ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental Safety East Lansing, Michigan 48823.

Similar documents
ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823

ASBESTOS BUILDING INSPECTION REPORT. for the. City of East Lansing Waste Water Treatment Plant East Lansing, Michigan

POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for

Asbestos-Containing Material Re-Inspection Report

1200 N. COLORADO WINSLOW, ARIZONA

Don Hau, Project Development, 100 Shops Building, th Avenue SE, Minneapolis, MN 55414

Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois Project No.:

2013 AHERA 3 Year Re-Inspection Report For. Northeast Elementary School 82 Scofieldtown Road Stamford, CT. Performed by

AHERA 3-Year Asbestos Re-Inspection

Asbestos Management POLICY

ASBESTOS NESHAP DEMOLITION SURVEY

NARRATIVE REPORT. The Asbestos Bulk Sample Results Table includes asbestos sampling data.

Asbestos Procedures. Asbestos Products

OGS LIMITED ASBESTOS & LEAD SURVEY REPORT

ASBESTOS BUILDING INSPECTION

1804 W. Colorado Avenue Colorado Springs CO Fax AlpineConsultInc.com

WORK PROCEDURES FOR ASBESTOS RELATED ACTIVITIES

6% Chrysotile NA White floor tile 2 nd Floor 10,000 sq ft Cat 1 2% Chrysotile Poor

Regulated Building Materials in Property Management. July 30, 2013

ASBESTOS INSPECTION REPORT 2 Delaware Street, 38 and 39 North Henry Court South Burlington, VT AIP 84

Approved by: UBC ACT Committee

LIMITED ASBESTOS INSPECTION POLICE DEPARTMENT - ROOFING 434 SOUTH 1 ST STREET MONTROSE, COLORADO

Restoration Specific Asbestos and Lead Based Paint Survey Report Logan Ave Colorado Springs, CO 80909

The Richard Stockton University ASBESTOS MANAGEMENT PLAN

Chicago Public Schools 6 Month Asbestos Surveillance Fall

ASBESTOS INSPECTION REPORT

EXHIBIT A SCOPE OF SERVICES

2009 Housing Provider Forum. Ontario Environmental & Safety Network Ltd.

Asbestos Survey Former Kraft General Foods Facility 500 Dalton Avenue and 1222 Statesville Avenue Charlotte, North Carolina. H&H Job No.

Request for Proposals ASBESTOS ABATEMENT SERVICES. Coffeyville Community College 400 W. 11 th Street Coffeyville, KS 67337

Professional Service Industries, Inc Gateway Drive Suite B Cypress, CA Phone 714/ Fax 714/

TAMPA ELECTRIC COMPANY ENERGY SUPPLY ASBESTOS AWARENESS PROGRAM

ASBESTOS-CONTAINING MATERIAL REPORT

ASBESTOS AWARENESS. Slide #1

ASBESTOS MANAGEMENT INTRODUCTION

Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector

DEMOLITION INSPECTION REPORT ASBESTOS CONTAINING MATERIALS

Asbestos Management Program

Asbestos Survey. for. Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington. May 1, Project #A2014/0406.

May 23, Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California

Asbestos Management Plan EC 45 Page 1

SECTION 16 ASBESTOS MANAGEMENT

Loss Control TIPS Technical Information Paper Series

Asbestos Inspection Project Procedure

ASBESTOS INSPECTION REPORT 31 DUMONT AVENUE SOUTH BURLINGTON, VT AIP 78. December 16, 2011 Revised January 31, 2012

NDSU TABLE OF CONTENTS

Asbestos 2 hr. Awareness

PRE-DEMOLITION ASBESTOS SURVEY

ASBESTOS BACKGROUND INFORMATION

ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA

Asbestos Survey Form (See Instructions)

CATALOGUE OF ASBESTOS MATERIALS. City of White Rock White Rock Library Buena Vista Avenue White Rock, BC

Asbestos NESHAP ISSUES AND QUESTIONS

If the address on this form is different than the address of the building, submit a written explanation.

IDENTIFICATION OF ASBESTOS You can t identify asbestos-containing materials with the naked eye. Experienced employees can identify suspected

ASBESTOS MANAGEMENT PROGRAM

SECTION EXISTING HAZARDOUS MATERIALS CONDITIONS

2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987.

ASBESTOS MANAGEMENT PROGRAM

Photo 1: This photograph shows drywall, joint compound, cove base mastic, carpet adhesive, and ceiling tile in store front No. 1.

Managing Asbestos* *Defined by Asbestos NESHAP 40 CFR 61, subp. M

The Management of Asbestos at the University of Manitoba

HART ENVIRONMENTAL RESOURCES

ASBESTOS SURVEY AND ASSESSMENT REPORT

Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site

ASBESTOS CONTAINING MATERIALS (ACM) REFERENCE GUIDE

ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015

UBC Plant Operations Asbestos Work Procedures April 2004

June 27, Project GSA Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102

Asbestos Frequently Asked Questions

University of British Columbia Memo Building Operations 2329 West Mall Vancouver, BC V6T 1Z1

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD

UNVERSITY HIGH SCHOOL U W. Gregory St. Normal, IL School Asbestos Management Plan. Supplemental.

Regulatory Requirements for Asbestos Inspections Prior to Renovation Projects

SUMMARY OF ASBESTOS CONTAINING MATERIAL IN BUILDINGS AND BULK SAMPLE ANALYSIS

MEMORANDUM. DATE: January 6, Campus Community. Tim Ridley, CSP, ARM-P Director, Safety and Risk Management. SUBJECT: Asbestos Notification 2015

ASBESTOS AWARENESS PLAN

How To Perform A Limited Asbestos Survey

Characteristics/Applications

STOCKTON UNIVERSITY ASBESTOS - GENERAL AWARENESS TRAINING. For workers and building occupants

TRU Asbestos Management

Asbestos Containing Material MANAGEMENT PLAN

University of Pittsburgh Safety Manual. EH&S Guideline Number: ASBESTOS

BRIEFING TO THE UN STAFF

Miami University s Asbestos Operations & Maintenance Program Administered by

Administrative Procedure. Asbestos

Asbestos Related Data For the Healthcare Facility

Safeway 691 Berkeley Shattuck Place Date: May 3, 2007 MDA. Store Data: Interior Construction Materials: Exterior Construction Materials:

WorkSafe BC Guidelines Regarding Demolition and Asbestos Waste Materials

ASBESTOS AWARENESS. For workers and building occupants

The Vermont Department of Health When is Asbestos a Public Health Threat? Town Health Officers (THO) Training

Chicago Public Schools 6 Month Asbestos Surveillance Spring

PROCEDURE 31 - Asbestos Safety. Table of Contents

The Truth About Asbestos In Your Home

Asbestos Awareness at the University of Toronto

University of the Sciences Environmental Health and Radiation Safety (EHRS) Department Q&A ON ASBESTOS

ASBESTOS in state and local government

Asbestos Management Program (EHS Program Manager 7.5)

Off white sheetrock May 07 no asbestos found. Bralley Annex sheetrock office/room 106 May 07 removed pipe insulation mechanical room Mar 05 removed

Transcription:

ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental Safety East Lansing, Michigan 48823 at the John C. Holmes Hall Building #300 East Lansing, Michigan 48823 Inspection conducted by Fibertec Industrial Hygiene Services, Inc. 1914 Holloway Drive Holt, Michigan 48842 Project #20120-1 Project dates: December 20 December 28, 2004 Final Report date: January 19, 2005 Page 1

Contents Introduction Certification General Inspection Procedures Results of Visual Inspection Bulk Sample Results Summary of Asbestos-Containing Materials Conclusion Recommendations Appendices A. Asbestos Inspector Credential B. Bulk Sample Log C. Bulk Sample Analytical Report D. Room by Room Asbestos Building Inspection Forms E. Photograph Log F. Floor Plan Sketches G. Significantly Damaged ACM H. Lyman Briggs Hazardous Materials Building Inspection Report Page 2

ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental and Occupational Safety John C. Holmes Hall Project #20120-1 INTRODUCTION Fibertec Industrial Hygiene Services, Inc. (Fibertec IHS) was retained by the Michigan State University Office of Environmental Safety to perform an asbestos building inspection in John C. Holmes Hall. The project was discussed with Ms. Mary Lindsey-Frary of the Michigan State University Office of Environmental and Occupational Safety prior to beginning the fieldwork. Ms. Lindsey-Frary requested a comprehensive asbestos building inspection, including the collection of an appropriate number of bulk asbestos samples in accordance with the provisions of the Asbestos in Construction Standard. The asbestos building inspection took place from December 20 to December 28, 2004. During the inspection, bulk samples were collected and quantities of suspect asbestos-containing materials were estimated. Fibertec IHS was also retained by the Michigan State University Engineering and Architectural Services Department, Physical Plant Division, to conduct a potentially hazardous materials building inspection on these specific areas that would potentially be affected by renovations planned for the Lyman Briggs School. This report for work at Lyman Briggs School appears in Appendix H (Lyman Briggs Potentially Hazardous Building Inspection Report, dated December 16, 2004). The Lyman Briggs School inspection took place from November 19 to November 29, 2004. CERTIFICATION The asbestos building inspection was conducted by Adam Cobb and John Luna, State of Michigan Accredited Asbestos Building Inspectors, who were assisted for purposes of recordkeeping by Gregg Kolodica and Ryan Storey. Mr. Cobb and Mr. Luna also maintain accreditation as Asbestos Contractor Supervisors. John Walker, Steven Day, Sean Hillaker and John Sink, trained Polarized Light Microscopists, analyzed all bulk asbestos samples in the Fibertec IHS Polarized Light Microscopy (PLM) laboratory. GENERAL INSPECTION PROCEDURES In an effort to identify asbestos-containing material (ACM) at John C. Holmes Hall, an extensive inspection procedure was followed. A visual inspection of the building was combined with the collection of an appropriate number and distribution of bulk samples. Material sampling that would potentially compromise the weather tight integrity of the building envelope was not conducted (e.g., window glazing compound, roofing) at the request of Michigan State University (including any outside sampling). The following rooms in John C. Holmes Hall were not accessible during the inspection: C110, C115, C120, E10, E13, E23, E23A, E648, E649, E650, W2, W4, W9, W13, W14, W15, W178, W179, W180, W548, W549 W550, W648, and W649. Determination of suspect asbestos-containing material was based on visual examination, bulk sample analysis, material age and professional experience. Specifically, materials similar in color and texture were classified into homogenous areas (e.g., drywall). An appropriate number of samples were collected from material in each homogenous area. The samples were analyzed by Polarized Light Microscopy (PLM) in the Fibertec IHS PLM Laboratory. When the results of analysis of all samples from a homogenous area indicate no asbestos present (less than or equal to one percent), the homogenous area is considered to be a non-asbestos containing material. When the results of analysis indicate asbestos present (in a quantity greater than one percent) in just one sample of those collected from a single homogenous area, the material in the entire homogenous area must be considered asbestoscontaining. Page 3

Destructive testing (i.e., demolition) was not conducted as part of this asbestos building inspection. Quantities of ACM shown in pipe chases, above drywall ceilings or other inaccessible areas have been estimated. Additionally, some asbestos-containing material hidden from view (e.g., pipe insulation in inaccessible pipe chases, between walls, floor leveling compound below floor tile, duct caulk on duct in mechanical shafts and vermiculite in cinderblock walls) may be present and may not have been accounted for as part of this inspection. RESULTS OF VISUAL INSPECTION Based on the inspection, 50 distinct suspect asbestos-containing materials were identified in John C. Holmes Hall. Some suspect asbestos-containing materials were sampled a number of times in different locations, ceiling plaster being an example. All suspect asbestos-containing materials observed at the time of the inspection are listed in the Room by Room Asbestos Building Inspection Forms. BULK SAMPLE RESULTS The information gathered from the inspection is included in Appendices B (Bulk Sample Log), C (Bulk Sample Analytical Report), D (Room By Room Asbestos Building Inspection Forms), E (Photograph Log), F (Floor Plan Sketches), G (Significantly Damaged ACM), and H (Lyman Briggs Potentially Hazardous Materials Building Inspection Report). SUMMARY OF ASBESTOS-CONTAINING MATERIALS The following materials were found to contain asbestos in John C. Holmes Hall: Steam and condensate pipe straight insulation Domestic water pipe joint and hanger insulation Ventilation duct expansion cloth Sewer drain pipe joint insulation Canvas wrap on fiberglass pipe straight insulation Condensate tank insulation 9 x 9 beige floor tile with swirls Green lab tables Interior window glazing/caulk Electrical insulation cloth Brown duct joint compound 9 x 9 light brown floor tile with cream and rust specks and associated mastic Black sink undercoating Laboratory Glove Roof flashing 9 x 9 cream floor tile with white and black streaks and associated mastic The following materials were assumed to contain asbestos in John C. Holmes Hall: Green chalkboards and associated glue pods Fire doors and frames The following materials were found not to contain asbestos in John C. Holmes Hall: 2 x 2 white lay-in ceiling tile with pin holes and fissures 12 x 12 white ceiling tile with fissures and associated glue pods 4 brown cove molding and associated mastic Plaster (smooth) Black slate lab sinks and table tops 12 x 12 green floor tile with marble pattern and associated mastic 12 x 12 cream floor tile with marble pattern and associated mastic 4 green cove molding 4 tan cove molding Page 4

CONCLUSION 2 x 4 white lay-in ceiling tile with pin holes and fissures Mastic to 9 x 9 beige floor tile 3 black cove molding and associated mastic Drywall Drywall joint compound 12 x 12 light brown floor tile with marble pattern and associated mastic 4 black cove molding and associated mastic 12 x 12 light cream floor tile with gray specks and associated mastic 4 gray cove molding and associated mastic 2 x 2 white drop-in ceiling tile with pin holes and fissures Fireboard Fire code gypsum board Fire code gypsum board joint compound Blue linoleum with mosaic pattern and associated mastic and leveling compound Gray lab tables 2 x 4 vibration panels (fiberglass) 6 brown cove molding and associated mastic Pink linoleum with mosaic pattern and associated mastic and leveling compound Spray-on acoustical plaster (popcorn) White linoleum with mosaic pattern and associated mastic 12 x 12 tan floor tile with cream and rust streaks and associated mastic Tan textured sink undercoating Tan linoleum with cream streaks and associated mastic 2 x 2 brown linoleum and stair tread with cream swirls and associated mastic Undamaged and damaged, non-friable (cannot be crumbled, pulverized or reduced to powder by hand pressure when dry) known or assumed asbestos-containing materials, as well as damaged and undamaged, friable known asbestoscontaining materials, were discovered during the course of this inspection. This facility inspection to determine the location of asbestos-containing materials was conducted in accordance with the provisions of the Asbestos in Construction Standard (and the EPA Sampling Bulletin of September 30, 1994), and current industry standards. RECOMMENDATIONS Based on the information collected during this asbestos building inspection, the following recommendations are offered. These recommendations are based on currently observed conditions and may have to be adjusted if change of ownership, emergency, or other factors substantially alter the condition, use or planned future use of the building. 1. Notify the building occupants, custodians, Physical Plant personnel and others who may encounter ACM during the routine execution of their assigned work of the presence of known or assumed asbestoscontaining products in or on the building. This notification must be given to any outside contractors (e.g., HVAC maintenance personnel) who work within or atop the building and may disturb the asbestoscontaining material(s). Depending on the specific activity being performed, maintenance or repair personnel may need to utilize personal protective equipment or other engineering controls and comply with the provisions of various asbestos regulations. 2. Provide two-hour asbestos hazard awareness training including specific information regarding the quantity, condition and location of ACM for those individuals in the building who may encounter asbestos during the course of their work. Ensure that contractors performing work in the building have equivalent training (at a minimum) and provide appropriate documentation. 3. Plan for the proper removal of any asbestos-containing materials which may be impacted by renovation or demolition prior to any renovation or demolition within the facility. Page 5

4. Label any ACM identified in routine maintenance areas, mechanical rooms, custodial closets, and inside ceiling access hatches at a minimum, in accordance with 29 CFR 1910.1200(7) (vii). In the case of John C. Holms Hall, labels have already been placed in mechanical room entrances, and should be placed on the inside of ceiling and pipe chase access hatches as well. 5. Repair or remove areas of significantly damaged ACM. Ensure contractors performing the work are licensed, provide appropriate regulatory notification and conduct appropriate air monitoring, including final clearance monitoring. Adam Cobb Michigan Accredited Asbestos Inspector Card #A29543 John Luna Michigan Accredited Asbestos Inspector Card #A4665 Phillip A. Peterson Vice President Page 6