Can You See It Coming? Examining and Mitigating the Common Causes of HDD Failures



Similar documents
New advances in planning a bore Software helps take out the guesswork

DIRECTIONAL DRILLING

Morgan County Quality Water District Water Main Flood Damage Repair Project

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Dewatering - Time and Cost Relief by way of Trenchless Construction

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

GEOTECH ENGINEERING and TESTING

Emerging Technologies in Wastewater Collection Systems

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

SETTLEMENT INSTRUMENTATION & MONITORING

WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

SECTION 5: SANITARY SEWER SYSTEM DESIGN

Guidelines for Fiber Optic Cable Permits

720 Contour Grading. General. References. Resources. Definitions

Repair or Replacement - Band-Aids vs. Surgery

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Specifications for Residential Property Owners Connection to New Public Sewer

Frequently Asked Transmission Pipeline Questions

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Moving Small Mountains Vesuvius Dam Rehab

System. Stability. Security. Integrity. 150 Helical Anchor

Section Installation of pipe and casing for sanitary sewer by methods of augering.

DETERMINATION OF SAFE PULLING LOADS ON FUSIBLE PVC PIPE DURING HORIZONTAL DIRECTIONAL DRILLING INSTALLATIONS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Drilling Problems. pull

LS 2540 SEWER LATERALS AND INSPECTION TEES

Sewer Line Rehabilitation

Sewer Rehabilitation Design Requirements

Carlon Bore-Gard and Boreable Multi-Gard Raceway

Tuesday, March 17, 2015 Houston, TX. Energy Exchange 9:20 9:50 a.m. and 9:55 10:25 a.m. OIL AND GAS: ENVIRONMENTAL INSURANCE IS IT NECESSARY?

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

Basic Hydrology. Time of Concentration Methodology

STORM DRAINS CHAPTER 7

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

Trenching and Excavation Safety

Guidelines For Sealing Groundwater Wells

Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS

CIVL451. Soil Exploration and Characterization

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

TUNNELING UNDER AUSTIN PROTECTING THE ENVIRONMENT, AND PRESERVING THE PEACE

DIRECT PUSH DRILLING.

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM

Section 2100-Trenching and Tunneling

Wastewater Capital Projects Management Standard Construction Specification

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

Table 4.9 Storm Drain Inlet Protetion Applicable for

DIRECTIONAL DRILLING BEST PRACTICES. Planning & Construction Considerations COMMITMENT & INTEGRITY DRIVE RESULTS

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

Miami-Dade s Water Main Government Cut Replacement Project

Caltrans Geotechnical Manual

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

BROOKS BRIDGE WATERLINE REHABILITATION

METHOD OF STATEMENT FOR STATIC LOADING TEST

Optical Cable Pre-Construction Survey. Keywords Stationary Reel Method, empty innerducts, sub-ducts, microducts, Intermediate-feed manholes

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Greensboro s Pilot Program for Water Pipe Bursting Leads to Expanded City Wide Program

Measuring the Condition of Prestressed Concrete Cylinder Pipe

BUTE Department of Construction Management and Technology

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

Storm Drain Inlet Protection - IP

GLOSSARY OF TERMINOLOGY

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

Meeting the Challenge of Pipeline Emergency Repair

High Strain Dynamic Load Testing of Drilled Shafts

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Helical Pier Foundations

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

product manual H-4210A PORTABLE STATIC CONE PENETROMETER

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

Work Type Definition and Submittal Requirements

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

Watershed Works Manual

Alternatives Presentation Meeting Middlebury WCRS(23)

SANITARY SEWER SPECIFICATIONS

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Offshore Structures. Offshore Drilling Equipment

Section SEWER PIPE INSTALLATION AND TESTING

SECTION HORIZONTAL DIRECTIONAL DRILLING (HDD)

Transcription:

North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 TM1-T2-04 Can You See It Coming? Examining and Mitigating the Common Causes of HDD Failures Blake Peters, PE, McKim & Creed, Sarasota, FL Jeffrey S. Lowe, PE, McKim & Creed, Clearwater, FL Seton Katz, PE, Sarasota County Capital Management Services, Sarasota, FL 1. ABSTRACT At 3:00 p.m. on a Friday afternoon, during the product pipe pullback of a horizontal directional drill, a hydrofracture occurred within inches of a federal highway. This caused the contractor s personnel to cancel their weekend plans, scramble to bring in maintenance-of-traffic devices, notify the state highway manager and deal with a myriad of other inconveniences and potential financial losses. Utility staff attempted to understand what had gone wrong, which revealed a hard truth. We didn t really know what had gone wrong. This left us feeling very lucky the hydrofracture hadn t actually washed out the highway, but also very exposed to the possibility of a repeat occurrence. Over the last eight years, horizontal directional drill (HDD) has become increasingly popular on County Utility projects. That time has been marked by an increase in the number, length and complexity of horizontal directional drills. Those projects have experienced many successes; however, there have also been many failures, such as lost drill tools, hydro-fracture, failed drill stems, and other abnormal events. Looking back at a wide variety of HDD projects, we found many of the failures were preceded by signs of impending problems. This made us wonder: Would it be possible to identify those signs in advance of an impending failure and, if so, intervene and mitigate the losses? This paper will identify commonalities and root causes of many directional drill failures, and will share strategies for preparing, recognizing and addressing those issues so that losses and failures can be reduced. 2. INTRODUCTION Like many aspects of engineering, good design and construction are based on experienced personnel who have expertise that was developed over time. In many cases, that expertise did not come easily and was shaped by a series of successes and failures. For the purposes of this paper, failure is defined as any part of the HDD that did not meet its intended objective during HDD design or construction, whether on a grand scale or a minor incident. While failure is not a pleasant event, it does offer learning opportunities which can reduce the chances of the same failure happening again. The following section provides a brief overview of three Sarasota County, Florida projects and their associated failures which provided learning opportunities. The subsequent section expands the discussion beyond the three County projects and includes strategies for preparing, recognizing and addressing those issues. The intent is to focus on failure types and prevention strategies and not the specific projects, which is why the project descriptions were kept relatively generic. Paper TM1-T2-04 - 1

3. HDD FAILURES Example Project No.1 This project involved replacing a 10-inch water main by constructing a single 2,700-linear-foot subaqueous HDD. The project site was within environmentally sensitive habitat with limited construction access. The majority of the HDD alignment was subaqueous and the horizontal alignment was generally straight. The primary failure originated from the contractor s decision to drill at a depth that exceeded the deepest geotechnical boring. The original design was for the HDD to have a maximum depth of 40 feet using 1,000-ft. and 1,200-ft. vertical curves. The contractor proposed to increase the entry angle of the drill from 16.5 degrees to 17 degrees and increase the drill rig setback distance to avoid a sea wall identified in the plans. This resulted in a deeper bore, down to 80 feet deep. The maximum geotechnical boring depth was 50 feet, so the contractor did not have geotechnical information for a significant length of the HDD. Although the HDD was successfully completed, the lack of geotechnical information was considered a failure and was cause for considerable concern by all parties involved and represented a significant risk to the successful completion of the project. A second failure occurred during reaming the pilot hole. A rod was brought on site without first being inspected as required in the specifications. The rod was clogged with cemented bentonite when it was threaded into the drill string. There were five days of downtime to find and remove the failed rod once the clog was discovered. The risk of losing the drill head and GPS steering tool was high due to the prolonged lack of mud flow and setting bentonite. Drilling proceeded following the delay without the loss of drilling tools, but the avoidable oversight caused financial loss and frustration to all parties and put the project at risk of a much bigger failure. Figure 1. Clogged rod that caused a failure. Example Project No. 2 This project consisted of 20-inch and 24-inch wastewater force main. The alignment included sections of open cut and HDD. Approximately 6,000 feet were installed by HDD using 24-inch DR-11 high-density polyethylene (HDPE). The longest HDD was 1,500 feet under a canal and roadway. There were two primary failure types for this project. The first was regarding the drill rig stabilizing outriggers. The existing utilities consisted of asbestos clay pipe (ACP) and clay pipe, which are brittle and problematic if disturbed. Because of the fragile existing utilities, the contractor did not utilize the stabilizing outriggers in most cases, out of concern of damaging these pipes. Therefore, a wrecker truck was used to stabilize the drill rig. The second failure originated from the lack of geotechnical information to support the contractor s decision to increase the depth of several HDD segments. The HDD design depth was 30 feet deep which matched the depth of Paper TM1-T2-04 - 2

the geotechnical borings. The contractor experienced problems stabilizing the bore hole and preventing settlement of the road surface at the design depth. In order to prevent problems on the remaining segments, the contractor requested to use FDOT standards which requires the HDD depth to be at least ten times the bore hole diameter under FDOT right-of-way. Based on the success of the first HDD installed at the deeper FDOT depths, the Contractor requested to deepen the remaining HDDs. The contractor believed the risk of drilling into unknown soils was warranted since denser soils and better bore hole stabilization were encountered at the increased depth. It was unclear if the drilling fluid mix contributed to the bore hole stabilization problems at the shallower depths. Like example project No. 1, the lack of geotechnical information was considered a failure and was cause for considerable concern by all parties. Example Project No. 3 This project consisted of the installation of 11,500 linear feet of 24-inch water transmission main to provide auxiliary water supply to the County to meet growing demands. Approximately 3,500 linear feet of the project passed through environmentally sensitive lands under a small waterway and a major crossing under an interstate highway. To traverse these obstacles, HDD with HDPE pipe was utilized. To provide an equivalent inside diameter, the line was upsized to a 30-inch SDR-11 pipe. There were two failure mechanisms on this project. The first occurred during the interstate crossing. The soil under the interstate had a mixed soil interface that included the presence of rock at the design elevation. During construction, the HDD subcontractor had a difficult time with the pilot hole. Several attempts to establish a drill path were made, but the drill head continued to bounce off the rock interface. After numerous unsuccessful passes, the general contractor retained a subsequent driller to evaluate and complete the drill. This contractor changed drill tools; also, elected to steepen the angle of attack and take the drill to a deeper depth to get into a more competent, consistent material. The drill was completed but the forensic drilling operation cost the project over 90 days of delay and cost the original driller and general contractor significantly. HDD pipe breakthrough in waterway Figure 2. HDD pipe breakthrough in waterway The second failure occurred because the waterway crossing was too short, making the radius of curvature aggressive. Also, the overburden was shallow and soft. The drill was initially completed, but shortly after installation the pipe was found floating in the waterway after it had broken through the soft soils, as shown in Figure 2. This line was subsequently re-permitted and installed as an open cut with precast ballast and bottom protection at a substantial cost. In addition to these capital losses, the project was delayed for an extended period. 4. POTENTIAL FAILURE CAUSES In order to identify potential failures before they happen, commonly occurring failure causes must be known. This can be accomplished by evaluating past projects and analyzing what went wrong, as evidenced by the examples that Paper TM1-T2-04 - 3

have been included in this paper. While not an exhaustive list by any measure, Table 1 expands the list of HDD failures by introducing several more common failure root causes. Table 1. Potential HDD Failures Failure Source Geotechnical Exploration Design Construction Cause(s) Soil borings not deep enough Soil borings not frequent enough Soil borings located on top of proposed pipe alignment Insufficient soil information obtained Utility/structure conflicts (SUE locates) Inadequate staging area Staging too close to obstacle 3D alignment proposed Drill calculations not completed Drill angle of attack too shallow Drill radius too small Drill depth at mixed face soil conditions Insufficient overburden/cover Soft soils Improper pipe specified Flooded vs. unflooded installation Lack of constructability review Equipment in disrepair Wrong drill rig for the job Wrong drill head for soil conditions Drill change by contractor Improper drilling fluid used Hydro-fracture Problematic soils causing the contractor to seek better soils 5. FAILURE MITIGATION OPTIONS Based on the previous discussion, failure causes can be categorized as geotechnical exploration, design or construction based. The following discussion summarizes several considerations that can help mitigate future HDD failures. Geotechnical Exploration Based on project examples used in this paper, the most prevalent cause for the failures in Sarasota County projects was related to geotechnical exploration. The following design considerations related to geotechnical exploration may help the County mitigate these types of failures on future projects. Boring Location A common error when conducting geotechnical borings to support HDD design is to locate the borings directly on top of the proposed horizontal alignment. Although the borings are required to be grouted, improperly grouted boreholes can create a potential pathway for drilling mud to escape the HDD bore hole. Therefore, it is recommended to offset geotechnical borings approximately 25 feet from the proposed centerline of the drilling alignment, alternating from one side to the other along the drill route. The offset should be increased if there is the potential for a significant change to the horizontal alignment during design. Paper TM1-T2-04 - 4

Boring Depth Boring at depths exceeding the available geotechnical investigations was a frequent occurrence on Sarasota County HDD projects discussed in this paper. The common failure was not anticipating there may be reasons to increase the HDD depth. Maximum separation from existing improvements and encountering or expecting soils where steering may be difficult are two such reasons bores have been constructed deeper than planned. If a contractor believes soil conditions may make steering difficult, they will want to use larger bend radii to make hitting the steering marks easier. Poorly consolidated soils, where it is challenging to gain traction with the drill tool or where hard interfaces exist are two conditions which can warrant flatter bend radii, and so deeper bores. To the extent possible conservative approaches for conflict avoidance and steering should be considered during design. Conducting drilling calculations using industry-accepted software also reduces this potential. Consider geotechnical information when finalizing design of the bore profile. Obtain additional geotechnical information if necessary. Lastly, consider including language in the specifications that requires contractors to conduct their own geotechnical borings if they propose drilling deeper than what is shown on the plans. Design Considerations Boring Information Once geotechnical information is obtained, it must be evaluated and incorporated into the HDD design. The lack of consideration of the geotechnical information during design appears to have been the root cause of the two failures discussed for Project No. 3. A strategy going forward is to pay extra attention during design when there are varying soil conditions such as soft soil underlain by rock, since this may impact the design entry and exit angle, as well as the drill head used to complete the drill. Another strategy learned from Project No. 3 is to check for pipe breakthrough when 1) the HDD is relatively shallow, 2) the vertical curve is aggressive and 3) the ground water table is high. Other items to consider when evaluating the geotechnical information are the density of the soils, the soil classification and the identification of any rock fractures. If HDD design software is being used, the geotechnical information should be entered into the program to further check the suitability of the soil to support the HDD design. Drill Geometry Drill geometry is an important consideration during design. The common failure associated with geometry is a design that is too aggressive for a contractor to install. An aggressive geometry is a design horizontal or vertical alignment that will be difficult for the contractor to install. An overly aggressive geometry increases the potential of the contractor to miss the target exit point and increases the risk of an unsuccessful drill to the owner. Radius of Curvature A HDD should be designed with the intent to minimize the difficulty of successfully completing the drill. One aspect related to difficulty is the relationship of horizontal curves to the vertical curves. The overlap of a horizontal curve location with a vertical curve location is called a three-dimensional (3D) curve. 3D curves require the contractor to simultaneously steer in both the horizontal and vertical planes, which substantially increases the difficulty to accurately steer the HDD. A good design strategy is to eliminate or minimize the location of 3D curves if at all possible. If it can t be avoided, it is recommended that the horizontal and vertical curve radius be increased so the curves are more conservative, which gives the contractor room to compensate for any over-steering. Drill Radius An appropriate drill radius can mitigate several types of HDD failures. The Second Edition Handbook of PE Pipe, published by the Plastics Pipe Institute (PPI), provides guidance in determining the drill radius based on the pipe material, pipe diameter and drill rod. In most cases, the rod minimum bend radius will govern, but both the pipe and rod minimum bend radius should be checked. In many cases, the minimum radius will be much less than the radius that should be considered during design. A strategy to mitigate failures caused by inappropriate drill radiuses is to establish the minimum radius, then increase the radius as high as the alignment will allow. Radiuses of 1,000 feet Paper TM1-T2-04 - 5

are not uncommon for 10-inch HDPE, and 2,000 feet for pipe 24 inches and up. If the radius is suspected to be aggressive, advice from an experienced contractor may provide valuable insight. Hydro-Fracture A hydro-fracture is an accidental release of drilling fluids to the ground surface or a water body, and can result in downtime, expense, equipment loss and loss of public confidence. To prevent this, the design activities should include a thorough evaluation of the proposed drill alignment utilizing an industry-accepted drilling software that evaluates soil conditions, overburden and mud pressures. This information can help guide the design process to minimize the potential for hydro-fracture on a project. However, soil evaluations only look at single points along the drill path, and the potential for hydro-fracture always exists on a project. As such, a hydro-fracture contingency plan should be required on all projects. Based on the County s experience, when evidence of a hydro-fracture occurred, projects with a hydro-fracture contingency plan experienced decreased downtime and associated costs when compared to those without a plan developed in advance. The contingency plan was also found to facilitate acquisition of permits from the Florida Department of Environmental Protection (FDEP), since the plan provided assurances that the County could react quickly to a hydro-fracture and mitigate any potential negative impact to the environment. Contingency plans for hydro-fracture, as well as other plan types such as a bore plan and drilling fluid plan, can significantly minimize the losses associated with these failure types. Construction Considerations In addition to the design considerations previously discussed, there are many considerations during construction that can help mitigate HDD failures. The following discussion summarizes two construction considerations that the County has recently experienced. Rollers vs. Ground There are two primary failure types of concern when rollers are considered: damage to the pipe by yielding due to excessive force applied by the drill rig or pipe wall surface damage caused by the ground that decreases pipe wall thickness, as shown in Figure 3. If the pull force dictates the need for rollers and rollers are not feasible, then using a thicker wall pipe may be required. These types of issues should be identified early during construction and be coordinated with the contractor so the appropriate pipe is provided. The decision to use rollers to protect the pipe from damage as it slides over the ground surface depends on the type of ground surface and the ability of the contractor to successfully keep the pipe on the rollers. Given its thick wall and robustness, the use of HDPE pipe is particularly useful in situations when the pipe will be subjected to surface damage. Steps must be taken to protect both the pipe and surface improvements. Paper TM1-T2-04 - 6

Figure 3. HDPE Surface Damage. Inspection A common observation by the County on its HDD projects is the need to provide detailed inspection services during HDD installation. Failures related to hydro-fracture, excessive pull back forces and mud management have shown the County the importance of having knowledgeable oversight in the field. When properly trained, an inspector will be able to spot the signs of a potential hydro-fracture such as loss of mud pressure, read the gauges on the drill rig to monitor pull back forces, monitor the rate of reaming and pull back, and spot failures in the drilling fluid plan such as using an excessive amount of mud relative to industry standards. The County is pursuing providing HDD training to its inspectors and strengthening the language in its standard specification to reduce failures that can be mitigated by good inspection techniques. 6. CONCLUSIONS As HDD installations become increasingly popular and complex on County Utility projects, the need to prepare, recognize and address the issues that can lead to failure will become increasingly important. By reviewing past HDD projects and learning from their success and failures, the County has obtained valuable insight regarding good HDD design and construction practices. The primary question of this paper was is it possible to identify signs of an impending failure and, if so, intervene and mitigate the losses. Based on the preceding review of past failures on County HDD projects and the identification of potential failure causes, there are several mitigation options that if implemented during design and construction can successfully be used to identify and mitigate failure on future HDD projects. 7. REFERENCES 1. The Plastics Pipe Institute, Inc. Handbook of PE Pipe, Second Edition 2. HDD Consortium (2004) - Horizontal Directional Drilling Good Practices Guidelines Paper TM1-T2-04 - 7