Catch Basin Rehabilitation Road Commission for Oakland County, Michigan



Similar documents
Unit Price Averages Reports

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

SECTION STORM DRAINAGE SYSTEM

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Wastewater Capital Projects Management Standard Construction Specification

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

Permeable Pavement Construction Guide

DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

SECTION STORM DRAINAGE TABLE OF CONTENTS

Chapter 3 Pre-Installation, Foundations and Piers

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

Table 4.9 Storm Drain Inlet Protetion Applicable for

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

SECTION STORM DRAIN SYSTEM

Safe & Sound Bridge Terminology

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Block and Gravel Inlet Protection (BIP)

SECTION ABANDONMENT OF SEWER MAINS

Minor Cracks in Horizontal Surfaces

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

R E S I D E N T I A L H O U S I N G

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Construction Specification for Concrete Curb and Concrete Curb and Gutter

CONSTRUCTION PERMIT REQUIREMENTS

APPENDIX B. I. Background Information

Lighthouse Engineering, L.L.C.

School Construction Authority Architecture & Engineering

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

8.7 Schluter -KERDI-LINE

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs

SECTION 7- STORM SEWER

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Finegan Inspection Services, Inc.

The AQUAFIN Approach to Concrete Repair

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

Metropolitan Builders Association Masonry & Concrete Standard

STANDARD SPECIFICATIONS

Division 2 Section Section 02795

What you need to know about concrete block basement construction.

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

DESCRIPTION OF WORK:

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.

Building Your Interlocking Concrete Pavement to Last a Lifetime

Stormwater/Wetland Pond Construction Inspection Checklist

SIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS. Prepared by Risi Stone Systems Used by permission.

STRUCTURAL ASSESSMENT

WATERPROOFING FOR CONCRETE STRUCTURES

40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT

FY08 SEWER POINT REPAIRS BID TABULATION

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST BID PROPOSAL

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01.

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Advancements in Permeable Pavements

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

Permeable Pavement Operation & Maintanence Guide

Storm Drain Inlet Protection - IP

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

ENERGY STAR Qualified New Homes Thermal Enclosure Checklist. Water Management Checklist. Eli Caudill

Section 402. STORM SEWERS

Transportation Infrastructure Asset Management

Pavement Patching Repair for AC and PCC Pavement Surfaces. Vern Thompson

Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

550 PIPE CULVERTS, SEWERS AND DRAINS

REQUEST FOR QUALIFICATIONS FROM FOUNDATION REPAIR CONTRACTORS BROOMFIELD DEPOT FOUNDATION REHABILITATION PROJECT

Chapter. Restoration of Damaged Structures

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

New Road 11.0m Asphalt 23m ROW

A guide to preventing structural damage

Guide for SOLID CONCRETE BLOCK SEALS

City of Hilshire Village Pine Creek Ln Reconstruction

Caltrans non-standard Special Provisions Pervious Concrete. David Akers Feb 28, 2012

LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

How to secure your property after a disaster

Sewer Rehabilitation Design Requirements

SECTION PLAYGROUND SURFACING TILES

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

Ironwork in Highways -Whole Life Cost Perspective. Reducing cost through collaboration

Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio

Moving Small Mountains Vesuvius Dam Rehab

The existing roof angle change terminations and flashings when sound and intact can be reused.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

Transcription:

Date: Location: September 14, 2011, 9:45a.m. start East side of street in front of 4656 Maura Lane, West Bloomfield Participants: Oakland County Michelle Belanger, Rick Hall, Matt Mountain, Gary Flounory, Willis Greer, Tim Hanson, Jamie Fordyce strataworks Jim Hill UGT David Wahl Weather: 65 o F., sunny Starting Conditions: The existing elevation assembly is of undetermined age. The road pavement was compromised and there was advanced wash out of aggregate in the sub-grade. The bottom course of block was broken at the base of the catch basin around the outlet/drain pipe (in the west arc of the structure, draining under the street to a catch basin located on the west curb of Maura Lane) Construction Notes: Elevation Rehabilitation: 1. Replacement block was laid in the second course, on the northwest point of the arc. The block was set in a cementitious masonry bed mixed by RCOC crew. 2. A 15 (+/-) clear opening was left around the outlet pipe (to road side) in the two courses of block. 3. Three block joints were filled using UGT s Crack n Seal, a polyurea elastomer. The Crack n Seal cured in 15 minutes. 4. A 1.0 coat of epoxy grout from UGT was applied to the top surface of the blocks to create a level bearing plane.

5. One, 5.5 high expanded polystyrene (EPS) adjustment unit was set in place and pressed into the grout. The wet grout compressed into the female interlocking channel of the EPS unit, creating a ½ nonslip keyway. Note: The 5.5 adjustment unit spanned the 15 opening. 6. An extension was constructed above the 15 opening between the 5.5 adjustment ring and the undisturbed aggregate fill. Made of the epoxy grout and capped with masonry, the extension will retain all new aggregate and prevent it from entering the catch basin structure. 7. The remaining elevation was dry fit and measured in place to ensure correct vertical adjustment and frame location in curb. The ten elevation units where marked and numbered, removed from the hole and bonded in place individually. 8. A continuous ¾ bead of Secure n Seal adhesive was applied to the top surface of each adjustment unit when it was set in place, starting with the 5.5 grade ring 9. Six, 2.0 high, EPS flat restoration units were vertically set in place. Each 2 unit was offset approx. 1.5 to the west of (away from) the back edge of the underlying ring. The offsetting over the six units moved the bearing alignment 9.5 to the west of the original position to ensure the frame was properly located in the curb face. 10. One, 1.0 high EPS grade unit was placed on top of the offset assembly. 11. One, 1.5 high grade unit was placed on top of the 1.0 grade unit. 12. One 1.0 x0.5 angle finish unit was placed on top of the 1.5 grade unit. The angle ran downhill from south to north along the curb line to follow the slope in road. 13. A ¾ bead of Secure n Seal adhesive was applied to the top surface of the finish unit to bond the ironworks frame (East Jordan model 7045) in place. 14. The adjusted height totalled 21 of vertical adjustment with a 9.5 east to west offset adjustment. 15. As constructed, the entire assembly is bonded as a monolithic structure from the top of the block to frame.

Curb Reconstruction: 16. RCOC formed and poured a new concrete curb around the rehabilitated catch basin on September 15, 2011. Road Paving: 17. RCOC replaced the granular aggregate and repaired the excavated asphalt pavement with hot mix material on September 15, 2011. Inspection Schedule: strataworks will co-ordinate a November 2011 and April 2012 inspection with RCOC s Highway Maintenance foreman. A copy of the final inspection report will be provided to RCOC upon completion.

Inspection Date: November 2, 2011 Participants: Inspection Notes: - Polyarmor coating: Pristine Oakland County Michelle Belanger strataworks Jim Hill - Secure-N-Seal Fully cured, pliable, secure in place. Bond between elevation rings is intact Bond to bottom of frame is intact - Grade units: Durability: No deterioration Alignment: Unchanged, as installed Stability: No lateral movement - Angled finish unit: Durability: No material deterioration Alignment: Unchanged, as installed Stability: No lateral movement - Overall Placement: Solid and properly aligned in concrete curb.

Inspection Date: May 3, 2012 Participants: strataworks Jim Hill Inspection Notes: - Polyarmor coating: Like new - Secure-N-Seal Unchanged. Bond between rings is intact Bond to bottom of frame is intact - Grade units: Alignment / Stability: Unchanged Durability: No deterioration - Angled finish unit: Alignment/ Stability: Unchanged Durability: No deterioration - Overall Placement: Solidly aligned in concrete curb. Note: The 10 lateral offset is solid and in place, as constructed Other Notes: 1. A 10 (+/-) diagonal crack has occurred in the concrete, on the southwest of the catch basin frame at the edge of the asphalt. 2. The top surface of the new asphalt pavement is in good condition. 3. The junction seams between the old and new asphalt are tightly abutted and appear well sealed. 4. The overall grade (height) of the new asphalt patch appears to be ¼ to ½ lower than the original asphalt.