Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1



Similar documents
An introduction to Earned Value Analysis

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

IST 302 : Project Cost Management

Earned Value and Agile Reporting

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Using Earned Value Management for Improving Processes. By Cynthia K. West

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

Basic Concepts of Earned Value Management (EVM)

Tracking Budgets and Schedules

Earned Value Formulae

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

700 Analysis and Reporting

Project Cost Management

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Introduction to earn value management in Civil Engineering

INSE 6230 Total Quality Project Management

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Project Cost Management

How To Manage A Project

Estimating Cost at Completion - Judgment & EV Information

Project Cost Management

Simple Earned Value (Using MS Project 2010)

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Brainstorm. What is Cost and Project Cost Management?

Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Earned Value Management Guidelines

Appendix D Glossary Of Terms

technical tips and tricks

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Forecasting Project Schedule Completion by Using Earned Value Metrics

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Chapter 7. (PMBOK Guide)

A Gentle Introduction to Earned Value Management Systems

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Project Management: Tracking Progress and Earned Value with MS Project 2003

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

EVM.01. Earned Value Analysis Why it Doesn't Work

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

Predicting progress on your project

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Using Earned Value Management Concepts to Improve Commercial Project Performance

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

// Benchmarking Project Schedules

Project Cost Management. Richard Boser

Project Control with ProTrack

Chapter 7: Project Cost Management. Munawar

Cost & Schedule Risk Assessment 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

PROJECTS SCHEDULING AND COST CONTROLS

Agile Project Management Controls

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

technical tips and tricks

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study

Project Control. 1. Schedule Updating

CPM -100: Principles of Project Management

DCMA DCMA-EA PAM October 2012

Earned Value Management System Description

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

Abstract. Earned Value Management Basics

L10: Budgeting and Cost Control. Olivier de Weck

Project Management Glossary

AACE International Recommended Practice No. 86R 14

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

Module 5 Cost Management PMP Exam Questions

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management Best Practices

Project Execution - PM Elements

Brief Introduction to Earned Value Management (EVM)

PMI Lexicon of Project Management Terms

Since 1985, the Test Program Set (TPS) development

PROJECT TRACKING and CONTROL

Project Management Using Earned Value

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Young Hoon Kwak Associate Professor School of Business The George Washington University

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Applied Project Management ( APM )

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004

plans based on actual cost, schedule and technical progress of work [1, 9].

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

Tracking Software Development Progress with Earned Value and Use Case Point

A collection of Safran Project report samples for project professionals

Monte Carlo analysis used for Contingency estimating.

What is the Health of my Project?

Earned Schedule Leads to Improved Forecasting

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

earned value management

Transcription:

Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1

Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control Systems Criteria (C/SCSC) to standardize contractor requirements for reporting cost and schedule performance on major contracts. A basic tenet of C/SCSC is the concept of Earned Value Management. Not for duplication nor distribution 2

What is Earned Value Management (EVM)? EVM is an incremental methodology for measuring project performance by determining cost and schedule performance of a project by comparing "planned" work with "accomplished" work in terms of the dollar value assigned to the work, and determining the need to recommend corrective actions. EVM results from an earned value analysis to indicate potential deviation of the project from cost and schedule baselines. Earned value is a Management Tool Provides a snapshot of project performance at a point in time. Compares where the project is now with: (1) previous work accomplished and (2) where the project was planned to be. Serves as an early warning system to detect deficient or endangered progress. EVM is a significant tool in the Project Manager's "toolbox" for gaining valuable insight into project performance and is the tool that integrates technical, cost, schedule and risk management. In addition, EVM provides valuable quantifiable performance metrics for forecasting at-completion cost and schedule for their project. Not for duplication nor distribution 3

Why use Earned Value Management (EVM)? When you manage project performance by just comparing planned to actual results, you could easily be on time but overspend according to your plan. Using EVM is a better method because it integrates cost, time and the work done (scope) and can be used to forecast future performance and project completion dates and costs. Earned value analysis results should be a major part of project reporting. EVM is the basis for course correction and will lead to new forecasted completion costs, change requests and other items that will need to be communicated. EVM provides an accurate picture of contract status and supports mutual goals of contractor and customer. The major objectives of applying earned value to a contract are to encourage contractors to use effective internal technical, cost and schedule management control systems, and to permit the customer to rely on timely data produced by those systems, for better management insight to bring project in on schedule and cost. This data is in turn used for determining product-oriented contract status, and projecting future performance based on trends to date. Not for duplication nor distribution 4

Why use Earned Value Management? EVM allows better and more effective management decision making to minimize adverse impacts to the project. Earned value provides an objective measurement of how much work has been accomplished on a project. EVM ensures a clear definition of work prior to beginning that work EVM presents a logical plan for accomplishing the work EVM provides early and accurate identification of trends and potential problems, and serves as a key element of a project's risk management process. To measure progress, there must be a standard against which the movement may be compared. EVM establishes that standard as the Performance Measurement Baseline and measures progress against that baseline. Unless you are tracking earned value, you really have no idea what is going on with your project! Not for duplication nor distribution 5

Key questions that Earned Value Management answers We analyze past performance to help us control the future PAST PRESENT FUTURE Are Are we we on on schedule? schedule? Are Are we we on on cost? cost? What What are are the the significant significant variances? variances? When When will will we we finish? finish? Why Why do do we we have have variances? variances? What What will will it it cost cost at at the the end? end? Who Who is is responsible? responsible? How How can can we we control control the the trend? trend? What What is is the the trend trend to to date? date? The Two Key Questions 1. Did we get what we wanted for what we spent? 2. At the end of the project, is it likely that the cost will be less than or equal to the original estimate? Not for duplication nor distribution 6

What do we measure progress against? Performance measurement baseline budget is spread over... time, to accomplish the scope of work against which progress can be measured Earned Value is a key concept how much progress did I make against my original plan? expressed in dollars or hours Not for duplication nor distribution 7

Ways of earning value Should be a quantitative and discrete whenever possible Discrete = tangible end product e.g. delivery of a specification, vendor parts contract awarded, foundation completed Should be integrated with success criteria or technical measures e.g., successful completion of clean-up, a specific test, reliability growth curve Not for duplication nor distribution 8

The Work Breakdown Structure (WBS) and Earned Value The WBS has been an integral part of the earned value concept. The WBS is a graphic portrayal of the project, exploding it in a level-by-level fashion, down to the degree of detail needed for effective planning and control. It must include all deliverable end items, and include the major functional activities that must be performed. A project consists of the sum total of all the elements of the WBS. Conversely, an element that is not contained in the WBS is not a part of the project. Any work that cannot be identified in the WBS requires authorization to proceed, either as a recognized omission or as an approved change order. The lowest levels of the WBS are significant because each defines a discrete element of work or task to be performed against which resources can be assigned and cost and schedule measured. These lowest level activities or tasks in the WBS, when assigned a schedule and cost, together with required resources (people and material) and the individual responsible for its accomplishment, define a work package, which can be rolled up to a control account via a process called cost aggregation. The control account is a critical point for performance measurement to occur, for this is where the integration of scope, schedule, and resources will take place and where the project will measure its performance throughout the duration of the project. Definition of the work package is critical to effective Earned Value Management and the use of earned value in risk management. Perhaps most critical to the use of earned value in risk management is the tenet that work packages either be limited in size to be accomplishable in a relatively short period of time, or that they include discrete milestones against which work performance can be measured. Not for duplication nor distribution 9

Cost Budgeting A budget is merely a compilation of the individual costs estimates. Activity costs are rolled up to work package costs. Work package costs are rolled up to control account costs. Control account costs are rolled up to project costs. Contingency reserve is for the risks remaining after risk response planning. The cost baseline is made up of the contingency reserve plus project costs. Management reserve is any extra amount of funds to be set aside to cover unforeseen risks or changes to the project. The cost budget will include the management reserve and the cost baseline. Not for duplication nor distribution 10

How does Earned Value work? Work is planned, budgeted and scheduled in time-phased increments utilizing a Work Breakdown Structure (WBS) to define activities and to assign costs to those activities. As work is accomplished, value is "earned" on the same basis it was planned. Comparison of this earned value with the planned value for a specific time period provides an indication of activity progress- if more value is planned than is earned for a specified period, then the project is in danger of not meeting its required schedule, unless action is taken to recapture the unaccomplished work. Similarly, comparison of the earned value for a task or group of tasks with the "actual" costs required to accomplish the same activities provides an indication of task cost performance- if actual costs are greater than planned costs for the accomplished activities, then the project is experiencing a cost overrun situation. Therefore, EVM requires that the project s scope be fully defined, and then a bottoms-up baseline plan be put in place that integrates the scope with the authorized resources, all set within a specific time frame for performance with detailed measurement taken against the project plan, and a periodic forecast of the final expected results based on the actual performance results. Not for duplication nor distribution 11

Earned value and your project Define the Work Plan the Work Work the Plan Collect Results Measure Performance Change Control Analyze Deviations External Changes Take Corrective Take Action Corrective Action Not for duplication nor distribution 12

Acronym PV EV AC BAC EAC ETC VAC Earned Value Terminology Term Planned Value Earned Value Actual Cost Budget at completion Estimate at Completion Estimate to Complete Variance at Completion Interpretation (as of today ) What is the estimated value of the work planned to be done? What is the estimated value of the work actually accomplished? What is the actual cost incurred for the work accomplished? How much did we BUDGET for the TOTAL project effort? What do we currently expect the TOTAL project to cost? From this point on, how much MORE do we expect it to cost to finish the project? How much over or under budget do we expect to be at the end of the project? Not for duplication nor distribution 13

Name Earned Value formulas Formula Interpretation (as of today ) Cost Variance (CV) Schedule Variance (SV) Cost Performance Index (CPI) Schedule Performance Index (SPI) Estimate to Complete (ETC) Variance at Completion (VAC) EV - AC EV PV EV / AC EV / PV EAC AC BAC EAC NEGATIVE is over budget, POSITIVE is under budget. NEGATIVE is behind schedule, POSTIVE is ahead of schedule. We are getting $ worth of work out of every $1 spent. Funds are or are not being used efficiently. We are (only) progressing at percent of the rate originally planned. How much more will the project cost? How much over or under budget will we be at the end of the project? Not for duplication nor distribution 14

Earned Value Formulas Estimate At Completion (EAC) Note: there are many ways to calculate EAC, depending on the assumptions made. BAC / CPI AC + ETC AC + (BAC - EV) AC + (BAC - EV) / CPI As of now, how much do we expect the total project to cost? Used if no variances from the BAC have occurred or you will continue at the same rate of spending. Actual plus a new estimate for remaining work. Used when original estimate was fundamentally flawed. Actual to date plus remaining budget. Used when current variances are thought to be atypical of the future. AC plus the remaining value of work to perform. Actual to date plus remaining budget modified by performance. Used when current variances are thought to be typical of the future. Not for duplication nor distribution 15

Earned Value in action PV Today BAC AC ETC EAC Not for duplication nor distribution 16

Earned Value Analysis example You have a project to build a new fence. The fence is four sided. Each side is to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. Today is the end of day three. Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3 Side 1 S------------F Complete, spent $1,000 Side 2 S-----------PF ------F Complete, spent $1,200 Side 3 PS S----PF 50% done, spent $600 Side 4 PS---------PF Not yet started Not for duplication nor distribution 17 Key S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned Finish

Earned Value analysis example interpretation What is? PV EV AC BAC CV CPI SV SPI EAC ETC VAC 2,500 2,800 2,500 / 2,800 2,500 3,000 2,500 / 3,000 4,000 /.893 4,479 2,800 4,000 4,479 Calculation 1,000 + 1,000 +1,000 complete, complete, half done or 1,000 + 1,000 + 500 1,000 + 1,200 + 600 1,000 + 1,000 + 1,000 + 1,000 Answer 3,000 2,500 2,800 4,000-300.893-500.833 4,479 1,679-479 Interpretation of answer We should have done $3,000 worth of work. We have actually completed $2,500 worth of work. We have actually spent $2,800. Our project budget is $4,000. We are over budget by $300. We are only getting 89 cents out of every dollar we put into the project. We are behind schedule. We are only progressing at 83 percent of the rate planned. We currently estimate that the total project will cost $4,479. We need to spend $1,679 to finish the project. We currently expect to be $479 over budget when the project is completed. Not for duplication nor distribution 18

Using performance measurements for decision making Behind Schedule - How critical is schedule? - Can I afford to work overtime to recover? - Can I do tasks concurrently? - Are there technical innovations which could speed up the process? - Am I gold plating instead of just meeting requirements? - Should I do a schedule risk assessment to project impact to program? Over Cost - Can I reschedule tasks? (Time phasing) - Is there a less costly facility I can use? - Are there tasks which can be deleted? - Should the element be added to my risk management profile? Not for duplication nor distribution 19

Earned Value Analysis techniques Sort on significant variances eliminate almost complete, just starting, etc. Graph and analyze trends Look at comparative data e.g. cumulative performance vs. projected performance Examine written analysis by contractor does it answer why? adequacy of corrective action plans Analysis of schedule trends, critical path Analysis of Estimate At Completion (EAC) realism what are the drivers? what can we do do about them? Not for duplication nor distribution 20

Cost variance chart Not for duplication nor distribution 21

Schedule variance chart Not for duplication nor distribution 22

What is a significant variance? % variance (e.g., >10%) $ variance (e.g., >$50,000 at the control account level) critical path element risk/complexity impact to other elements Top 10, Top 20, etc. contractor defined Not for duplication nor distribution 23

EVM Performance Reporting Not for duplication nor distribution 24

Earned value analysis reporting (+) Under Budget 10 D Behind schedule 5 Y-Axis X-Axis A Ahead of schedule (-) Variance % -10-5 -5 5 10 (+) B C 0% Cost or schedule variance = On Schedule On Budget -10 (-) Variance % Over budget Cost and schedule performance chart. Graphing the cost and schedule variance of Projects A, B, C, and D quickly identifies which needs the most immediate attention. Earned value reporting uses cost data to give more accurate cost and schedule reports. It does this by combining cost and schedule status to provide a complete picutre of the project. Project cost can also be graphed versus time. Not for duplication nor distribution 25

References A Guide to the Project Management Body of Knowledge, 3 rd Edition, by PMI PMP Exam Prep, 5 th Edition, by Rita Mulcahy. Use of Earned Value Management to Mitigate Software Development Risk, by Paul E. Young. Using Earned Value Management For Better Contract Administration, by U.S.A Government Department of Energy. Earned Value Management, by James R. Chapman. Earned Value Management, by U.S.A. Government NASA Earned Value Project Management, 2 nd Edition, by Quentin W. Fleming and Joel M. Koppelman Not for duplication nor distribution 26