1 MANUAL FOR THE EURO-HEALTHY INTERNAL AND PERIODIC PROJECT MONITORING AND REPORTING Coimbra, May, 2015 EURO-HEALTHY project has received funding from the European Union s Horizon 2020 research and innovation programme under Grant Agreement No

2 Foreword The Manual for the EURO-HEALTHY internal and periodic project monitoring and reporting was designed for the purpose of fulfilling the reporting requirements stated under the EU Framework Program for Research and Innovation H2020 Framework. All articles stated in this document refer to the AGA-Annotated Model Grant Agreement Version 2.0.1, 12 May Important contacts: Project coordinator: Prof. Paula Santana Project manager, Alexandre Leal WP1: Iwa Stefanik 2

3 Table of contents Foreword... 2 Important contacts:... 2 INTRODUCTION REPORTING Article 20.3 Periodic reports Requests for interim payments Article 20.4 Final report Request for payment of the balance INTERNAL MONITORING Internal Technical Reports WP Leader Report Deliverable Reports Milestone Reports Internal Financial Monitoring Useful links INFORMATION: SUPPORT: List of figures Figure 1. Template for the WP Leader Report (internal and periodic) Figure 2. Template for the Deliverable Report-doc form (official and non-official one) Figure 3. Template for the Deliverable Report-excel form (official and non-official one) Figure 4. Template of a Milestone Report including contribution of a specific WP Figure 5. Template of the Milestones Report to be submitted by UC/IST Figure 6. Template of the Internal Financial Report to be submitted by each beneficiary Figure 6a. Template of the Internal Financial Report-zoom A Figure 6b. Template of the Internal Financial Report-zoom B Figure 6c. Template of the Internal Financial Report-zoom C Figure 7. Template for time recording provided by EU: basic version Figure 8. Template for time recording provided by UC: detailed version

4 INTRODUCTION The information contained in the document is meant to guide the EURO-HEALTHY partners to implement a mechanism to monitor and report all technical and financial activities related to the EURO-HEALTHY project. Accordingly the manual aims to assist WP Leaders and individual partners by setting out procedures and requirements for project administrative execution. Management WP1 will manage all the tasks of the EURO-HEALTHY project. As stated in the Grant Agreement, the management structure of the EURO-HEALTHY project will i) ensure that effective methods for planning, communicating, and decision making are in place, ii) manage the project work so as to be on schedule, iii) ensure that the deliverables and reports are on time and within the allocated budget, and in line with the expected research quality, and iv) to ensure that the project objectives and outcomes are achieved. For further information please see the Grant Agreement, section Management structures and procedures, page Purpose The main purpose of this manual is to help users understand and interpret their responsibilities towards the EURO-HEALTHY project reporting. The document is designed to help readers find answers to practical administrative requirements linked to the project. The end-results aimed at are regular reports and documents that comply with the European Commission (EC) regulations stated in the Horizon 2020 Framework Programme for and the EURO-HEALTHY Grant Agreement. The manual contains two distinct segments: REPORTING: This section outlines the role and responsibilities of the project coordinator and beneficiaries regarding mandatory reporting to EC. The chapter covers technical aspects of periodic reporting practice including financial and technical aspects. INTERNAL MONITORING: This part provides practical internal monitoring mechanisms that need to be processed to execute reporting requirements, within timelines, and communicate results to the project manager, project coordinator and the EC. 4

5 Contact point with European Commission The project coordinator will be the contact person with the European Commission. Except the coordinator, a partner shall never contact directly the EC Project Officer. Changes in the Grant Agreement and amendments If during the course of the project you identify any major change to your legal details or contractual deliverables as stated in the GA, eg. Change of name or address of a coordinator vs. update of beneficiaries' data in the Participant Portal; Changes to Annex 1: a significant change of the action tasks; Changes concerning in-kind contributions or subcontracts; Changes to Annex 2 = estimated budget: form of costs that is not in Annex 2; Removal of a beneficiary for non-accession to GA; Change of beneficiary due to universal takeover; Please inform as soon as possible the coordinator or the project manager. They will assess the situation and guide you on the best procedure to follow for updating this at the EC level, if needed by requesting an amendment to the GA. Important note: Please note that the Manual covers the basic elements for implementing reporting and internal monitoring requirements. The AGA Annotated Model Grant Agreement provides detailed information regarding reporting requirements, including technical and financial aspects i.e. cost eligibility, that should serve as a reference point for beneficiary-specific needs. Please find reference to the AGA at the end of the Manual called useful links. Please note that all templates provided in the Manual are available to upload on the EURO-HEALTHY Intranet. 5

6 1. REPORTING This chapter contains information based on Article 20 Reporting-Payments Request (AGA, 2015 p.160). Terms and Conditions (All Annexes are attached to Grant Agreement EURO-HEALTHY.pdf. Please note that Annex 4 in this Manual corresponds to Annex 5 in the above mentioned document). Annex 1 Annex 2 Annex 3 Annex 4 Description of the action Estimated budget for the action Model for the financial statements Model for the financial statements 1.1 Article 20.3 Periodic reports Requests for interim payments The coordinator must submit a periodic report within 60 days following the end of each reporting period. The EURO-HEALTHY project has two periodic reports (each 18 months). The Periodic Report must include the following: A. A Periodic Technical Report containing: o An explanation of the work carried out by the beneficiaries; o An overview of the progress towards the objectives of the action, including milestones and deliverables identified in Annex 1. This report must include explanations justifying the differences between work expected to be carried out in accordance with Annex 1 and that actually carried out. The report must also detail the exploitation and dissemination of the results and if required in Annex 1 an updated Plan for the Exploitation and Dissemination of the Results; o A summary for publication by the [Commission][Agency]; o The answers to the Questionnaire, covering issues related to the action implementation and the economic and societal impact, notably in the context of 6

7 the Horizon 2020 key performance indicators and the Horizon 2020 monitoring requirements; B. A Periodic Financial Report containing: o An Individual Financial Statement from each beneficiary [and from each linked third party], for the reporting period concerned. The individual financial statement must detail the eligible costs (actual costs, unit costs and flat-rate costs [and lump sum costs]; see Article 6) for each budget category (see Annex 2). The beneficiaries [and linked third parties] must declare all eligible costs, even if for actual costs, unit costs and flat-rate costs they exceed the amounts indicated in the estimated budget (see Annex 2). Amounts which are not declared in the individual financial statement will not be taken into account by the [Commission][Agency]. If an individual financial statement is not submitted for a reporting period, it may be included in the periodic financial report for the next reporting period. The Individual Financial Statements of the last reporting period must also detail the receipts of the action (see Article 5.3.3). Each beneficiary [and each linked third party] must certify that: the information provided is full, reliable and true; the costs declared are eligible (see Article 6); the costs can be substantiated by adequate records and supporting documentation (see Article 18) that will be produced upon request (see Article 17) or in the context of checks, reviews, audits and investigations (see Article 22), and for the last reporting period: that all the receipts have been declared (see Article 5.3.3); o o An explanation of the use of resources and the information on subcontracting (see Article 13) and in-kind contributions provided by third parties (see Articles 11 and 12) from each beneficiary [and from each linked third party], for the reporting period concerned; A Periodic Summary Financial Statement (see Annex 4), created automatically by the electronic exchange system, consolidating the individual financial statements for the reporting period concerned and including except for the last reporting period the request for interim payment. 7

8 1.2 Article 20.4 Final report Request for payment of the balance In addition to the periodic report for the last reporting period, the coordinator must submit the final report within 60 days following the end of the last reporting period. The Final Report must include the following: 1. A Final Technical Report with a summary for publication containing: An overview of the results and their exploitation and dissemination; The conclusions on the action, and The socio-economic impact of the action; 2. A Final Financial Report containing: Final Summary Financial Statement (see Annex 4), created automatically by the electronic exchange system, consolidating the individual financial statements for all reporting periods and including the request for payment of the balance and A Certificate on the Financial Statements (drawn up in accordance with Annex 5) for each beneficiary [and for each linked third party], if it requests a total contribution of EUR or more, as reimbursement of actual costs and unit costs calculated on the basis of its usual cost accounting practices (see Article 5.2 and Article 6.2, Point A). NOTE: General conditions for costs to be eligible (see Article 6.1) Eligible costs are costs that meet the following criteria: A. For actual costs: they must be actually incurred by the beneficiary; they must be incurred in the period set out in Article 3, with the exception of costs relating to the submission of the periodic report for the last reporting period and the final report (see Article 20); 8

9 they must be indicated in the estimated budget set out in Annex 2; they must be incurred in connection with the action as described in Annex 1 and necessary for its implementation; they must be identifiable and verifiable, in particular recorded in the beneficiary s accounts in accordance with the accounting standards applicable in the country where the beneficiary is established and with the beneficiary s usual cost accounting practices; they must comply with the applicable national law on taxes, labour and social security, and they must be reasonable, justified and must comply with the principle of sound financial management, in particular regarding economy and efficiency; B. For unit costs: they must be calculated as follows: {amounts per unit set out in Annex 2 or calculated by the beneficiary in accordance with its usual cost accounting practices (see Article 6.2, Point A) multiplied by the number of actual units}; the number of actual units must comply with the following conditions: o the units must be actually used or produced in the period set out in Article 3; o the units must be necessary for implementing the action or produced by it, and o the number of units must be identifiable and verifiable, in particular supported by records and documentation (see Article 18); C. For flat-rate costs: they must be calculated by applying the flat-rate set out in Annex 2, and the costs (actual costs or unit costs[or lump-sum costs]) to which the flat-rate is applied must comply with the conditions for eligibility set out in this Article [;][.] D. [OPTION] if lump sum foreseen in Article 5.2: for lump sum costs: the eligible amount is equal to the amount set out in Annex 2, and 9

10 the corresponding tasks or parts of the action must have been properly implemented in accordance with Annex INTERNAL MONITORING In order to facilitate submission of bounden reports mentioned in the 1st chapter Reporting, all beneficiaries are required to adapt an internal monitoring of all activities assigned to the EURO-HEALTHY project. For this reason WP1 has prepared five templates to simplify the monitoring process. The templates are designed in the line with requirements stated in the Annotated Model Grant Agreement 2014 and Fit for Health 2.0. All templates were specifically prepared to assure consistency while carrying out the project. They also quicken the process of documentation, planning and organization. Internal monitoring of: Activities done Person moths used Budget spent Process: Gathering data through internal reporting Continuous check of: o Status quo o Analysis of deviations o Adapted planning o Counter-steering if necessary When/how often? Duration of the EURO-HEALTHY project: 36 months 2 official reporting periods to the EC: each 18 months and Final Report 6 internal reporting periods: each 6 months 2.1 Internal Technical Reports They are prepared by the coordinator and the beneficiaries together. 10

11 There are two main objectives of submitting the Technical Reports. First one includes controlling the project progress by informing what has already been achieved. For this reason real achievements will be compared with the objectives, deliverables and milestones described in Annex 1. Second, if any differences are recognized between work expected to be carried out as described in Annex 1 and that actually carried, explanation and justification will need to be reported WP Leader Report All WPs Leaders are required to submit a WP Leader Report to the coordinator every 6 months counting a starting point of the project as January 1 st, Main objective of the WP Leader Report includes monitoring technical progress and financial statement. Accordingly the performance of each WP will be assessed based on information provided in the report. Each WP Leader Report (see fig. 1) includes data regarding: Progress towards objectives and details for each task; Significant results; Deviations on tasks and corrective actions; Person month used and; Budget spent Below please find listed deadlines for submission internal and periodic WP Leaders Reports: 1 st Internal WP Leader Report 15 th July 2015 (for the period January-June 2015) 2 nd Internal WP Leader Report 15 th January 2016 (for the period July-December 2015) 3 rd Internal WP Leader Report 15 th July 2016 (for the period January-June 2016) 1 st Periodic WP Leader Report 15 th July 2016 (for the period January 2015 June 2016) 4 th Internal WP Leader Report 15 th January 2017 (for the period July December 2016) 5 th Internal WP Leader Report 15 th July 2017 (for the period January June 2017) 6 th Internal WP Leader Report 15 th January 2018 (for the period July-December 2017) 2 nd Periodic WP Leader Report 15 th January 2018 (for the period July 2016-December 2017) Final Report - 15 th January 2018 (for the period January 2015-December 2017) 11

12 Figure 1. Template for the WP Leader Report (internal and periodic). Please find a doc form of the WP Leader Report to download on the EURO-HEALTHY Intranet. 12

13 2.1.2 Deliverable Reports Each WP will produce the outputs referred as deliverables. Accordingly the EURO- HEALTHY will have 56 deliverables, equally distributed by the participants and the timeline of the project. Due to European Commission's lack of capacity to assess all original deliverables, the number of deliverables that need to be reported to the EC has decreased to 20. Nevertheless, in order to accomplish the original project's goal all deliverables need to be delivered and reported. The high complexity and interconnection of the project's tasks among WPs prevent removal of any of deliverables. Therefore, it is obligatory that each (official and non-official one) deliverable will be submitted together with the Deliverable Reports: doc form and excel (see fig. 2 and fig. 3). This is of particular importance to monitor, forecast and fix potential delays caused by delayed delivery of interconnected tasks. Deliverable Reports must be submitted by a lead beneficiary of an assigned deliverable. There are two Deliverable Reports. First one (fig. 2) includes data regarding: Description of the task; Description of the Deliverable; Implementation of work; Results; Sub-contracting Second one (fig. 3) refers to inclusion of progress/deviations, requesting provision of listed information: Achieved yes/no/in progress Forecast delivery date Justification of delay Each WP leader should do and send to the coordinator the deliverable report on date (in accordance with the timing and conditions set out in the Grant Agreement). 13

14 Figure 2. Template for the Deliverable Report-doc form (official and non-official one). Please find a doc form of the Deliverable Report to download on the EURO-HEALTHY Intranet. 14

15 Figure 3. Template for the Deliverable Report-excel form (official and non-official one). IMPORTANT: Please note, that provided template is a screenshot of a randomly chosen WP. An individual excel spreadsheet document is prepared for each WP separately and accessible via the EURO-HEALTHY Intranet Milestone Reports The PSG defines eight milestones for monitoring the evolution of the project (figure 4). These milestones will allow the project coordinator, the Project Steering Group and the European Commission to chart the research project and confirm that it is running as planned. Milestones correspond to the completion of key deliverables, allowing the next phase of the work to begin or be needed at intermediary points. For this reason it is of significant importance to monitor progress of milestones achievements. Responsibility of submission the Milestone Report is divided into two beneficiaries: UC and IST. Accordingly UC will act as the lead beneficiary for milestones: MS1, MS2, MS5, and MS6, while IST will take the responsibility of MS3, MS4, MS7 and MS8. 15

16 To successfully achieve each milestone, input of all WPs is essential. To clarify contribution of each WP to each milestone please see figure 5. Additionally in the prepared templates each WP excel document contains two spreadsheets called: WP[nr]Deliverables and WP[nr] Milestones. The Milestone spreadsheet (see fig. 4) indicates contribution of certain WP to assigned milestones. It is crucial that each WP will monitor its progress towards achievement of linked milestones. Two Milestone Reports include information regarding progress/deviations: Achieved yes/no Forecast delivery date Justification of delay Figure 4. Template of a Milestone Report including contribution of a specific WP. Please find an excel form of a Milestone Report for each WP to download on the EURO-HEALTHY Intranet. 16

17 Figure 5. Template of the Milestones Report to be submitted by UC/IST. Please find an excel form of the Milestones Report to download on the EURO-HEALTHY Intranet. 2.2 Internal Financial Monitoring A. Internal Financial Progress Report: Each beneficiary must send the financial progress report to monitor person months used and budget spent on the Euro-Healthy project tasks. For this reason WP1 has prepared an excel file for internal financial progress report. All partners are required to send this document to the coordinator every 6 months counting a starting point of the project as January 1 st, The project manager will send the file during the last month of each period. Financial Progress Report includes: Person months planned/used for each WP; 17

18 Budget spent for different categories of expenses (Direct personnel costs; Direct costs of Subcontracting; Other Direct Costs); Comments about some problems/deviations. Figure 6. Template of the Internal Financial Report to be submitted by each beneficiary. 18

19 Figure 6a. Template of the Internal Financial Report-zoom A. Figure 6b. Template of the Internal Financial Report-zoom B. Figure 6c. Template of the Internal Financial Report-zoom C. 19

20 B. Record time (Time-sheets): Each beneficiary is obliged to monitor and record time, person months used and budget spent on the Euro-Healthy project tasks. As mentioned in the section WP Leader Report, WP Leaders must submit listed information in addition with the timesheet. For this reason WP1 has prepared a template for time recording. The manual contains two templates: one proposed by the EU (see fig. 6) and second one advised by the EURO-HEALTHY project manager, which is designed by Coimbra University (see fig. 7). Please note that both templates are examples of an acceptable timesheet. It is not a mandatory model. Beneficiaries are entitled to use any other model of timesheet provided that it fulfils the minimum conditions and it contains at least the information detailed below. Time records should include: The title and number of the action, as specified in the GA The beneficiary s full name as specified in the GA The full name, date and signature of the person working for the action The number of hours per day declared for the action The supervisor s full name and signature A reference to the action tasks or work package described in Annex1, to easily verify the work carried out matches the work assigned A description of the activities carried out, to understand and show what work was carried out Source: AGA Annotated Model Grant Agreement: H2020 General MGA: V2.0.1 May 2015, p

21 Figure 7. Template for time recording provided by EU: basic version. Source: 21

22 Figure 8. Template for time recording provided by UC: detailed version. Please find an excel template of UC timesheet to upload on the EURO-HEALTHY Intranet. 22

23 Useful links 1. INFORMATION: Time recording for a Horizon 2020 Action: Annotated Model Grant Agreement H2020 Online Manual: FAQs on the Participant Portal 2. SUPPORT: Fit for Health 2.0: 23

URBACT III Programme Manual

URBACT III Programme Manual URBACT III Programme Manual Fact Sheet 2E Network Management Table of contents Fact Sheet 2E 0. Introduction... 1 1. Roles and responsibilities of Lead and Project Partners... 2 2. The legal framework...

More information

Negotiations feedback for successful project preparation. ERANIS workshop, 27.11.2007, Minsk

Negotiations feedback for successful project preparation. ERANIS workshop, 27.11.2007, Minsk Negotiations feedback for successful project preparation Negotiations procedure Feedback from the Commission on the project plan issues that need to be explained in more detail Request to formulate Annex

More information

H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi)

H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi) H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi) Version 1.0 9 June 2015 HISTORY OF CHANGES Version Publication date Changes 1.0 09.06.2015 Initial version 1 EUROPEAN COMMISSION

More information

Model Grant Agreement

Model Grant Agreement HORIZON HORIZON 2020 2020 Model Grant Agreement Horizon 2020 model Grant Agreement: Objectives Simplification Provisions Wording Flexibility To accommodate particularities Coherence Within H2020 and with

More information

Horizon 2020 Annotated Model Grant Agreements

Horizon 2020 Annotated Model Grant Agreements Horizon 2020 Annotated Model Grant Agreements General Model Grant Agreement and specific Model Grant Agreements (ERC, SME Instrument, ERA-NET Cofund, PCP-PPI Cofund, EJP Cofund, Framework Partnerships

More information

Financial management of the project, tools and reporting

Financial management of the project, tools and reporting Financial management of the project, tools and reporting Lead Partner Seminar 4th Call for Proposals Budapest, Hungary 11 December 2012 SEE Joint Technical Secretariat Financial management of the project,

More information

Administrative forms (Part A) Project proposal (Part B)

Administrative forms (Part A) Project proposal (Part B) Ref. Ares(2015)2346168-04/06/2015 Project Grants (HP-PJ) Administrative forms (Part A) Project proposal (Part B) Version 2.0 05 June 2015 Disclaimer This document is aimed at informing potential applicants

More information

Guide to Financial Issues relating to FP7 Indirect Actions

Guide to Financial Issues relating to FP7 Indirect Actions Guide to Financial Issues relating to FP7 Indirect Actions Version 3/10/2014 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are

More information

South East Europe (SEE) Implementation Manual

South East Europe (SEE) Implementation Manual South East Europe (SEE) Implementation Manual Version 5.0 Date of approval (v1.2): 8 th May 2009 1 st amendment (v2.1): 7th July 2009 2 nd amendment (v3.1): 21 st January 2011 3 rd amendment (v3.2): 27

More information

Model Grant Agreement

Model Grant Agreement HORIZON HORIZON 2020 2020 Model Grant Agreement Horizon 2020 model Grant Agreement: Objectives Simplification Provisions Wording Flexibility To accommodate particularities Coherence Within H2020 and with

More information

Project management in FP7. Gorgias Garofalakis ETAT S.A.

Project management in FP7. Gorgias Garofalakis ETAT S.A. Project management in FP7 Gorgias Garofalakis ETAT S.A. The whole process EU FP7 Project Project idea Proposal writing Evaluation Negotiations Project implementation Contact with partners after the evaluation

More information

EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO)

EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO) EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) Director H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO) Introductory remark MSC-IF Mono deviates from

More information

Reporting transnational access and service activity costs. Version May 2011

Reporting transnational access and service activity costs. Version May 2011 Reporting transnational access and service activity costs Version May 2011 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are not

More information

Model Grant Agreement FINANCIAL ISSUES. Communication Campaign, Prague, 28 April 2015

Model Grant Agreement FINANCIAL ISSUES. Communication Campaign, Prague, 28 April 2015 HORIZON HORIZON 2020 2020 Model Grant Agreement FINANCIAL ISSUES Communication Campaign, Prague, 28 April 2015 Table of Contents 1. FP7 : Lessons learned 2. H2020: Model Grant Agreement 3. Cost Categories

More information

Guide for Applicants. Call for Proposal:

Guide for Applicants. Call for Proposal: Guide for Applicants Call for Proposal: COSME Work Programme 2014 TABLE OF CONTENTS I. Introduction... 3 II. Preparation of the proposal... 3 II.1. Relevant documents... 3 II.2. Participants... 4 II.2.1.

More information

The Marie Curie Actions FP7 Financial Guidelines

The Marie Curie Actions FP7 Financial Guidelines The Marie Curie Actions FP7 Financial Guidelines SPECIFIC PROVISIONS RELATED TO MARIE CURIE ACTIONS FINANCED UNDER THE FP7 "PEOPLE" PROGRAMME Part 3: projects funded in the 2007-2011 Work Programmes calls

More information

Proposal template (technical annex) Health, demographic change and wellbeing Two-stage Research and Innovation actions Innovation actions

Proposal template (technical annex) Health, demographic change and wellbeing Two-stage Research and Innovation actions Innovation actions Proposal template (technical annex) Health, demographic change and wellbeing Two-stage Research and Innovation actions Innovation actions Note: This is for information only. The definitive templates to

More information

Guide for ERC Grant Holders Part II

Guide for ERC Grant Holders Part II EUROPEAN RESEARCH COUNCIL Guide for ERC Grant Holders Part II Reference Manual on Financial Management and Administration of the ERC Grants Starting and advanced grants Version 1-24/06/2008 Disclaimer:

More information

Guide to Financial Issues relating to FP7 Indirect Actions

Guide to Financial Issues relating to FP7 Indirect Actions Guide to Financial Issues relating to FP7 Indirect Actions Version 28/02/2011 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are

More information

Horizon 2020. Proposal template for: H2020 Widespread 2014 1 Teaming

Horizon 2020. Proposal template for: H2020 Widespread 2014 1 Teaming Horizon 2020 Proposal template for: H2020 Widespread 2014 1 Teaming Framework Partnership Agreement (FPA) and Coordination and support action (CSA) 1 This proposal template has been designed to ensure

More information

Frequently Asked Questions

Frequently Asked Questions SME Instrument Frequently Asked Questions Contents FOR APPLICANTS A. Eligibility and type of SMEs targeted... 2 B. Preparing your application and submitting your proposal... 4 C. Evaluation of your proposal...

More information

Project reports and reviews in FP6

Project reports and reviews in FP6 Project reports and reviews in FP6 Zoe Ketselidou IST Operations NCP meeting Brussels, 8 March 2005 Periodic reporting At the end of each reporting period 1. Periodic activity report (overview of progress)

More information

Version 0.3 25 September 2014

Version 0.3 25 September 2014 Guide for Grant Agreement Preparation Version 0.3 25 September 2014 Disclaimer: This document is aimed at assisting applicants and beneficiaries for Horizon 2020 funding. Its purpose is to explain the

More information

Guide for Applicants COSME calls for proposals 2015

Guide for Applicants COSME calls for proposals 2015 Guide for Applicants COSME calls for proposals 2015 CONTENTS I. Introduction... 3 II. Preparation of the proposal... 3 II.1. Relevant documents... 3 II.2. Participants... 4 Consortium coordinator... 4

More information

SESAR 2020 EXPLORATORY RESEARCH INFO DAY PROPOSALS SUBMISSION & EVALUATION & PROGRAMME MANAGEMENT REQUIREMENTS

SESAR 2020 EXPLORATORY RESEARCH INFO DAY PROPOSALS SUBMISSION & EVALUATION & PROGRAMME MANAGEMENT REQUIREMENTS SESAR 2020 EXPLORATORY RESEARCH INFO DAY PROPOSALS SUBMISSION & EVALUATION & PROGRAMME MANAGEMENT REQUIREMENTS ALESSANDRO PRISTER PROGRAMME MANAGER ER, SJU ER CALL COORDINATOR List of topics covered Call

More information

From the light to the full application form focus on work plan

From the light to the full application form focus on work plan Lead Applicant Training, Prague, 20 October 2015 From the light to the full application form focus on work plan Monika Schönerklee-Grasser, Head of JS Evaluation and Monitoring Unit Full application form

More information

Guide for reporting, documentation of activities and financial management of grants, 2016

Guide for reporting, documentation of activities and financial management of grants, 2016 Nordplus Adult Guide for reporting, documentation of activities and financial management of grants, 2016 All beneficiaries of the Nordplus Adult programme must submit a final report to the programme administration

More information

Project reporting in FP6

Project reporting in FP6 Guidance notes for Integrated Projects, Networks of Excellence, Specific Targeted Research or Innovation Projects, Coordination Actions, Specific Support Actions, Co-operative Research Projects and Collective

More information

Guidance on Joint Action Plans

Guidance on Joint Action Plans EGESIF_14-0038-01 Guidance on Joint Action Plans Structural and Cohesion Funds 2014-20 Social Europe EGESIF_14-0038-01 Guidance on Joint Action Plans Structural and Cohesion Funds 2014-20 European Commission

More information

Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013

Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013 EUROPEAN COMMISSION European Social Fund Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013 Version of June 2015 Please consult http://ec.europa.eu/esf/sco

More information

Proposal template (Technical annex) Research and Innovation actions

Proposal template (Technical annex) Research and Innovation actions Proposal template (Technical annex) Research and Innovation actions Please follow the structure of this template when preparing your proposal. It has been designed to ensure that the important aspects

More information

FP7 Project reporting. FP7 INCO National Contact Points Meeting 9 June 2010 - Athens Anne Mandenoff - European Commission - RTD A.

FP7 Project reporting. FP7 INCO National Contact Points Meeting 9 June 2010 - Athens Anne Mandenoff - European Commission - RTD A. FP7 Project reporting FP7 INCO National Contact Points Meeting 9 June 2010 - Athens Anne Mandenoff - European Commission - RTD A.6 Reference documents 1 Model grant agreement - Grant Agreement (GA): Article

More information

SME INSTRUMENT PHASE 1 - FINAL REPORT SME Instrument Phase 1 FINAL REPORT

SME INSTRUMENT PHASE 1 - FINAL REPORT SME Instrument Phase 1 FINAL REPORT SME INSTRUMENT PHASE 1 - FINAL REPORT SME Instrument Phase 1 FINAL REPORT Grant Agreement number: Acronym: Title: Type of the action: SME Instrument Phase 1 Date of latest version of Annex I against which

More information

The Terms of Reference should be completed by the Beneficiary and be agreed with the Auditor

The Terms of Reference should be completed by the Beneficiary and be agreed with the Auditor ANNEX V-A FORM - TERMS OF REFERENCE FOR THE CERTIFICATE OF FINANCIAL STATEMENTS TABLE OF CONTENTS TERMS OF REFERENCE FOR AN INDEPENDENT REPORT OF FACTUAL FINDINGS ON COSTS CLAIMED UNDER A ERC GRANT AGREEMENT

More information

SPECIFIC PROGRAMME "CRIMINAL JUSTICE" (2007-2013) CALL FOR PROPOSALS JUST/2012/JPEN/AG/EJT Action grants

SPECIFIC PROGRAMME CRIMINAL JUSTICE (2007-2013) CALL FOR PROPOSALS JUST/2012/JPEN/AG/EJT Action grants EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE SPECIFIC PROGRAMME "CRIMINAL JUSTICE" (2007-2013) CALL FOR PROPOSALS JUST/2012/JPEN/AG/EJT Action grants 1. INTRODUCTION On 12 February 2007, the Council

More information

Frequently asked questions. FP7 Financial Guide

Frequently asked questions. FP7 Financial Guide Frequently asked questions FP7 Financial Guide Budgetary matters Eligible costs of a project What are the criteria for determining whether the costs of a project are eligible? First of all, costs must

More information

1st call for proposals: Administrative and submission procedures Infoday La Valeta, Malta, June 17th 2015

1st call for proposals: Administrative and submission procedures Infoday La Valeta, Malta, June 17th 2015 1st call for proposals: Administrative and submission procedures Infoday La Valeta, Malta, June 17th 2015 SIZE OF THE PARTNERSHIP As a minimum requirement, the partnership must involve: at least 4 financing

More information

FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues

FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues National Documentation Center (EKT/NHRF) FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues Maria Samara, Administrative

More information

Guidance notes and templates for Project Technical Review involving Independent Expert(s)

Guidance notes and templates for Project Technical Review involving Independent Expert(s) Guidance notes and templates for Project Technical Review involving Independent Expert(s) FP7 Collaborative Projects, Networks of Excellence, Coordination and Support Actions Version 18/12/2007 Disclaimer

More information

HORIZON 2020. Rules for Participation and Dissemination Simplification and Innovation. Alexandros IATROU DG RTD K.7

HORIZON 2020. Rules for Participation and Dissemination Simplification and Innovation. Alexandros IATROU DG RTD K.7 THE EU FRAMEWORK PROGRAMME FOR RESEARCH AND INNOVATION HORIZON 2020 Rules for Participation and Dissemination Simplification and Innovation Alexandros IATROU DG RTD K.7 Rules for participation: Three main

More information

Project deliverables and reviews

Project deliverables and reviews Project deliverables and reviews Angelo Marino REA.S.3 3 May 2012 Reporting requirements Periodic report (within 60 days after end of each reporting period) Final report (within 60 days after end of project)

More information

Template for essential information to be provided for proposals including clinical trials / studies / investigations

Template for essential information to be provided for proposals including clinical trials / studies / investigations Template for essential information to be provided for proposals including clinical trials / studies / investigations Document history Version 2016callsV1 September 2015 Modifications (compared to previous

More information

EUROPEAN COMMISSION INFORMATION SOCIETY AND MEDIA DIRECTORATE-GENERAL. [title of the project] Grant Agreement No ICT PSP GRANT AGREEMENT

EUROPEAN COMMISSION INFORMATION SOCIETY AND MEDIA DIRECTORATE-GENERAL. [title of the project] Grant Agreement No ICT PSP GRANT AGREEMENT EUROPEAN COMMISSION INFORMATION SOCIETY AND MEDIA DIRECTORATE-GENERAL [title of the project] Grant Agreement No ICT PSP GRANT AGREEMENT Version 3, 20/01/2012 GRANT AGREEMENT NO The European Union ( the

More information

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME GUIDANCE NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP VERSION 1 APPROVED

More information

Guide to Financial Issues for Cleansky GAPs

Guide to Financial Issues for Cleansky GAPs Guide to Financial Issues for Cleansky GAPs Version of 16/01/2012 adopted by the Commission and subsequently adapted for the Clean Sky Joint Undertaking on 08/05/2012 Disclaimer This guide is aimed at

More information

Administration and Finances under H2020 in MSCA Helsinki 21/4/2015

Administration and Finances under H2020 in MSCA Helsinki 21/4/2015 Administration and Finances under H2020 in MSCA Helsinki 21/4/2015 Marcela Groholova Research Executive Agency Overview 1. EU contribution 2. Eligible costs 3. Cost categories 4. Parental and maternity

More information

EMPIR Reporting Guidelines Part 0 Guide to the parts

EMPIR Reporting Guidelines Part 0 Guide to the parts Part 0 Guide to the parts EMPIR Reporting Guidelines Part 0 Guide to the parts EURAMET MSU, Hampton Road, Teddington, Middlesex, TW11 0LW, UK Phone: +44 20 8943 6666 Email: msu@npl.co.uk msu.euramet.org

More information

D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E

D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E D 1.1 Document identifier: V-Must.net - D1.1 Definition of quality control procedure V.1.1 Due Date of Delivery to EC End of Month

More information

Frequently Asked Questions to the Marie Curie Actions Financial Guidelines

Frequently Asked Questions to the Marie Curie Actions Financial Guidelines Frequently Asked Questions to the Marie Curie Actions Financial Guidelines Updated 26/06/2012 Table of contents Q1: FOR CATEGORIES A-C (1-2 AS OF WP2011), WHICH AMOUNT HAS TO BE DECLARED IN THE FORM C

More information

Project management: tips and tools for monitoring. 22.01.2015 Brussels, Belgium Ines Haberl Austrian Research Promotion Agency

Project management: tips and tools for monitoring. 22.01.2015 Brussels, Belgium Ines Haberl Austrian Research Promotion Agency Project management: tips and tools for monitoring your project 22.01.2015 Ines Haberl Austrian Research Promotion Agency Overview Project-internal monitoring processes Project management tools Recommendations

More information

Rules and Procedures in the new Programme 14-20

Rules and Procedures in the new Programme 14-20 Rules and Procedures in the new Programme 14-20 OBJECTIVES Overview of main rules and procedures to be followed Main novelties compared to the 2007-2013 period Risky points Information to be completed

More information

CEF Energy model grant agreement

CEF Energy model grant agreement CEF Energy model grant agreement Main features, financial and reporting conditions CEF Energy Info Day Delphine Silhol - Legal Adviser, INEA 16 March 2015 Background Single model grant agreement for the

More information

GRANT AGREEMENT. NUMBER 674463 i2d

GRANT AGREEMENT. NUMBER 674463 i2d EUROPEAN COMMISSION Executive Agency for Small and Medium-sized Enterprises (EASME) Director GRANT AGREEMENT NUMBER 674463 i2d This Agreement ( the Agreement ) is between the following parties: on the

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD ABDUCTION ALERT MECHANISMS SPECIFIC ACTION GRANTS

EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD ABDUCTION ALERT MECHANISMS SPECIFIC ACTION GRANTS EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE Directorate A: Civil justice Unit A.4: Programme management SPECIFIC PROGRAMME "DAPHNE III (2007 2013) CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD

More information

Administrative + Management Aspects. EU - Framework Programme 7. Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.

Administrative + Management Aspects. EU - Framework Programme 7. Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05. Administrative + Management Aspects EU - Framework Programme 7 Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.2008 Dr. Jürgen Ertel Department Program Planing and Management Head of Project

More information

H2020 rules for participation, new instruments, evaluation criteria

H2020 rules for participation, new instruments, evaluation criteria H2020 rules for participation, new instruments, evaluation criteria Disclaimer : H2020 Regulations are not yet adopted by the legislator. Any information contained in this presentation is legally not binding

More information

PROPOSAL ACRONYM - ETN / EID / EJD (delete as appropriate and include as header on each page) START PAGE MARIE SKŁODOWSKA-CURIE ACTIONS

PROPOSAL ACRONYM - ETN / EID / EJD (delete as appropriate and include as header on each page) START PAGE MARIE SKŁODOWSKA-CURIE ACTIONS START PAGE MARIE SKŁODOWSKA-CURIE ACTIONS Innovative Training Networks (ITN) Call: H2020-MSCA-ITN-2015 PART B PROPOSAL ACRONYM This proposal is to be evaluated as: [ETN] [EID] [EJD] [delete as appropriate]

More information

Erasmus+ General Information. Application Form Call: 2015. KA2 Cooperation and Innovation for Good Practices

Erasmus+ General Information. Application Form Call: 2015. KA2 Cooperation and Innovation for Good Practices General Information This application form consists of the following main sections: - Context: this section asks for general information about the type of project proposal you want to submit; - Participating

More information

Funding excellence in innovation. Guidelines for declaration of changes. Version 1.0

Funding excellence in innovation. Guidelines for declaration of changes. Version 1.0 The Eurostars TM Programme Funding excellence in innovation Guidelines for declaration of changes Version 1.0 The Eurostars Programme is a joint initiative of EUREKA and the European Community This document

More information

Guidance notes and templates for Project Technical Review involving Independent Expert(s)

Guidance notes and templates for Project Technical Review involving Independent Expert(s) Guidance notes and templates for Project Technical Review involving Independent Expert(s) FP7 Collaborative Projects (CP), Networks of Excellence, Coordination and Support Actions (CSA), CP-CSA, ERA-NET,

More information

Horizon 2020 Secure Societies

Horizon 2020 Secure Societies Horizon 2020 Secure Societies Angelo MARINO Head of Unit, Security Research European Commission Research Executive Agency NOT LEGALLY BINDING 2013 Where we come from: FP7-Security R&D (2007-2013): EUR

More information

BUDGET HEADING 04.03.03.03 INFORMATION, CONSULTATION AND PARTICIPATION OF REPRESENTATIVES OF UNDERTAKINGS CALL FOR PROPOSALS

BUDGET HEADING 04.03.03.03 INFORMATION, CONSULTATION AND PARTICIPATION OF REPRESENTATIVES OF UNDERTAKINGS CALL FOR PROPOSALS EUROPEAN COMMISSION Employment, Social Affairs and Inclusion DG Employment and Social Legislation, Social Dialogue Labour Law BUDGET HEADING 04.03.03.03 INFORMATION, CONSULTATION AND PARTICIPATION OF REPRESENTATIVES

More information

Grant Agreement Implementation and Reporting under H2020 in MSCA

Grant Agreement Implementation and Reporting under H2020 in MSCA Grant Agreement Implementation and Reporting under H2020 in MSCA Helsinki 21/4/2015 Marcela Groholova Research Executive Agency MSCA Date: in 12 pts A - Grant Agreement Implementation Structure of the

More information

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS MATERIALS PREPARED BY THE WORKING GROUP ON CERTIFICATE ON THE METHODOLOGY UNDER FP7: DG RESEARCH AND INNOVATION DG

More information

Research proposal (Part B)

Research proposal (Part B) Research and Innovation Actions (RIA) Innovation Actions (IA) Research proposal (Part B) Version 1.1 3 November 2014 Disclaimer This document is aimed at informing potential applicants for Horizon 2020

More information

Guide for Applicants

Guide for Applicants Third EU Health Programme (2014-2020) Project Grants (HP-PJ) Guide for Applicants Version 1.0 06 June 2014 Disclaimer This document is aimed at informing potential applicants for 3 rd EU Health Programme

More information

Webinar on third parties in Horizon 2020

Webinar on third parties in Horizon 2020 Webinar on third parties in Horizon 2020 03.02.2016 Martin Baumgartner FFG OVERVIEW What is a third party in Horizon 2020? Types of third parties How to involve contract research organisations (CROs) Third

More information

GUIDE FOR APPLICANTS

GUIDE FOR APPLICANTS European Commission THE SEVENTH FRAMEWORK PROGRAMME The Seventh Framework Programme focuses on Community activities in the field of research, technological development and demonstration (RTD) for the period

More information

Guide for ERC Grant Holders PART I

Guide for ERC Grant Holders PART I EUROPEAN RESEARCH COUNCIL Guide for ERC Grant Holders PART I GENERAL GUIDANCE NOTES Starting and advanced grants Version 1 24/06/2008 Disclaimer: This Guide aims to assist grant holders, whether individual

More information

GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING

GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING The aim of this guide is to give a summary of the main points of the administrative and financial processes governing

More information

Periodic Technical Report (parts A and B) Periodic Financial Report. Version 1.0 15 July 2015

Periodic Technical Report (parts A and B) Periodic Financial Report. Version 1.0 15 July 2015 Periodic Report Template (RIA, IA, CSA, SME instrument, MCSA) Periodic Technical Report (parts A and B) Periodic Financial Report Version 1.0 15 July 2015 Disclaimer This document is aimed at informing

More information

COMMISSION DECISION. of XXX

COMMISSION DECISION. of XXX EUROPEAN COMMISSION Brussels, XXX [ ](2014) XXX draft COMMISSION DECISION of XXX authorising the use of reimbursement on the basis of unit costs for actions requiring the conduct of clinical studies under

More information

Project Execution Guidelines for SESAR 2020 Exploratory Research

Project Execution Guidelines for SESAR 2020 Exploratory Research Project Execution Guidelines for SESAR 2020 Exploratory Research 04 June 2015 Edition 01.01.00 This document aims at providing guidance to consortia members on the way they are expected to fulfil the project

More information

Guide for Applicants 2015

Guide for Applicants 2015 Third EU Health Programme (2014-2020) Project Grants (HP-PJ-2015) Guide for Applicants 2015 11 June 2015 Disclaimer This document is aimed at informing potential applicants for 3 rd EU Health Programme

More information

FREQUENTLY ASKED QUESTIONS Version November 2011

FREQUENTLY ASKED QUESTIONS Version November 2011 FREQUENTLY ASKED QUESTIONS Version November 2011 Composition of a Comenius Regio Partnership Which types of institutions are eligible to participate in Comenius Regio? Comenius Regio partnerships are bilateral

More information

PROGRAMME MANUAL 3. APPLICATION STAGE

PROGRAMME MANUAL 3. APPLICATION STAGE PROGRAMME MANUAL 3. APPLICATION STAGE 3. APPLICATION STAGE...1 Introduction...3 3.1. Application procedure...6 3.1.1. Application Procedure for modular projects...6 3.1.2. Application Procedure for horizontal

More information

PRIORITY 2 INFORMATION SOCIETY TECHNOLOGIES (IST) FREQUENTLY ASKED QUESTIONS on Project management in FP6

PRIORITY 2 INFORMATION SOCIETY TECHNOLOGIES (IST) FREQUENTLY ASKED QUESTIONS on Project management in FP6 PRIORITY 2 INFORMATION SOCIETY TECHNOLOGIES (IST) FREQUENTLY ASKED QUESTIONS on Project management in FP6 March 2005 Evolution of the consortium 1. If a sum has been allocated within the budget for new

More information

SPECIFIC AGREEMENT No./.. 1 ON A GRANT FOR AN ACTION

SPECIFIC AGREEMENT No./.. 1 ON A GRANT FOR AN ACTION ANNEX II MODEL SPECIFIC GRANT AGREEMENT FOR AN ACTION SPECIFIC AGREEMENT No./.. 1 ON A GRANT FOR AN ACTION This specific agreement ("the agreement") is concluded between: The European Union ("the Union"),

More information

Proposal Negotiation. a guide. Constantine Vaitsas, vaitsas@help-forward.gr

Proposal Negotiation. a guide. Constantine Vaitsas, vaitsas@help-forward.gr Proposal Negotiation a guide Constantine Vaitsas, vaitsas@help-forward.gr Presentation Outline Proposal Time Scale Negotiation Process Legal Negotiations Financial Negotiations Technical Negotiations NEF

More information

Full-Cost Accounting and Certification Modalities in FP7

Full-Cost Accounting and Certification Modalities in FP7 Prague, 30 March 2009 Full-Cost Accounting and Certification Modalities in FP7 Philippe Coenjaarts European Commission DG Research Overview of presentation Accountability context FP7 Accounting modalities

More information

Disclaimer. The present document is an internal document that outlines the procedure as currently envisaged by the Commission.

Disclaimer. The present document is an internal document that outlines the procedure as currently envisaged by the Commission. Disclaimer The present document is an internal document that outlines the procedure as currently envisaged by the Commission. It is made available only for advance information and will be integrated into

More information

Guidelines for reporting. for Accompanying Measures. implemented as. Specific Support Action

Guidelines for reporting. for Accompanying Measures. implemented as. Specific Support Action SIXTH FRAMEWORK PROGRAMME Research Infrastructures Action Guidelines for reporting for Accompanying Measures implemented as Specific Support Action This document can be found on the INTERNET at the following

More information

PROJECT MANAGEMENT PLAN HEKLA

PROJECT MANAGEMENT PLAN HEKLA MANAGEMENT PLAN HEKLA CONTENT 1. Introduction --------------------------------------------------------------------------- 0 2. Project organisation and management --------------------------------------------

More information

GUIDANCE NOTES ON PROJECT REPORTING

GUIDANCE NOTES ON PROJECT REPORTING GUIDANCE NOTES ON PROJECT REPORTING Career Integration Grants (CIG) International Reintegration Grants (IRG) European Reintegration Grants (ERG) Marie Curie Actions http://ec.europa.eu/msca Version March

More information

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government of the Republic of Poland

More information

Guillem Bernat (RAPITA) Communication, Deliverable, Dissemination, Publication, Reporting

Guillem Bernat (RAPITA) Communication, Deliverable, Dissemination, Publication, Reporting D5.2 Project Handbook Document Information Contract Number 249100 Project Website Contractual Deadline Dissemination Level Nature Author Contributors Reviewer Keywords www.proartis-project.eu PM04 Public

More information

28 September 2007 LIFELONG LEARNING PROGRAMME GUIDE FOR APPLICANTS: ADMINISTRATIVE AND FINANCIAL RULES

28 September 2007 LIFELONG LEARNING PROGRAMME GUIDE FOR APPLICANTS: ADMINISTRATIVE AND FINANCIAL RULES 28 September 2007 LIFELONG LEARNING PROGRAMME GUIDE FOR APPLICANTS: ADMINISTRATIVE AND FINANCIAL RULES 1 Table of Content 2 1. GENERAL PROVISIONS This document contains supplementary information to the

More information

GUIDE FOR APPLICANTS SUPPORT FOR EUROPEAN COOPERATION PROJECTS

GUIDE FOR APPLICANTS SUPPORT FOR EUROPEAN COOPERATION PROJECTS Education, Audiovisual and Culture Executive Agency Culture Unit GUIDE FOR APPLICANTS SUPPORT FOR EUROPEAN COOPERATION PROJECTS CREATIVE EUROPE (2014-2020) CULTURE SUB-PROGRAMME VERSION: July 2014 Disclaimer:

More information

Calculation of Staff costs

Calculation of Staff costs Fact sheet no. 01/2011 Calculation of Staff costs 0. Foreword Within CENTRAL EUROPE, the costs definitively paid by partner institutions for the personnel involved in project activities are eligible with

More information

O.1.2.5 General Reporting Obligations

O.1.2.5 General Reporting Obligations 3CE335P4 O.1.2.5 General Reporting Obligations Workpackage 1 Action 1.2 Author Version LP V1 Index 1. Introduction...3 1.2 Reporting and payment flows...3 2. Progress Report...4 3. Reporting procedure...5

More information

RFCS Information Package 2015

RFCS Information Package 2015 RESEARCH AND INNOVATION Research Fund for Coal and Steel RFCS Information Package 2015 Volume I Proposal preparation and submission V18.07.2015 Table of contents 1 INTRODUCTION 5 2 FUNDING OPPORTUNITIES

More information

GUIDE FOR FILLING IN THE APPLICATION FORM. Central Baltic Programme 2014-2020. Version 2.0 (21.8.2015)

GUIDE FOR FILLING IN THE APPLICATION FORM. Central Baltic Programme 2014-2020. Version 2.0 (21.8.2015) GUIDE FOR FILLING IN THE APPLICATION FORM Central Baltic Programme 2014-2020 Version 2.0 (21.8.2015) Contents INTRODUCTION... 2 Small and regular projects... 2 The emonitoring System... 2 Support when

More information

Application requirements

Application requirements Application requirements SBogoly@fgsz.hu CEF Energy Info Day Olga Sihmane - CEF Programme and Call Coordinator, INEA 16 March 2015 Before starting the application: Action vs PCI Types of actions Content

More information

The Marie Curie Actions FP7 Financial Guidelines

The Marie Curie Actions FP7 Financial Guidelines The Marie Curie Actions FP7 Financial Guidelines. These guidelines complement and should be considered in conjunction with the FP7 Guide on Financial Issues which is available for download at ftp://ftp.cordis.europa.eu/pub/fp7/docs/financialguide_en.pdf.

More information

Fifth Annual report Guidelines

Fifth Annual report Guidelines 1 www.seadatanet.org Fifth Annual report Guidelines The annual report includes : - scientific and technical report - financial report 1. Scientific and technical Report If not yet done: send the requested

More information

Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations

Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations Marlen Damjanović, PhD National Contact Point Health & ICT Euresearch Head Office marlen.damjanovic@euresearch.ch phone:

More information

In2LifeSciences Implementation Guidelines Insight and Collaboration Incentives 4 th Call

In2LifeSciences Implementation Guidelines Insight and Collaboration Incentives 4 th Call In2LifeSciences Implementation Guidelines Insight and Collaboration Incentives 4 th Call IN2LifeSciences - Guidelines for insight and collaboration incentive projects 1. Project execution The insight or

More information

Internal Communications Channels

Internal Communications Channels Learning Analytics Community Exchange Internal Communications Channels Public Deliverable D9.1 By: Hendrik Drachsler, Maren Scheffel Published: 30 April 2014 Keywords: management, internal communications,

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014 the European Economic Area (EEA) Financial Mechanism 2009-2014 adopted by the EEA Financial Mechanism Committee pursuant to Article 8.8 of Protocol 38b to the EEA Agreement on 13 January 2011 and confirmed

More information

Administrative forms (Part A) Research proposal (Part B)

Administrative forms (Part A) Research proposal (Part B) Research and Innovation actions Innovation actions Administrative forms (Part A) Research proposal (Part B) 1 April 2015 Disclaimer This document is aimed at informing potential applicants for Horizon

More information