CONSTRUCTION PERMIT REQUIREMENTS
|
|
|
- Delphia Patterson
- 10 years ago
- Views:
Transcription
1 CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department of Public Works. CONSTRUCTION PERMIT REQUIRES Engineering Plan Review & Escrow Permit Application & Fee Cash Bond & Proof of Insurance Inspection Escrow Deposit ENGINEERING PLAN REVIEW The applicant shall provide three (3) signed and sealed sets of plans for the proposed project, along with an engineer's estimate of the construction cost. For the engineering plan review fee, and escrow amount of a minimum $500 or 1.35%, whichever is greater, as established by the city engineer, based on the applicant's estimated cost of the project, including labor, materials and overhead. PERMIT APPLICATION Must be completed and returned to the Department of Public Works by the party providing the Proof of Insurance. The party applying for the permit must bring the following information. Complete Permit Application Permit Fee in the amount of $100 CASH BOND AND PROOF OF INSURANCE As a condition of obtaining a permit, a cash bond in and amount of at least $5,000 for work in Local Road ROW $10,000 for work in Major Road ROW or five percent, whichever is greater, as established by the city engineer, based on the applicant's estimated cost of the project, including labor, materials and overhead, which may be utilized to pay all valid claims for damages resulting from activity within the public right-of-way. Refer to Section of the City of Clawson Code of Ordinances. Proof of Insurance is required listing the City of Clawson as an additional insured party, for at least $1,000,000 in liability coverage. Both the Cash Bond and the Certificate of Insurance must list the address at which the permit work will be performed. INSPECTION ESCROW DEPOSIT The applicant shall deposit 6% of the construction cost estimate for the project to establish an escrow account to cover the cost of project inspection. Minimum Deposit: $1, Inspection time is charged as follows: Straight Time $ / hour Overtime (time and 1/2) $ / hour Overtime (double time) $ / hour Any remaining escrow balance is returned after the project is finale. Any money owed is billed to the permit holder within $500 of the deposit being depleted.
2 PAVEMENT BREAKS For any breach of the paved public right-of-way, the City of Clawson requires that the applicant restore sidewalks, roads, and driveway approaches with temporary pavement and make payment to the City of Clawson to permanently restore the area during its annual patching program. Payment for this will be accomplished using funds deposited by the applicant with each construction permit. If the cost of restoration exceeds the funds collected, the additional funds to complete the work will be deducted from the applicant's bond deposit. Fees shall be deposited based on the following: 4" Sidewalk $85.00 per Flag (5' x 5') 6" Sidewalk $ per Flag (5' x 5') Roadway Standard 27' Width (estimated 10 foot wide trench) $1, to center of road $3, Full Width DEMOLITION During demolition, water services and sewer leads are required to be terminated at the main connection. This work shall be performed by the City of Clawson. Fees will be established based on review of the demolition plan. Fees related to this work shall be paid by the applicant. ENGINEERING PLAN PHASE - BRING 1) Three (3) sets of Engineering Plans 2) Engineer's Construction Cost Estimate 3) Engineering Review Fee RIGHT OF WAY PERMIT PHASE - BRING 1) Approved Engineering Plans 2) Permit Application & Fee 3) Cash Bond 4) Proof of Insurance 5) Check to cover inspection fees (escrow) 6) Check to cover pavement breaks 7) Soil Erosion Control Permit from Oakland County Drain, Soil Erosion & Sedimentation Control Division may be required. They can be reached at (248) TO: Clawson Department of Public Works, 635 W. Elmwood FOR INSPECTION: Call the Department of Public Works at (248) (48-hour notice is required). Give address of the work, and the Permit Number when calling.
3 DEPARMENT OF PUBLIC WORKS & ENGINEERING PERMIT CONDITIONS AND SPECIFICATIONS CONDITIONS The following conditions apply to permitted activities within City of Clawson Rights-of- Way, within utility easement(s), and on private property. The permitted activities are those described in the detailed work description included on the permit. The permitee has the obligation to operate, use and/or maintain the City facility and work area to the satisfaction of the City of Clawson Department of Public Works and Engineering until the permitted activity is complete. All work will be carried out in the manner applied for and in accordance with plans, specifications, and statements filed with the City of Clawson as part of the permit application. If said permit is granted, the applicant agrees to do the following: 1. Give notice to the Department of Public Works and Engineering at ( ), at least one business day prior to commencement of operations covered by this permit. 2. In any and all operations under this permit, meet all requirements of the City of Clawson Standard Specifications and Supplemental Specifications as set forth below. 3. Take, provide, and maintain all necessary precautions to prevent injury or damage to persons and property from operation covered by this permit, and use safety devices which are MIOSAH and City of Clawson approved. 4. Save harmless the City of Clawson against any and all claims for damages arising from operations covered by this permit and furnish proof of insurance coverage for the term of this permit for a minimum of $1 million personal injury and $1 million property damage for operations covered by this permit. 5. Surrender the permit herein applied for, cease operations, and surrender all rights there under whenever notified to do so by the Superintendent of Public Works and Engineering, because of his/her need for the area covered by the permit, or because of a default in any of the conditions of the permit. 6. Immediately remove, alter or relocate, at applicant's own expense, the facility for which this permit is granted, if requested by the City of Clawson to do so. Upon failure to remove, alter, relocate or surrender the facility pursuant to the request of the City of Clawson, reimburse the City of Clawson for its cost in doing same. 7. File a cash construction bond in an amount to be determined by the Department of Public Works and Engineering, and conditioned upon, performance of the conditions of the permit and compliance with all requirements of law. 8. Additional conditions.
4 SUPPLEMENTAL SPECIFICATIONS 1. PERMIT The person in charge of the work shall have the permit and the approved plans or sketches, in his possession on the job at all times. 2. EXCAVATION AND DISPOSAL OF EXCAVATED MATERIAL The Department of Public Works and Engineering may specify if trenches or excavations under or adjacent to the road surface shall be sheeted, shored, and/or braced in such a manner as to prevent caving, loss, or settlement of foundation material supporting the pavement. This in no way relieves the contractor of responsibility for damages to persons or property caused by a failure to properly shore any trench. Excavated material shall be stocked in such locations that it does not obstruct vision on the traveled portion of the street or highway and in such manner that it will interfere as little as possible with the flow of traffic. Sod and topsoil shall be stocked separately from other excavated material. The applicant shall dispose of all surplus and unsuitable material unless the permit provides for disposal at approved locations within the right-of-way. In the latter case, the material shall be leveled and trimmed in accordance with the approved project plans, or to the satisfaction of the Inspector. 3. BACKFILLING AND COMPACTING BACKFILL All trenches, holes, and pits shall be filled with sand, placed in successive layers not more than 12 inches in depth, loose measure. Each layer shall be thoroughly compacted and all backfill subject to check by the Controlled Density Method. The Department of Public Works and Engineering will specify if compaction testing is required, and if so, the applicant will be responsible for the costs of that testing. Testing will be performed by the materials testing consultant under contract to the City of Clawson, at the time of the work. Sand backfill material shall meet the gradation requirements of MDOT Class II Material. Sod and topsoil shall be replaced in kind, and under the direction of the City of Clawson Inspector. 4. CROSSING ROADBED BY TUNNELING When pipe is installed by tunneling, boring or jacking without cutting the existing pavement, the backfill shall be made by tamping a dry mix of lean concrete into place so as to completely fill any voids remaining around the installation. The concrete shall be composed of one part Portland cement and 10 parts of sand. Sand shall conform to the requirements given in Paragraph 3.
5 5. CROSS BY CUTTING PAVEMENT AND TRENCHING When this method is used, the pavement shall be cut back so that the pavement opening is at least 6 inches wider on each side than the width of the trench. All pavement surfaces will be cut with a concrete saw and carefully broken out without disturbing the cut edge. Chipped or broken edges of pavement will be re-sawed prior to pavement replacement. Pavement shall be replaced with new pavement and base material to match the original type and depth. Where an asphalt cap exists, the concrete patch will be poured full depth, unless otherwise specified on the approved plans. 5/8" hook bolts will be used in local roads to tie a new concrete patch to the existing pavement. 1 1/4" dia. Epoxy coated dowel bars will be used in major roads parallel to the direction of travel, and $5 hook bolts used to tie in the sides of a patch. If weather conditions make it infeasible to replace pavement in kind, a temporary surface of bituminous material shall be placed, and later replaced with pavement of original type at the applicant's expense. 6. DEPTH OF COVER MATERIAL Pipes shall be placed to a depth that will provide not less than 3 feet of cover between the top of roadway surface and the pipe. 7. TREE TRIMMING OR TREE REMOVAL Secure permission and/or a permit from the City of Clawson Department of Public Works and Engineering. 8. INSPECTION In all cases the applicant shall notify the City of Clawson at least one business day before the work will commence, so arrangements may be made to have an Inspector present while the work is in progress. The applicant will be billed for the necessary expense of the inspector at the current rate in effect on the date listed on the permit. 9. Any operation in the right-of-way not covered by the above specifications submitted with the permit, or the City of Clawson Standard Specifications, shall be done in accordance with instructions of the City of Clawson Department of Public Works and Engineering. 10. Full compliance is required with any regulations of the Department of Public Works and Engineering, and any public utilities in the vicinity of the work. 11. CONSTRUCTION HOURS CLAUSE All construction under or relevant to this permit shall not begin before sunup or at the earliest 7:00 a.m. and all construction shall cease at sundown or at the latest 7:00 p.m. The Contractor shall adhere to this schedule unless specifically authorized in writing by the Superintendent of Public Works and Engineering. Sunup and sundown shall be determined by the shutting off or turning on of the street lights in the area of the project. This shall expressly forbid the operating of any mechanical equipment except during the permitted hours. The Contractor shall schedule his construction so that operations including installing pipe, back filling, finishing pavement, applying curing compound, cleanup and placing of proper barricades and lighting and any other construction are done during the required time. No inspections personnel will be furnished for hours in addition to those specified, and any work performed outside of these hours will not be accepted by the Department of Public Works and Engineering.
6 No Sunday or Holiday work will be allowed unless specifically authorized in writing by the Superintendent of Public Works and Engineering. Holiday work shall include all legal holidays, national, state, county and City Election days and any other day when the City Hall of the City of Clawson is officially closed. THE FOLLOWING MUST BE ATTACHED TO THE PERMIT APPLICATION WHEN REQUESTED BY THE DEPARTMENT OF PUBLIC WORKS AND ENGINEERING Permit Fee, Cash Construction Bond, Certificate of Insurance, (except for utility companies); Approved Plans, Approved Traffic Control Plan in case of street closures, Inspection Escrow Deposit, a copy of the Oakland County Soil Erosion Control Permit and all other necessary permits. City of Clawson Department of Public Works and Engineering 635 West Elmwood (248) WATER DEPARTMENT FEES FOR INSPECTION: Call the Department of Public Works at (248) (48- hour notice is required). Give address of the work, and the Permit Number when calling. WATER DEPARTMENT FEES AS OF May 1, 2012 WATER TAP 1" Water Tap (Service) $1, FEES 1.5" Water Tap (Service) $1, " Water Tap (Service) $2, WATER SERVICE DISCONNECT fee $800 + Restoration SEWER SERVICE DISCONNECT fee $1,200 + Restoration WATER METER 5/8" Meter $ FEES 1" Meter $ " Meter $ " Meter $1, METER HORN 5/8" Meter Horn $ " Meter Horn $ METER TEST Time & Material Water tap & meter prices subject to change based on current market pricing. Water service shut offs after regular business hours: Monday - Saturday $ Sunday & Holiday $ Water service shut off or reactivation due to non-payment $50.00 *Refer to the Water Shut-off Policy Clawson Department of Public Works, 635 West Elmwood (248)
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
DESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address:
City of Woodland Park Internet Service Provider (IPS) Permit for Installation of Telecommunication Infrastructure within City Owned Rights-of-Way (up to five locations per single permit) Permit No. Permit
SECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS
1 SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS TABLE OF CONTENTS I. Introduction II. General Information and Requirements A. Applying for Sewer connection B. Excavation C. Cutting Concrete and Asphalt
SECTION 02221 SELECTIVE DEMOLITION
SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Borough of Matawan 201 Broad Street, Matawan, New Jersey 07747
Borough of Matawan 201 Broad Street, Matawan, New Jersey 07747 (732) 566-3898 Fax (732) 290-7585 DEPARTMENT OF PUBLIC WORKS APPLICATION FOR PERMIT TO CUT SURFACE OF PUBLIC PLACE PERMIT NO: DATE: Application
CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS
CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS 10.1 APPLICATION REQUIREMENTS AND PROCEDURES 10.1.1 A permit shall be required for any construction or installation within the public right-of-way
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
SECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
SECTION 33 41 00 REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:
SECTION 33 41 00 REINFORCED CONCRETE PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes construction of reinforced concrete pipe for storm drainage, culverts, and sanitary sewer, including
City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014
City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 Section Subsection Name Date Modification Division 1 All subsections General Provisions
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
CITY OF SAN ANTONIO. Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03
CITY OF SAN ANTONIO Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03 (010) FORMAL INVITATION FOR BIDS (IFB) to CONTRACT 2016-2017 TASK ORDER CONTRACT
Developer s/consultants Field Services Guidelines
Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
SECTION 13 REPLACEMENT AND CLEANUP 13.01 SCOPE OF WORK
13.01 SCOPE OF WORK Under this item, the Contractor will restore all lawns, trees, gardens, landscape plantings, sidewalks, ramps, trails, fences, commercial signs, water courses and sand, gravel, dirt,
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
Close-Out Documents... 9
Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter
FIBER-OPTIC CABLE PLAN CHECK
Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans
SECTION EIGHT BONDING REQUIREMENTS
SECTION EIGHT BONDING REQUIREMENTS 8-00 BONDING REQUIREMENTS 8-01 No building permit for any construction in the subdivision shall be issued nor any lot within the subdivision conveyed until a bond has
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
ARLINGTON COUNTY CODE. Chapter 18 PLUMBING AND GAS CODES
Chapter 18 18-1. Title and Scope. 18-2. Definitions. 18-3. Availability of Codes. 18-4. Administration and Enforcement. 18-5. Registration of Contractors and Certification Requirements. 18-6. Permits and
Underground Commercial Electric Service
Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains
City of West Chicago Community Development Department 475 Main Street, West Chicago, IL 60185 Phone: (630) 293-2200 x 131 / Fax: (630) 293-1257
City of West Chicago Community Development Department 475 Main Street, West Chicago, IL 60185 Phone: (630) 293-2200 x 131 / Fax: (630) 293-1257 APPLICATION FOR DEMOLITION PERMIT Permit Number: Date Received:
Asphaltic Wedge Paving
OFFICIAL NOTICE ADVERTISEMENT FOR BIDS Notice is hereby given by the Town of Oregon, Dane County, Wisconsin, will receive sealed bids for Road Construction as listed in this request until 4:00 P.M., Local
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08
The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are
Customer Procedures and General Information for Sewer Customers
Customer Procedures and General Information for Sewer Customers Helpful Hints for Customers Ordinance Review of District and Customer Responsibility of New and Existing Sewer Lines Material and Manner
A. In this chapter, the following terms have the meanings indicated.
08.07.02.01 Title 08 DEPARTMENT OF NATURAL RESOURCES Subtitle 07 FORESTS AND PARKS Chapter 02 Roadside Tree Care Authority: Natural Resources Article, 5-209 and 5-406, Annotated Code of Maryland.01 Purpose.
How To Install An Overhead Sewer
Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage
MDWASD 8/1999 SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS
PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS A. The work included under this Section consists of excavating, backfilling and compaction as required for
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309
EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF
TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
JEFFERSON COUNTY ROAD DEPARTMENT HIGHWAY PERMIT USE OF ROADS FOR HAUL ROUTE / EVENT ROUTE. Hereinafter referred to as County/Owner and Name
JEFFERSON COUNTY ROAD DEPARTMENT HIGHWAY PERMIT USE OF ROADS FOR HAUL ROUTE / EVENT ROUTE WHEREAS ROAD DEPARTMENT, JEFFERSON COUNTY, PO BOX 322 14991 94TH ST., OSKALOOSA, KS 66066 Hereinafter referred
CITY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS BUREAU OF ENGINEERING 2015-16 STANDARD FEE LIST (updated 10/3/2015)
SURCHARGE [1] A surcharge of 7% or $1, whichever is greater will be added to the listed fee pursuant to Los Angeles Municipal Code (LAMC) Section 61.03; [2] A surcharge of 2% or $1, whichever is greater
SECTION 4Aggegate Subbase
The contractor shall moist-cure the completed Lime Treated Subbase for a minimum of days before allowing any traffic on the compacted surface. The contractor shall be responsible for repairing any damages
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES
CITY OF PETALUMA STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES AUGUST 1999 Revised 10/98 City of Petaluma Petaluma, California STORM DRAIN INSTALLATION DETAIL
City of Hilshire Village Pine Creek Ln Reconstruction
City of Hilshire Village Pine Creek Ln Reconstruction OVERVIEW The City will be soliciting bids for the Pine Creek Reconstruction Project with construction scheduled to begin in January 2015. This project
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
Exhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.
Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
SPECIFICATIONS FOR SANITARY SEWER LINE REPLACEMENT IN PIONEER PARK. City of Des Peres, Missouri. 12325 Manchester Road. Des Peres, Missouri 63131
SPECIFICATIONS FOR SANITARY SEWER LINE REPLACEMENT IN PIONEER PARK City of Des Peres, Missouri 12325 Manchester Road Des Peres, Missouri 63131 Prepared by City Engineer March 2011 INVITATION TO BID SANITARY
EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is
~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions
ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION
ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS for (PVC) SANITARY SEWER MAIN CONSTRUCTION VI(A).1 General VI(A).2 Materials and Equipment VI(A).3 Installation of Sanitary Sewer Mains VI(A).4 Laying of
Bond Release Process for New Subdivision Developments in Fairfax County
Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
Test Bore, Monitoring Well, & Underground Storage Tank Decommissioning Permit Application Packet
Test Bore, Monitoring Well, & Underground Storage Tank Decommissioning Permit Application Packet This packet contains the requirements and forms needed to apply for a permit allowing test bore, monitoring
SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE
PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE 311.1 DESCRIPTION: This item shall consist of a cement treated subgrade base course composed of a mixture of local soil, portland
ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION
ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION N.B. WORK MUST NOT COMMENCE UNTIL LICENCE IS ISSUED June 2014 Roads Section
SPECIAL PROVISIONS - GENERAL
SPECIAL PROVISIONS - GENERAL SPECIAL PROVISIONS - GENERAL INDEX No. Description Page G1 Execution of Contract 1 G2 Failure to Execute Contract 1 G3 Commencement and Completion 2 G4 Local Labour 2 G5 Non-Resident
TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION
TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION April 25, 2014 DUE DATE/LOCATION: Friday, May 9, 2014 Bid forms and references are due by 9:30 A.M. at:
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
CHAPTER 32 PLUMBING CODE
CHAPTER 32 PLUMBING CODE 32.01 DEFINITION Plumbing for the purpose of this chapter is hereby defined as follows: (a) As is stated in Section 145.01 (1), (a), (c), (d), and (e) of the Wisconsin Statutes.
CHAPTER 111 ELECTRIC FRANCHISE. 111.01 Franchise Granted 111.02 Regulatory Power of City
CHAPTER 111 111.01 Franchise Granted 111.02 Regulatory Power of City 111.01 FRANCHISE GRANTED. MidAmerican Energy Company, a corporation, its successors or assigns are hereby granted and vested with the
Please Refer to Attached Sample Form
Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 29987-G Cancelling Revised Cal. P.U.C. Sheet No. 22381-G Gas Sample Form No. 62-0982 Distribution and Service
SECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
Let Us Give Utilities the Respect that they Deserve.
Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
CITY ENGINEERS ASSOCIATION OF MINNESOTA
CITY ENGINEERS ASSOCIATION OF MINNESOTA STANDARD SPECIFICATIONS 2600 Trench Excavation and Backfill/Surface Restoration 2611 Water Main and Service Line Installation 2621 Sanitary Sewer and Storm Sewer
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
agrees to replace at no charge any tree that dies and subsequent inspection shows that the wire basket was not properly removed.
Adopted 12/5/00; revised as of 1/2/07 Marietta Tree Commission Rules and Regulations I. Tree Planting A. Planting Specifications 1. Trees must be: A) of a minimum 1¼ inches caliper; B) single stem, straight,
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS
TABLE OF CONTENTS 2.18 CONCRETE AND/OR CORRUGATED STEEL STORM SEWER... 1 2.18.1 GENERAL... 1 2.18.2 MATERIALS... 1 2.18.2.1 Storm Sewer Pipe... 1 2.18.2.2 Cement Mortar... 1 2.18.2.3 Granular Materials...
SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes all labor, materials, equipment, and incidentals required and installation of Polyvinyl Chloride
Guidelines for Excavations
O c t o b e r 2 0 0 1 Guidelines for Excavations in the vicinity of gas lines Technical Standards & Safety Authority Putting Public Safety First Guidelines for Excavations in the Vicinity of Gas Lines
Permeable Pavement Construction Guide
Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce
Guidelines for Fiber Optic Cable Permits
Guidelines for Fiber Optic Cable Permits NOVA District (Fairfax/Arlington) Permits www.virginiadot.org/business/fairfax-permits-main.asp Email: [email protected] 14685 Avion Parkway
Right-of Way Use Permit Application
Right-of Way Use Permit Application 400 SW 152 nd Street, Suite 300 Burien, WA 98166 Phone: (206) 439-3161 Inspection: Line 206-439-3162 Email address: [email protected] For City Use Only Reviewed
San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION
ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,
Chapter 18 - Plumbing Code City of South Milwaukee
Chapter 18 - Plumbing Code City of South Milwaukee NOTE: The information listed below may not be accurate and up-to-date. The information is accurate as of the date listed at the bottom of the page; however,
Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY
Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Policy: This policy will replace all previous policies regarding the selection of pipe material for cross drains, drive pipe, drop pipe, storm
Permit Number: Date Issued: Permit Fee: Invoice Number:
City of Burnaby Page 1 of 4 Encroachment Application and Permit Agreement (Testpit, Monitoring Well, Borehole or Vacuum-Hole Installation, Minor Excavation or other Non-Intrusive Work) Rev. 5-2013 Permit
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Specifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
STANDARD PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF DOMESTIC WATER, SEWER AND RECYCLED WATER FACILITIES
STANDARD PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF DOMESTIC WATER, SEWER AND RECYCLED WATER FACILITIES Marina Coast Water District 11 Reservation Road Marina, CA 92933 (831) 582-2665 TABLE OF CONTENTS
ARTICLE IV. DRIVEWAYS
ARTICLE IV. DRIVEWAYS 10-20-390 Definitions. For purposes of this article, the following definitions shall apply: Commercial driveway means any Class B driveway as specified in section 10-20- 420 of this
BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
Right-of-Way Use Permit Application Instructions
Please type or print clearly. Incomplete applications will not be processed. Typical processing time is 5 business days. 1. Property Address (MANDATORY) Applicant must provide a physical property address