Plant Engineering Magazine - Saving energy through front end engineering



From this document you will learn the answers to the following questions:

What is the optimum time to consider when modifying process equipment to meet new manufacturing requirements?

How is the cost of thermal oxidizers calculated?

What type of manufacturing ad has a thermal oxidizer that has a design feature?

Similar documents
HEAT RECOVERY OPTIONS FOR DRYERS AND OXIDIZERS

Presentation Outline. Background

Efficiency Options for Thermal & Catalytic Oxidizers

Thermal and Catalytic Oxidation Systems

RTO UPGRADE PROVIDES COST SAVINGS AND PERFORMANCE IMPROVEMENTS

Description of Thermal Oxidizers

VOC Oxidizers: Where to begin? Robert F. Keibler NacahTech, LLC 4/2006 Revised 9/6/2011

Evaluating Thermal & Catalytic Oxidation Technology for VOC, HAP & Odor Abatement. John Strey

1180 NW Maple Street, Ste. 310 Issaquah, WA U.S.A. +1 (425) ; +1 (425) (cell)

steam centre of excellence Steam Boiler System Optimization

THERMAL AND CATALYTIC OXIDIZERS

QUADRANT SR- Thermal Oxidizer Process Design & Environmental Control Benefits for the Sand Coating Industries

Effect of Self-Heat Circulation on VOCs Decomposition in Regenerative Thermal Oxidizer

Improving Energy Efficiency through Biomass Drying

THE SAFE USE OF THERMAL OXIDISER (INCINERATION) SYSTEMS FOR POTENTIALLY FLAMMABLE MIXTURES. Gordon Newsholm

Options and Incentives to Rebuild or Replace VOC Oxidation Equipment

DURR Thermal Oxidizer Research. 4/27/2004 Intel Corporation Community Meeting

Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard

Ecopure RL Abatement System

ALUMINUM. BestPractices Assessment Case Study. Alcoa North American Extrusions Implements Energy Use Assessments at Multiple Facilities.

OPTIMIZING CONDENSER WATER FLOW RATES. W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa

Steam System Efficiency. Bill Lumsden Leidos Engineering

Case History: Ethanol Facility Retrofit with a Lower Emissions, Improved Fuel Efficiency Thermal Oxidizer and Dryer Burners

Glossary of HVAC Terms

Repair, Modify or Replace?? What is the right answer?? By : Joe Mozeika

ASTACEA4 Inspect complex/central air conditioning systems

Boiler NOx Emissions and Energy Efficiency

Continuous Monitoring of Flue and Combustible or Hazardous Gases and Vapors

Analysis of HVAC Control Strategies

The ASHRAE HQ Building Can the energy efficiency of the different mechanical systems really be compared? RESIDENTIAL LIGHT COMMERCIAL COMMERCIAL

5.5 INCINERATORS Incinerator Control Mechanisms Types of Incinerators Thermal Incinerators... 5.

State of New Jersey. General Permit. For. Boilers and Heaters [Individually Less Than 10 MMBTU/HR]

Printing and Publishing Energy Savings Guide

INTRODUCTION. Fact Sheet: Air Pollution Emission Control Devices for Stationary Sources

Increasing Natural Gas Boiler Efficiency by Capturing Waste Energy from Flue Gas

10 Strategic Steps to Reducing Your Energy Costs AEE Regional Chapter Meeting February 2, 2005

Factsheet & Process Description Regenerative Thermal Oxidizer (RTO) Vopak Terminal Amsterdam Westpoort

SPECIAL APPLICATIONS

HVAC Code Requirements

Boiler Efficiency Workshop

High Altitude HVAC. Silvertip Integrated Engineering Consultants

School & Commercial Bus Climate Control Design Manufacture Install Service. A Bus Air Conditioning Informational Bulletin by

Data Realty Colocation Data Center Ignition Park, South Bend, IN. Owner: Data Realty Engineer: ESD Architect: BSA LifeStructures

A GUIDE TO SELECTING YOUR INDUSTRIAL OVEN

THERMAL OXIDISER FIRE & EXPLOSION HAZARDS

Process Heater Burners, Flare Systems, Thermal Oxidizers and Catalyst Systems. Combustion Technology

Glossary of Heating, Ventilation and Air Conditioning Terms

Waste Incineration Plants

Control Device Requirements Charts For Oil and Gas Handling and Production Facilities

Natural Gas Conversions of Existing Coal-Fired Boilers

ECO-STAR II. ECO-nomical ECO-logical the ECO-STAR II. Packaged Low NOx Multi-Fuel Burner. Features. Benefits. Combustion Excellence Since 1888 ESII-1

Tips from the Help Desk

Impact of Control System Technologies on Industrial Energy Savings

Energy Efficient Grain Drying. Kenneth Hellevang, Ph.D., P.E. Professor & Extension Engineer

Energy Efficiency in Industrial HVAC Systems

Practical Examples of Heat Regenerative System at Steelmaking Works

Chapter 6 Odor Control

Feasibility Study Proposal & Report Guide. Industrial Optimization Program

DIRECT STEAM INJECTION HOT WATER SYSTEMS FOR JACKETED HEATING

Improving Data Center Efficiency with Rack or Row Cooling Devices:

Optimization of Water - Cooled Chiller Cooling Tower Combinations

Section 3 VOC Controls

Walnut Drying Design and Operation. Selecting Dryer Type. Tray Drying Before Don Osias Jim Thompson

Waste to Energy. Anders Damgaard. Thanks to Jiri Hyks and Thomas H Christensen DTU for some slides

SELECTION OF THERMAL OXIDISERS

ENERGY AUDIT REPORT MINIMUM REQUIREMENTS

BEST PRACTICES ADOPTED IN JINDAL STEEL & POWER LTD., RAIGARH TO ACHIEVE ENERGY EFFICIENCY. Presented By : Kumar Rohit Sudhanshu Rometra

Texas Commission on Environmental Quality Page 1 Chapter Control of Air Pollution from Nitrogen Compounds

rbital Fields of application Variants

Presented By: WALTER E. JOHNSTON, PE CEM, CEA, CLEP, CDSM, CPE

Energy Efficiency in Steam Systems

A Cover HVAC ENERGY EFFICIENT

Heat Recovery Dehumidification (HRD) system. Designed for municipal swimming pools

Fuel and Energy Conversion and Equivalence Chart

Building Energy Systems. - HVAC: Heating, Distribution -

Demand Based Static Pressure Reset Control for Laboratories

Nitrogen Blanketing for Methanol Storage and Transportation

UNDERSTANDING REFRIGERANT TABLES

Home Energy Evaluation Report

How To Calculate Total Cooling Requirements For Data Center

International Telecommunication Union SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES IN PUBLIC NETWORKS

Type 1 dryers: Domestic dryers to be used primarily in a family living environment. Residences Individual apartments or condominiums

TODAY S THERMAL OXIDIZER SOLUTIONS TO MEET TOMORROW S CHALLENGES

Performance Monitoring For Gas Turbines

Creating Efficient HVAC Systems

Understanding Tier 4 Interim and Tier 4 Final EPA regulations for generator set applications

ENERGY CONSERVATION PRESENTATION BY : PCG CORPORATION

CODE NOTES. Insulation Requirements in Commercial Buildings for Mechanical and Service Hot-Water Piping

Efficient Pneumatic Conveying Dense Phase vs. Dilute Phase: How Being Accurate is More Cost Effective Than Being Conservative

How To Evaluate Cogeneration

Johnson Air-Rotation Systems

STATE OF MISSOURI, DEPARTMENT OF NATURAL RESOURCES MISSOURI AIR CONSERVATION COMMISSION PERMIT TO CONSTRUCT

A Prototype Alternative Ventilation System for Retrofit, Rehab and Renovation of Rural Alaska Houses

Addition of general construction conditions applicable to the portable emergency turbine because they were omitted from the original Part 70 Permit.

Transcription:

http://www.manufacturing.net/ple/article/ca209063?text=thermal+oxidizer& Page 1 of 5 Welcome, Michael Herron. (Not Michael? Log in here.) Wednesday, May 26, 2004 Search for: thermal oxidizer in All of Plant Engineering Search Click here for search tips Home Products Resources Newsletter Archives Free Subscription PE Magazine General Info Media Kit Online ad specs BPA Statement Editorial Quality Audit Reader Info Request Contributor's Guide Resources Technology Evaluation Center Product Showcase Guide ecards Decks Archives General Saving energy through front end engineering Plant Engineering April 5, 2002 By David J. Herron, PE, VP of Engineering, Unified Theory, Inc., Woodbury, MN Key concepts Examine all options when considering energy conservation An option can have a low first cost and operating cost. The optimum time to consider energy conservation is when making modifications to process equipment to meet new manufacturing requirements. Although this is obvious, it is not always done because of the rush to get a project completed and of the internal effort to reduce engineering cost. A good example of this is in the installation of a thermal oxidizer for pollution control. ADVERTISEMENT Registration Edit your individual information, change your e-mail address, or add/cancel e-letter subscriptions. Update Basically a thermal oxidizer (sometimes referred to as an afterburner or a fume incinerator) is provided to destroy Volatile Organic Compounds (VOCs) and/or for odor control. The concept of a thermal oxidizer is based on the three Ts: time, temperature, and turbulence. The three Ts depend on the type and design of the thermal oxidizer and the process exhaust being treated. Most often the temperature for destruction of VOCs and odors ranges from 1450 1550 F and the time at the destruction temperature is 0.5 to 0.7 sec. The turbulence factor depends on the design of the thermal oxidizer and is required to ensure the design destruction efficiency of the VOCs and/or odors. Types of thermal oxidizers Simple flares at the process exhaust Channels Air Conditioning Ventilation and Refrigeration Compressors and Prime Movers Construction and Buildings Electrical Power Combustion chambers with no heat recovery Recuperative, having an air-to-air heat exchanger for heat recovery Regenerative, having a ceramic or stoneware bed for heat recovery Catalytic bed

http://www.manufacturing.net/ple/article/ca209063?text=thermal+oxidizer& Page 2 of 5 Distribution and Application Fire Protection, Safety, and Health Fluid and Mechanical Power Transmission Fluid Handling Illumination Instruments and Controls Lubrication Maintenance Material Handling Paints and Protective Coatings Plant Management Process and Space Heating Software Tools and Welding Ads by Google Lean Manufacturing Toyota, Gillette, Ford, Visteon, Weyerhaeuser use Activplant Specialty variations within the above categories. When applying a thermal oxidizer or any new modifications to process equipment, the entire system must be considered. In the case of pollution control equipment, the processes and pollution control equipment must be evaluated as a single system to ensure that system operation will be safe and the equipment selected will result in the lowest owning and operating cost. A process hazard analysis should be conducted to ensure that the system design will result in a functional and safe design. The intent of this example is to illustrate the necessity of looking at viable options when considering energy conservation while at the same time demonstrating that energy conservation options sometimes have a low first cost along with a low operating cost. The airflow rates, type of process equipment, combination of and percentages of solvents used in the following calculations are arbitrary and do not reflect any actual process. However, values used in the calculations do represent realistic conditions. Assumptions for example Total process exhaust rate is 150,000 scfm from four individual dryers. The dryers may not all operate at the same time due to product changeovers, etc. The utilization rate for the dryers is 75%. When solvents are being evaporated in a dryer, the dryer exhaust is directed to the pollution control equipment. When the processes are online the average process exhaust airflow rate is 112,500 scfm. The dryers are 25 years old and were installed at the time the plant was built. The normal production schedule is 24 hr/day, 5.5 days/wk, and 50 wk/yr. The total maximum pounds of solvent evaporation from the four dryers is 756.3 lb/hr. The solvent evaporated is a mixture of toluene, methyl ethyl ketone, ethyl acetate and heptane. The solvent heat value is 15,120 Btu/lb. During normal operation the process exhaust is at 3% lower flammability limit (LFL). Lean Consulting Firm TBM is the leading lean mfg. and service industry consulting firm. Process air inlet temperature at thermal oxidizer is 125 F. Estimated yearly average outdoor air temperature is 50 F. Natural gas cost is $3.90 per MMBtu and electrical cost, including demand charges is $0.075/kWh. The required VOC capture efficiency is 93%. In order to achieve the required capture efficiency the pollution control equipment, in this case a thermal oxidizer, must achieve a minimum destruction efficiency of 97%. Two options are considered in this example: Option 1 is based on leaving the dryer exhaust as is. Option 2 is based on modifying the dryer exhaust. So as not to confuse the issue of the energy conservation opportunity presented and to simplify the calculations for the two options, both options are based on regenerative thermal oxidizers having similar life spans, annual maintenance costs, and hot gas recirculation. The primary difference between the two options is the size and thermal efficiency of the thermal oxidizers. Option 1: To achieve the required destruction efficiency, the thermal oxidizer manufacturer recommends a destruction temperature (therma oxidizer combustion chamber) of 1530 F. Thermal efficiency required for the thermal oxidizer to be self-sustaining at the above conditions is 95.3%. Thermal oxidizer selection for this option is a regenerative thermal oxidizer having a 95% thermal efficiency with an air pressure drop of 25 in. wc at the design airflow. An additional 5 in. wc is required for the process collection ductwork. The minimum required airflow through the thermal oxidizer, based on a 4 to 1 turndown, is 37,500 scfm. The unit is provided with hot gas recirculation to reduce the operating cost when all processes are offline and when the process exhaust air volume is less than the minimum required airflow. To provide for a redundant exhaust fan, three exhaust fans, each sized for 75,000 scfm, are provided and each fan is equipped with a variable speed drive and an outlet isolation damper.

The estimated total project cost to provide the thermal oxidizer, collection exhaust ductwork, controls, engineering, and installation is $13,500,000. Page 3 of 5 Hours of thermal oxidizer operation per year: 24 hr/day x 7 day/wk x 51 wk/yr = 8568. Hours of operation per year with process exhaust = 24 hr/day x 5.5 day/wk x 50wk/yr = 6600 hr/yr. Hours of standby operation without any process exhaust and utilizing hot gas recirculation: 8568 hr/yr 6600 hr/yr = 1968 hr/yr. Estimated temperature leaving the thermal oxidizer stack based on unit having a 95% thermal efficiency: 195 F. Estimated natural gas cost: Because the solvent loading is not always at design loading due to the process ramping up and down, infiltration, etc., it can be reasonably estimated that a minimal amount of natural gas energy will be required at all times. The actual amount of natural gas required can range from 10 to 45 times the calculated natural gas requirements. To present a reasonable example of projected energy costs, a factor of 20 times is used. Fuel cost = (285,000 Btu/hr x 20) x $3.90/1,000,000 Btu x 6600 hr/yr = $146,718/yr. Standby operation including the required combustion air when operating in this mode: Btu/hr for recirculation = 37,500 scfm x 4.5 x 0.26 x 25 ( t) = 1,096,875 Btu/hr. Btu/hr for combustion air = 1,096,875 106 x 0.075 x 0.26 x (1530 50) = 298,640. Total MMBtu/yr for standby operation = (1,096,875 + 298,640) x 1980 hr/yr x $3.90 1,000,000 Btu = $10,776. Total estimated annual cost for natural gas: $146,718 + $10,776 = $157,494. Estimated electrical cost: Average airflow of 112,500 scfm and 50 scfm of combustion air at an average system pressure drop of 26 in. wc, exhaust fan efficiency of 75%, and a 0.9 power factor. Total estimated fan horsepower based on the above conditions = 615 hp. KWh = approximately 510. Cost per year = 510 kwh x 6600 hr/yr x $0.075/kWh = $252,450. Standby operation: Minimum airflow of 37,500 scfm and 175 scfm of combustion air, average system pressure drop of 12 in. wc, exhaust fan efficiency of 75%, and a 0.9 power factor. Total estimated fan horsepower based on the above conditions = 95 hp. kwh = approximately 79. Cost per year = 79 kwh x 1980 hr/yr x $0.075/kWh = $11,732. Total estimated annual cost for electricity: $252,450 + $11,732 = $264,182. Estimated total energy cost: Total estimated energy cost per year for natural gas and electricity: $421,676. Option 2: Under this option the percent-lfl control will be added to the existing dryers to reduce the amount of process exhaust by

Page 4 of 5 increasing the percent-lfl in the process exhaust from 3% to 8%. The total air circulation rate through the dryer will remain the same so as not to disturb the existing curing process. Even though the percent-lfl will be increased, the change in percent-rh within the dryers is insignificant. Estimated cost to add the percent-lfl control to the dryers is $750,000 each for a total of $3,000,000. To achieve the required destruction efficiency, the thermal oxidizer manufacturer recommends a destruction temperature of 1530 F, the same as indicated for Option 1. Thermal oxidizer selection for this option is a regenerative thermal oxidizer having an 88% thermal efficiency with an air pressure drop of 24 in. wc at the design airflow. An additional 5 in. wc will be required for the process collection ductwork. The minimum required airflow through the thermal oxidizer, based on a 4:1 turndown, is approximately 13,400 scfm. The unit is provided with hot gas recirculation to reduce the operating cost when all processes are offline and when the process exhaust air volume is less than the minimum required airflow. To provide for a redundant exhaust fan, three exhaust fans, each sized for 26,625 scfm, are provided, and each fan is equipped with a variable speed drive and an outlet isolation damper. Estimated total project cost to provide the thermal oxidizer, collection exhaust ductwork, controls, engineering, and installation is $5,000,000. Hours of thermal oxidizer operation per year = 24 hr/day x 7 day/wk x 51 wk/yr = 8568 hr/yr. Hours of operation per year with process exhaust = 24 hr/day x 5.5 day/wk x 50 wk/yr = 6600 hr/yr. Hours of standby operation without any process exhaust and utilizing hot gas recirculation = 8568 hr/yr 6600 hr/yr = 1968 hr/yr. Estimated temperature leaving the thermal oxidizer stack based on unit having a 95% thermal efficiency = 195 F. Estimated natural gas cost: As explained under Option 1, the actual amount of natural gas required can very easily range from 10 to 45 times the calculated natural gas requirements. To present a reasonable example of projected energy costs, a factor of 20 times is used. Fuel cost = (125,000 Btu/hr x 20) x $3.90 1,000,000 Btu x 6600 hr/yr = $64,350 per year. Standby operation including the required combustion air when operating in this mode: Btu/hr for recirculation = 13,400 scfm x 4.5 x 0.26 x 25 ( t) = 91,950 Btu/hr. Btu/hr for combustion air = 391,950 106 x 0.075 x 0.26 x (1530 50) = 106,715 Btu/hr. Total MMBtu/yr for standby operation = (391,950 + 106,715) x 1980 hr/yr x $3.90/ 1,000,000 Btu = $3,850 MMBtu/yr. Total estimated annual cost for natural gas: $64,350 + $3,850 = $68,200. Estimated electrical cost: Assume average airflow of 56,200 scfm and 20 scfm of combustion air at an average system pressure drop of 26 in. wc, exhaust fan efficiency of 75%, and 0.9 power factor. Total estimated fan horsepower based on the above conditions = 308 hp. Electric power = approximately 255 kwh. Cost per year = 255 kwh x 6600 hr/yr x $0.075/kWh = $126,225. Standby operation: Assume minimum airflow of 13,400 scfm and 80 scfm of combustion air, average system pressure drop of 12 in. wc, exhaust fan efficiency of 75%, and 0.9 power factor.

Total estimated fan horsepower based on the above conditions = 34 hp. Page 5 of 5 Electric power = approximately 29 kwh. Cost per year = 29 kwh x 1980 hr/yr x $0.075/kWh = $4310. Total estimated annual cost for electricity: $126,225 + $4,310 = $130,535. Estimated total energy cost: Total estimated energy cost per year for natural gas and electrical is $198,735. Conclusion Option 1 has a first cost of $13,000,000 for the thermal oxidizer with an annual energy cost of $421,676. Option 2 has a first cost of $3,000,000 for dryer modifications plus $5,000,000 for the thermal oxidizer for a total of $8,000,000 with an annual energy cost of $198,735. Clearly option 2 is the system having the lowest energy consumption while at the same time having the lowest first cost. Additional advantages of Option 2 include: v Additional annual energy savings resulting from reducing the amount of makeup air required for dilution (lower exhaust air volumes) v A portion of the capital expenditure was used to upgrade the controls of the dryers, which in turn will increase the product yield and quality. This is just one example of a viable energy conservation project. Usually a simple initial evaluation of a process can be used to determine if the process may be a candidate for energy conservation. If the initial evaluation determines the process is a strong candidate for energy conservation, then an indepth analysis should be provided to verify the magnitude of the project cost, the value of the projected energy saved, and estimated project pay back based on the value of the energy reduction. Edited by Joseph L. Foszcz, Senior Editor, 630-320-7135, jfoszcz@cahners.com More info Mr. Herron is available to answer questions about this article. He can be reached at 651-578-8100. 2004, Reed Business Information, a division of Reed Elsevier Inc. All Rights Reserved. about us recommend our site help your account contact us ad info free subscription Plant Engineering Magazine 2004 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved. Use of this web site is subject to its Terms and Conditions of Use. View our Privacy Policy.