Short Interval Production Schedule Research



Similar documents
BILL OF QUANTITIES Part No.: Part Description

SWAN POINT YACHT & COUNTRY CLUB

QUOTATION FOR EXAMPLE BATHROOM RENOVATION

SCHEDULING AND PROJECT MANAGEMENT

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year

Milestones Primary. Early Start. Orig Dur. Early Finish. Act ID. Description NOTICE TO PROCEED START CONSTRUCTION

SECTION TABLE OF CONTENTS. H Proposed Material, Product or Equipment Substitution Request

PHASE VI INSTALLATION OF FURNISHING AND INTERIOR DECOR

T170 Interior Design Technology MTCU Code Program Learning Outcomes

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

COMMON FOR ARCHITECTS AND ENGINEERS Excerpts from HB 2284, 82 nd R

What to Expect Next. A Step-By-Step Guide To Building Your New Home

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series

17,280 square feet Overview:

Lindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

Segreti Design Scope of Interior Design Services

New Employee / Applicant - Information Pack (Includes: Driver Back round Release Form, Skills & Tools Assessment

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

WARRANTIES AND PERFORMANCE STANDARDS T A B L E O F C O N T E N T S General Provisions Introduction Warranties Effective Date of Warranties Exclusive

52 Ways To Save. 3. Ask for feedback. Ask about the pros and cons of different elements of your design and how each will affect your budget.

General Contractor & Construction Management Firm

SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME)

Building Condition Assessment Report

Takeoff and Estimating for Design-Build Contractors

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

How To Prevent Water Damage To A Home

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

Special Use Commercial Properties

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

In Partnership with. TDIndustries Diplomat Drive Dallas, Texas Phone: Fax: Website: TDIndustries.

All references to Pre-Construction Services in this Specification shall apply to requirements for CM-R and DB contract types only.

Your Company Name. Your Company Address Your City, State, Zip Your Phone Number Your Address. Project Information

Custom Home Designs, LLC

Join ASID! Industry Partner Application

ESTIMATE ORIG. ESTIMATE: TOTAL: $204,249 DATE: 01/15/08 DESCRIPTION OF WORK QUANTITY DIVISION TOTAL

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Home Repair Program. Section 1: Homeowner Information. Section 2: Special Needs Homeowner Application

Walmart 4th Wall. Advertising and Lease Line Guidelines. June Customerexperience

Title: Attic Keyword: Structure Description: roof framing rafters and decking File Name: P

KIEWIT CM/GC Enabling/Utilities

Civil Engineering and Architecture (CEA) Detailed Outline

Construction Technologies Career Field Pathways and Course Structure

Your Basement Remodeling Specialist LLC

Home Ownership & Basic Home Repair

CONSTRUCTION PROGRESS MONITORING REPORT

Borges Construction Company A limited liability Corporation Page1 of 1

WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL

Learning Objectives for the Interior Design program Department of Design, Textiles, Gerontology, & Family Studies

Design Development Quality Management Phase Checklist Project Phase Checklist Series

CHARLOTTE COUNTY Community Development Department

Home Designer. Interiors. New Version!

IMPROVEMENT COST ESTIMATE powered by HomeFixers

Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School

Quality Building Products for over 50 Years

Commercial Building Valuation Report

BUILDING PERMIT SPECIFICATIONS

Primavera P6 Exercise Worksheet

PATTERSON ELEMENTARY SCHOOL

Olilo's AEC Design Services. SrinSoft Inc, Partners of

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.

City of Peterborough

YOU VE BEEN HIRED AS A GENERAL CONTRACTOR

ISSUING AGENCY: New Mexico Public Regulation Commission, Insurance Division. [7-1-97; NMAC Rn & A, 13 NMAC 17.6.

LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

Print Shop/Mail Room

Every Student I Every Day I Every Possibility

HOMEOWNER S PERMIT GUIDE

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

DRAFT Document valid at the date shown on the page header. DETE Facilities Design Standards and Guidelines. General Index. Planning Guidelines

Facility Assessment Report, Montgomery Independent School District

0 - Initial Services

Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) Applications

Irvinton Village Apartments 2901 Fulton Houston, Texas Houston Housing Authority J. Allen Management Managing Agent

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION PAGE 1

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

Please note that exhibitor move out will not be permitted prior to 8:05 p.m and must be complete by 9:30pm.

SECTION 19 RESIDENTIAL CONSTRUCTION IN FLOODZONES

ARCHITECTURAL DRAWINGS OF THE APARTMENT BUILDING (S) CAD FILE. PROVIDED BY CUSTOMER. IF REQUIRED FROM US, ($1.80 SQ FT)

EMPLOYMENT APPLICATION

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule

ATTACHMENT A STRUCTURAL INTERIOR DESIGN (SID) REQUIREMENTS

Design Scenario Interior Design STAR Event

Think Of Us First! When It s Time to Distribute Your Plans

City of Fort Smith Building Permit Process Frequently Asked Questions

Scheduling Best Practices

Transcription:

Short Interval Production Schedule Research Background Nationals Park has multiple highly repeatable tasks that can be scheduled as efficiently as possible by the development of a Short Interval Production Schedule (SIPS). SIPS is a highly detailed way to schedule a repetitive construction project. Many construction projects go over budget and over schedule due to poor detailed scheduling and with the use of a SIPS it can make sure the project gets completed on time and on budget. A SIPS is developed to detail the necessary day-to-day production or task-to-task production during any repeatable construction project. It details scheduling at the crew level and must rely on exact information that is vital to the successful completion of any construction task. The most usefully cases where a SIPS can be beneficial is for a project that has many highly repeatable activities, such as apartments, hotels, office buildings and even schools. Typically, these projects will have a standardized interior floor or wing layout that makes the use of a SIPS desirable. The ballpark has just that with 58 of the same exact luxury suite. The interior build out of the suites will gain a great deal of scheduling time if SIPS was used to construct the luxury suites. There are 3 main ideas that differentiate SIPS from any other standard scheduling methods: Only one major specific operation is detailed A higher level of detail is developed then typically seen There must be personnel involvement and commitment from everyone contributing to the operation Final Architectural Engineering Senior Thesis Page 25

There are 5 steps that need to be taken to develop a SIPS: 1. Break the operation into specific activities 2. Assign production rates to each activity 3. Calculate extensions and set goals 4. Develop a time-scaled, resource loaded bar chart The major benefits that will be seen throughout the project will only be achieved if every participant involved had at least a general understanding of the SIPS that will be utilized. The superintendents and the subcontractors must have firsthand knowledge of the minor details that will go into the construction of the building. The crew members must be given a very detailed schedule of the general building sequencing and time period the tasks needs to be completed before the job can even begin. Burkhart, A. (1989). "The use of SIPS as a productivity improvement tool." Construction Congress 1989, Concrete Construction Publications, Inc. 381-386. Problem Statement Due to the repeatability of the 58 luxury suites, how can the use of a Short Interval Production Schedule benefit the completion of the ballpark? Proposal The development of a SIPS will have major time implications if it is properly designed and executed for the interior build out for the 58 luxury suites. Methodology There are 5 steps that need to be taken to develop a SIPS (Burkhart): 1. Break the operation into specific activities 2. Assign production rates to each activity Final Architectural Engineering Senior Thesis Page 26

3. Calculate extensions and set goals 4. Develop a time-scaled, resource loaded bar chart Step 1 Break the operation into specific activities The first step is to break the selected tasks into a list of activities that will be necessary to complete all of the work at hand. One great way to come up with activities is by sitting down with the all of the supervisors and have a brainstorming session about the order of tasks. This is the finishing sequence of the 58 luxury suites that was developed. Subroof GWB Framing Tie-in Conduit/Pull Wire Hang GWB Walls Paint Walls Acoustic Ceiling Grid GWB Ceiling Framing GWB Ceilings Light Fixtures and MEP Drops Millwork Plumbing Fixtures Flooring Doors and Architectural Trim Toilet Accessories Finish Painting and Wall Covering Ceiling Pads MEP Devices FF & E Final Architectural Engineering Senior Thesis Page 27

Step 2 Assign production rates to each activity Assigning the right production rate to each activity is the most important and difficult step to complete properly. As seen on the this page, each task is broken into manageable groups and each production rate is assigned to each individual activity. Grouping of the activities was necessary to make sure each task would fit well into allotted time constraint of a 2 day activity group. ID 1 2 3 4 5 6 7 Interior Buildout Production Rates # days to complete 10 Suites # of days to complete 1 suite # of suites completed per day Subroof 5 0.5 2 GWB Framing 15 1.5 0.666667 Suite Exterior Slider System 15 1.5 0.666667 Tie-in Conduit/Pull Wire 5 0.5 2 Hang GWB Walls 10 1 1 Paint Walls 5 0.5 2 Acoustic Ceiling Grid 5 0.5 2 GWB Ceiling Framing 5 0.5 2 GWB Ceilings 5 0.5 2 Light Fixtures and MEP Drops 10 1 1 Millwork 15 1.5 0.666667 Plumbing Fixtures 5 0.5 2 Flooring 10 1 1 Doors and Architectural Trim 5 0.5 2 Toilet Accessories 5 0.5 2 Finish Painting and Wall Covering 5 0.5 2 Ceiling Pads 5 0.5 2 MEP Devices 5 0.5 2 FF & E 5 0.5 2 Final Architectural Engineering Senior Thesis Page 28

Step 3 Calculate extensions and set goals This is the step were you try to figure out any setbacks that might occur throughout the construction of the suites. Because this is being done in the beginning of the suites scheduling process there are no unforeseen setbacks currently. It is important however to brainstorm any unanticipated incidents because it can help serve as a guideline giving you ideas about what to look out for during the installation process. Step 5 Develop a time-scaled, resource loaded bar chart This is the last step in the development of a SIPS. This is where you take all of the information that you have gathered in the previous steps and combine it to create your Short Interval Production Schedule. Below is a sample of the SIPS that was developed for the interior suites build out. The more detail and complete schedule can be found in appendix C. Final Architectural Engineering Senior Thesis Page 29

Conclusion and Recommendation After the development of the SIPS for the interior suites it was discovered that it will only take the suites a total of 123 days to complete the interior build out. The project schedule gave the suites 157 days to complete the entire suites. That is a saving of 34 important days that can be saved due to the repeatability of the suites as well as the very detailed scheduling that occurred. Since many construction projects go over budget and over schedule due to poor detailed scheduling and SIPS will not only help keep it on schedule it can also help reduce the overall time that a activity can take due to the high level of detail and repetition that can occur. Final Architectural Engineering Senior Thesis Page 30

Appendix C Detailed Short Interval Production Schedule Final Architectural Engineering Senior Thesis Page 55

Level Zone Area Room Number Room Name Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Week 9 Week 10 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 21 Week 22 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 23 Week 24 Week 25 Week 26 Month 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 3 B 2 3.22.04 Suite 1 3 B 2 3.24.01 Suite 2 3 B 2 3.24.04 Suite 3 3 B 2 3.26.01 Suite 4 3 B 2 3.26.04 Suite 5 3 B 3 3.28.01 Suite 6 3 C 3 3.31.02 Suite 7 3 C 3 3.33.01 Suite 8 3 C 3 3.33.04 Suite 9 3 C 3 3.34.01 Suite 10 3 C 3 3.35.01 Suite 11 3 C 3 3.36.01 Suite 12 3 C 3 3.36.04 Suite 13 3 C 3 3.37.01 Suite 14 3 C 3 3.37.03 Suite 15 3 C 4 3.38.01 Suite 16 3 C 4 3.38.04 Suite 17 3 C 4 3.40.01 Suite 18 3 C 4 3.43.01 Suite 19 3 C 4 3.45.01 Suite 20 3 C 4 3.45.04 Suite 21 3 C 4 3.47.01 Suite 22 4 B 2 4.22.01 Suite 23 4 B 2 4.22.03 Suite 24 4 B 2 4.22.05 Suite 25 4 B 2 4.24.01 Suite 26 4 B 2 4.24.03 Suite 27 4 B 2 4.24.05 Suite 28 4 B 2 4.26.01 Suite 29 4 B 2 4.26.03 Suite 30 4 B 2 4.26.05 Suite 31 4 B 3 4.28.01 Suite 32 4 B 3 4.28.03 Suite 33 4 C 3 4.28.05 Suite 34 4 C 3 4.31.01 Suite 35 4 C 3 4.31.03 Suite 36 4 C 3 4.31.05 Suite 37 4 C 3 4.33.01 Suite 38 4 C 3 4.33.03 Suite 39 4 C 3 4.34.01 Suite 40 4 C 3 4.34.03 Suite 41 4 C 3 4.36.01 Suite 42 4 C 3 4.36.03 Suite 43 4 C 4 4.38.01 Suite 44 4 C 4 4.38.03 Suite 45 4 C 4 4.38.05 Suite 46 4 C 4 4.40.01 Suite 47 4 C 4 4.40.03 Suite 48 4 C 4 4.40.05 Suite 49 4 C 4 4.43.01 Suite 50 4 C 4 4.43.03 Suite 51 4 C 4 4.43.05 Suite 52 4 C 4 4.45.01 Suite 53 4 C 4 4.45.03 Suite 54 4 C 4 4.45.05 Suite 55 4 C 4 4.47.01 Suite 56 4 C 4 4.47.03 Suite 57 4 C 4 4.47.05 Suite 58 1 2 3 4 5 6 7