Guidance notes and templates for Project Technical Review involving Independent Expert(s)



Similar documents
Guidance notes and templates for Project Technical Review involving Independent Expert(s)

ARTEMIS-ED Guidance notes and templates for Project Technical Review involving independent expert(s)

Project deliverables and reviews

Guidelines for reporting. for Accompanying Measures. implemented as. Specific Support Action

IGLO Training Session Module 5

Project management in FP7. Gorgias Garofalakis ETAT S.A.

Project reporting in FP6

Administrative + Management Aspects. EU - Framework Programme 7. Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting,

EMPIR Reporting Guidelines Part 0 Guide to the parts

H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi)

Negotiations feedback for successful project preparation. ERANIS workshop, , Minsk

D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E

Proposal Negotiation. a guide. Constantine Vaitsas, vaitsas@help-forward.gr

PROPOSAL ACRONYM - ETN / EID / EJD (delete as appropriate and include as header on each page) START PAGE MARIE SKŁODOWSKA-CURIE ACTIONS

FP7 Project Reporting Tool Quick guide for beneficiaries

FP7 Project Reporting ****** Research Participant Portal. Peter Härtwich European Commission DG Research-A6

Guillem Bernat (RAPITA) Communication, Deliverable, Dissemination, Publication, Reporting

Fast track to Innovation: a new instrument in Horizon 2020

Administrative forms (Part A) Project proposal (Part B)

MANUAL FOR THE EURO-HEALTHY

Project reports and reviews in FP6

Frequently asked questions. FP7 Financial Guide

The TIPS project is supported by the European Commission through the Seventh Framework Programme for Research and Technological Development /

PRIORITY 2 INFORMATION SOCIETY TECHNOLOGIES (IST) FREQUENTLY ASKED QUESTIONS on Project management in FP6

Guide to Financial Issues relating to FP7 Indirect Actions

D 1.1 Project Toolbox

GUIDE FOR APPLICANTS

Guide for ERC Grant Holders

SESAR 2020 EXPLORATORY RESEARCH INFO DAY PROPOSALS SUBMISSION & EVALUATION & PROGRAMME MANAGEMENT REQUIREMENTS

Deliverable 1.1 Description of Quality Management and Risk Processing Responsible partner:

Version September 2014

NEXT. Tools of the Participant Portal: Scientific Reports & Deliverables

Grant Agreement Implementation and Reporting under H2020 in MSCA

FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues

Impacting through Horizon 2020

PREANNOUNCES RESEARCH WITHIN PRIORITY SECTORS CALL FOR PROPOSALS

Mid-Term Review: A contractual obligation and a fruitful dialogue

South East Europe (SEE) Implementation Manual

Proposal template and GUIDE FOR APPLICANTS (updated by FIspace)

Research proposal (Part B)

Guide to Financial Issues relating to FP7 Indirect Actions

EUROPEAN COMMISSION. CASSANDRA Common assessment and analysis of risk in global supply chains

H2020 rules for participation, new instruments, evaluation criteria

D01.1 Project Management Plan

HERON (No: ): Deliverable D.2.6 DATA MANAGEMENT PLAN AUGUST Partners: Oxford Brookes University and Università Commerciale Luigi Bocconi

Deliverable D6.2: Quality Plan FP7-ICT

GUIDELINES FOR PREPARING PROJECT REPORTS (may be downloaded from or

Horizon 2020 Secure Societies

Proposal template (technical annex) Health, demographic change and wellbeing Two-stage Research and Innovation actions Innovation actions

HabEat - FP HabEat

Erasmus Mundus Joint Doctorate Application Form

Deliverable D1.1. Building data bridges between biological and medical infrastructures in Europe. Grant agreement no.:

Erfahrungen bei der Antragstellung im 7. Forschungsrahmenprogramm

Reporting transnational access and service activity costs. Version May 2011

SCHEDULE 8 Generalist Project Services Framework 2015

Guidelines for Applicants

Guide to Financial Issues for Cleansky GAPs

Qualification of innovative floating substructures for 10MW wind turbines and water depths greater than 50m

Guidelines for Applicants

Guidelines for applicants for the 1 st Transnational Call for Proposals (pre-proposal phase)

EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) H MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO)

Project Execution Guidelines for SESAR 2020 Exploratory Research

Deliverable 9.1 Management Plan

Guidelines for reporting. for Transnational Access. implemented as. Specific Support Action

Guidelines for applicants for the 2nd Transnational Call for Proposals (full-proposal phase)

How to write proposal section 3: IMPLEMENTATION? The Hague Christiane Kummer Pt-Juelich

Guide for ERC Grant Holders PART I

Proposal template (Technical annex) Research and Innovation actions

Smart Open Services for European Patients Open ehealth initiative for a European large scale pilot of patient summary and electronic prescription

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME

Guide for reporting, documentation of activities and financial management of grants, 2016

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS

C-IPM. Guidelines for applicants for the 1 st Transnational Call for Proposals. Full-proposal phase. Coordinated Integrated Pest Management in Europe

IMI2 MANUAL FOR SUBMISSION,

International Collaboration on Research Data Infrastructure

RESEARCH FOR THE BENEFIT OF SMES

Terms of reference Call for the selection of an Expert on Indian STI

TENDER SPECIFICATIONS

Deliverable D8.1 Water Reuse Europe (WRE) website design and functionality specification

ZEPHYR project Deliverable D1.1 QUALITY PLAN

RFCS Information Package 2015

Sustaining Ethical Aquatic Trade. Management

FP7 Project reporting. FP7 INCO National Contact Points Meeting 9 June Athens Anne Mandenoff - European Commission - RTD A.

Impact of extreme weather on critical infrastructure. Deliverable 7.2. Website and Collaboration Platform Online

Standard operating procedure

Public Transportation - Accessibility for All

EICSTES DELIVERABLE D7.1. Evaluation, assessment and users involvement plan

Erasmus+ General Information. Application Form Call: KA2 Cooperation and Innovation for Good Practices

FWK Contract - Support for safety and accident analyses

Model Grant Agreement

EUROPEAN COMMISSION Directorate-General for Research & Innovation. Guidelines on Data Management in Horizon 2020

CODE OF PRACTICE DEALING WITH THE RELATIONSHIP BETWEEN THE NATIONAL AUDIT OFFICE AND THE COMPTROLLER AND AUDITOR GENERAL

Starting Independent Researcher Grants Call Information

PROJECT DELIVERABLE. Funding Scheme: Collaborative Project

Funding excellence in innovation. Guidelines for declaration of changes. Version 1.0

Data Management Plan ehcobutler Project

BUDGET HEADING CALL FOR PROPOSALS. Support for social dialogue VP/2014/001

BUDGET HEADING CALL FOR PROPOSALS VP/2014/002

COST Evaluation Procedure

18. Fast Track to Innovation Pilot Revised

Transcription:

Guidance notes and templates for Project Technical Review involving Independent Expert(s) FP7 Collaborative Projects, Networks of Excellence, Coordination and Support Actions Version 18/12/2007 Disclaimer The information and advice contained herein is not intended to be comprehensive and readers are advised to seek independent professional advice before acting upon them. The Commission does not accept responsibility for the consequences of errors or omissions herein enclosed.

CONTENTS 1. INTRODUCTION... 3 2. MANDATE OF THE INDEPENDENT EXPERT(S)... 3 2.1. Objectives... 3 2.2. Outline of the review process... 3 2.3. Review material... 4 2.4. Reporting... 4 3. PROJECT REPORT ASSESSMENT OF THE COMMISSION... 4 4. TEMPLATE FOR THE TECHNICAL REVIEW REPORT... 5 2

1. INTRODUCTION The aim of a technical audit or review is to assess the work carried out under the project over a certain period and provide recommendations to the Commission. Such review may cover scientific, technological and other aspects relating to the proper execution of the project and EC grant agreement (ECGA) in line with its article II.23 (General Conditions). This document provides guidance for the reviewers on the review process as well as on the content of their report to the Commission. 2. MANDATE OF THE INDEPENDENT EXPERT(S) 2.1. Objectives The reviewer's task is to give external advice to the Commission on the project, with respect to the following issues: 1. the degree of fulfilment of the project work plan for the relevant period and of the related deliverables 2. the continued relevance of the objectives and breakthrough potential with respect to the scientific and industrial state of the art 3. the resources planned and utilised in relation to the achieved progress, in a manner consistent with the principles of economy, efficiency and effectiveness 4. the management procedures and methods of the project 5. the beneficiaries contributions and integration within the project 6. the expected potential impact in scientific, technologic, economic, competitive and social terms (where relevant), and the plans for the use and dissemination of results. The reviewer(s) will also assist the Commission by recommending any reorientation that may be required, but the final decision on recommendations and reorientation is taken only by the Commission. 2.2. Outline of the review process If a review meeting is scheduled, the expert(s) will read all relevant documents before the meeting and will attend the review meeting. He/she will then provide an assessment of the project based on the written material and information provided at the meeting. In the case of remote review, the assessment will be based on written documents only. 3

2.3. Review material The documents to be reviewed should normally include the following: Annex I (contractual Description of Work) Progress report for the period under review Deliverables necessary for the assessment of the work, due in this period, according to the deliverable table in Annex I, For a final technical review, the following additional documents should also be part of the material to review: The final publishable summary report The report covering the wider societal implications of the project, including gender equality actions, ethical issues, efforts to involve other actors and spread awareness as well as the plan for use and dissemination of foreground 1. 2.4. Reporting At the end of the review exercise, the expert will prepare a report with his/her findings, containing an assessment of the facts as well as suggestions for further actions or changes. A template for the project review report is included in this document. This document has to be completed and returned to the Project Officer within the requested deadline. When more than one expert is involved in the project review, they might be asked to issue a single consolidated report. 3. PROJECT ASSESSMENT OF THE COMMISSION On the basis of the experts' formal recommendations, the Commission will inform the coordinator of its decision (which may differ from the experts' recommendations): - to accept or reject the deliverables; - to allow the project to continue without modification of Annex I or with minor modifications; - to consider that the project can only continue with major modifications; - to initiate the termination of the grant agreement or of the participation of any beneficiary according to Article II. 38 of the grant agreement; - to issue a recovery order regarding all or part of the payments made by the Commission and to apply any applicable sanction. 1 In FP7, the term "Foreground" means information and results arising from the project, as opposed to "Background" which is information and rights prior to accession to the grant agreement 4

4. TEMPLATE FOR THE TECHNICAL REVIEW REPORT The template hereafter provides the structure for the technical review report that needs to be prepared by the expert(s) after the review. It may be completed on-line via the IT reporting tool (username and password are required). The template can be found at http://cordis.europa.eu/fp7... by... In case the expert feels that he/she does not have the competence or the information to answer a question, he/she must declare it in the corresponding sections. 5

TECHNICAL REVIEW REPORT Grant Agreement number: Project Acronym: Project title: Funding Scheme: Project starting date: Project duration: Project coordinator name and organisation: Period covered by the report, from to.. Date of review meeting (if applicable): Name(s) of expert(s): - - - - Name of expert drafting the report: Individual report Consolidated report 6

1. OVERALL ASSESSMENT a. Executive summary, in particular highlighting the scientific/technical achievements of the project, its contribution to the State of the Art and its impact: Good to excellent progress (the project has fully achieved its objectives and technical goals for the period and has even exceeded expectations). Acceptable progress (The project has achieved most of its objectives and technical goals for the period with relatively minor deviations). Unsatisfactory progress (The project has failed to achieve critical objectives and/or is not at all on schedule). b. Overall recommendations (e.g. on overall modifications, corrective actions at WP level, or re-tuning the objectives to optimise the impact or keep up with the State of the Art, or for other reasons, like best use of resources, re-focussing ). 7

2. OBJECTIVES and WORKPLAN a. Have the objectives for the period been achieved? In particular, has the project as a whole been making satisfactory progress in relation to the Description of Work (Annex I to the grant agreement)? b. Has each work package (WP) been making satisfactory progress in relation to the Description of Work (Annex I of the grant agreement)? c. Have planned milestones and deliverables been achieved for the reporting period? DELIVERABLES LIST STATUS No. Title Status (Approved/Rejected) Remarks 8

d. Are the objectives for the coming period(s) i) still relevant and ii) still achievable within the time and resources available to the project? i ii e. For Networks of Excellence (NoEs) only: Has the Joint Programme of Activities been realised for the period, with all activities foreseen satisfactorily completed? 9

3. RESOURCES a. To the best of your estimate, have resources used, i.e. personnel resources and other major cost items, been (i) utilised for achieving the progress, (ii) in a manner consistent with the principle of economy, efficiency and effectiveness. Note that both aspects (i) and (ii) have to be covered in the answer. i ii b. If applicable, please comment on large deviations with respect to the planned resources. 10

4. IMPLEMENTATION OF THE PROJECT a. Has the project management been performed as required? b. Has the collaboration between the beneficiaries been effective? c. Do you identify evidence of underperforming beneficiaries, lack of commitment or change of interest of any beneficiaries? 11

5. USE AND DISSEMINATION OF FOREGROUND 2 a. Is there evidence that the project has/will produce significant scientific, technical, commercial, social, or environmental impacts (where applicable)? b. Is the plan for the use of foreground, including any update, appropriate? Namely, please comment on the plan for the exploitation and use of foreground for the consortium as a whole, or for individual beneficiary or groups of beneficiaries and its progress to date. 12

c. Have the contractors disseminated project results and information adequately (publications, conferences )? d. Are potential users and other stakeholders (outside the consortium) suitably involved (if applicable)? e. Is the consortium interacting in a satisfactory manner with other related Framework Programme projects or other R&D national/international programmes, standardisation bodies (if relevant)? 13

6. OTHER ISSUES a. Have policy-related and/or regulatory issues been properly handled (if applicable)? b. Have ethical issues been appropriately handled (if applicable)? c. Have safety issues been properly handled (if applicable)? d. Has progress on Gender Equality Actions been satisfactory (if applicable for this reporting period)? 14

Name (s) of the expert(s): Date: Signature(s): 15