Forecasting Project Schedule Completion by Using Earned Value Metrics



Similar documents
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

Project Control with ProTrack

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

TIME FORECASTING USING EARNED SCHEDULE

PROJECTS SCHEDULING AND COST CONTROLS

Earned Value Formulae

Earned Schedule Leads to Improved Forecasting

Assessing Schedule Performance with Earned Value

IST 302 : Project Cost Management

Using Earned Value Management for Improving Processes. By Cynthia K. West

Schedule Adherence a useful measure for project management

Abstract. Earned Value Management Basics

PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS

Project Cost Management

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

An introduction to Earned Value Analysis

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

CPM -100: Principles of Project Management

Earned value method as a tool for project control

Introduction to earn value management in Civil Engineering

INSE 6230 Total Quality Project Management

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

700 Analysis and Reporting

performance management system that is based on Earned Schedule Management.

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Project Cost Management

Earned Schedule application to Project Management

Brainstorm. What is Cost and Project Cost Management?

earned value management

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

Estimating Cost at Completion - Judgment & EV Information

How To Manage A Project

Chapter 7. (PMBOK Guide)

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

AACE International Recommended Practice No. 86R 14

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

L10: Budgeting and Cost Control. Olivier de Weck

Schedule Adherence. and Rework Walt Lipke, PMI Oklahoma City Chapter. PUBLISHER s CHOICE

EVM.01. Earned Value Analysis Why it Doesn't Work

Earned Value and Agile Reporting

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

A Gentle Introduction to Earned Value Management Systems

Project Management Using Earned Value

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Simple Earned Value (Using MS Project 2010)

Tracking Budgets and Schedules

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

Schedule Analysis Using Earned Value Concepts ABSTRACT

Chapter 7: Project Cost Management. Munawar

Project Cost Management

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Predicting progress on your project

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004

Earned Value Management Guidelines

Schedule Compression

The To Complete Performance Index

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

Applying Fuzzy Control Chart in Earned Value Analysis: A New Application

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Project Time Management

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study

plans based on actual cost, schedule and technical progress of work [1, 9].

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry

PERCEPTION. Tracking Progress & EAC

Project Control. 1. Schedule Updating

Create Stoplight charts using Milestones Professional

Earned Value Analysis Exercise

Monitoring Scrum Projects with AgileEVM and Earned Business Value (EBV) Metrics

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Project Management Glossary

Project Time Management

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects

DCMA DCMA-EA PAM October 2012

Agile Project Management Controls

Chapter 6. (PMBOK Guide)

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Transcription:

Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems svv@fabricom.be 1

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 2

Introduction Earned Value Management (EVM) as defined in the 2000 Edition of the PMBOK Guide: A method for integrating scope, schedule and resources, and for measuring project performance. Definition implies equal weight to both cost & schedule Reality is that most EVM metrics focus primarily on cost EVM was developed for cost measurement, not scheduling There is currently a trend to use performance indicators for predicting project duration. 3 methods are presented here. 3

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 4

Schedule Variance (SV) SV = Earned Value - Planned Value = EV - PV Positive (+) variance: volume of work performed ahead of plan Negative (-) variance: volume of work performed behind plan SV does not measure time, it measures volume of work done versus planned on same basis (Euros) SV does not identfy work, requires drill down analysis + may be bad: work done not on critical path, offsetting tasks - may be good: work behind has float, offsetting tasks SV is zero at end of project, even when project is late Suggestions for other name: Progress Variance or Accomplishment Variance 5

Example - SV Early Finish Project Late Finish Project 500 0 400 300-50 -100-150 200 100 0-100 SV CV -200-250 -300-350 -400 SV CV -200 1 2 3 4 5 6 7 8 9 10 11 12-450 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 6

Schedule Performance Index (SPI) SPI = Earned Value / Planned Value = EV / PV SPI > 1: volume of work performed ahead of plan SPI = 1: volume of work perfomred according to plan SPI < 1: volume of work performed behind plan SPI does not have a dimension SPI does not identfy work, requires drill down analysis >1 may be bad: work done not on critical path, offsetting tasks <1 may be good: work behind has float, offsetting tasks SPI equals 1 at end of project: even when project is late, the index shows a perfect schedule performance 7

Example - SPI Early Finish Project Late Finish Project 1,200 1,000 1,150 1,100 1,050 1,000 0,950 CPI SPI 0,975 0,950 0,925 0,900 0,875 0,850 0,825 CPI SPI 0,900 1 2 3 4 5 6 7 8 9 10 11 12 0,800 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 8

Discussion of schedule metrics Strenghts of SV & SPI: provides a reliable early warning Reflects cost/schedule integration Weaknesses of SV & SPI: SV initially follows a trend, but moves towards 0, even if project is late SPI initially follows a trend, but moves towards 1, even is project is late SV & SPI does not indicate the real performance of the project At a certain point in time, the SV & SPI are no more reliable for forecasting purposes. This grey area occurs usually the last third of the project. 9

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 10

Generic Formula EDAC = Actual Duration + Estimated Duration Work Remaining EDAC = AD + EDR EDAC = Estimated Duration at Completion AD = Actual Duration ( time now) EDR = Estimated Duration of Remaining Work The EDR is the portion to guess at best The Estimated Duration of Work Remaining is influenced by the project environment 6 types are defined 11

Types of EDR Estimates (1) Case 1: new EDR estimate occurs when original assumptions are no longer valid a new estimate (new schedule) needs to be developped forecasting formulas are useless in this case Case 2: EDAC as planned project will be on schedule, even when prior performance is poor f.e. we ll catch up during the testing phase can be dangereous,as unfixed problems don t fix themselves Case 3: EDR substantially higher as planned f.e. additional time is needed to fix various problems estimate in general not quantified more common as we believe 12

Types of EDR Estimates (2) Case 4: EDR as planned past schedule problems will not occurr in the future future progress will be according to plan Case 5: EDR will continue with current SPI trend past problems will continue in the future f.e. because of delaying corrective actions, is a realistic case Case 6: EDR will continue with current SCI trend SCI = critical ratio = CPI * SPI used when adherence to budget is critical to organization 13

Forecasting Methods Forecast Method Case 1 EDAC = new 2 EDAC as originally planned 3 EDAC is very high Anbari (*) Jacob (**) Lipke (***) re-schedule monitor schedule re-schedule 4 EDR according to plan EDACpv1 EDACed1 EDACes1 5 EDR will follow current SPI trend EDACpv2 EDACed2 EDACes2 6 EDR will follow current SCI trend EDACpv3 EDACed3 EDACes3 EDAC = Estimated Duration at Completion Planned Value Rate Earned Duration Earned Schedule * Earned Value Project Management Method and Extensions, Project Management Journal, Dec. 2003 ** Forecasting Project Schedule Completion with EV Metrics, The Measurable News, Summer 2004 *** Further Developments in Earned Schedule, The Measurable News, Spring 2004 14

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 15

Method 1: PV Rate PV Rate = BAC / TAC PV Rate = Planned Value Rate ( /month, /week, ) TAC = Time at Completion, number of periods (months, weeks, ) BAC = Budget at Completion TV = SV / PV Rate TV= Time Variance (months, weeks, ) SV = Schedule Variance 16

Method 1: PV Rate EDR according to plan EDACpv1 = TAC - TV EDR with continued SPI performance EDACpv2 = TAC / SPI EDR with continued SCI performance EDACpv3 = TAC / SCI 17

Method 1: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: 35.000 (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV 5.000 10.000 15.000 20.000 25.000 30.000 35.000 AC 3.750 9.100 12.750 EV 3.500 8.500 12.000 SPI 0,70 0,85 0,80 CPI 0,93 0,93 0,94 SCI 0,65 0,79 0,75 PV Rate = BAC / TAC = 35.000 / 7 = 5.000 / week TV = SV / PV Rate = (12.000-15.000) / 5.000 = -0,6 weeks EDACpv1 = TAC - TV = 7 - (-0,6) = 7,6 weeks EDACpv2 = TAC / SPI = 7 / 0,80 = 8,75 weeks EDACpv3 = TAC / SCI = 7 / 0,75 = 9,33 weeks 18

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 19

Method 2: ED Method ED = AD * SPI ED = Earned Duration AD = Actual Duration SPI = Schedule Performance Index EDAC = AD + (TAC - ED) / P.F. EDAC= Estimated Duration at Completion TAC = Time at Completion ED = Earned Duration P.F. = Performance factor (according to different cases) 20

Method 2: ED Method EDR according to plan (P.F. = 1) EDACed1 = AD + (TAC - ED) / 1 = TAC + AD x (1 - SPI) EDR with continued SPI performance (P.F. = SPI) EDACed2 = AD + (TAC - ED) / SPI = TAC / SPI EDR with continued SCI performance proposed in reference: EDACed3 = TAC / SCI mathematically correct: EDACed3m = TAC / SCI + AD x (1-1/CPI) 21

Method 2: Extension Corrective action metric: TCSPI TCSPI = (TAC - ED) / (TAC - AD) TCSPI = To Complete Schedule Performance Index a measure of the required performance needed to bring in the project on the planned time TCSPI = (TAC - ED) / (EDAC - AD) TCSPI = To Complete Schedule Performance Index a measure of the required performance needed to bring in the project on the estimated EDAC time 22

Method 2: Extension What when work is not finished and planned duration is passed? Mathematically: AD > PD and SPI < 1 TAC is being replaced by AD EDACed1 = AD (2 - SPI) EDACed2 = AD / SPI EADCed3 = AD / SCI EADCed3m = AD (1-1/CPI + 1/SCI) 23

Method 2: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: 35.000 (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV 5.000 10.000 15.000 20.000 25.000 30.000 35.000 AC 3.750 9.100 12.750 EV 3.500 8.500 12.000 SPI 0,70 0,85 0,80 CPI 0,93 0,93 0,94 SCI 0,65 0,79 0,75 ED = AD x SPI = 3 x 0,8 = 2,4 weeks EDACed1 = TAC + AD (1 - SPI) = 7 + 3 (1-0,80) = 7,6 weeks EDACed2 = TAC / SPI = 7 / 0,80 = 8,75 weeks EDACed3 = TAC / SCI = 7 / 0,75 = 9,33 weeks EDACed3m = TAC / SCI + AD (1-1/CPI) = 9,14 weeks 24

Method 2: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: 35.000 (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV 5.000 10.000 15.000 20.000 25.000 30.000 35.000 AC 3.750 9.100 12.750 EV 3.500 8.500 12.000 SPI 0,70 0,85 0,80 CPI 0,93 0,93 0,94 SCI 0,65 0,79 0,75 TCSPI = (TAC - ED) / (TAC - AD) = (7-2,4) / (7-3) = 1,15 TCSPI = (TAC - ED) / (EDACed1 - AD) = 1,00 TCSPI = (TAC - ED) / (EDACed2 - AD) = 0,80 TCSPI = (TAC - ED) / (EDACed3 - AD) = 0,73 TCSPI = (TAC - ED) / (EDACed3m - AD) = 0,75 25

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 26

Method 3: Earned Schedule Idea of Earned Schedule is identical as Earned Value Instead of using cost for measuring schedule performance, we will use time Earned Schedule is determined by comparing Earned Value to the performance baseline (= planned value). The time associated with the Earned Value is found from the PV-curve. So we project the Earned Value onto the Planned Value curve 27

EV vs. ES - Graphical Display AC CV AC Projection of EV onto PV PV SV PV EV EV time ES AT Earned Value Earned Schedule time 28

ES Calulation ES = N + (EV - PV N ) / (PV N+1 - PV N ) ES = Earned Schedule N = time increment of PV that is less than current PV PV N = Planned Value at time N PV N+1 = Planned Value at time N + 1 PV N = 2 EV I M1 M2 M3 M4 M5 time ES AT = PT 29

ES Derived Metrics Derived metrics, similar to the classical Earned Value: SV(t) = ES - AT positive = ahead of schedule negative = lagging SPI(t) = ES / AT >1 = ahead of schedule >1 = lagging EDAC = AT + Estimated Remaining Time to Completion = AT + (TAC - ES) / P.F. 30

ES Forecasting EDR according to plan (P.F. = 1) EDACes1 = AD + (TAC - ES) EDR with continued SPI(t) performance EDACes2 = AD + (TAC - ES) / SPI(t) EDR with continued SPI performance EDACes3 = AD + (TAC - ES) / SCI(t) Corrective Action Metric TCSPI(t) = (TAC - ES) / (TAC - AT) 31

Method 3: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: 35.000 (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV 5.000 10.000 15.000 20.000 25.000 30.000 35.000 AC 3.750 9.100 12.750 EV 3.500 8.500 12.000 N 1 2 3 4 5 6 7 ES 0,70 1,70 2,40 SPI(t) 0,70 0,85 0,80 SCI(t) 0,65 0,79 0,75 EDACes1 = AD + (TAC - ES) = 3 + (7-2,4) = 7,6 weeks EDACes2 = AD + (TAC - ES) / SPI(t) = 8,75 weeks EDACes3 = AD + (TAC - ES) / SCI(t) = 9,33 weeks TCSPI(t) = (TAC - ES) / (TAC - AT) = (7-2,4) / (7-3) = 1,15 32

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 33

Summary of Results Forecast Method Case 1 EDAC = new 2 EDAC as originally planned 3 EDAC is very high Anbari (*) Jacob (**) Lipke (***) re-schedule monitor schedule re-schedule 4 EDR according to plan 7,60 7,60 7,60 5 EDR will follow current SPI trend 8,75 8,75 8,75 6 EDR will follow current SCI trend 9,33 9,33 (9,14) 9,33 Planned Value Rate Earned Duration Earned Schedule All results are the same! Why? 34

Why are Results the Same? All methods apply the same basic parameters (EV, PV, ) All methods are based on sound analytical thought Formulas used in methods are linear, as well as the used PV in the example. If the PV is non-linear, differences between the methods could be introduced. These errors can be reduced by using smaller time increments (more reporting periods) 35

Non Linear PV Rate Scope: TAC: install 350 TFT Monitors, including learning curve 7 weeks BAC: 35.000 (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV 1.500 4.000 7.500 12.000 18.000 26.000 35.000 AC 3.750 9.100 12.750 EV 3.500 8.500 12.000 SPI 2,33 2,13 1,60 CPI 0,93 0,93 0,94 SCI 2,18 1,98 1,51 AT 1 2 3 4 5 6 7 ES 1,80 4,00 4,00 SPI(t) 1,80 2,00 1,33 SCI(t) 1,68 1,87 1,25 35.000 PV 30.000 25.000 20.000 15.000 10.000 5.000 0 W1 W2 W3 W4 W5 W6 W7 36

Results - Non Linear PV - W3 Forecast Method Case 1 EDAC = new 2 EDAC as originally planned 3 EDAC is very high Anbari (*) Jacob (**) Lipke (***) re-schedule monitor schedule re-schedule 4 EDR according to plan 6,10 5,20 6,00 5 EDR will follow current SPI trend 4,38 4,38 5,25 6 EDR will follow current SCI trend 4,65 4,65 5,39 Planned Value Rate Earned Duration Earned Schedule 37

Discussion Results are no longer identical, and depends on used method. The Earned Schedule method appears to forecast higher durations, compared with other methods. But most important: So far we applied the formulas to a single activity. How do the methods behave on higher WBS levels? Which method is the best? 38

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level Case Study Conclusion 39

Case Study 400.000 350.000 300.000 250.000 200.000 150.000 100.000 50.000 973.xxx C.I. 6 - R11/12 Scope: revamping of C.I. Island BAC: 360.738 TAC: 9 months WBS: Project Level 0 juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AC EV PV BAC 40

Case Study - EV Metrics juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AC 25.567 66.293 78.293 124.073 191.367 259.845 285.612 290.843 303.489 316.431 320.690 336.756 349.379 EV 25.645 68.074 89.135 125.244 198.754 268.763 292.469 306.725 312.864 327.694 338.672 349.861 360.738 PV 28.975 81.681 91.681 138.586 218.141 302.478 323.632 345.876 360.738 360.738 360.738 360.738 360.738 SV -3.330-13.607-2.546-13.342-19.387-33.715-31.163-39.151-47.874-33.044-22.066-10.877 0 SPI 0,89 0,83 0,97 0,90 0,91 0,89 0,90 0,89 0,87 0,91 0,94 0,97 1,00 20.000 1,100 10.000 1,050 0-10.000-20.000-30.000-40.000-50.000 juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 SV CV 1,000 0,950 0,900 0,850 0,800 juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 SPI CPI 41

Case Study - ES Calulation juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AC 25.567 66.293 78.293 124.073 191.367 259.845 285.612 290.843 303.489 316.431 320.690 336.756 349.379 EV 25.645 68.074 89.135 125.244 198.754 268.763 292.469 306.725 312.864 327.694 338.672 349.861 360.738 PV 28.975 81.681 91.681 138.586 218.141 302.478 323.632 345.876 360.738 360.738 360.738 360.738 360.738 SV -3.330-13.607-2.546-13.342-19.387-33.715-31.163-39.151-47.874-33.044-22.066-10.877 0 SPI 0,89 0,83 0,97 0,90 0,91 0,89 0,90 0,89 0,87 0,91 0,94 0,97 1,00 ###### 10 11 9 10 10 10 10 10 10 11 12 12 13 ###### 10,168649 10,33395 9,83463248 9,68900263 9,4611219 9,6424529 10,711879 11,611469 12,478873 12,53026225 12,897112 13,062198 13 AT 1 2 3 4 5 6 7 8 9 10 11 12 13 ES 0,885 1,742 2,745 3,716 4,756 5,600 5,881 6,201 6,491 7,183 7,676 8,268 9,000 PT 1 2 3 4 5 6 7 8 9 9 9 9 9 SV(t) -0,115-0,258-0,255-0,284-0,244-0,400-1,119-1,799-2,509-2,817-3,324-3,732-4,000 SPI(t) 0,89 0,87 0,92 0,93 0,95 0,93 0,84 0,78 0,72 0,72 0,70 0,69 0,69 Example ES Calculation (period 09/02, 4th period): ES = 3 + (125.244-91.681) / (138.586-91.681) = 3,716 months Example ES Calculation (period 01/03, 8th period): ES = 6 + (306.725-302.478) / (323.632-302.478) = 6,201 months 42

Case Study - ES Calulation juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AT 1 2 3 4 5 6 7 8 9 10 11 12 13 ES 0,885 1,742 2,745 3,716 4,756 5,600 5,881 6,201 6,491 7,183 7,676 8,268 9,000 PT 1 2 3 4 5 6 7 8 9 9 9 9 9 SV(t) -0,115-0,258-0,255-0,284-0,244-0,400-1,119-1,799-2,509-2,817-3,324-3,732-4,000 SPI(t) 0,89 0,87 0,92 0,93 0,95 0,93 0,84 0,78 0,72 0,72 0,70 0,69 0,69 Example SPI(t) Calculation (period 12/02, 7th period): SPI(t) = 5,881 / 7 = 0,84 Project is progressing at at a rate of 0,78 months for each month of actual time Example SV(t) Calculation (period 12/02, 7th period): SV(t) = 5,881-7 = - 1,119 Project lags it expected performance by 1,119 months 43

Case Study - SV vs. SV(t) 0-5.000-10.000-15.000-20.000-25.000-30.000-35.000-40.000-45.000-50.000 0,0-0,5-1,0-1,5-2,0-2,5-3,0-3,5-4,0-4,5-5,0 44 Euros juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 Months SV SV(t)

Case Study - SPI vs. SPI(t) In this timeframe, SPI & SPI(t) correlates very well AT 11/02, or at the ca. 75% completion point, the SPI becomes unreliable 1,00 0,95 0,90 0,85 0,80 0,75 0,70 0,65 juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 SPI SPI(t) 45

Case Study - EDAC P.F. = 1 14 13 12 At 11/02, or at the ca. 75% completion point, the IDACes is clearly more accurate 11 10 9 06/02 07/02 08/02 09/02 10/02 11/02 12/02 01/03 02/03 03/03 04/03 05/03 06/03 EDACpv 9,08 9,34 9,06 9,33 9,48 9,84 9,78 9,98 10,19 9,82 9,55 9,27 9,00 EDACed 9,11 9,33 9,08 9,39 9,44 9,67 9,67 9,91 10,19 10,92 11,67 12,36 13,00 EDACes 9,11 9,26 9,25 9,28 9,24 9,40 10,12 10,80 11,51 11,82 12,32 12,73 13,00 PV Rate Method: correlates well at early stages, but is useless towards the end ED Method: correlates well till 75% completion point ES Method: predicts more accurate towards the final stages 46

Case Study - EDAC P.F. = SPI 14 13 12 At 11/02, or at the ca. 75% completion point, the IDACes is clearly more accurate 11 10 9 06/02 07/02 08/02 09/02 10/02 11/02 12/02 01/03 02/03 03/03 04/03 05/03 06/03 EDACpv 10,17 10,80 9,26 9,96 9,88 10,13 9,96 10,15 10,38 9,91 9,59 9,28 9,00 EDACed 10,17 10,80 9,26 9,96 9,88 10,13 9,96 10,15 10,38 11,01 11,72 12,37 13,00 EDACes 10,17 10,33 9,83 9,69 9,46 9,64 10,71 11,61 12,48 12,53 12,90 13,06 13,00 PV Rate Method: correlates well at early stages, but is useless towards the end ED Method: correlates well till 75% completion point ES Method: predicts more accurate towards the final stages 47

Case Study - EDAC P.F. = SCI 14 13 12 11 At 11/02, or at the ca. 75% completion point, the IDACes is clearly more accurate 10 9 8 06/02 07/02 08/02 09/02 10/02 11/02 12/02 01/03 02/03 03/03 04/03 05/03 06/03 EDACpv 10,14 10,52 8,13 9,87 9,51 9,79 9,73 9,62 10,07 9,57 9,08 8,93 8,72 EDACed 10,14 10,52 8,13 9,87 9,51 9,79 9,73 9,62 10,07 10,63 11,09 11,91 12,59 EDACes 10,14 10,12 9,00 9,64 9,30 9,52 10,62 11,42 12,37 12,44 12,80 13,02 13,00 PV Rate Method: correlates well at early stages, but is useless towards the end ED Method: correlates well till 75% completion point ES Method: predicts more accurate towards the final stages 48

Case Study - ED vs. ES AT ES PT EDACed PF=SPI EDACes PF=SPI(t) EDACed PF=SCI EDACes PF=SCI(t) 14 12 10 8 6 4 2 0 06-02 07-02 08-02 09-02 10-02 11-02 12-02 01-03 02-03 03-03 04-03 05-03 06-03 49

Discussion During early and middle project stage All methods seems to correlate well All methods produce same results within the same range During late project stage The PV Rate method is useless and meaningless (at project level, the PV is non-linear, but follows a S- curve) The ED method tends to underestimate the final duration ( remember the strange SPI behaviour, the grey area ) The ES method produces the best forecast results 50

Other example (presentation 2) AT PT ES EDACes spi(t) EDACed spi 14 12 10 8 At M6-7, or at the ca. 70% completion point, the IDACes is clearly more accurate 6 4 2 0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 51

Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 52

Schedule Forecasting The use of EV metrics to forecast the schedule should happen at least on the overall project level (early warning signal): for early and middle poject stages, each method can be used for late project stage (mostly the most important period), the ES method produces clearly the best results When performance is poor, a drill-down into the lower WBS levels will help detect the troubled tasks If tasks are on the critical path, evaluation of the forecasted duration impact ca be made The use of earned duration and earned schedule metrics is NOT a replacement for scheduling tools such as PERT, CPM, Monte Carlo scheduling 53

Forecasting Methods At early and middle stage Forecast Method PV Rate ED ES EDR according to plan TAC - TV TAC + AD (1 - SPI) AD + (TAC - ES) EDR will follow current SPI trend TAC / SPI TAC / SPI AD + (TAC - ES) / SPI(t) EDR will follow current SCI trend TAC / SCI TAC / SCI AD + (TAC - ES) / SPI(t) At late stage Forecast Method PV Rate ED ES EDR according to plan --- --- AD + (TAC - ES) EDR will follow current SPI trend --- --- AD + (TAC - ES) / SPI(t) EDR will follow current SCI trend --- --- AD + (TAC - ES) / SPI(t) 54

Conclusion SPI & SV indicators are flawed and exhibit strange behaviour over the final third of the project, and are as a consequence not reliable. The use of the Earned Schedule method provides indicators SPI(t) & SV(t), which behave correctly during the project life. It has been demonstrated that the use of ES metrics provides a more reliable forecast for total project duration. Why not starting to use the earned schedule method as a standard procedure? 55