Overview of the LHC IR Upgrade Phase-1

Similar documents
LHC MACHINE PROTECTION

The commissioning of the LHC: first the technical systems, then the commissioning with beam

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator

Large Systems Commissioning

FCC JGU WBS_v0034.xlsm

The half cell of the storage ring SESAME looks like: Magnetic length =

SHORT STRAIGHT SECTION TYPES IN THE MATCHING SECTIONS

Brookhaven Magnet Division - Nuclear Physics Program Support Activities

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I)

Lecture VI Magnetic Design

New Machine Layout in IR3 and IR7

10 Project Costs and Schedule

Possible Upgrades and New Design. F. Velotti and B. Goddard

Zero Degree Extraction using an Electrostatic Separator

& Tunnel Cross Section

Projects and R&D activities

How To Use High Temperature Superconductor For A Power Source

PERFORMANCE EVALUATION AND QUALITY ASSURANCE MANAGEMENT DURING THE SERIES POWER TESTS OF LHC MAIN LATTICE MAGNETS

A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson

Ramesh Gupta Brookhaven National Laboratory New York, USA

Technical Specification for the Cryogenic Testing of HTS Current Leads

Expression of Interest in providing design and manufacturing of detectors for the construction of the European X-ray Free Electron Laser Facility

LEReC Engineering. J. Tuozzolo, C-AD Chief Mechanical Engineer (LEReC Project Engineer)

Minimum requirements for the 13 ka splices for 7 TeV operation

THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES

Big Data Analytics. for the Exploitation of the CERN Accelerator Complex. Antonio Romero Marín

DOE LHC Quarterly Review. Magnet Production Cable Testing Cost to Complete issues. Mike Harrison, BNL July 26, 2004

Manufacturing and Testing of Accelerator Superconducting Magnets

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN

CABLE DESIGN AND RELATED ISSUES IN A FAST-CYCLING SUPERCONDUCTING MAGNETS

THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Laboratory for Particle Physics SUPERCONDUCTIVITY AND CRYOGENICS FOR FUTURE HIGH-ENERGY ACCELERATORS

AS COMPETITION PAPER 2007 SOLUTIONS

Cathode Ray Tube. Introduction. Functional principle

MECHANICAL AND THERMAL ANALYSES OF THE CABLE/ STRAND STRAIN TEST FIXTURE

Mark Jaski. Multi-Bend-Achromat (MBA) Magnets

Presentation of the work and activities done at the Forschungszentrum Karlsruhe

Information about the T9 beam line and experimental facilities

Industrial Involvement in the Construction of Synchrotron Light Sources

Results: Low current ( ) Worst case: 800 MHz, GeV, 4 turns Energy oscillation amplitude 154 MeV, where

Peter C. Vander Arend Cryogenic Consultants, Inc. Allentown, Pennsylvania

Mid InfraRed Instrument (MIRI) Cooler Subsystem Design

1 WATERFLUX - Comparisonon COO Rectangular Magmeter in water applications

OVERVIEW OF PROTON DRIVERS FOR NEUTRINO SUPER BEAMS AND NEUTRINO FACTORIES*

SUPERCONDUCTING CABLE SYSTEMS

Lecture 7 Thermal Insulation & Cryostat Basics. J. G. Weisend II

Tom Wilson Product Marketing Manager Delivery Systems Varian Medical Systems International AG. CERN Accelerator School, May 2015

AMSC s Superconductor Cable Technologies for Electric Utilities

Running in Luminosity. Mike Lamont Verena Kain

World-first Proton Pencil Beam Scanning System with FDA Clearance

MICE Major Milestone Status Revision date: 4/4/12 (MICO 181)

physics 112N magnetic fields and forces

BB-18 Black Body High Vacuum System Technical Description

Technical Challenges for Conversion of U.S. High-Performance Research Reactors (USHPRR)

Status of IP FB system design

Thermal Modeling Issues Concerning the Mechanically Pumped Two-Phase CO 2 Cooling for the AMS-2 2 Tracker

Reliability and Availability Aspects of. the IPHI Project

Single Photon Counting Module COUNT -Series

R&D activities at ITA for High Energy Physics. F. Arteche

Introduction to vacuum gauges. Vacuum Gauges where the Pressure Readings are Independent of the Type of Gas (Mechanical Vacuum Gauges)

FREESTUDY HEAT TRANSFER TUTORIAL 3 ADVANCED STUDIES

Thermal insulation. Don t be afraid of low temperatures. Institute for Technical Physics Holger Neumann

LHCC TOTEM STATUS REPORT

Thermal Storage Unit Using the Triple Point of Hydrogen

Activities at the University of Frankfurt (IAP)

Calibration of Dallas sensors

SUMMARY OF THE 4TH LHC CRAB CAVITY WORKSHOP LHC-CC10

The Three Heat Transfer Modes in Reflow Soldering

Lab 4: Magnetic Force on Electrons

Machine Protection and Interlock Systems for Circular Machines Example for LHC

The High Luminosity LHC (HL-LHC) Project at CERN: The Challenge Ahead

Large Hadron Collider am CERN

Power distribution systems

Magnet Power Supplies for TESLA. Hans-Jörg Eckoldt DESY TESLA

E/M Experiment: Electrons in a Magnetic Field.

Insertion Devices Lecture 4 Permanent Magnet Undulators. Jim Clarke ASTeC Daresbury Laboratory

Status of EVOLVE boiling flow regime experiments

Building Services Engineering Technician

HTS Cables: Pitfalls and Potential LIPA Cable Project. J. Maguire American Superconductor. DOE Wire Workshop January, 2007 Panama City, FL

THE LAYOUT DATABASE SERVICE

Salvatore Buontempo. on behalf of the FOS4CMS Group

Lecture 7 Heat Transfer & Thermal Insulation. J. G. Weisend II

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

Relativistic kinematics basic energy, mass and momentum units, Lorents force, track bending, sagitta. First accelerator: cathode ray tube

Laserlyte-Flex Alignment System

SECTION 5 COMMERCIAL REFRIGERATION UNIT 22 CONDENSERS

FIVE PROJECTS OF HIGH RF POWER INPUT COUPLERS & WINDOWS FOR SRF ACCELERATORS*

Machine nozzle with needle shut-off type HP pneumatically or hydraulically controlled

Shielding and Radiation Measurements at ESRF

Electrically operated valves Series M-05, 3/2-, 5/2- and 5/3-way G1/8 650 and 750 Nl/min (0.661 and Cv)

AS COMPETITION PAPER 2008

3 Main Linac. 3.1 Introduction. 3.2 Beam Dynamics II-63

VITOSOL r 200-T SP2A. VITOSOL 200-T Type SP2A

Lucio Rossi CERN- High Luminosity LHC Project Leader. CERN: un opportunità per le aziende Torino, 31 Marzo 2014, Centro Congressi Unione Industriali

CRYOGENIC CONTROL VALVES

Interference. Physics 102 Workshop #3. General Instructions

Butt Fusion Welding of HDPE Pipes Work Procedure

PCB Relays Twin Relays

Transcription:

Overview of the LHC IR Upgrade Phase-1 1. Project goals and constraints 2. Milestones, collaborations, budget 3. Status of studies: Layout and slhc optics Magnets and cryogenics Equipment integration 4. Conclusions R. Ostojic, Chamonix-2010

slhc projects and design studies CMS/ATLAS Upgrade Phase-1 Strategy based on: Steadily increasing operational performance of the LHC year to year; Preparation of long-lead time hardware for known bottlenecks; Coordinated shutdowns with the goal of ensuring continuously increasing performance on a longer term. slhc Phase-1 readiness for installation end 2014.

The ATLAS and CMS interaction regions Dispersion suppressor Matching section Separation dipoles Final focus LHC low-β triplet Position L* = 23 m Quad gradient 205 T/m Coil aperture 70 mm β*, L 55 cm, 10 34 cm -2 s -1 Dissipated power 180 W @ 1.9 K

The low-β triplet in IP1

LHC IR Upgrade Phase-1 Goal of the Project: Provide more flexibility for focusing of the LHC beams in the ATLAS and CMS insertions, and enable reliable operation of the LHC at 2 10 34 cm -2 s -1. Scope of the Project: 1. Upgrade of ATLAS and CMS interaction regions. The interfaces between the LHC and the experiments remain unchanged. 2. The cryogenic cooling capacity and other infrastructure in IR1 and IR5 remain unchanged and will be used to the full potential. 3. Replace the present triplets with wide aperture quadrupoles based on the LHC dipole (Nb-Ti) cables cooled at 1.9 K. 4. Upgrade the D1 separation dipoles, TAS, TAN and other beam-line equipment so as to be compatible with the inner triplets. 5. Upgrade the LHC optics, ensure optics flexibility and machine protection with appropriate layout and additional protection equipment.

Constraints (1) Interfaces with the experiments: Very tight interfaces between the triplet and the experiments; there is no possibility of reducing L* (23m) in ATLAS and CMS insertions. Cryogenics: Ultimate cooling capacity is 500 W@1.9K per triplet (design capacity 1. A of local sub-cooler cryo-system at triplet for entry). RF in IR4 Operational experience should will show be if ultimate included cooling as part power of is LHC available. consolidation. The triplet in 5L will have less cooling capacity (cryogenic sector feeding RF in IR4). 2. Plan for new cryogenics, dedicated to Due to the distance to the the cold triplets refrigerators in IP1 (3.3 and km), IP5, the temperature useful for of the superfluid bath in Phase-1 the triplets triplet is close and to 2 K. later upgrades. The replacement of triplets in IR1 and IR5 requires warm-up of two adjacent sectors (in total at least four sectors of the LHC).

Constraints (2) LHC Optics: Reduction of β* drives aberrations all around the ring. A new optics solution for all arcs and insertions is necessary. New underground areas in IR1 and Accessibility and maintenance: IR5 may all be electronics needed. equipment They should for the triplets and the DFBX cover should all be the located requirements in lowradiation areas. Severe consolidation space constraints and around upgrade IP1 and projects IP5 of for any new equipment. (including Phase-1 triplets). Tunnel transport: access from the surface to IR1/5 requires that the overall dimensions of the new magnets are similar to the LHC main dipole. Upgrade implementation: Must be compatible with CERNwide planning requiring medium-duration shutdown.

Project milestones Project Start Jan 2008 CD Report Nov 2008 TD Report end 2010 Model magnets end 2010 Pre-series quadrupole mid 2011 Series magnets 2011-2014 Triplet string test 2014 Readiness for installation end 2014

Collaborations SLHC-PP (CEA, CERN, CIEMAT, CNRS, STFC) CERN Design and construction of quadrupole and corrector model magnets Design of cryostats LHC IR Upgrade Phase-1 Quadrupole production Cryostating and testing Power converters Protection String test Tunnel integration Special French contribution (CEA, CNRS) US-APUL (BNL, Fermilab) Quadrupole components Cryostat components Production of correctors D1 separation dipoles Feedboxes and SC links

Budget The project was approved by Council as part of New initiatives with a CERN materials budget of 33 MCHF (exclusive of the available SC cable, other materials and tooling remaining from the LHC production). The project relies on a strong international effort and brings together all presently available expertise and resources in accelerator superconducting magnet systems. Contributions from EU, US and a special French contribution have been secured for a considerable part of new equipment. Nevertheless, the present MTP materials budget falls short by about 10 MCHF.

Triplet layout LHC triplet ~66m Issues: Quadrupole length and powering Orbit correctors BPMS position CP and QDXS length and D1 position D1 QDXS CP Q3 Q2b Q2a Q1 Phase-1 triplet

Matching Sections Reduction of β* inevitably reduces the flexibility of the matching sections. Improvements of the matching section are limited to repositioning of the existing magnets (and eventually modification of their beam screens). At present, the Phase-1 Upgrade assumes that: the matching section magnets (D2-Q6) remain unchanged. TAN vacuum chamber to be replaced. Protection If redesigned, against beam halo the (tertiary matching collimators) sections extended should to all be insertion magnets (Q4-D2, Q5 and Q6). Interventions on warm equipment can be done in normal shutdowns. preferably optimized to satisfy also the optics and equipment requirements of Phase-2. The time and effort to complete these studies may delay the completion of the technical design.

Optics issues Insertions. The strength and aperture of the magnets are the limiting factors for reducing β*. Arcs. Correction of aberrations requires re-phasing of all the arcs and insertions for β* < 0.5 m. Triplets. Parasitic dispersion in the triplets due to large crossing angle has to be controlled. Beam crossing schemes in IP1 and IP5 need to be flexible. A complete solution for the new LHC optics has been developed.

Magnet cooling Quadrupoles and correctors: Pressurised static superfluid He bath at 1.3 bar, cooled by two-phase flow of saturated superfluid helium in a bayonet heat exchanger. Heat exchanger dimensioned for the ultimate power of 500 W/1.9 K and ultimate vapour velocity of 7 m/s. Due to the distance of the QRL (3.3 km), the temperature at high heat load increases from the outlet of the refrigerator (1.776 K) to 1.97 K on the outer surface of the heater exchanger. D1 dipole: Pressurised static superfluid He bath at 1.3 bar, cooled by heat conduction to the triplet. Beam screen: Cooled with supercritical helium, 5-20 K.

Triplet cooling scheme Main features: Control and safety valves integrated in the new service module QDXS. Warm-up of the triplet independent of the arc. Warm-up of the SC link/dfx independent of the triplet.

MQXC low-β quadrupole Coil aperture 120 mm Gradient 127 T/m Operating temp 1.9 K Current 13.8 ka Inductance 5.2 mh/m Yoke ID 260 mm Yoke OD 550 mm LHC cables 01 and 02 Enhanced cable polyimide insulation Self-supporting collars Single piece yoke Welded-shell cold mass

MCXB, MQSX correctors Coil aperture 140 mm Operating temp 1.9 K Current 2.4 ka Yoke OD 550 mm New 4 mm cable design Cable polyimide insulation Self-supporting collars Single piece yoke Welded-shell cold mass MCXB field strength 1.5 Tm MCXB inductance 10 mh MQSX field strength 0.65 T MQSX inductance 3 mh

D1 separation dipole Two optimised BNL DX magnets assembled in one helium vessel Coil aperture 180 mm Field 4.1 T Magnetic length 7.4 m Operating temp 1.9 K Current 6.35 ka Inductance 98 mh Yoke OD 620/550 mm

Protection against particle debris Protection against particle debris is the single most serious issue of the upgrade. Triplet shielding efficiency: Phase-1 = 2.5 LHC Energy deposition in the coils and magnet lifetime. Equipment protection around the beamline (TAS, TAN). Protection of electronic equipment in underground areas. Maintenance and interventions Average dose 1.5 MGy/100 fb -1 All equipment built for a lifetime of 1000 fb -1, compatible with the lifetime of ATLAS and CMS before their Phase-2 upgrade.

Powering equipment in IR1 Split powering chosen as a compromise between volume and complexity. Protection of the magnets ensured by the energy extraction system and by the quench heaters. DFX DFX, converters and switches located in lowradiation areas. DFX connected to the QDXS service module via a SC link (~30-100 m.) Link Cryo Service Module (QDXS) Link DSX Length ~28 m DFX 3 sharp (~ 1.5 m radius) bends plus some curves

Equipment in IR5 DFX Link Cryo DSX Service Module (QDXS) Length ~95 m One 180 degree curve plus some longer curves

Equipment in IR5 New underground areas in IR1 and IR5 would considerably ease equipment installation and maintenance. Length ~50m 5 sharp bends DSX DFX Service Module (QDXS)

Comparison of LHC and Phase-1 triplets Nominal LHC triplet LHC Phase-I Upgrade triplet Gradient 205 T/m 120 T/m Aperture: coil/beam Screen 70/57.8 mm 120/99.2 mm Crossing plane Fixed Any Magnetic length (optimised for) 23.7 m (7 TeV) 34 m (7 TeV) Length (Q1-D1) 61.4 m 64 m LRBB (distance end_q3-ip) 14.2 (53.3 m) 17.3 (64.5 m) Minimum β* 0.55 m 0.30 m Luminosity at minimum β* (rel) 1 1.4 Field quality (rel) Very good Good Field correctors Full complement Full complement Alignment system (rel) Excellent Excellent Orbit correction (rel) Excellent Good Cooling capacity (HX) 250 W @1.9 K 500 W @ 1.9 K Radiation safety margin (rel) 1 2.5 Sectorization No Yes Access Difficult Good

In conclusion A conceptual design for the Phase-1 Upgrade, in line with the general constraints, is at hand. The technical design, the limited R&D and tooling preparations for magnet construction, are advancing. Due to the fact that the LHC dipole cable is readily available, the magnets and other equipment can be built, under reasonable assumptions, by the end of 2014. The available resources at CERN and worldwide for the construction of the magnets and other equipment for the Phase-1 Upgrade are limited. The collaborations with European and US laboratories, which bring in their expertise and resources, have been formalised and are in effect. Separate cryogenic systems for the triplets in IR1 and IR5, together with new underground areas, if available around 2015-16, would considerably ease the installation and improve the performance of the new triplets. Such investment is necessary for further IR upgrades. The new triplets provide considerable flexibility for beam collisions in ATLAS and CMS insertions. Several ways are open to reach stable operation at a luminosity of 2 10 34 cm -2 s -1.

Acknowledgments Members of the Technical Design Group R.Assmann M.Bajko A.Ballarino C.Boccard F.Butin F.Cerutti R.Denz D.Duarte Ramos O.Dunkel S.Fartoukh S.Feher P.Fessia B.Holzer M.Kaducak M.Karppinen G.Kirby N.Kos H.Mainaud Durand S.Maridor J.Miles Y.Muttoni T.Peterson S.Plate H.Prin S.Roesler S.Russenschuck H.Thiesen J-P.Tock A.Vande Craen R.Van Weelderen R.Veness B.Vullierme S.Weisz P.Wanderer L.Williams K.C.Wu