NO DIG BERLIN 2015 Symposium and Exhibition 24 27 March. Paper 5-4. Cases study on application of rectangular shield jacking machine



Similar documents
Tunnelling & Underground. Specialists

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Open Access Numerical Analysis on Mutual Influences in Urban Subway Double-Hole Parallel Tunneling

How To Calculate Tunnel Longitudinal Structure

Milan M5 metro extension the construction of Lotto station

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

Safe & Sound Bridge Terminology

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

Dulles Corridor Metrorail Project

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Analysis One Code Desc. Transaction Amount. Fiscal Period

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

Specification Guidelines: Allan Block Modular Retaining Wall Systems

MLD: Domestic Maritime Transport Project

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

SULTANATE OF OMAN SPECIAL ECONOMIC ZONE AUTHORITY AT DUQM

Hanna delivers the technical and marketing expertise needed to produce a car wash that meets the car wash customer's expectations.

Training Approved by JAC (C&S)

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES

Case 2:08-cv ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

TBM CROSSING OF STATIONS

(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT Nina Tveiten Norwegian National Rail Administration

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

Appendix A: Acceptable pipe and fitting materials

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

Geotechnical Building Works (GBW) Submission Requirements

Design Guidelines for Sequential Excavations Method (SEM) Practices for Road Tunnels in the United States

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Life after 30! Innovative investigation and repair of the Overvaal railway tunnel. r a i l w a y s a n d h a r b o u r s PROJECT TEAM

Permits to Dig / Permits to Excavate / Permits to work near underground services

BRIDGES ARE relatively expensive but often are

Integrated Manhole Ladder System

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

Airport Rail Link is gathering speed. Wolfgang Rueprich, Project Manager Airport Rail Link, October 21, 2009

Repair or Replacement - Band-Aids vs. Surgery

Flowtite Jacking Pipe

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

Granger Bay Boulevard and Green Point Roundabout

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2

Section 402. STORM SEWERS

(52) In6 Publication CCM2 May 2000 ADVANCED DRAINAGE SYSTEM CATCHPITS, CHAMBERS & MANHOLES RIDGIDRAIN ENGINEERING EXCELLENCE

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

Advanced Natural Gas Storage (ANGAS) Project and Verification Tests of Experimental Lined Rock Cavern in Japan

CHAPTER 8 CIVIL DESIGN

Buildings Construction Procurement Strategy

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SECTION 1 GENERAL REQUIREMENTS

How To Retaining Wall Guide

1.2 Advantages and Types of Prestressing

REQUIREMENTS FOR REGISTRATION AS A PROFESSIONAL ENGINEER WITH THE PROFESSIONAL ENGINEERS BOARD SINGAPORE

Member Nation Report 2010 from Denmark.

BIM for Infrastructure GeoSmart Asia 2015

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems

METHOD OF STATEMENT FOR STATIC LOADING TEST

Wastewater Capital Projects Management Standard Construction Specification

Ardessie Hydro Electric Project

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Taylor Wimpey UK Ltd. December 2007

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

Free Stall Cleaner System with Cable. A new generation of equipment and systems. GEA Farm Equipment Houle

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES

hs2 Ground A non-technical guide

IH-635 MANAGED LANES PROJECT, SEG. 3.2

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

KWANG SING ENGINEERING PTE LTD

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

Overview of Singapore s Drainage Management Approach July 2011

CHAPTER 2 QUANTITY TAKE-OFF

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

Drainage Composites. The ready-made solution to sub soil drainage

Pro-Lift Steel Pile Foundation Repair

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

Numerical modelling of shear connection between concrete slab and sheeting deck

Important Dates Calendar FALL

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Unit Price Averages Reports

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Ridgistorm-XL - the latest innovative

Transcription:

NO DIG BERLIN 2015 Symposium and Exhibition 24 27 March Paper 5-4 Cases study on application of rectangular shield jacking machine Trisha Sun, W&M Consultants. Singapore, Zhang daoguang, Yangzhou Guanxin, China, Yu bingquan, Yangzhou Guanxin, China, Abstract: The paper will discuss and share the knowledge/experience in the application of rectangular shield jacking method via case study. It will highlight that the basic concept of design, construction and machine manufacture through projects which had been carried out in China and Singapore. Meanwhile, the comparison between different methods of Rectangular shield jacking and Pipe roof will also be made via two example projects which had been executed in China and Singapore. The comparison will focus on not only the cost and quality of projects but also schedule and environment protection of the projects. The Rectangular jacking projects explored in the case study are as followings: Four 4.9m X 6.9m (OD) parallel rectangular jacking project in Foshan, China. The project was completed in 2012. Refer to chapter B in the paper. The pipe roof method jacking project is presented below: 4m X 6m (ID) Outlet Drain at North Buona Vista Road, Singapore. The project was completed in 2005. Refer to chapter C in the paper. In conclusion, this paper deals with the consideration of the design and construction for rectangular shape underground crossings. It also highlights the key issues to be considered in the construction method selection at earlier stage of the project. The problems encountered during the construction, subsequent solutions adopted as well as monitoring of settlement will also be briefly discussed in the paper.

A. General Pipe jacking is currently a common construction method for the underground structure of pipe line; normally by circular pipes are used in the practice. Due to increasing requirements of rapid urbanization, more pipe lines such as the water supply, sewer, cables, traffic etc. have to make full use of underground space and this will cause more opportunities or challenges to develop the underground networking especially in the congested city areas. In order to minimise the diversion of existing underground networking and the influence of the heavy traffic during the construction of underground pipe lines or structures, the use of rectangular shield jacking may be considered especially where limited head room is available. This paper will discuss the rectangular shield jacking from the perspective of design, manufacture and construction via projects which had been practiced successfully in mainland of China. Part of the projects which had been constructed by method of rectangular shield jacking summarised in Table -1 as followings. Table-1, Examples of the rectangular shield jacking projects 1 S/N Project name Jacking Length (m) Period of construction (Month) 1 Underground Access at Kaiming Street and Medicine Street, Ningbo, 2 X 50 Jun 2006 - Sept 2006 ( 4 ) Zhejiang 2 4th entrance of Longyang Road Station Shanghai Metro 1x 40.5 Nov 2006- Dec 2006 ( 1) 3 5 th and 6th entrance at Qibao Station Shanghai Metro 2 x 56 Jan 2007- Mar 2007 ( 3) 4 Exit 4 at Spring Road Station, 9th Line, Shanghai, Metro 1 x 44.8 Apr 2007- May 2007 ( 2) 5 Underground access at Zhongshan hospital, Shanghai 1 x 78.5 Sept 2010- Feb 2011 ( 4) 6 2 nd Entrance at 7th line, South Chen Road Station Shanghai Metro 1 x 37.3 Aug 2008- Oct 2008 ( 3) 1 Source from Guangxin, Yangzhou manufacture 2

S/N Project name Jacking Length (m) Period of construction (Month) 7 Exit 3, Bus supporting projects in Pujiang Town 2 1 x 44 Jul 2008 Oct 2008 (3) 8 Exit 5, 7, 8 for interchange station Shanghai Metro (New Bay) 2 x ( 56.5m, 43.5 m) Aug 2008- Dec 2008 ( 5) 9 3rd entrance at 10th Yin High Road Station, Shanghai Metro 1 x 48 Sept 2008-Nov 2008 ( 3) 10 Nanjing West ancestral hall Lane 1 x 42.2 Nov 2008-Jan 2009 (3) 11 Underground access at Nanjing Military General 1 x 44 Jan 2009- Mar 2009 (3) 12 Pedestrian at Hongwu Road, Nanjing, 1x 43.3 Nov 2009- Dec 2009 (2) 13 Underground pedestrian at Simon Street Memorial of Nanjing Water 1 x 60 Dec 2009- Jan 2010 (2) 14 Foshan, underground space (will be further discussed in the paper) 4 x 60.5 Dec 2011- May 2012 (11) 15 Buotou underground pedestrian 1x 65 Nov 2012- April 2013 (2) Projects summarised in Table - 1 are more for entrance and exit to underground train stations, underground pedestrian crossings, underground connections/access between existing buildings, outlet drain etc. The rectangular shield method had been in use in China since 2005. It had been further developed and improved via increasing market demand during the last 10 years. 1. Design consideration: The rectangular shield jacking is considered as a more efficient and safer construction method for underground structures especially in the congested areas of the cities. However, feasibility study has to be carried out in the preliminary design stage in order to evaluate the project from the perspective of quality, cost, schedule, and environment protection. The following factors are essential for the adoption of rectangular shield jacking method. Soil condition 3

Surrounding existing building and structure conditions Surrounding utilities and traffic conditions Shaft location, sizes, jacking force and soil treatment if necessary Pipe design and materials Pipes connection and water proofing. Environment protection 2. Manufacture of the machine The jacking equipment is one of the important factors for the successful completion of rectangular shield jacking project; this chapter will focus on the discussion of the cutter head design and the special Sand/Soil pump which has to be put in place to control alignment deviation during operation. 2.1. Cutter head There are three types of the cutter head design used in the projects listed in Table-1. Type 1 is the mix and overlapped type as shown in Fig-1. This cutter head consist of one bigger cutter (extend forward) in the centre and four smaller cutters (receding) in each corner of the rectangular surface. It forms a combination of overlapping surface. Blind zone (yellow portion), around 8% of the areas of the rectangular face area Fig 1. Type-1, Mix cutter design 2 Type 1 cutter head had been used in most of the Projects as listed in Table-1, e.g. Projects in Shanghai, Nanjing, Guangzhou and Huizhou, the soil condition is more for clay, sandy soil, silt, fine sand etc. One project needs to be highlighted; it is an underground connection access to two existing old buildings at Zhongshan hospital Shanghai, China. The rectangular shield jacking is operated below existing oxygen 2 Picture from Yangzhou Guangxing,, China 4

station and substation which required minimal soil movement and settlement. The same cutter head been used for this project. The advantage of this type is the ease of operation, flexibility for direction control and stability of jacking. There is minimum settlement after construction. However, it will not perform well in the soil condition of high cohesive soil and bigger N value due to the 8% of blind areas existed in the cutter areas. Meanwhile, the deformation of the shell of the machine been found when the machine goes through strengthened soil treatment areas in the shafts (when the strengthening soil strength is more than 10 Mpa) Type 2 of the cutter is the multi cutter arrangement as shown in Fig 2. It had been used in Project number 14 in Table-1. This type is broken up in two parts (Top and Bottom) for easy installation and transportation. Meanwhile, the blind zone is much smaller as compare with Type1. Fig 2 Type 2, Multi cutter arrangement 3 Patent number:cn2217645, Year 1995 Type 3 is Epicyclic Gearing transmission system with the full section cutting without blind point arrangement. It had been used in projects in harder ground conditions, such as consolidation sandy soil and soft rock. Cuter moving trace Fig. 3. Epicyclic Gearing transmission with full section cutter type 4 3 Source from Yangzhou Guangxin, China 4 Source from Yangzhou Guangxin, China 5

2.2. Soil/Sand pump to rectify the deviation Rectangular shield pipe jacking construction in general is very difficult to control the alignment deviation due to the size and mess of the machine. In order to control and correct the deviation, the special Sand/Soil pump is essential for the successful implementation of the projects. Projects listed in Table-1 had been successfully implemented with the use of Sand /Soil pump during construction. Fig.4 shows the picture of the Sand/Soil pump and the disposal from execution of the projects. Fig 4a, Sand/Soil pump Fig 4b, hydraulic power source Fig 4c, disposal Fig 4, Soil and Sand Pump 5 (Patent certification Number is 200720067906. 200820059282. 201220472450) The grouting holes had been provided in the rectangular shield machine as Fig.5. It will be used during rectifying the deviation, if necessary, during the operation. Grouting hole Grouting hole Fig 5. Grouting holes in the rectangular shield machine 6 5 Source from Yangzhou Guangxin, China 6 Source from Yangzhou Guangxin, China 6

3. Construction consideration 3.1. Construction proceeds: It is important to emphasize the rectangular pipe jacking construction process as outlined below, Fig.6 1. Control theory soil pressure Yes 2. Control Jacking pressure or adjustment Yes 3. Decision of operation condition or adjustment Yes No No No 4. Preliminary Test Run Yes 5. Equal Balance between internal chamber pressure and control pressure Yes 6. Equal Balance between disposal volume and jacking space (95% to 100%) 排 土 量 与 进 尺 空 间 土 的 质 量 相 等 Yes 7. Ground settlement ±5mm Yes 8. Jacking in common process Fig.6 Construction program 7 7 From 2 nd rail construction china for Foshan project 7

3.2 Principle for construction of Rectangular pipe jacking The construction of the pipe jacking is the process of the pipe line being jacked from the working shaft to the receiving shaft by the jacking machine. Fig 7 shows the pipe jacking system starting from working shaft. 1. Pipes, 2.trucker, 3. Ladder, 4. Oil pump, 5. Hoisting system, 6. Railing, 7. Grouting system, 8. Control room, 9. Electric Box, 10. Operation system, 11. Back support, 12.Syveloy system, 13. Main cylinder, 14, Guide tracker, 15. Push ring, 17. Pipes, 18. Disposal car, 19. Jacking head Fig. 7 Principal diagram of rectangular Jacking 8 3.3. Key issue to be considered in Rectangular Jacking Deviation in the process of jacking Technology of the soil treatment during jacking process Balance between friction and grouting during jacking process Control of soil movement during the jacking Control and operation skill in the in and out from working and receiving shaft The settlement control after jacking 3.4. Comprehensive issues in the jacking process Water stop in the working shaft during jacking Soil treatment during breakthrough in the receiving shaft. 8 Source from 2nd rail construction of China 8

B. Rectangulaur Pipe Jacking Project 1. Project briefing and discussion The project is consist of four parallel underground commercial retail and vehicle passes, each of dimension 4.9m x 6.9m in Foshan, China. It is also an uderground connections between two exsiting buildings located at Nanhai street, Foshan, Guangdong, China. The project is located at the an area with complex and heavy traffic flow, as well as a proposed MRT rail of 2 circle lines below the project itself. Meanwhile, the exsiting concrete drain (4.2m X 2.5m) is directly above the project with 500mm distance from bottom of the drain to top of the tunnels. The depth of the project is 5.5 meter from the road surface to top of the pipe lines, the soil condition is clay, fine sand silt and sandy soil. For more details and discussion refer to following. (Fig. 8 to Fig.16) 9 Fig.8 Completed underground connections tunnels Existing building 1 Existing building 2 4 parallel Underground pipe lines Fig 9. Layout for 4 parallel undergrong connection tunnels 9 Foshang project, 2nd Rail Construction, China 9

Existing building 1 Existing building 2 Fig 10. Longitudinal section of connections between two buildings (Jacking distance is around 55 meter for each line) Line 1 Line 3 Line 2 Line 4 Fig.11 Section through 4 parallel tunnels (300mm space in between pipe lines, 2 meter length of rectangular concrete pipes and 450mm thick of the pipe) Heavy traffic on the road Existing drain 4.2mx4.5m Jacking tunnel Proposed MRT Mechanical room MRT Fig.12 Section of soil profile and the constraint of construction space 10

Prestressed strand for pipes Receiving shaft 13.17*33.7*11.85 (m*m*m) Working shaft 15.95*33.77*12.9 (m*m*m) Fig.13 Jacking from break out (working shaft) to break through (receiving shaft) Prestressed strand had been provided for the concrete pipes to enhance the longitudinal stiffness Line 3 Line 4 Line 1 Line 2 Fig.14 Site Photos during construction (constructin seqence is line1, line3, line 2 and line4) Fig.15 utilities layout and details 11

Fig. 16 Settlement diagrame (Maximum settlement is 22mm according to the monitoring report) 2. Construction schedule From the construction record as Table 2 and 3, It expressed that the jacking speed had been well satisfied if comparing with the common practice of using circlular pipes. Table-2 Jacking schedule 10 Items Line1 Line 2 Line 3 Line 4 Length (meter) 60.5 60.5 60.5 60.5 Date of start 9-Dec-11 22-Mar-12 13-Feb-12 28-Apr-12 Date of completion 13-Jan-12 12-Apr-12 6-Mar-12 15-May-12 Average spped of jacking (meter /day) 1.78 2.75 2.75 No record Maximum speed of jacking (meter / day) 4.5 6 7 7.5 Table -3 Shaft construction schedule 11 Shafts Date of start Date of completion Working shaft May,2011 Sept, 2011 Receiving shaft Oct,2011 Dec, 2011 10 from 2nd rail construction, China 11 from 2nd rail construction, China 12

C. Practice Pipe Roof Project 12 1. Project briefing The project is Tanglin Halt Outlet Drain at North Buona Vista Road comprising the design and construction of a 120m long permanent RC (reinforcement concrete) box culvert, sewer diversion and other related works located along Commonwealth Avenue, Commonwealth Avenue West and North Buona Vista Road.Singapore. Part of the works under this contract is the construction of approximately 53m of drainage box culvert (4m X 6m) under-crossing North Buona Vista Road using approved tunneling method.the jacking is from Jacking shaft to receiving shaft as shown in Fig.17 Fig. 17 Project Layout Refering to Fig.17, the yellow portion is the proposed rectangular drainage box culvert, the red line is existing east west (EW) overhead MRT viaduct, and the purple line is the circle MRT line underneath of tunnel. For more information, read the Fig17 in conjection of Fig.18 Fig.18 Longitudinal section of drainage box culvert 12 Paper related to the project published in International conference and exhibition on tunnelling and trenchless technology, Year 2011 by the Institution of Engineers, Malaysia 13

Fig.19 General soil profile of the mined tunnel zone Fig. 20 Utilities and protection measures adopted 2. Discussion The temporary earth retaining structure to support the ground during the excavation of the mined tunnel consists of a series of 780mm diameter, 16mm thick circular steel pipes interconnected by clutch to form an inverted U pipe-roof structure around the footprint of the proposed drain. The pipe roof method was adopted for the project due to site constraint. It was formed by 22 rows of steel pipes, comprised of 10 at top and 6 on either side. The interlocking steel pipes forming the pipe roof together with the support system shown in Fig.22 and 23. Moveover, the 22 numbers of steel pipes will be left in the underground space as it has no more function after the completion of the outlet drain construction. 14

Fig.21 Details of pipe clutch Fig.22 Transverse view of interlocking pipe roof Fig. 23 Complete pipe roof with interlocking pipes Fig.24 Layout of instrumentation and monitoring system settlement monitoring 15

Fig.25 The predicted settlement Fig.26 Settlemt from reading From Fig. 25 and 26, it can be seen that the actual settlement of 30mm is well controlled within the predicted value of 50mm. D. Comparison between pipe roof and rectangular shield jacking From chapter B and chapter C in the paper, Case Studies carried out for two projects in almost similar basic conditions are summarised as followings: Similar size of 4m X 6m(ID) for the rectangular underground structure, Constraint by heavy traffic above the rectangular underground structure, Existing /proposed MRT tunnel below the rectangular underground structure for project in chapter C and B respectively, Existing joint bay above the proposed tunnel for project in chapter C, Existing concrete drain above the tunnel for project at chapter B, There are many utilities surrounding the rectangular underground structure without diversion before construction, Both projects were completed in year 2005 and 2012 respectively by different construction methodology - pipe roof and rectangular shield pipe jacking. It were considered as successful during the time of the completion. However, it become significant for further study and discussion according to the technology of rectangular shield pipe jacking which are used recently in the world. The detailed comparisons between two methods of construction had been summarised in Table 4 of the paper. It highlighted several areas of interest in the construction methodology for us to further study and consider before the commencement of future projects. 16

Table - 4. Comparison Between Pipe Roof and Rectangular shield Pipe Jacking Nos Items to compare Rectangular shield jacking project (Chapter B) 1 Site constraint and condition Heavy traffic above Existing MRT (two circle line) below MRT Viaduct near by the project 2 Utility condition Joint bay above the Refer to Fig.18 and Fig 20 Pipe roof project (Chapter C) Heavy traffic above Proposed MRT and Mechanical room below (three circles) Existing drain above Refer to Fig.12 Remarks Quite similar conditions 3 Soil condition Sand and sandy soil Clay,Sand and sandy soil 4 Size of jacking section (ID, m*m) 4 X 6 4 X 6 5 Jacking length (meter) 6 Construction Period (Month) 7 Maximum Settlement (mm) 8 Contract sum (Million) 242 (60.5 X 4 ) 50 11 22 Including shafts 22 30 Refer to Fig.16, 25,26 9 Environment Pipe roof occupied underground space Refer to Fig.22, 23 17

Acknowlegment The authors would like to thank for all who contribute for the paper. Yanzhuo Guangxin, China, 2nd Rail construction, China and Or Kim Peow Contractors (Pte) Ltd (OKP), Singapore for this paper. The views presented in the paper are solely that of the authors, unless otherwise stated. References: Atalah, A.L. and D.T. Iseley, 1991. "Pipe Arch Horizontal Drift Method for MARTA's Transit Extension Under I-285," Proceedings of Rapid Excavation and Tunneling Conference, SME, Chapter 24, June, pp. 435-453. Darling, P., 1993. "Jacking Under Singapore's Busiest Street, Pacific Rim Supplement to Tunnels & Tunnelling, summer, pp. 19-23. Jacking under Singapore s Busiest Street. LTA 2009a, LTA interpretive soil report for C 8288. LTA 2009b, Correspondence between OKP/LTA and Authorities (LTA comments on contractor s response to LTA earlier comments on DAR 8288/CON/0019(DATED 7 May 09). LTA 2009c,LTA Civil Design Criteria LTA 2009d,Code of practice for RailWay Protecvtion. LTA 2009e, Code of practice for works on Public Street. Parsons Brinckerhoff, 2009, Design Report for Mined Tunnel submitted to LTA. Parsons Brinckerhoff, 2010, Report for overall constriction Impact Assessment (CIAR). Wong K S, O/ 2009, Independent report on Tanglin Halt Outlet Drain-mined tunnel. Report from Seminar on 2012 for Foshang project, 2nd Rail Construction, China 18