A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry
|
|
|
- Roderick Caldwell
- 9 years ago
- Views:
Transcription
1 A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry Pranam B 1, Madhusudan G Kalibhat 2, Sudharshan KR 3 1 Student, Master of Technology (Construction Engineering and Management), Department of Civil Engineering, Manipal Institute of Technology, Manipal Assistant Professor, Department of Civil Engineering, Manipal Institute of Technology, Manipal Senior Vice President, Planning, Sobha Developers Ltd., Bangalore Abstract In this paper, we look to describe a new perspective to consider and quantify uncertainty in construction schedules where a methodology was presented by modeling construction project scheduling using event chains, classification of the events and event chains, identification of critical events, analysis of effect of the events on project duration, and chance of project completion to find out the applicability of the proposed methodology. A residential apartment is considered as a pilot project and a project specific schedule risk analysis system and risk break down structure is also developed as an essential part. Earned Value Analysis is carried out to quantify the performance of the scheduling technique through Schedule Performance Index. The average Scheduling Performance Index value for the Event Chain Methodology schedule over the duration of the project is found to be 10.96% greater than that of Critical Path Method which can be used as one of the contributing factors to promote usage of Event Chain Methodology. Keywords Event chain methodology, Critical Path Method, Earned Value Analysis, Project Scheduling, Scheduling Risk Analysis System. I. INTRODUCTION Construction managers plan, coordinate, budget, and supervise construction projects from development to completion. In spite of so many efforts, man hours and resources, we still find it very difficult to finish construction projects on time within budget and available resources. Type of structure, complexity, location, type of resources and natural conditions make every project unique. There is no ideal condition for construction activity. Although the existing project management techniques like CPM, PERT, CCPM, LOB are facilitating better performance, effective utilization of these techniques is not done satisfactorily. Identification of the suitable construction management technique is very important for the successful completion of any construction project. The construction industry has been using quantitative network modelling techniques to simulate the construction process since the late 1950s. However, much has been written on the problems concerned with traditional scheduling processes. One of the issues with traditional scheduling processes is that the critical-path method (CPM) is deterministic in nature; the process thereby ignores the effects of uncertainty by using a single value for the time estimate of each activity and even the entire construction of the project. Practically, in most cases, duration, start and finish time, and other task parameters are uncertain. To solve this issue, the PERT model (Program Evaluation and Review Technique) was developed in 1950s to address uncertainty in the estimation of project parameters. The expected task duration in PERT model is calculated as the weighted average of the most optimistic, the most pessimistic, and the most likely time estimates. However, the main problem with classic PERT is that it gives accurate results only if there is a single dominant path through a precedence network. When a single path is not dominant, classic PERT usually provides overly optimistic results. Another approach to project scheduling with uncertainties is CCPM (Critical Chain Project Management) which was developed by Goldratt. Goldratt applied the theory of constraints (TOC) to project management known as critical chain project management (CCPM). The cornerstone of TOC is resource constrained critical path called a critical chain. Goldratt s approach is based on a deterministic critical path method. To deal with uncertainties, Goldratt suggested using project buffers and encouraged early task completion. Theory of constraints is well accepted in project management; however, this approach still does not pay enough attention to the specific stochastic risk events occurred in on-site construction environment. In addition, for its complex operation process, the range of use of this method is limited. Event chain methodology (ECM) was developed as a risk and uncertainty modelling technique for project management based on existing mature quantitative method such as Monte Carlo simulation and Bayesian theorem. 69
2 Event chain methodology focuses on identifying and managing the events and event chains that affect projects. Event chain methodology improves the accuracy of project planning while simplifying the modelling and analysis of uncertainties in the project schedules which the PERT and Critical Chain are not sufficiently equipped with. The highlight of this work is on the comparative study of two different scheduling techniques viz. Critical Path Method (CPM) and Event Chain Methodology (ECM) which aims to give a comparison of the scheduling techniques on their application through Earned Value Analysis. II. RESEARCH OBJECTIVE 1. To simplify and adopt a model for scheduling risk analysis system made according to project requirements. 2. To provide a methodology for modelling a construction project schedule using event chains, classification of the events and event chains, identification of critical events, analysis of effect of the events on project duration. 3. To check the applicability of the proposed Event Chain Methodology when compared to the application of Critical Path Method in terms of Schedule Performance Index. III. IMPLEMENTATION PROCESS This study starts with the implementation of CPM and ECM for a pilot project on a trial basis for a residential apartment (G+4) framed structure with the scheduling done in CPM for the structural aspect of the building. The total duration for the handover of the structure was initially considered as 8 months, the project was on hold for several approvals and it had to resume from Ground Floor. The scheduling process involved the creation of an Enterprise Project Structure (EPS) with the pilot project being one among them, an Organizational Breakdown Structure (OBS) which indicates the roles of a particular individual in the pilot project, a detailed micro-level Work Breakdown Structure (WBS) where every small sub-division concerned to the project is indicated and every activity or the task concerned to the sub-divisions of the WBS are added. Labour and Non-Labour resources, such as engineers and equipment are generally time bound, but this schedule has assigned these resources to the respective activities in terms of Cost/Unit and not in hours, the materials are also assigned in terms of Cost/Unit. The formula used for calculating the required manpower by using the productivity details maintained by the company is, Manpower Requirement (numbers) = (Total Quantity for the Activity or Task) / (Average Productivity per day Duration of the Activity in days) Sl. No. Table I The Pilot Project Information Project Information - Vijay Kumar Residence Description 1 Super Built-up Area in sft 12, Number of floors B+G+4 3 No. of Blocks 1 4 Total number of apartments 4 Nos. of 3BHK 5 Project duration 539 Days 6 Structure Duration 222 Days A baseline schedule is created using the Critical Path Method (CPM) technique. The schedule so created is taken as a benchmark for the creation of a baseline schedule using the Event Chain Methodology (ECM) technique. The principles of ECM were the basis for the generation of the baseline schedule. A Scheduling Risk Analysis Model was developed for the pilot project according to the needs of the project and it is project specific. The flow chart shown in Figure 1 indicates the procedure through which the baseline schedule for ECM was created. Having taken the baseline schedule of CPM technique as benchmark, the risk register or the Risk Breakdown Structure (RBS) was created where the risk factors along with the probabilities and impact have been derived from the review technique with the help of members of the Planning Department of the organization, the past experience and the delay reports of five recently concluded projects of the organization with changes in the probabilities and impact through a continuous review technique involving the same members of the organization. 70
3 Figure I The Scheduling Risk Analysis Model The schedules with different techniques were finalized and the baselines were worked out to be the following: Table II Baseline Durations Corresponding To Scheduling Techniques Serial No. Scheduling Technique Baseline Duration (Days) 1 CPM ECM 191 After the baseline schedule was fixed, the tracking and monitoring of the activities or tasks was started. The construction sequence of the pilot project was tracked with the two different schedules viz., CPM and ECM. The schedule was updated every fortnight in both the schedules. The actual start and actual finish of the activities were the same for both techniques and consequently Earned Value (EV) was carried to track the progress of work v/s planned work financially to quantify the project performance. IV. RESULTS Earned Value Analysis was carried out to give a clear picture on the Schedule Performance Index (SPI) with respect to time for both the scheduling techniques. All the relevant cost details are according to the Delhi Schedule of Rates (DSR) released by the Central Public Works Department, New Delhi. A. Critical Path Method Results Figure 2 shows the variation of the EV with time for CPM and the graph does not show much variation in the end, i.e. the deviation of the actual cost to the higher value than the planned value is not highly significant as the only important factor contributing to the higher value is the inflation of material cost for A-Class materials. The planned value is significantly higher than the earned value for the duration between September 2013 and Jan 2014 due to several delays that were anticipated but not accommodated in the schedule. 71
4 Figure II Earned Value Over Time For Cpm Technique Table III Values Used To Generate EV And SPI Graphs For CPM Technique: CPM ACTUAL COST PLANNED VALUE EARNED VALUE Aug , , , Sep , ,053, , Oct-13 1,737, ,493, ,799, Nov-13 2,294, ,929, ,995, Dec-13 4,238, ,020, ,294, Jan-14 5,621, ,097, ,540, Feb-14 6,864, ,097, ,718, Mar-14 7,101, ,097, ,921, Apr-14 7,246, ,097, ,060, The average SPI value for the CPM schedule over the duration of the project is found to be approximately 0.73 which is less than the ideal value of 1 indicating the project has been behind schedule. B. Event Chain Methodology Results Figure 4 shows the variation of the EV with time for ECM technique and the graph indicates a small deviation of the actual cost to the higher value than the planned value is not highly significant as the only important factor contributing to the higher value is the inflation of material cost for A-Class materials. The planned value is significantly higher than the earned value for the duration between September 2013 and December 2013, but lesser than that compared to the CPM schedule because of the incorporation of the scheduling risk analysis model. Figure IV Earned Value Over Time For Ecm Technique (GENERATED FROM THE VALUES IN TABLE 4) TABLE IV VALUES USED TO GENERATE EV AND SPI GRAPHS FOR ECM Figure III Schedule Performance Index Over Time For Cpm Technique Figure 3 indicates the variation of SPI with time for CPM. The ideal value of the SPI for the project to be on track with the schedule is 1. The graph gives an indication that the project has never been on track with the schedule except for the month of August 2013 where the project was ahead of schedule. Technique: ACTUAL PLANNED EARNED ECM COST VALUE VALUE Aug , , , Sep , ,830, , Oct-13 1,737, ,185, ,799, Nov-13 2,294, ,157, ,995, Dec-13 4,238, ,040, ,294, Jan-14 5,621, ,899, ,540, Feb-14 6,864, ,097, ,718, Mar-14 7,101, ,097, ,921, Apr-14 7,246, ,097, ,060,
5 The study can be concluded by saying ECM approach is a better approach to this kind of a project. Figure V Schedule Performance Index Over Time For Ecm Technique Figure 5 indicates the variation of SPI with time for the ECM technique. The ideal value of the SPI for the project to be on track with the schedule is 1. The graph gives an indication that the project has never been on track with the schedule except for the month of August 2013 where the project was ahead of schedule. The average SPI value for the schedule ECM over the duration of the project is found to be 0.81 which is greater than that of CPM but lesser than the ideal value of 1 indicating the project has been behind schedule. V. CONCLUSION As discussed in the results, the implementation of ECM gave better results than CPM. The preferred choice of a scheduling technique for a similar project would be ECM among CPM and ECM for the following reasons: 1. The average SPI for ECM schedule was found to be 10.95% better than that of CPM. 2. ECM gives some importance to resource allocation and resource calendar constraints unlike CPM where there is no emphasis on resource allocation. 3. ECM is seen to be very effective in construction project management where a structured approach is provided to identify the sources of risk and based on these risks, to determine the range of schedule outcomes. The incorporation of risk analysis is ground zero for ECM unlike CPM. 4. ECM gives equal importance to non-critical activities which is indicated by a Critical Event Chain which is a sequence of linked activities which affect the project's completion date due to risk assignments. Critical Event Chains can lie outside of the calculated critical path. VI. SCOPE FOR FUTURE RESEARCH Research has shown that Event Chain Methodology gave good results to an airport terminal project and also is applicable to different time related development projects. We can also try to implement the same for different types of construction like bridge construction, commercial buildings and infrastructure projects and so on as a part of extending the research. The contractor s perception towards the acceptance of ECM can also be a part of the extended research where the contractor s direct cost and indirect cost shoots up with prolonged delays and reduces his profit margin. REFERENCES [1] B. Mulholland, J.C., Risk Assessment in Construction Schedules, Journal of Construction Engineering and Management, Vol. 125, No. 1, (1999) [2] Cho J. G., Y.B.J. An Uncertainty Importance Measure of Activities in PERT Networks, International Journal of Production Research, 1964 (12): p [3] C, Newbold. R, Project Management in the Fast Lane: Applying the Theory of Constraints, Boca Raton, FL: St. Lucie Press (1998). [4] Goldratt, E., Critical Chain, Great Barrington, Mass: North River Press (1997). [5] Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Third Edition, Newtown Square, PA: Project Management Institute (2004). [6] Lev Virine, Michael Trumper, Schedule Network Analysis Using Event Chain Methodology, Intaver Institute Inc. (2004). [7] Wei Peng, Liangfa Shen, Deyin Liu, Construction Project Scheduling Risk Analysis Using Event Chain Methodology: An Example of Airport Terminal Project, Trans Tech Publications, Applied Mechanics and Materials Vols (2012) [8] K K Chitkara (1998), Construction Project Management- Planning, Scheduling and Controlling, Tata McGraw Hill Publishing Company Limited. [9] Russel, A. and Wong, W. (1993), New Generation of Planning Structures, Journal of Construction Engineering and Management, ASCE, 119(2), [10] Joseph A Lukas(2008), Earned Value Analysis Why it Doesn t Work?, AACE INTERNATIONAL TRANSACTIONS (EVM.01), USA 73
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
Software Project Scheduling under Uncertainties
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL Jan, Shu-Hui Ph.D. Student Construction Engineering & Management Program Department of Civil Engineering National Taiwan University
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
PROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Quantitative Risk Analysis with Microsoft Project
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp.
Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp. Code for Course: MBL45-5 Assignment Number: 2 Student number: 75-163-3 Group Code Number: BOT1 Table of Contents
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP
Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented
CCPM: TOC Based Project Management Technique
CCPM: TOC Based Project Management Technique Prof. P.M. Chawan, Ganesh P. Gaikwad, Prashant S. Gosavi M. Tech, Computer Engineering, VJTI, Mumbai. Abstract In this paper, we are presenting the drawbacks
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
Event Chain Methodology in Project Management
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Basic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management [email protected] 1 What is Project Management? A set of principles, methods, tools, and
earned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
PBL: Project Management. Competency: Project Definition
Competency: Project Definition 1. Define project management and the context of modern project management. 2. Describe how to manage projects throughout the five major process groups. 3. Define the characteristics
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) [email protected] Dr. P.K.
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
Introduction. http://www.alexsbrown.com/ Page 1
Modeling Tough Scheduling Problems with Project Management Software Alex S. Brown, PMP, Strategic Planning Manager, Mitsui Sumitomo Marine Management (U.S.A.), Inc. Introduction Despite year-over-year
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
Analysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.
Module 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the
EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
Mario Vanhoucke. Project Management. with Dynamic Scheduling. Baseline Scheduling, Risk Analysis. and Project Control. Second Edition.
Mario Vanhoucke Project Management with Dynamic Scheduling Baseline Scheduling, Risk Analysis and Project Control Second Edition 4^ Springer Contents 1 Introduction 1 1.1 Introduction 1 1.2 The Project
Integrated Qualitative and Quantitative Risk Analysis of Project Portfolios. Lev Virine
Integrated Qualitative and Quantitative Risk Analysis of Project Portfolios Lev Virine Presented at the: 2013 Enterprise Risk Management Symposium April 22-24, 2013 2013 Casualty Actuarial Society, Professional
CRASHING-RISK-MODELING SOFTWARE (CRMS)
International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management.
Knowledge Areas The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management. These are: Project Integration Management Project Scope
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
Project Management with Dynamic Scheduling
Mario Vanhoucke Project Management with Dynamic Scheduling Baseline Scheduling, Risk Analysis and Project Control 4u Springer 1 Introduction 1 1.1 Introduction 1 1.2 The Project Life Cycle (PLC) 2 1.2.1
Demonstrate and apply knowledge of project management in
Demonstrate and apply knowledge of project management in mechanical engineering 22918 version 2 Page 1 of 5 Level 6 Credits 15 Purpose This unit standard is intended primarily for use in diploma courses
Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects
Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects Ar. A. Cindrela Devi and K. Ananthanarayanan Abstract Resource continuity is a key issue for Mass housing construction
Project Management Planning
Overview of Resource Planning Every organization has a limited number of resources to perform tasks. A project manager's primary role is to find a way to successfully execute a project within these resource
Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control
Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP
SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
Industry Environment and Concepts for Forecasting 1
Table of Contents Industry Environment and Concepts for Forecasting 1 Forecasting Methods Overview...2 Multilevel Forecasting...3 Demand Forecasting...4 Integrating Information...5 Simplifying the Forecast...6
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
A Step-by-Step Approach for Planning Your Small Project
A Step-by-Step Approach for Planning Your Small Project Dohn Kissinger, MBA, PhD, PMP Planning for a small project is difficult. The PMBOK Guide (PMI, 1996) is an impressive document, which thoroughly
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
// Benchmarking Project Schedules
// Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...
Scheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
Family Computer Centre
PMP - Project Professional 35 Contact Hours Comprehensive Training Program Designed on the basis of Project Body of Knowledge (PMBOK Guide) Family Computer Centre Ground Floor, Al Rayyan Complex P. O Box:
CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR
JULY 2015 Area (RS-1) GSR GSR (LCS-1) Texarkana Incorporated July-15 $0.50690/Ccf $0.45450/Ccf $0.00000/Ccf $2.85090/MMBtu $17.52070/MMBtu Texarkana Unincorporated July-15 $0.56370/Ccf $0.26110/Ccf $1.66900/Ccf
Earned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
Cost Management. How Much Will This Project Cost?
Cost Management How Much Will This Project Cost? Moderator Janelle Abaoag Project Insight Marketing, Public Relations [email protected] www.projectinsight.net All participants will be on
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD [email protected] California State University, LA Computer and Information System Department Chapter 6: Project Time Management
PMI Lexicon of Project Management Terms
Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan
CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number
Is Critical Chain Project Management Really a Novel Technique?
Is Critical Chain Project Management Really a Novel Technique? Mario Špundak VIPnet usluge d.o.o. Vrtni put 1, 10000 Zagreb, Croatia [email protected] Krešimir Fertalj, Damir Kalpić University of Zagreb
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
MICROSOFT OFFICE PROJECT - SYLLABUS
MICROSOFT OFFICE PROJECT - SYLLABUS Sessions Session 1 Description 1. INTRODUCTION a. Introduction to CADFORUM and PPM b. Project c. Examples of project d. Project Triangle e. Project Management f. Life
PMP 2013 Exam Prep. Course Overview
PMP 2013 Exam Prep Course Overview This course has been designed to prepare participants to take the Project Management Institute's Project Management Professional (PMP) Exam, 2013 edition and is based
Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager
Resource Management Spreadsheet Capabilities Stuart Dixon Resource Manager Purpose Single view of resource data Shows rolling demand vs supply for 14 months, 2 months back, current month, and 11 forward
TECH. Tracking Progress. Project Schedule PHASE 1 STEP 1 ACTIVITY 1.1. Activity and Milestone STEP 1 STEP 2 : ACTIVITY 2.2 : ACTIVITY 1.
CH03 Planning and Managing the Project * Tracking Progress * Project Personnel * Effort Estimation * Risk Management * The Project Plan * Process Models and Project Management Tracking Progress Questions
A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method
Send Orders for Reprints to [email protected] 254 The Open Cybernetics & Systemics Journal, 2014, 8, 254-258 Open Access A Robustness Simulation Method of Project Schedule based on the Monte Carlo
Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule
1 (Image) 2 The process required to manage timely completion of the project. Project time management start with planning by the project management team (not shown as a discrete process). In small project,
The principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Winter : Lecture # Project Time Management Homework Discussion Homework
The Situation of Cost Management in Execution of Building Projects in Syria 1)
The Situation of Cost Management in Execution of Building Projects in Syria 1) Sarab Kasem and Mohammad Bachar Alhaffar 2) 1) This research has been conducted as part of a master dissertation by Eng. Sarab
Time Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved.
Time Management II http://lbgeeks.com/gitc/pmtime.php June 5, 2008 Copyright 2008, Jason Paul Kazarian. All rights reserved. Page 1 Outline Scheduling Methods Finding the Critical Path Scheduling Documentation
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
CPM-200: Principles of Schedule Management
CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright
Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Efficient Planning Scheduling And Delay Analysis Of Residential Project
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 3 Ver. I (May. - Jun. 2015), PP 126-133 www.iosrjournals.org Efficient Planning Scheduling