Project management in FP7. Gorgias Garofalakis ETAT S.A.
|
|
|
- Colin Leonard
- 9 years ago
- Views:
Transcription
1 Project management in FP7 Gorgias Garofalakis ETAT S.A.
2 The whole process EU FP7 Project Project idea Proposal writing Evaluation Negotiations Project implementation
3 Contact with partners after the evaluation The coordinator should inform the partners on the good news and the bad news message immediately sending the Evaluation Summary Report in attachment If the ESR is positive: project may be invited to negotiations with the European Commission partners will need to answer the ESR s comments (technical and financial)
4 Negotiations: Overview Letter of invitation Technical and financial/legal negotiations Legal verification Consortium Agreement Completion of negotiations & Grant Agreement signature Contract negotiations
5 Invitation to negotiation Letter of invitation to negotiations contains: Negotiation Mandate - contains requests for clarifications & changes, max. Community contribution, proposed duration Evaluation Summary Report Ethical Review Report (if applicable) - contains Requirements, Recommendations, Follow up GPFs (Grant Agreement Preparation Forms) Deadlines for negotiations are given!
6 Content of negotiations Technical Adapt work plan, deliverables, Set or modify milestones or other indicators Financial Review total funding and funding per partner and method for calculating indirect costs Review subcontracting Determine pre-financing Verify financial capacity Legal Determine special clauses Agree on the start date of the project Verify the legal data per partner
7 Consortium agreement (CA) It provides the legal basis for the relationship and responsibilities between the partners with regard to: - Technical management, allocation of tasks and deliverables - Organisation of the consortium, procedures, confidentiality - Budget and finances - Intellectual property rights - Settling disputes, change of the consortium, termination Mandatory in FP7, unless otherwise provided in the call Complements the Grant Agreement (but does not prevail over it) It is a private agreement, concluded between the participants (not involving the EC)
8 Negotiations Consortium provides all needed documents Agreement on all technical, financial and legal points The Coordinator and each partner sign a Form A (accession to the GA) Finalisation of the Grant Agreement (GA) The EC and the Coordinator sign the GA The project starts
9 Tasks in project management Communication Decision-making Project meetings Conflict management Managing finances Understanding the concepts Monitoring expenses and cash-flows Reporting Monitoring work Check work towards deliverables Reporting IPR Optimise exploitation Apply the provisions of the CA
10 Communication within the consortium Good communication is essential for project success Types of communication: Personal, through meetings Remote, via , letters, web-software, etc. The project work is the focal point Potential obstacles: Cultural differences Misunderstandings in the work plan Partner indifference
11 Communication: Project meetings They cost a lot BUT are necessary and effective! They should be: arranged well in advance have a clear agenda and clear objectives well attended by all partners, if possible having adequate time for discussion (and sufficient breaks!) properly chaired and minuted The kick-off meeting is particularly important! The Project Officer from the EC may attend
12 Communication: Decision making Everyone taking part in every decision Problems and delays in taking decisions Partner excluded from decision-making Lack of commitment to the project The consortium should use a balanced and efficient decision-making process
13 Communication: Conflict management Prevention: - Set and protect democratic structures - Clarify each partner`s position ( Silence is not agreement ) Measures: - Depersonalize the problem, clarify the basis - Coordinator as mediator - Discussion with concerned parties in private - Discussion at the Project Meeting - If everything else fails, refer to the CA
14 Problems and conflicts Frequently encountered: Serious delays on deadline Overspending Low quality of personnel competences/ low quality of work Conflicts about intellectual property rights Change of personnel/ loss of contractor Special cases: Inadequate effort Change of interest Solutions: Discussion, diplomacy Termination of the contact, Change of partners Discussion, consortium-wide
15 Finances: Key concepts The EC reimburses actual eligible costs The eligible costs are direct + indirect Partners can report indirect cost as: Actual indirect cost [available to all] Flat rate: a percentage of direct costs (excluding subcontracting): Transitional flat rate (60%) [non-profit public bodies, secondary and higher education establishments, research organisations, SMEs unable to identify the real indirect cost for the project] Standard flat rate (20%) [available to all] Partners from ICPC can opt for Lump sum amounts Conditions may be set in the Work Programme/ call for proposals
16 Lump sum budgeting Lump sum contribution per country income group These amounts must be multiplied by the total number of person-years for the project requested by the ICPC legal entity. The lump sum is deemed to cover all costs of a participant from an ICPC country (personnel, travel, equipment, consumables, subcontracts and indirect costs).
17 Activities financed in FP7 projects Research and technological development activities Demonstration activities, designed to prove the viability of new technologies that offer a potential economic advantage Management activities linking together all the project components and maintaining communications with the Commission Any other activities such as: dissemination, support, coordination of research, training
18 Maximum funding rates In Cooperation projects Organisation Public non profit, research, education and SMEs others Research 75 % 50 % Activity Demonstration Training Management 50 % 100 % 100 % 50 % 100 % 100 % Others 100 % 100 %
19 Maximum reimbursement rates of eligible costs Research and technological development (*) Demonstration activities Training activities Management of the consortium activities Other activities (**) Network of excellence 100% 100% Collaborative project 50% 75% (***) 50% 100% 100% 100% Research project for the benefit of specific groups (SMEs) 50% 75% (***) 50% 100% 100% 100% Coordination and support action 100% (****) 100% (****) 100% (****) (*) Research and technological development includes operational activities directly related to the protection of foreground and coordination of research activities. (**) Other activities means any "specific activity" covered by Annex I. (***) For beneficiaries that are non profit public bodies, secondary and higher education establishments, research organisations and SMEs (****) The reimbursement of indirect eligible costs, in the case of coordination and support actions, may reach a maximum 7% of the direct eligible costs, excluding the direct eligible costs for subcontracting and the costs of reimbursement of resources made available by third parties which are not used on the premises of the beneficiary.
20 Project funding EUROPEAN COMMISSION COORDINATOR Partner 2 Partner 3 Partner N
21 Prefinancing One prefinancing: 160% of the average EC funding per period transferred to Coordinator 45 days after entry into force of the GA Coordinator distributes prefinancing: once minimum number of beneficiaries have signed Form A only to those who have signed and returned Form A 5% of EC total grant is transferred to Guarantee Fund it is kept aside (risk limiting mechanism) and will be recovered at the end of the project
22 Further payments Interim payments Transferred by EC after approval of submitted periodic reports (max. 105 days from the end of the period) Calculated on the basis of declared costs and on reimbursement rates 10% of EC total grant withheld until the approval of the final report Final payment after approval of final reports difference between total EC contribution and amounts already paid
23 Timeline of reporting and payments GA into force Prefinancing Final report on distribution of community financial contribution Periodic report I Periodic report II Final report 45d P1 P2 P3 Start date project 60d 105d Interim Payment 60d 105d Interim Payment 60d 105d 30d End date project Final Payment
24 Timeline of workflow Work Package Name WP1: Co-ordination and Project Management WP2: Dissemination and Exploitation WP3: Assessment and Evaluation WP1.1: WP1.2: WP2.1: WP2.2: WP2.3: WP2.4: WP3: WP4: Milestones Deliverables D01 M1 M2 D121 D122 D123 M3 M4 M5 D211 D221 D231 D241 M6 D311 D321 D331 M7 D411 D421 D431 D441
25 Reporting At the end of each period: Technical report + Management (financial) report Guidelines for reporting: ftp://ftp.cordis.europa.eu/pub/fp7/docs/project_reporting _en.pdf Financial report should be completed in =>conversion rate available at (date: first day of the month after the end of the period) Certificate on financial statement required to certify costs incurred in the frame of the project each time if the added-up EC contribution >
26 Scheme of reporting Coordinator 3.Templates revised and approved European Commission Project Officer 2. Templates filled out 1.Templates Partner 1 Partner 2 Partner N
27 FORM C part of periodic report
28 FORM C how to fill in?
29 Reporting by FORCE It is a web-based tool to edit and submit Forms C Services: Preparation of FORMS C with updated and correct contract/grant information of each beneficiary participating in the project/grant The coordinator can check Forms C before submission Printing of Forms C Electronic submission of FORMS C to the Commission (signed paper version to be sent afterwards) Correction of Forms C after refusal by Commission
30 Audits The EC can audit any organisation during or after the end of the grant agreement Project duration + 2 years: upon request, EC has to be informed about the foreground of the project Project duration + 5 years: - financial, technical audits as well as ethics audits can be arranged - confidential information has to be kept confidential - data for review, impact assessments and evaluations can be requested
31 What is IPR? Intellectual Property Rights = legal instruments to protect someone s intangible assets (non-physical assets) Converting Intellectual Assets into Property By granting a legal title which entitles the owner the right to prevent others from exploiting it (reward for the inventors!)
32 IPR a strategic factor in a successful FP7 project Before Project Proposal preparation, incl. potential impact Defining projectrelated know-how Defining IP-protected areas Negotiating a CA Negotiating with the EC During Project Strategy for protection & management of foreground Granting of access rights After Project Protection of generated IP Exploitation of the results Dissemination AT ALL STAGES
33 Provisions on IPR aspects in FP7 Rules for participation EC Grant Agreement (and related Annexes, Annex II in particular) it does not regulate everything and provides for the possibility of further specifications Consortium Agreement - fundamental for Intellectual Property Management; it is compatible with the Grant Agreement, which prevails in case of contradiction
34 IPR terminology Background: information, know-how and IPR (granted or applied) before signature of the EC grant agreement Foreground: Results generated by the project and any IPR attached to these results Use: Direct or indirect utilisation of foreground in further research or commercial activities Access rights: Licences and user rights to foreground and background for the execution of the project or the use of the foreground
35 Plan for the use and the dissemination of foreground (PUDF) It summarises the strategy and the concrete actions of a consortium for the protection, exploitation and dissemination of the results. It must contain information on: exploitable foreground and its use dissemination of foreground publishable results Participant Foreground Protection Dissemination Use
36 Is it easy to manage FP7 projects? The requirements are detailed in the support documents Good communication and good faith within the consortium is essential Experienced partners can help a lot A well designed CA can help when things go really wrong The Project Officer can offer support Usually, everybody wants an FP7 project to succeed!
37 Thank you for your attention!
Guide for ERC Grant Holders Part II
EUROPEAN RESEARCH COUNCIL Guide for ERC Grant Holders Part II Reference Manual on Financial Management and Administration of the ERC Grants Starting and advanced grants Version 1-24/06/2008 Disclaimer:
Administrative + Management Aspects. EU - Framework Programme 7. Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.
Administrative + Management Aspects EU - Framework Programme 7 Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.2008 Dr. Jürgen Ertel Department Program Planing and Management Head of Project
Frequently asked questions. FP7 Financial Guide
Frequently asked questions FP7 Financial Guide Budgetary matters Eligible costs of a project What are the criteria for determining whether the costs of a project are eligible? First of all, costs must
The TIPS project is supported by the European Commission through the Seventh Framework Programme for Research and Technological Development /
FP7 Requirements for your Project's Exploitation Plan Ulrich BOES URSIT Ltd., Bulgaria Outline Goal of the presentation Summarise the exploitation requirements of FP7 Outline Definitions Official documents
Negotiations feedback for successful project preparation. ERANIS workshop, 27.11.2007, Minsk
Negotiations feedback for successful project preparation Negotiations procedure Feedback from the Commission on the project plan issues that need to be explained in more detail Request to formulate Annex
FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues
National Documentation Center (EKT/NHRF) FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues Maria Samara, Administrative
Proposal Negotiation. a guide. Constantine Vaitsas, [email protected]
Proposal Negotiation a guide Constantine Vaitsas, [email protected] Presentation Outline Proposal Time Scale Negotiation Process Legal Negotiations Financial Negotiations Technical Negotiations NEF
Model Grant Agreement
HORIZON HORIZON 2020 2020 Model Grant Agreement Horizon 2020 model Grant Agreement: Objectives Simplification Provisions Wording Flexibility To accommodate particularities Coherence Within H2020 and with
GUIDE FOR APPLICANTS
European Commission THE SEVENTH FRAMEWORK PROGRAMME The Seventh Framework Programme focuses on Community activities in the field of research, technological development and demonstration (RTD) for the period
Guide to Financial Issues for Cleansky GAPs
Guide to Financial Issues for Cleansky GAPs Version of 16/01/2012 adopted by the Commission and subsequently adapted for the Clean Sky Joint Undertaking on 08/05/2012 Disclaimer This guide is aimed at
Intellectual Property in FP7 projects
Intellectual Property in P7 projects IGLO training, russels, 25 th ebruary 2010 Stéphane eslier IPR Helpdesk - University of Alicante IPR-Helpdesk is a constituent part of the IP Awareness and Enforcement:
H2020 rules for participation, new instruments, evaluation criteria
H2020 rules for participation, new instruments, evaluation criteria Disclaimer : H2020 Regulations are not yet adopted by the legislator. Any information contained in this presentation is legally not binding
Guide to Financial Issues relating to FP7 Indirect Actions
Guide to Financial Issues relating to FP7 Indirect Actions Version 28/02/2011 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are
H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi)
H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi) Version 1.0 9 June 2015 HISTORY OF CHANGES Version Publication date Changes 1.0 09.06.2015 Initial version 1 EUROPEAN COMMISSION
Guidance notes and templates for Project Technical Review involving Independent Expert(s)
Guidance notes and templates for Project Technical Review involving Independent Expert(s) FP7 Collaborative Projects, Networks of Excellence, Coordination and Support Actions Version 18/12/2007 Disclaimer
AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME
AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME GUIDANCE NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP VERSION 1 APPROVED
EUROSTARS Consortium Agreement Skeleton
Aim Higher EUROSTARS Consortium IMPORTANT NOTICE The aim of this Skeleton is to sum up the main items for the drafting of a consortium agreement between participants of the same Eurostars project. The
MANUAL FOR THE EURO-HEALTHY
MANUAL FOR THE EURO-HEALTHY INTERNAL AND PERIODIC PROJECT MONITORING AND REPORTING Coimbra, May, 2015 EURO-HEALTHY project has received funding from the European Union s Horizon 2020 research and innovation
Guide to Financial Issues relating to FP7 Indirect Actions
Guide to Financial Issues relating to FP7 Indirect Actions Version 3/10/2014 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are
Model Grant Agreement
HORIZON HORIZON 2020 2020 Model Grant Agreement Horizon 2020 model Grant Agreement: Objectives Simplification Provisions Wording Flexibility To accommodate particularities Coherence Within H2020 and with
RULES FOR PARTICIPATION IN THE IMI JU COLLABORATIVE PROJECTS
Innovative Medicines Initiative IMI-GB-DEC-2012-12 RULES FOR PARTICIPATION IN THE IMI JU COLLABORATIVE PROJECTS OUTLINE 1. Definitions 2. Participation in an IMI JU collaborative project 2.1 General provisions
Guidance notes and templates for Project Technical Review involving Independent Expert(s)
Guidance notes and templates for Project Technical Review involving Independent Expert(s) FP7 Collaborative Projects (CP), Networks of Excellence, Coordination and Support Actions (CSA), CP-CSA, ERA-NET,
EUROPEAN COMMISSION INFORMATION SOCIETY AND MEDIA DIRECTORATE-GENERAL. [title of the project] Grant Agreement No ICT PSP GRANT AGREEMENT
EUROPEAN COMMISSION INFORMATION SOCIETY AND MEDIA DIRECTORATE-GENERAL [title of the project] Grant Agreement No ICT PSP GRANT AGREEMENT Version 3, 20/01/2012 GRANT AGREEMENT NO The European Union ( the
Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations
Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations Marlen Damjanović, PhD National Contact Point Health & ICT Euresearch Head Office [email protected] phone:
The Marie Curie Actions FP7 Financial Guidelines
The Marie Curie Actions FP7 Financial Guidelines. These guidelines complement and should be considered in conjunction with the FP7 Guide on Financial Issues which is available for download at ftp://ftp.cordis.europa.eu/pub/fp7/docs/financialguide_en.pdf.
PRIORITY 2 INFORMATION SOCIETY TECHNOLOGIES (IST) FREQUENTLY ASKED QUESTIONS on Project management in FP6
PRIORITY 2 INFORMATION SOCIETY TECHNOLOGIES (IST) FREQUENTLY ASKED QUESTIONS on Project management in FP6 March 2005 Evolution of the consortium 1. If a sum has been allocated within the budget for new
Frequently Asked Questions
SME Instrument Frequently Asked Questions Contents FOR APPLICANTS A. Eligibility and type of SMEs targeted... 2 B. Preparing your application and submitting your proposal... 4 C. Evaluation of your proposal...
Open Disruptive Innovation (ODI) & the SME instrument: Frequently Asked Questions
Open Disruptive Innovation (ODI) & the SME instrument: Frequently Asked Questions 1. The concept in a nutshell The SME instrument is targeted at all types of innovative SMEs showing a strong ambition to
Project reports and reviews in FP6
Project reports and reviews in FP6 Zoe Ketselidou IST Operations NCP meeting Brussels, 8 March 2005 Periodic reporting At the end of each reporting period 1. Periodic activity report (overview of progress)
The Marie Curie Actions FP7 Financial Guidelines
The Marie Curie Actions FP7 Financial Guidelines SPECIFIC PROVISIONS RELATED TO MARIE CURIE ACTIONS FINANCED UNDER THE FP7 "PEOPLE" PROGRAMME Part 3: projects funded in the 2007-2011 Work Programmes calls
IP specificities in research for the benefit of SMEs
January 2012 IP specificities in research for the benefit of SMEs TABLE OF CONTENTS Introduction... 1 1. Actions for the benefit of SMEs... 2 1.1. Research for SMEs... 2 1.2. Research for SME-Associations...
Checklist for a Coordination Agreement for Coordinated Calls (Option 2)
Checklist for a Coordination Agreement for Coordinated Calls (Option 2) 01/04/08 Note There are two different types of coordinated calls: one where the result is a joint project, i.e. the third country
IPR aspects in the 7th Framework Programme
6th Framework Programme of the European Union - European Commission, DG Enterprise and Industry IPR aspects in the 7th Framework Programme Salvatore Amico Roxas IPR-Helpdesk Bari, 30 Ottobre 2007 Topics
Version 0.3 25 September 2014
Guide for Grant Agreement Preparation Version 0.3 25 September 2014 Disclaimer: This document is aimed at assisting applicants and beneficiaries for Horizon 2020 funding. Its purpose is to explain the
Reporting transnational access and service activity costs. Version May 2011
Reporting transnational access and service activity costs Version May 2011 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are not
Horizon 2020 Secure Societies
Horizon 2020 Secure Societies Angelo MARINO Head of Unit, Security Research European Commission Research Executive Agency NOT LEGALLY BINDING 2013 Where we come from: FP7-Security R&D (2007-2013): EUR
Agreements in FP7 Projects Frequent Questions to the IPR-Helpdesk
Agreements in FP7 Projects Frequent Questions to the IPR-Helpdesk: Contract Negotiations, Project Management, IP and Dispute Resolution Alicia Blaya Senior Legal Adviser Intellectual Property and Knowledge
Administration and Finances under H2020 in MSCA Helsinki 21/4/2015
Administration and Finances under H2020 in MSCA Helsinki 21/4/2015 Marcela Groholova Research Executive Agency Overview 1. EU contribution 2. Eligible costs 3. Cost categories 4. Parental and maternity
PROPOSAL ACRONYM - ETN / EID / EJD (delete as appropriate and include as header on each page) START PAGE MARIE SKŁODOWSKA-CURIE ACTIONS
START PAGE MARIE SKŁODOWSKA-CURIE ACTIONS Innovative Training Networks (ITN) Call: H2020-MSCA-ITN-2015 PART B PROPOSAL ACRONYM This proposal is to be evaluated as: [ETN] [EID] [EJD] [delete as appropriate]
SME INSTRUMENT PHASE 1 - FINAL REPORT SME Instrument Phase 1 FINAL REPORT
SME INSTRUMENT PHASE 1 - FINAL REPORT SME Instrument Phase 1 FINAL REPORT Grant Agreement number: Acronym: Title: Type of the action: SME Instrument Phase 1 Date of latest version of Annex I against which
FP7 Project Reporting ****** Research Participant Portal. Peter Härtwich European Commission DG Research-A6
FP7 Project Reporting ****** Research Participant Portal Peter Härtwich European Commission DG Research-A6 1 Model grant agreement Reporting - Reference documents - Grant Agreement (GA): Article 4. - Annex
Factsheet: Rules under Horizon 2020
23 October 2013 Factsheet: Rules under Horizon 2020 The Horizon 2020 Framework Programme represents a radically new and comprehensive approach to the EU's research and innovation funding policies. The
EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO)
EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) Director H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO) Introductory remark MSC-IF Mono deviates from
CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS
CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS MATERIALS PREPARED BY THE WORKING GROUP ON CERTIFICATE ON THE METHODOLOGY UNDER FP7: DG RESEARCH AND INNOVATION DG
Fact Sheet Intellectual Property rules within the Fusion for Energy contractual framework
European IPR Helpdesk Fact Sheet Intellectual Property rules within the Fusion for Energy contractual framework November 2011 Introduction... 1 1. Grants & Procurement granted by F4E... 4 2. Background
Proposal template and GUIDE FOR APPLICANTS (updated by FIspace)
European Commission THE SEVENTH FRAMEWORK PROGRAMME The Seventh Framework Programme focuses on Community activities in the field of research, technological development and demonstration (RTD) for the period
Project reporting in FP6
Guidance notes for Integrated Projects, Networks of Excellence, Specific Targeted Research or Innovation Projects, Coordination Actions, Specific Support Actions, Co-operative Research Projects and Collective
GUIDE FOR APPLICANTS ECHORD++ PDTI activities
GUIDE FOR APPLICANTS ECHORD++ PDTI activities This guide, and all other information related to ECHORD++ Calls for Public enduser Driven Technological Innovation (PDTI) activities. The call text and other
Guide for ERC Grant Holders
Ref. Ares(2012)894501-23/07/2012 European Research Council Guide for ERC Grant Holders [Final version July 2012] Disclaimer: This Guide includes two main parts: firstly an ERC grants descriptive part,
Guidance. Establishing a consortium agreement
EUROPEAN COMMISSION Directorate-General for Research & Innovation Guidance Establishing a consortium agreement Version 0.1 IMPORTANT NOTICE Disclaimer You remain fully responsible for your consortium agreement.
Frequently Asked Questions version 3.0 09.09.2014
EUROPEAN COMMISSION Executive Agency for Small and Medium-sized Enterprises (EASME) Department A - Operations Unit A1 - COSME Frequently Asked Questions version 3.0 09.09.2014 COS-WP2014-2-05- Call for
IP in EU-funded projects
Welcome to our online training session: IP in EU-funded projects, 04 October 2013 Get your ticket to innovation. Today s speaker Jörg Scherer Managing Director of Research and Project Office (Eurice) GmbH,
Intellectual Property in Horizon 2020 overview with a focus on comparison with FP7
European IPR Helpdesk Intellectual Property in Horizon 2020 overview with a focus on comparison with FP7 The European IPR Helpdesk is managed by the European Commission s Executive Agency for Small and
28 September 2007 LIFELONG LEARNING PROGRAMME GUIDE FOR APPLICANTS: ADMINISTRATIVE AND FINANCIAL RULES
28 September 2007 LIFELONG LEARNING PROGRAMME GUIDE FOR APPLICANTS: ADMINISTRATIVE AND FINANCIAL RULES 1 Table of Content 2 1. GENERAL PROVISIONS This document contains supplementary information to the
Template for essential information to be provided for proposals including clinical trials / studies / investigations
Template for essential information to be provided for proposals including clinical trials / studies / investigations Document history Version 2016callsV1 September 2015 Modifications (compared to previous
ARTEMIS-ED-21-09. Guidance notes and templates for Project Technical Review involving independent expert(s)
Guidance notes and templates for Project Technical Review involving independent expert(s) 1 CONTENTS 1 INTRODUCTION... 3 2 THE PROJECT REVIEW PROCESS... 3 3 MANDATE OF THE INDEPENDENT EXPERT(S)... 5 3.1
FP7 Project reporting. FP7 INCO National Contact Points Meeting 9 June 2010 - Athens Anne Mandenoff - European Commission - RTD A.
FP7 Project reporting FP7 INCO National Contact Points Meeting 9 June 2010 - Athens Anne Mandenoff - European Commission - RTD A.6 Reference documents 1 Model grant agreement - Grant Agreement (GA): Article
GRANT AGREEMENT. NUMBER 674463 i2d
EUROPEAN COMMISSION Executive Agency for Small and Medium-sized Enterprises (EASME) Director GRANT AGREEMENT NUMBER 674463 i2d This Agreement ( the Agreement ) is between the following parties: on the
Administrative forms (Part A) Project proposal (Part B)
Ref. Ares(2015)2346168-04/06/2015 Project Grants (HP-PJ) Administrative forms (Part A) Project proposal (Part B) Version 2.0 05 June 2015 Disclaimer This document is aimed at informing potential applicants
Guidelines for a Consortium Agreement (CA)
Guidelines for a Consortium Agreement (CA) The CA is an agreement made between participants in a collaborative project to govern a number of issues, i.e. relationship between partners, organisation and
COMMISSION DECISION. of XXX
EUROPEAN COMMISSION Brussels, XXX [ ](2014) XXX draft COMMISSION DECISION of XXX authorising the use of reimbursement on the basis of unit costs for actions requiring the conduct of clinical studies under
How to write proposal section 3: IMPLEMENTATION? 26.06.2014 The Hague Christiane Kummer Pt-Juelich
How to write proposal section 3:? 26.06.2014 The Hague Christiane Kummer Pt-Juelich Research Proposal (Part B) - Structure Stage 1 1. Excellence 2. Impact 3. Implementation 3.1 Work plan Work packages,
HORIZON 2020. Rules for Participation and Dissemination Simplification and Innovation. Alexandros IATROU DG RTD K.7
THE EU FRAMEWORK PROGRAMME FOR RESEARCH AND INNOVATION HORIZON 2020 Rules for Participation and Dissemination Simplification and Innovation Alexandros IATROU DG RTD K.7 Rules for participation: Three main
The Eurostars Programme
The Eurostars Programme TM funding excellence in innovation Guidelines for applicants Publication date: 29 June 2009 Version: 9.0 The Eurostars Programme is a joint initiative of EUREKA and the European
MEMORANDUM OF UNDERSTANDING AND NON-DISCLOSURE AGREEMENT (Template)
MEMORANDUM OF UNDERSTANDING AND NON-DISCLOSURE AGREEMENT (Template) Disclaimer This sample document has been produced by the European IPR Helpdesk, based on the experiences and acknowledgments gathered
SESAR 2020 EXPLORATORY RESEARCH INFO DAY PROPOSALS SUBMISSION & EVALUATION & PROGRAMME MANAGEMENT REQUIREMENTS
SESAR 2020 EXPLORATORY RESEARCH INFO DAY PROPOSALS SUBMISSION & EVALUATION & PROGRAMME MANAGEMENT REQUIREMENTS ALESSANDRO PRISTER PROGRAMME MANAGER ER, SJU ER CALL COORDINATOR List of topics covered Call
Jörg Scherer/Eurice GmbH
IP Management in Horizon 2020 Jörg Scherer/Eurice GmbH Paris, 09-12-2014 EU research funding Outcome of FP7 impact assessments Less than 50% of industrial partners use the publicly funded applied research
Amendments Guide for FP7 Grant Agreements
Amendments Guide for FP7 Grant Agreements Version 10/09/2013 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are not intended to
Guide for ERC Grant Holders PART I
EUROPEAN RESEARCH COUNCIL Guide for ERC Grant Holders PART I GENERAL GUIDANCE NOTES Starting and advanced grants Version 1 24/06/2008 Disclaimer: This Guide aims to assist grant holders, whether individual
Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013
EUROPEAN COMMISSION European Social Fund Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013 Version of June 2015 Please consult http://ec.europa.eu/esf/sco
EUROPEAN COMMISSION Directorate-General for Research & Innovation. Guidance How to draw up your consortium agreement
EUROPEAN COMMISSION Directorate-General for Research & Innovation Guidance How to draw up your consortium agreement Version 2.0 23 February 2015 Guidance How to draw up your consortium agreement: V2.0
AUSTRIAN RESEARCH PROMOTION AGENCY FFG THE STRONG PARTNER IN R&D:
AUSTRIAN RESEARCH PROMOTION AGENCY FFG THE STRONG PARTNER IN R&D: Major national funding agency addressing the innovation base of the Austrian business sector focus on applied research Comprehensive portfolio
Frequently Asked Questions to the Marie Curie Actions Financial Guidelines
Frequently Asked Questions to the Marie Curie Actions Financial Guidelines Updated 26/06/2012 Table of contents Q1: FOR CATEGORIES A-C (1-2 AS OF WP2011), WHICH AMOUNT HAS TO BE DECLARED IN THE FORM C
Webinar on third parties in Horizon 2020
Webinar on third parties in Horizon 2020 03.02.2016 Martin Baumgartner FFG OVERVIEW What is a third party in Horizon 2020? Types of third parties How to involve contract research organisations (CROs) Third
Horizon 2020 Energy Calls Project Types and Funding Levels. 1. Types of Funding Actions why do I need to know this?
Horizon 2020 Energy Calls Project Types and Funding Levels This document sets out the types of activity that will be funded under Horizon 2020. In the Energy Work Programme there are five types of projects,
EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD ABDUCTION ALERT MECHANISMS SPECIFIC ACTION GRANTS
EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE Directorate A: Civil justice Unit A.4: Programme management SPECIFIC PROGRAMME "DAPHNE III (2007 2013) CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD
Guidelines for Applicants
Guidelines for Applicants CORNET 19 th Call for Proposals Opening National and Regional Programmes for transnational Collective Research between SME Associations and Research Organisations. Closing date:
Fast track to Innovation: a new instrument in Horizon 2020
Fast track to Innovation: a new instrument in Horizon 2020 29.01.2015 Webinar Ines Haberl Austrian Research Promotion Agency 29.01.2015 Webinar Fast track to Innovation in Horizon 2020 Content 1. Concept
Guidelines for Applicants
Guidelines for Applicants CORNET 21 st Call for Proposals Combining national and regional programmes for international Collective Research for the benefit of SMEs. Closing date: 30 st of March 2016, 12
Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme
Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government of the Republic of Poland
O.1.2.5 General Reporting Obligations
3CE335P4 O.1.2.5 General Reporting Obligations Workpackage 1 Action 1.2 Author Version LP V1 Index 1. Introduction...3 1.2 Reporting and payment flows...3 2. Progress Report...4 3. Reporting procedure...5
The Terms of Reference should be completed by the Beneficiary and be agreed with the Auditor
ANNEX V-A FORM - TERMS OF REFERENCE FOR THE CERTIFICATE OF FINANCIAL STATEMENTS TABLE OF CONTENTS TERMS OF REFERENCE FOR AN INDEPENDENT REPORT OF FACTUAL FINDINGS ON COSTS CLAIMED UNDER A ERC GRANT AGREEMENT
Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014
the European Economic Area (EEA) Financial Mechanism 2009-2014 adopted by the EEA Financial Mechanism Committee pursuant to Article 8.8 of Protocol 38b to the EEA Agreement on 13 January 2011 and confirmed
Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014
Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014 adopted by the Norwegian Ministry of Foreign Affairs pursuant to Article 8.8 of the Agreement between the Kingdom of Norway
New Energy Jobs Fund. Application Guidelines
New Energy Jobs Fund Application Guidelines i Table of Contents 1. Background... 1 2. The Program... 1 2.1. Objectives... 1 2.2. Overview... 1 2.3. Program Timetable... 2 3. Funding... 3 4. Eligibility...
URBACT III Programme Manual
URBACT III Programme Manual Fact Sheet 2E Network Management Table of contents Fact Sheet 2E 0. Introduction... 1 1. Roles and responsibilities of Lead and Project Partners... 2 2. The legal framework...
PREANNOUNCES RESEARCH WITHIN PRIORITY SECTORS CALL FOR PROPOSALS
THE GENERAL SECRETARIAT FOR RESEARCH AND TECHNOLOGY AS PROGRAMME OPERATOR OF THE GREEK-EEA RESEARCH PROGRAMME IMPLEMENTED UNDER THE GREEK FINANCIAL MECHANISM 2009-2014 PREANNOUNCES RESEARCH WITHIN PRIORITY
The Marie Curie Actions FP7 Financial Guidelines.
The Marie Curie Actions FP7 Financial Guidelines. SPECIFIC PROVISIONS RELATED TO MARIE CURIE ACTIONS FINANCED UNDER THE FP7 "PEOPLE" PROGRAMME Part 1: projects funded in the 2007-2010 Work Programmes calls
Issues and Recommendations following feedback from and discussion among EARTO members
Contracting and Financial Management in FP7 Research for SME Associations Research for SMEs Issues and Recommendations following feedback from and discussion among EARTO members The FP7 SME instruments
Open Access and Open Research Data in Horizon 2020
Open Access and Open Research Data in Horizon 2020 Celina Ramjoué Head of Sector Open Access to Scientific Publications and Data Digital Science Unit CONNECT.C3 22 November 2013 Train the Trainer for H2020
IP Management in Horizon 2020 Focus on MSCA
IP Management in Horizon 2020 Focus on MSCA European IPR Helpdesk Jörg Scherer Head of Training & Communication CEO Eurice GmbH Webinar 04-05-2015 Brussels Roadmap IP Management in H2020/ MSCA Knowing
Guidelines for applicants for the 2nd Transnational Call for Proposals (full-proposal phase)
SUSFOOD - An FP7 ERA-NET on Sustainable Food Production and Consumption Guidelines for applicants for the 2nd Transnational Call for Proposals (full-proposal phase) Closing date for full-proposals: August
