PERFORMANCE REPORT
COST AND PERFORMANCE REPORT Pump and Treat of Contaminated Groundwater at the United Chrome Superfund Site Corvallis, Oregon September 1998 Prepared by: SITE INFORMATION Identifying Information: United
How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska
APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED
Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples
Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: [email protected]
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines Jeff Schell General Manager United Pipeline Middle East, Inc. Introduction HDPE Liners A cost effective and environmentally beneficial
Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole
An Interdisciplinary Response to Mine Water Challenges - Sui, Sun & Wang (eds) 2014 China University of Mining and Technology Press, Xuzhou, ISBN 978-7-5646-2437-8 Treatment Practice for Controlling Water
KWANG SING ENGINEERING PTE LTD
KWANG SING ENGINEERING PTE LTD 1. INTRODUCTION This report represents the soil investigation works at Aljunied Road / Geylang East Central. The objective of the soil investigation is to obtain soil parameters
Liner system design for tailings impoundments and heap leach pads
Liner system design for tailings impoundments and heap leach pads John F. Lupo, Ph.D., P.E. AMEC E&E TAILINGS & MINE WASTE 08, VAIL Liner Systems Liner systems Environmental containment of process solutions
AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month
, as published in July 2008 Opflow Question of the Month Thanks to: Mike Grahek, Los Angeles Department of Water, Los Angeles, California Ahmad Havivian, Black & Veatch, Gaithersburg, Maryland David Kroon,
Guidelines For Sealing Groundwater Wells
Guidelines For Sealing Groundwater Wells Government of Newfoundland and Labrador Department of Environment and Conservation Water Resources Management Division Government of Newfoundland and Labrador Department
c. Borehole Shear Test (BST): BST is performed according to the instructions published by Handy Geotechnical Instruments, Inc.
Design Manual Chapter 6 - Geotechnical 6B - Subsurface Exploration Program 6B-2 Testing A. General Information Several testing methods can be used to measure soil engineering properties. The advantages,
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
Rehabilitation of Existing Foundation Building to Resist Lateral and Vertical Loads
International Journal of Current Microbiology and Applied Sciences ISSN: 2319-7706 Volume 3 Number 12 (2014) pp. 950-961 http://www.ijcmas.com Original Research Article Rehabilitation of Existing Foundation
REPORT. Earthquake Commission. Christchurch Earthquake Recovery Geotechnical Factual Report Merivale
REPORT Earthquake Commission Christchurch Earthquake Recovery Geotechnical Factual Report Merivale REPORT Earthquake Commission Christchurch Earthquake Recovery Geotechnical Factual Report Merivale Report
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,
-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION
-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION -Unit number- 4420798 -Unit title- CONSTRUCTION TECHNOLOGY 2: SUBSTRUCTURE AND REMEDIAL WORKS -Superclass category-
load on the soil. For this article s examples, load bearing values given by the following table will be assumed.
How Many Piers? By Gary Collins, P.E. A clear-cut guide to helical pier spacing Introduction Helical pier spacing is not an exact science. How many does it take to support a structure adequately or repair
Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.
TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may
Specifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
Pile test at the Shard London Bridge
technical paper Pile test at the Shard London Bridge David Beadman, Byrne Looby Partners, Mark Pennington, Balfour Beatty Ground Engineering, Matthew Sharratt, WSP Group Introduction The Shard London Bridge,
WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10
WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta
Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation
Trench Rescue by Buddy Martinette
Trench Rescue by Buddy Martinette SOIL TYPE AND TESTING It is imperative that rescue personnel understand soil types and testing procedures if the want to be competent at trench rescue operations. Determining
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
ENCE 4610 Foundation Analysis and Design
This image cannot currently be displayed. ENCE 4610 Foundation Analysis and Design Shallow Foundations Total and Differential Settlement Schmertmann s Method This image cannot currently be displayed. Strength
Design Considerations for Water Storage Structures on Porous Foundation in South West Western Australia
Design Considerations for Water Storage Structures on Porous Foundation in South West Western Australia Michael Ashley, Robert Wark GHD The construction of service reservoirs has been an integral part
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
Oakland Macomb Interceptor Drain Rehabilitation State Revolving Fund Project Plan Overview. Public Meeting June 10, 2009
State Revolving Fund Project Plan Overview Public Meeting June 10, 2009 What is the OMI? The OMI is the Oakland Macomb Interceptor Sewer. The OMI transports much of the sanitary sewage from Oakland and
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
SNC-Lavalin Inc. Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report. October 2011
SNC-Lavalin Inc. Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report October 2011 SNC-Lavalin Inc Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report Table of Contents 1.0
Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle
Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle EPB-TBM Face Support Control in the Metro do Porto Project, Portugal S. Babendererde, Babendererde Engineers LLC, Kent, WA; E. Hoek, Vancouver,
REPAIRS TO DAMAGED SEWERS
REPAIRS TO DAMAGED SEWERS A digout is the replacement of sewer or storm water pipes that are either broken or blocked due to tree roots, ground movement or ageing of pipes. When the use of high-pressure
Flowtite Jacking Pipe
U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
MINIMIZING DEFECTS OCCURRENCES ON SFRC TUNNEL SEGMENT OF KLANG VALLEY MRT PROJECT
Journal of Engineering Science and Technology Special Issue on 4th International Technical Conference 2014, June (2015) 13-23 School of Engineering, Taylor s University MINIMIZING DEFECTS OCCURRENCES ON
Soil behaviour type from the CPT: an update
Soil behaviour type from the CPT: an update P.K. Robertson Gregg Drilling & Testing Inc., Signal Hill, California, USA ABSTRACT: An initial application of CPT results is to evaluate soil type and soil
SECTION 02612 NONREINFORCED CONCRETE SEWER PIPE
SECTION 02612 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Furnishing and installing nonreinforced concrete sewer pipe. Provide concrete sewer pipe less than 12 inches in diameter, and in other sizes
Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels
Estimation of Adjacent Building During Drilling of Urban Tunnels Shahram Pourakbar 1, Mohammad Azadi 2, Bujang B. K. Huat 1, Afshin Asadi 1 1 Department of Civil Engineering, University Putra Malaysia
Repair or Replacement - Band-Aids vs. Surgery
Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing
June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
APPENDIX K PIPE INSPECTION
APPENDIX K PIPE INSPECTION **Virginia Test Method 123** Post Installation Inspection of Buried Storm Drain Pipe and Pipe Culverts June 25, 2010 SCOPE For all roadway projects that are constructed by private
CPT interpretation in marine soils less than 5m depth examples from the North Sea
CPT interpretation in marine soils less than 5m depth examples from the North Sea R. Mitchell SEtech (Geotechnical Engineers) Limited, Great Yarmouth, England S. Wootton & R. Comrie SEtech (Geotechnical
FREDERICK SHERRELL LTD
FREDERICK SHERRELL LTD CONSULTING ENGINEERING GEOLOGISTS AND GEOTECHNICAL ENGINEERS 66 WEST STREET TAVISTOCK DEVON PL19 8AJ Your Ref: Our Ref: 2962.NS.JR Telephone: 01822 612915 Facsimile: 01822 617394
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
Drained and Undrained Conditions. Undrained and Drained Shear Strength
Drained and Undrained Conditions Undrained and Drained Shear Strength Lecture No. October, 00 Drained condition occurs when there is no change in pore water pressure due to external loading. In a drained
SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS
Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and
Commercial Roof Inspection Form
Inspection Date: Inspector: Building Information Building ID: No.: Used For: Year Roof Applied: Building Description: Permanent Temporary Building Type: Retail Industrial Residential Building Name: Building
IS THAT LINER THICK ENOUGH?
IS THAT LINER THICK ENOUGH? Philip McFarlane, Opus International Consultants Ltd ABSTRACT The amount of pipeline rehabilitation being undertaken in New Zealand is increasing each year. Larger diameter
Understanding Septic Tank Systems
Understanding Septic Tank Systems Sewage and effluent can contain a variety of human disease-causing microorganisms and parasites. Disease can be spread to humans from this material by direct contact or
GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S-000900-0109-3 HOUSTON, TEXAS
GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S-000900-0109-3 HOUSTON, TEXAS Reported To: LAN, Inc. Houston, Texas by Aviles Engineering
Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective
Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning
Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE
Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE To satisfy the performance goals of the NEHRP Recommended Seismic Provisions, a number of characteristics are important to the
CPTic_CSM8. A spreadsheet tool for identifying soil types and layering from CPTU data using the I c method. USER S MANUAL. J. A.
CPTic_CSM8 A spreadsheet tool for identifying soil types and layering from CPTU data using the I c method. USER S MANUAL J. A. Knappett (2012) This user s manual and its associated spreadsheet ( CPTic_CSM8.xls
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
Assessment. Ian Uglow Technical Director, SLR Consulting [email protected]. 7 th October 2010
Peat Stability Risk and Hazard Assessment Ian Uglow Technical Director, SLR Consulting [email protected] 7 th October 2010 What goes into a Peat Stability Risk Assessment? You will need: An understanding
APPENDIX G SETTLEMENT
APPENDIX G SETTLEMENT TABLE OF CONTENTS G.1 IN T R O D U C T IO N... 1 G.2 MATERIAL PLACEMENT AND COMPACTION... 1 G.2.1 Incom pressible M aterials... 1 G.2.2 Compressible Materials... 2 G.2.3 Soil P lacem
March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS
March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High
SEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
Cone Penetration Testing in Geotechnical Practice. Tom Lunne Peter K. Robertson John J.M. Powell
Cone Penetration Testing in Geotechnical Practice Tom Lunne Peter K. Robertson John J.M. Powell BLACKIE ACADEMIC & PROFESSIONAL An Imprint of Chapman & Hall London Weinheim New York Tokyo Melbourne Madras
Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy
Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy ITA CBT Seminario SAT2008 Sao Paolo, June 25 2008 1 Contents Peculiar aspects of Tunnelling in urban areas
Designed and Engineered to Perform
History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the
SECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
Emergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design
GEOTECHNICAL ENGINEERING FORMULAS A handy reference for use in geotechnical analysis and design TABLE OF CONTENTS Page 1. SOIL CLASSIFICATION...3 1.1 USCS: Unified Soil Classification System...3 1.1.1
QUESTION TO AUDIENCE
Site investigation some aspects of EN1997 Part 2 David Norbury David Norbury Limited BGA Symposium Eurocode 7 Today and Tomorrow, Cambridge, England, March 2011 QUESTION TO AUDIENCE How many of you have
Pro-Lift Steel Pile Foundation Repair
Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair System Pro-lift steel piles are designed for the stresses of Texas soils. They can have multiple steel walls, depending on the
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF
Validation of methods for assessing tunnelling-induced settlements on piles
Validation of methods for assessing tunnelling-induced settlements on piles Mike Devriendt, Arup Michael Williamson, University of Cambridge & Arup technical note Abstract For tunnelling projects, settlements
Installation of Large Diameter Buried Pipes
Installation of Large Diameter Buried Pipes Sullivan (Sully) Curran P. E., Executive Director I. Introduction and Scope There is an ongoing need to provide designers, specifiers, engineers, consultants
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
Preventing water damage in the basement
Preventing water damage in the basement Thousands of home insurance claims are filed every year. Some losses are major, others aren t, but they re always an inconvenience and usually avoidable! As prevention
A case study of large screw pile groups behaviour
Jongerenforum Geotechniek 5 juni 2015 A case study of large screw pile groups behaviour Alice Manzotti Content of the presentation 2 Introduction General soil conditions at the site Foundation design -
Geotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns
1. Introduction 1.1 Scope of Work The Asian Disaster Preparedness Centre (ADPC) is implementing the project Seismic Hazard and Vulnerability Mapping for Rangamati, Bandarban and Khagrachari Municipality.
PILE FOUNDATIONS FM 5-134
C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics
Soil Mechanics. Soil Mechanics
Soil is the most misunderstood term in the field. The problem arises in the reasons for which different groups or professions study soils. Soil scientists are interested in soils as a medium for plant
Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008
Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008 Kenneth E. Tand, P.E. Practicing Geotechnical Engineer FRIEND OR FOE Trees are our friends. They extract carbon
How To Map A Lake In The North Of The Holland (Fiji)
1. Hydrogelogical mapping Jiri Sima Aim of HG map Groundwater and rocks qualitative permeability and quantitative potential of rock units aquifers / aquitards / aquiclides Water points (spatial distribution
A Guide to Structural Waterproofing
A Guide to Structural Waterproofing Part One Waterproofing Protection For Below Ground Structures 1 2012 W. R. Grace & Co Benjamin J. Brooks Table of Contents Grace Around The World Reference Material
FY15 Gravity Sewer and Manhole Rehabilitation
Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE
Septic Records and Maintenance Guidelines
1 Septic Records and Maintenance Guidelines Proper design, installation, and maintenance of your septic system will maximize your system's life. It will prevent failures that can be unsightly, foul-smelling,
9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems
9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES Hunter Underground Systems 9.01 General 9.02 Surface water Drainage 9.03 Groundwater Drainage 9.04 Dispersal of Septic Tank Effluent 9.01 The use of
Structural Damage Due to Floods
Structural Damage Due to Floods By Craig D. Rogers, P.E. The Federal Emergency Management Agency (FEMA) reports that each year approximately 90 percent of all disaster-related property damage results from
Sewer systems: Failures and rehabilitation
Water Utility Journal 8: 17-24, 2014. 2014 E.W. Publications Sewer systems: Failures and rehabilitation C. N. Damvergis Hellenic Association of Hydraulic Works and Water Resources Management Consulting
JOHNSON STREET BRIDGE REPLACEMENT PROJECT
JOHNSON STREET BRIDGE REPLACEMENT Victoria, BC GEOTECHNICAL INVESTIGATION REPORT Prepared for: City Hall No. 1 Centennial Square Victoria, BC VW 1P Prepared by: Stantec 7 Dominion Street, Suite 5 Burnaby,
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
Numerical Simulation of CPT Tip Resistance in Layered Soil
Numerical Simulation of CPT Tip Resistance in Layered Soil M.M. Ahmadi, Assistant Professor, [email protected] Dept. of Civil Engineering, Sharif University of Technology, Tehran, Iran Abstract The paper
APPENDIX A PRESSUREMETER TEST INTERPRETATION
APPENDIX A PRESSUREMETER TEST INTERPRETATION PRESSUREMETER TEST INTERPRETATION Description of test The pressuremeter test, discussed in great detail by Martin (1977), Baguelin et al. (1978), Barksdale
