1 Asbestos NESHAP ISSUES AND QUESTIONS
2 FIRE-DAMAGED BUILDINGS HOW DOES THE NESHAP APPLY?
3 After the Fire Is Out Building condition can vary widely from smoke damage to complete destruction with variations in between Insurance company/owner arranges to secure the building and surroundings from entry A disaster restoration service often provides water, fire, and contents restoration services This may involve renovation and/or demolition of the structure or part of the structure
4 What is Required by the Asbestos NESHAP for Burned Structures? First, if there is no structure or building remaining, the NESHAP is not applicable There is no facility to renovate or demolish Any work performed is clean-up and disposal Usually, some load supporting structure of the burned building is left for demolition or re-building /renovation
5 What is Required by the Asbestos NESHAP for Renovation/Demolition? As we learned earlier: Thorough inspection for asbestos Notification for renovation/demolition Removal of friable asbestos-containing material (ACM) or ACM likely to become friable Work practices must be observed Waste disposal How do you comply for burned buildings?
6 How Do You Do a Thorough Inspection for Asbestos When a Fire Has Occurred? If no load supporting structure remains, no inspection is required If any load supporting structure remains for renovation or demolition, thorough inspection is required
7 How Do You Do a Thorough Inspection for Asbestos When a Fire Has Occurred? Use an Accredited Inspector (as required by NCDHHS) Inspect, sample and test suspect materials in all areas that can be accessed safely Estimate the quantity and assess the condition of the suspect material Was the suspect material burned, subject to high temperature, made friable, or was it unharmed? For suspect friable materials, do point counting if initial Polarized Light Microscopy (PLM) testing is < 10% asbestos
8 Based on the Inspection Results, How Do You Comply With NESHAP? If NESHAP quantities are present, pri0r to renovation or demolition: Unburned friable ACM (Regulated ACM or RACM) and Category II ACM must be removed Category I ACM (resilient flooring and roofing) that is heat damaged, but not burned, is friable and must be removed Non-fire damaged Category I ACM may remain in place or be removed if it will not be made friable RACM and Category I ACM that has burned has released asbestos into the structure, and the entire structure is RACM and is subject to NESHAP
9 What NESHAP Compliance Issues May Result From Areas Not Inspected? Areas not inspected are presumed to contain RACM RACM that has burned has released asbestos into the structure, and the entire structure is RACM and is subject to NESHAP
10 Based on the Pictures Below, How Must the ACM be handled to Comply With NESHAP?
11 What If the Structure is Unsafe and RACM Cannot Be Safely Removed? If the building can be made safe by shoring, bracing, adding flooring, etc., do so, then do asbestos removal in compliance with NESHAP The municipality can order demolition of the structure when imminent danger is present and/or when there are significant violations of building code standards The order must come from an agency that regulates building safety
12 Notification for Ordered Demolition If the municipality has ordered demolition: Submit a NESHAP notification as early as possible, but not later than the following working day MCAQ recommends requesting a 10-working day waiver prior to demolition so we can evaluate the circumstances and provide confirmation or denial The notification must include all of the required information (see the form), AND The name, title, and authority of the ordering agency representative; The date the order was issued; The date the demolition was ordered to begin A copy of the order must be attached to the notification
13 Work Practice Requirements for Ordered Demolitions The structure must be presumed to contain RACM because a thorough inspection for asbestos cannot be safely done Remove facility components that are covered or coated with or contain RACM that can be safely removed before demolition Prior to and during the wrecking operation, adequately wet the portion of the facility that contains RACM One supervisory person with approved current training in the provisions of the asbestos NESHAP and the means of complying with them must be present for the duration of the demolition
14 Work Practice Requirements for Ordered Demolitions All demolition debris is asbestos-containing waste material (ACWM) and must be adequately wetted after demolition and during handling and loading into the container for disposal Discharge no visible emissions to outside air All demolition debris (ACWM) must be disposed of in a NESHAP landfill ACWM does not need to be sealed in leak-tight containers or wrappings but may be transported and disposed of in bulk (lined and covered trucks, etc.)
15 Asbestos Inspection and Removal In Unsafe Structures Some burned structures are deemed to be unsafe because structural members are weak or collapsing, but demolition has not been ordered and they cannot be made safe NESHAP still requires a thorough inspection for asbestos including Category I and Category II nonfriable ACM in all areas that can be accessed safely Areas not inspected must be presumed to contain RACM because a thorough inspection for asbestos cannot be safely done
16 Asbestos Inspection and Removal In Unsafe Structures If RACM is not burned, it must be removed in all areas that can be accessed safely prior to demolition Category I ACM need not be removed if it is not friable Before and during the wrecking operation, adequately wet the portion of the facility that contains RACM RACM need not be removed before demolition if it was not accessible for testing and, therefore, was not found until after demolition began and, as a result, cannot be safely removed All debris must be considered ACWM ACWM must be kept adequately wet at all times until disposed
17 SUSPECT ACM DISCOVERY DURING DEMOLITION HOW DO YOU COMPLY WITH THE NESHAP REQUIREMENTS?
18 During Demolition You Find This! Do You Know What It Is?
19 Or You Find This! Do You Know What It Is? What Do You Do?
20 When You Don t Know STOP! First, do your machine operators know how to recognize suspect ACM? Consider adding awareness of suspect ACM to demolition operator training If the discovered material is friable or may become friable, adequately wet it and cover it until disposition is made For thorough inspection, sample and test the new suspect ACM for asbestos If it is RACM or ACM likely to be made friable, remove it in accordance with NESHAP before resuming demolition
21 ASBESTOS INSPECTION AND POINT COUNTING NESHAP REQUIREMENTS
22 What Does the NESHAP Say About Asbestos Inspection and Point Counting? The answer is: not much! 40 CFR (a): prior to the commencement of the demolition or renovation, thoroughly inspect the affected facility or part of the facility where the demolition or renovation operation will occur for the presence of asbestos, including Category I and Category II nonfriable ACM 40 CFR Definitions: Friable asbestos material means any material containing more than 1 percent asbestos that, when dry, can be crumbled, pulverized, or reduced to powder by hand pressure. If the asbestos content is less than 10 percent verify the asbestos content by point counting using PLM.
23 How Can This Benefit You? Consider the following scenario:
24 School Building for Demolition Specifications Building is 40,000 square feet Ceiling (30,000 sq.ft.) is textured skim coat 2% asbestos Flat, built-up roofing and flashing-10% asbestos Demolition job is turnkey Lowest bid gets the work What can you do (legally) to turn in the lowest possible bid?
25 NESHAP Considerations Ceiling is RACM and must be removed prior to demolition - $$$ ACWM (RACM ceiling) must be disposed of in NESHAP landfill - $$$ Roofing material in good condition may be left in place for demolition All waste except RACM ceiling can be taken to C&D landfill - $ Anything else to consider?
26 Point Counting! Demolition contractor calls the asbestos laboratory The retained ceiling sample is enough to do point counting using PLM Asbestos result by point counting is 0.75% Conclusion: Ceiling is not RACM Asbestos removal is not needed - $$$$$$ saved Contractor gets the demolition job!!
27 Summary Consider using point counting when initial asbestos test results for friable asbestos are over 1% but less than 10% The low cost of the additional test may eliminate much higher RACM removal and disposal costs Caution! Regulations other than NESHAP may need to be considered for compliance
28 NESHAP CONTACT INFORMATION MCAQ Main Telephone Number: (704) Rick Nelson: (704) Ruth Jacquot: (704)
Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector
Click to edit Master title style Maricopa County Asbestos NESHAP Overview Valerie Brodeur Asbestos NESHAP Inspector Click to edit Master title style Some Asbestos Facts Asbestos is a proven human carcinogen
More informationOwner Name: Address: City: State: Zip: Name: Address: City: State: Zip: Contact: Tel: DEMOLITION CONTRACTOR Name: Address: City: State: Zip:
FORSYTH COUNTY ENVIRONMENTAL ASSISTANCE & PROTECTION NOTIFICATION AND PERMIT APPLICATION ASBESTOS DEMOLITION/RENOVATION OPERATIONS 12/11 1. TYPE OF NOTIFICATION: Original Revised Courtesy 2. FACILITY INFORMATION
More informationDIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions
DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of
More informationTitle 11, Hawaii Administrative Rules (HAR), Department of Health (DOH), Chapter 501, Asbestos Requirements.
TO: FROM: SUBJECT: OWNERS/CONTRACTORS STATE DEPARTMENT OF HEALTH INDOOR AND RADIOLOGICAL HEALTH BRANCH ASBESTOS ABATEMENT OFFICE STATE OF HAWAII, DEPARTMENT OF HEALTH HAWAII ADMINISTRATIVE RULES (HAR),
More informationAsbestos Inspection Project Procedure
EOSMS 402 Date: 01/13/2014 Page 1 of 6 1) Purpose This document is intended to specify the scope of services required of Asbestos Contractor in asbestos inspection projects at Kennesaw State University
More informationASBESTOS MANAGEMENT INTRODUCTION
SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous
More informationMARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD 21230 410-537-3000 1-800-633-6101 www.mde.state.md.
MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD 21230 410-537-3000 1-800-633-6101 www.mde.state.md.us/asbestos Martin O Malley Governor Robert M. Summers, Ph.D. Secretary
More information(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at:
3745-20-05 Standard for asbestos waste handling. [Comment: For dates of non-regulatory government publications, publications of recognized organizations and associations, federal rules, and federal statutory
More informationARKANSAS POLLUTION CONTROL and ECOLOGY COMMISSION REGULATION NO. 21 ARKANSAS ASBESTOS ABATEMENT REGULATION
Pollution Control and Ecology Commission # 014.00-021 ARKANSAS POLLUTION CONTROL and ECOLOGY COMMISSION REGULATION NO. 21 ARKANSAS ASBESTOS ABATEMENT REGULATION Adopted by the PC&E Commission September
More informationASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
More informationHow To Manage Asbestos From Roofing And Siding
Contents Frequently Asked Questions Asphaltic Roofing and Siding Materials.... 1 Floor Tile.... 4 Non-Traditional Asbestos Abatement Work Practice Approvals.... 6 Survey Requirements.... 7 Vermiculite
More informationAsbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308
Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308 557 West Polk Street, Suite 201 Chicago, IL 60607 312.447.1200 p 312.447.0922
More informationOGS LIMITED ASBESTOS & LEAD SURVEY REPORT
our people and our passion in every project OGS LIMITED ASBESTOS & LEAD SURVEY REPORT Building 44 Willard Drug Treatment Center 7116 County Road 132 Willard, NY Prepared for: NYSOGS 33 rd Floor, Corning
More informationNorth Carolina State University. Asbestos Management Plan
North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building
More informationEXHIBIT A SCOPE OF SERVICES
EXHIBIT A SCOPE OF SERVICES 1.0 INTRODUCTION Asbestos consulting services are required for Item/Segment No. 227775-1, SR-7 (US 441) from Fillmore Street to South of Stirling Road, Hollywood, Broward County,
More informationASBESTOS BUILDING INSPECTION REPORT. for the. City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823.
ASBESTOS BUILDING INSPECTION REPORT for the City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823 at the City of East Lansing Waste Water Treatment Plant and Woodingham Pump Station
More information2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987.
Penn State University Environmental Health and Safety Asbestos Management Program I. Introduction Over the past several decades the hazards of asbestos exposure have become well known. With this influx
More informationAsbestos in Soil Who Knew? A Consulting Perspective 1 st Annual Southeast Brownfields Association
Asbestos in Soil Who Knew? A Consulting Perspective 1 st Annual Southeast Brownfields Association Presented by: Russell E. Stauffer, PE AMEC Environment & Infrastructure, Inc. October 30, 2014 75 East
More informationLRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material
LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material Asbestos Policy and Criteria Policy: Pierce County Recycling Composting and Disposal (LRI) has established an
More informationNDSU TABLE OF CONTENTS
NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION
More informationUniversity of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
More informationASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
More informationPURCHASING OFFICE 2010 N. 59 TH STREET ROOM 370 \ KANSAS CITY, KS 66104 WEB SITE: WWW.KCKPS.ORG/PURCHASING
KANSAS CITY KANSAS PUBLIC SCHOOLS / USD 500 PURCHASING OFFICE 2010 N. 59 TH STREET ROOM 370 \ KANSAS CITY, KS 66104 WEB SITE: WWW.KCKPS.ORG/PURCHASING ASBESTOS ABATEMENT GRANT ELEMENTARY SCHOOL BID NO:
More informationPRE-DEMOLITION ASBESTOS SURVEY
PRE-DEMOLITION ASBESTOS SURVEY For: City of Largo PSTA Building 14840 49th Street North Largo, Pinellas County, Florida Prepared for: Collman & Karsky Architects 4301 Anchor Plaza Parkway, Suite 100 Tampa,
More informationManaging Asbestos* *Defined by Asbestos NESHAP 40 CFR 61, subp. M
Managing Asbestos* *Defined by Asbestos NESHAP 40 CFR 61, subp. M Dilbert Comic (2006) Asbestos what is it? Fibrous mineral very strong, heat resistant, fire retardant Airborne hazard asbestos can be inhaled
More informationUNITED STATES ENVIRONMENTAL PROTECTION AGENCY WASHINGTON, D.C. 20460 JUN - 8 2012
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY WASHINGTON, D.C. 20460 JUN - 8 2012 DEPUTY ADMINISTRATOR MEMORANDUM SUBJECT: FROM: TO: U.S. Environmental Protection Agency's Notification of Rules and Regulations
More information40 CFR, Chapter 61, Subpart M National Emission Standard for Asbestos
40 CFR, Chapter 61, Subpart M National Emission Standard for Asbestos 61.140 Applicability. 61.141 Definitions. 61.142 Standard for asbestos mills. 61.143 Standard for roadways. 61.144 Standard for manufacturing.
More informationPOTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for
POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT for Michigan State University Engineering and Architectural Services Physical Plant Building, Room 101 East Lansing, Michigan 48824-1326 at Michigan
More informationApproved by: UBC ACT Committee
The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy
More information(Adopted October 6, 1989)(Amended April 8, 1994) (Amended November 3, 2006)(Amended October 5, 2007)
(Adopted October 6, 1989)(Amended April 8, 1994) (Amended November 3, 2006)(Amended October 5, 2007) RULE 1403. ASBESTOS EMISSIONS FROM DEMOLITION/RENOVATION ACTIVITIES (a) (b) (c) Purpose The purpose
More informationASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823
ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 at Bailey Hall Building #315 East Lansing, Michigan 48823
More informationLIMITED ASBESTOS INSPECTION POLICE DEPARTMENT - ROOFING 434 SOUTH 1 ST STREET MONTROSE, COLORADO
LIMITED ASBESTOS INSPECTION POLICE DEPARTMENT - ROOFING 434 SOUTH 1 ST STREET MONTROSE, COLORADO Inspected by Grande River Environmental, LLC CDPHE CONSULTING FIRM #18631 October 15, 2014 LIMITED ASBESTOS
More information1200 N. COLORADO WINSLOW, ARIZONA
ASBESTOS HAZORD EMERGENCY RESPONSE ACT (AHERA) INSPECTION & REPORT OF FIINGS FOR IUSTRIAL ARTS 1200 N. COLORADO WINSLOW, ARIZONA Submitted to: MR. RICHARD WILLIAMS BELFOR PROPERTY RESTORATION 23610 N.
More informationAsbestos Management Plan EC 45 Page 1
Name: Asbestos and ACBM (asbestos containing building material) Management Plan Areas Affected: All buildings that contain asbestos and ACBM on campus Effective Date: 1/1/09 Reviewed/Revised: 12/15/12
More informationASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in
More informationUI Procedures for Asbestos Management
UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing
More informationUnderstanding the Asbestos NESHAP
Michigan Department of Environmental Quality Air Quality Division Understanding the Asbestos NESHAP Fact Sheet The Clean Air Act (CAA) requires the U.S. Environmental Protection Agency (U.S. EPA) to develop
More informationASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA
ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA May 22, 2013 Robert R. Jones, Ph.D., REM, AHERA Asbestos Inspector, 5/22/13 Signature Date Asbestos Virginia
More informationFor the purpose of this rule, the following definitions shall apply:
ANTELOPE VALLEY AIR QUALITY MANAGEMENT DISTRICT RULE 1403 -- ASBESTOS EMISSIONS FROM DEMOLITION/RENOVATION ACTIVITIES (Adopted: 10/06/89; Amended: 04/08/94) (a) Purpose The purpose of this rule is to specify
More informationASBESTOS, DEMOLITION OR RENOVATION, SANDBLASTING, AND GRINDING STANDARDS
ASBESTOS, DEMOLITION OR RENOVATION, SANDBLASTING, AND GRINDING STANDARDS The purpose of City Code 11-4-2150-11-4-2190 is to reduce the potential risk of harm to the public's health, safety and welfare
More informationSECTION 02 8213 ASBESTOS ABATEMENT
PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.
More information100 North Senate Avenue, Indianapolis, IN 46204 Phone: (317) 308-3103 Toll Free: (800) 451-6027
GUIDANCE OLQ GENERAL ID #003-02-SW INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT OFFICE OF LAND QUALITY ASBESTOS HANDLING AND DISPOSAL REQUIREMENTS www.idem.in.gov Mitchell E. Daniels, Jr. Thomas W. Easterly
More informationAsbestos Survey Form (See Instructions)
Asbestos Survey Form (See Instructions) 777 12th Street, 3rd Floor Sacramento, CA 95814 Office (916) 874-4800 Fax (916) 874-4899 Email: asbestos@airquality.org 1. Purpose of Survey Renovation Demolition
More informationDEMOLITION INSPECTION REPORT ASBESTOS CONTAINING MATERIALS
DEMOLITION INSPECTION REPORT ASBESTOS CONTAINING MATERIALS Property Address: The Verandas @ Rocky Ridge 3741 Chesnut Ridge Inspection ordered by: Cotton Commercial USA 5443 Katy Hockley Cutoff Rd. Katy,
More informationASBESTOS INSPECTION REPORT 2 Delaware Street, 38 and 39 North Henry Court South Burlington, VT 05403 AIP 84
ASBESTOS INSPECTION REPORT 2 Delaware Street, 38 and 39 North Henry Court South Burlington, VT 05403 AIP 84 December 16, 2011 Revised January 31, 2012 KAS PROJECT # 509110228 PREPARED FOR: Stantec, Inc.
More informationENVIRONMENTAL QUALITY
Chapter 51. Title 33 ENVIRONMENTAL QUALITY Part III. Air Comprehensive Toxic Air Pollutant Emission Control Program Subchapter M. Asbestos 5151. Emission Standard for Asbestos A. Applicability. The provisions
More informationJune 27, 2013. Project GSA1570019. Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102
June 27, 2013 Project GSA1570019 Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102 Subject: Determination of Asbestos Conditions Former USDA
More informationASBESTOS NESHAP REGULATIONS FOR RENOVATION AND DEMOLITION ACTIVITIES
ASBESTOS NESHAP REGULATIONS FOR RENOVATION AND DEMOLITION ACTIVITIES As per; Title 40, Code of Federal Regulations, Part 61, Subpart M, National Emission Standards for Asbestos Arizona Department of Environmental
More informationASBESTOS INSPECTION REPORT 31 DUMONT AVENUE SOUTH BURLINGTON, VT 05403 AIP 78. December 16, 2011 Revised January 31, 2012
ASBESTOS INSPECTION REPORT 31 DUMONT AVENUE SOUTH BURLINGTON, VT 05403 AIP 78 December 16, 2011 Revised January 31, 2012 KAS PROJECT # 509110226 PREPARED FOR: Stantec, Inc. 55 Green Mountain Drive South
More informationAsbestos Management POLICY
Asbestos Management POLICY All Asbestos Containment Material (ACM) removal activities shall comply with applicable federal, state, and local regulations. Areas of responsibility of Facilities Management
More informationSubpart M National Emission Standard for Asbestos. 40 CFR Ch. I (7 1 11 Edition)
61.140 40 CFR Ch. I (7 1 11 Edition) (C) The date of each determination of the maximum concentration point, as described in 61.139(h), and a brief reason for the determination. (ii) For each vapor incinerator,
More informationAsbestos Survey. for. Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington. May 1, 2014. Project #A2014/0406.
Asbestos Survey for Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington May 1, 2014 Project #A2014/0406 prepared for: Port of Pasco PO Box 769 Pasco, WA 99301 prepared by: Blue Mountain
More informationCharacteristics/Applications
Facilities Operations and Development Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://fod.osu.edu The Ohio State University Asbestos Management
More informationFrequently Asked Questions Concerning Verification of Asbestos Surveys Before Issuing Building Permits
Frequently Asked Questions Concerning Verification of Asbestos Surveys Before Issuing Building Permits 1. Why do we need Occupations Code 1954.259/ 25 Texas Admin. Code (TAC) 295.34(l)? The Department
More informationLoss Control TIPS Technical Information Paper Series
Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM Asbestos-Containing Material (ACM) In Buildings The presence of asbestos in buildings, particularly those
More informationAsbestos Licensure Law. Code of West Virginia Chapter 16, Article 32 (As amended by the 1993 Legislative Session)
Asbestos Licensure Law Code of West Virginia Chapter 16, Article 32 (As amended by the 1993 Legislative Session) Be it enacted by the Legislature of West Virginia: That chapter sixteen of the code of West
More informationARTICLE 18. ASBESTOS MANAGEMENT NOTE: IC 13-1 and IC 13-7 were repealed by P.L.1-1996, SECTION 99, effective July 1, 1996.
ARTICLE 18. ASBESTOS MANAGEMENT NOTE: IC 13-1 and IC 13-7 were repealed by P.L.1-1996, SECTION 99, effective July 1, 1996. Rule 1. Asbestos Management Personnel; Licensing 326 IAC 18-1-1 Applicability
More informationASBESTOS NESHAP DEMOLITION SURVEY
ASBESTOS NESHAP DEMOLITION SURVEY PERFORMED AT REDDING GARDENS APARTMENTS 419 SOUTH LOCUST AVENUE SANFORD, FLORIDA 32771 PREPARED FOR SANFORD HOUSING AUTHORITY 94 CASTLE BREWER COURT SANFORD, FLORIDA 32771
More informationDemolition Practices Under the Asbestos NESHAP
Demolition Practices Under the Asbestos NESHAP SECTION 1 DEMOLITION PRACTICES AND NONFRIABLE MATERIALS INTRODUCTION EPA revised the asbestos NESHAP regulations on November 20, 1990 (see 40 CFR Part 61
More informationFinal Amendments of 310 CMR 7.15: Asbestos
Final Amendments of 310 CMR 7.15: Asbestos Published in the Massachusetts Register on June 20, 2014, Typographical Corrections Published on November 21, 2014 7.00 AIR POLLUTION CONTROL Definitions Revised
More informationRegulatory Requirements for Asbestos Inspections Prior to Renovation Projects
Regulatory Requirements for Asbestos Inspections Prior to Renovation Projects Subject: Abstract for the 2012 Healthcare Engineering Society of Northern Illinois Mr. Kohon, having attended last yearʼs event
More informationHow To Perform A Limited Asbestos Survey
Limited Asbestos Survey Report Presented To: Barbara Wethington Project Manager Weston Solutions, Inc. 960 West Elliot Road, Suite 201 Tempe, Arizona 85284 Project: Southeast Corner of Arizona Highway
More informationStandards for Asbestos Abatement
19a-332a-1. Definitions Standards for Asbestos Abatement 19a-332a-1. Definitions The following definitions shall apply for the purpose of Section 19a-332a-1 to Section 19a-332a- 16 inclusive. (a) "Adequately
More informationAdministrative Procedure. Asbestos
Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour
More informationCHEMICAL CONTROL ORDER FOR ASBESTOS
DENR ADMINISTRATIVE ORDER No. 02 Series of 2000 Subject: CHEMICAL CONTROL ORDER FOR ASBESTOS Section 1. Legal Authority This Chemical Control Order (CCO) is issued on the basis of authority given to the
More informationBEFORE THE ARKANSAS POLLUTION CONTROL AND ECOLOGY COMMISSION ) ) ) RESPONSIVE SUMMARY FOR REGULATION NO. 21, ARKANSAS ASBESTOS ABATEMENT REGULATION
BEFORE THE ARKANSAS POLLUTION CONTROL AND ECOLOGY COMMISSION IN THE MATTER OF AMENDMENTS TO REGULATION NO. 21, ARKANSAS ASBESTOS ABATEMENT REGULATION ) ) ) DOCKET NO. 13-009-R RESPONSIVE SUMMARY FOR REGULATION
More informationAsbestos Disposal in the Northern Territory
Information on the requirements for the disposal of Asbestos in the Northern Territory Scope These guidance notes have been developed to assist industry, local government, consultants and other relevant
More informationASBESTOS SURVEY AND ASSESSMENT REPORT
ASBESTOS SURVEY AND ASSESSMENT REPORT BUILDING NUMBER: 4194 BUILDING NAME: FT. PIERCE CITGO SERVICE STATION BUILDING ADDRESS (SR/MP): 091-144 CITY/COUNTY: AGENCY: DISTRICT: DATE OF SURVEY: FT. PIERCE/ST.
More informationThe Richard Stockton University ASBESTOS MANAGEMENT PLAN
The Richard Stockton University ASBESTOS MANAGEMENT PLAN January 2015 Asbestos Management Plan Table of Contents I. Introduction II. III. IV. Definitions Identification of Asbestos Notification and Labeling
More informationSPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC
ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION
More informationBritish Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT
BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk
More informationASBESTOS MANAGEMENT PLAN. Tufts University Medford, Massachusetts
ASBESTOS MANAGEMENT PLAN Tufts University Medford, Massachusetts October 2008 Revised 35 New England Business Center Andover, MA 01810 (978) 557-8150 www.woodardcurran.com TABLE OF CONTENTS SECTION PAGE
More informationASBESTOS CONTROL PLAN
ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization
More informationHow To Care For Asbestos
Asbestos Awareness Training 1 Please watch video https://www.youtube.com/watch?v=pgzewa0 aafu 2 Asbestos is a Hazard that has No Visible Signs. Known as the silent killer, asbestos is an odorless, colorless
More informationFLOODS FACT SHEET ADVICE FOR RESIDENTS Approvals for repairing, renovating or rebuilding flood-affected houses
2 February 2011 Updated 16 March 2011 FLOODS FACT SHEET ADVICE FOR RESIDENTS Approvals for repairing, renovating or rebuilding flood-affected houses This fact sheet provides advice for residents about
More informationASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD
More informationIAC 7/16/08 Labor Services[875] Ch 155, p.1. CHAPTER 155 ASBESTOS REMOVAL AND ENCAPSULATION [Prior to 10/18/00, see 875 Chs 81 and 82]
IAC 7/16/08 Labor Services[875] Ch 155, p.1 CHAPTER 155 ASBESTOS REMOVAL AND ENCAPSULATION [Prior to 10/18/00, see 875 Chs 81 and 82] 875 155.1(88B) Definitions. Asbestos means material containing at least
More informationPROTECTING TRIBAL CHILDREN & COMMUNITY MEMBERS FROM ASBESTOS-IN-SCHOOL HAZARDS
PROTECTING TRIBAL CHILDREN & COMMUNITY MEMBERS FROM ASBESTOS-IN-SCHOOL HAZARDS PROTECTING TRIBAL CHILDREN & COMMUNITY MEMBERS FROM ASBESTOS-IN-SCHOOL HAZARDS 19 th Annual Tribal EPA Environmental Conference.
More informationASBESTOS in state and local government
ASBESTOS in state and local government Inspection campaign In 2013/14, WorkSafe WA is conducting a proactive inspection campaign focusing on the management of asbestos in state and local government buildings.
More informationASBESTOS MANAGEMENT AND OPERATING PLAN FOR MCCONNELL AIR FORCE BASE
ASBESTOS MANAGEMENT AND OPERATING PLAN FOR MCCONNELL AIR FORCE BASE LAST UPDATE 2003 TABLE OF CONTENTS TABLE OF CONTENTS... 1 GLOSSARY OF TERMS... 4 LIST OF ACRONYMS... 7 LIST OF REFERENCES... 9 1.0 INTRODUCTION...
More informationASBESTOS INSPECTION REPORT
ASBESTOS INSPECTION REPORT F&R PROJECT NUMBER: 65R-3125 Regarding: Hwy 295 Baseball Park Score Tower Structure 2100 Southport Road Spartanburg, South Carolina Prepared for: Spartanburg County Parks Department
More informationRestoration Specific Asbestos and Lead Based Paint Survey Report. 2503 Logan Ave Colorado Springs, CO 80909
Restoration Specific Asbestos and Lead Based Paint Survey Report Property Information: 2503 Logan Ave Colorado Springs, CO 80909 Inspection Conducted By: Shannon Anderson Colorado Cert #14225 Ted Anderson
More informationThe Vermont Department of Health When is Asbestos a Public Health Threat? Town Health Officers (THO) Training
When is Asbestos a Public Health Threat? Town Health Officers (THO) Training Asbestos and Lead Regulatory Program 2013 When is Asbestos a Public Health Threat? Town Health Officer (THO) Training August
More informationRULE 902 ASBESTOS Adopted 6-2-75 (Amended 5-31-89, 1-14-92, 6-1-95, 10-1-98, 1-22-15, 2-26-15) INDEX
RULE 902 ASBESTOS Adopted 6-2-75 (Amended 5-31-89, 1-14-92, 6-1-95, 10-1-98, 1-22-15, 2-26-15) INDEX 100 GENERAL 101 PURPOSE 102 APPLICABILITY 110 EXEMPTIONS 111 PARTIAL EXEMPTIONS 200 DEFINITIONS 201
More informationAsbestos: Regulations & Requirements presented by Kentucky Division for Air Quality visit our website at http://www.air.ky.gov
Asbestos: Regulations & Requirements presented by Kentucky Division for Air Quality visit our website at http://www.air.ky.gov What Is Asbestos? fibrous silicate mineral used in >3000 products insulating
More informationAsbestos Abatement Work Plan for the Carter Carburetor Superfund Site
for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project
More informationPolicy on the Management of Asbestos
WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other
More informationAppendix A NESHAP Discussion of Terms and Policy Decisions. Table of Contents
Appendix A NESHAP Discussion of Terms and Policy Decisions 1. Applicability 2. Asbestos-Containing Material (ACM) 3. Boarding Houses 4. Bricks 5. Bridges 6. Category I Nonfriable ACM 7. Category II Nonfriable
More informationAsbestos NESHAP. Uses, Health Effects and Regulations Governing Commercial Buildings and Structures
Asbestos NESHAP Uses, Health Effects and Regulations Governing Commercial Buildings and Structures Background Information on Asbestos Become familiar with history of asbestos use Recognize the characteristics
More informationBRIEFING TO THE UN STAFF
BRIEFING TO THE UN STAFF Topics History, Properties and Uses of Asbestos Important Definitions Regulatory Overview Asbestos Abatement Procedures History And Use What is Asbestos? Asbestos is a mineral
More informationNeighborhood Stabilization Program. Asbestos Abatement Services Request for Proposal (RFP)
Neighborhood Stabilization Program Asbestos Abatement Services Request for Proposal (RFP) June 2010 REQUEST FOR PROPOSAL (RFP) ASBESTOS ABATEMENT FOR RESIDENTIAL STRUCTURES BACKGROUND Communities across
More informationBuilding Owners Responsibilities for Asbestos
Building Owners Responsibilities for Asbestos August 2012 Minnesota Department of Labor and Industry Occupational Safety and Health Division This material can be provided to you in a different format (Braille,
More informationAsbestos-Containing Material Re-Inspection Report
Asbestos-Containing Material Re-Inspection Report WA032 PFC JOE E. MANN UNITED STATES ARMY RESERVE CENTER Site Code 53920 4415 North Market Street Spokane, Washington 99207 Prepared for: 88 th Regional
More informationPREPARED FOR: Branch Banking & Trust Environmental Risk Management 5130 Parkway Plaza Boulevard Charlotte, North Carolina 28217 (704) 954-1725
WATER INTRUSION AND VISUAL MOLD ASSESSMENT & LIMITED ASBESTOS-CONTAINING MATERIALS SURVEY FREDRICK WHITE 1119 DUSTIN STREET LADY LAKE, LAKE COUNTY, FLORIDA BB&T PROJECT NO. OMS-155500-REPORT #1 PREPARED
More informationRevised Environmental Site Assessment Guidelines & Asbestos Inspection Guidelines for Bridges
Revised Environmental Site Assessment Guidelines & Asbestos Inspection Guidelines for Bridges Revised Environmental Site Assessment Guidelines Revised Environmental Site Assessment Guidelines Developed
More informationMiami University s Asbestos Operations & Maintenance Program Administered by
Miami University s Asbestos Operations & Maintenance Program Administered by ENVIRONMENTAL SAFETY & RISK MANAGEMENT 529-2829 Table of Contents Purpose 2 Personnel Covered Under the Asbestos Mangement Plan
More informationMay 23, 2014. Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California 95993-2240
May 23, 2014 Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California 95993-2240 RE: Pre-Demolition Asbestos Survey Report 6150 Farrell Street, Marysville, California 95901
More informationWhy was asbestos used?
Asbestos Awareness What is Asbestos? Why was asbestos used? Asbestos appealed to manufacturers and builders for a variety of reasons. It is strong yet flexible, and it will not burn. It conducts electricity
More informationTITLE 64 LEGISLATIVE RULE DIVISION OF HEALTH SERIES 63 ASBESTOS ABATEMENT LICENSING RULE. the director 1 of the division of health.
TITLE 64 LEGISLATIVE RULE DIVISION OF HEALTH SERIES 63 ASBESTOS ABATEMENT LICENSING RULE 64-63-1. General. 1.1. Scope. -- This legislative rule establishes procedures and standards for the licensure and
More information