The To Complete Performance Index



Similar documents
Earned Schedule application to Project Management

Earned Value Formulae

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

Since 1985, the Test Program Set (TPS) development

Schedule Adherence. and Rework Walt Lipke, PMI Oklahoma City Chapter. PUBLISHER s CHOICE

700 Analysis and Reporting

Earned Schedule Leads to Improved Forecasting

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule

Schedule Adherence a useful measure for project management

Project Cost Management

Project Cost Management

Project Control with ProTrack

Simple Earned Value (Using MS Project 2010)

Assessing Schedule Performance with Earned Value

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Abstract. Earned Value Management Basics

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

How To Manage A Project

Chapter 7. (PMBOK Guide)

Brainstorm. What is Cost and Project Cost Management?

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

Using Earned Value Management for Improving Processes. By Cynthia K. West

A Gentle Introduction to Earned Value Management Systems

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

TIME FORECASTING USING EARNED SCHEDULE

Introduction to earn value management in Civil Engineering

Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

IST 302 : Project Cost Management

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

An introduction to Earned Value Analysis

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

L10: Budgeting and Cost Control. Olivier de Weck

CVR/IT Consulting LLC

performance management system that is based on Earned Schedule Management.

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Project Management Using Earned Value

EVM.01. Earned Value Analysis Why it Doesn't Work

Forecasting Project Schedule Completion by Using Earned Value Metrics

Agile Project Management Controls

Earned Value Management Guidelines

A Guide to Managing Programs Using Predictive Measures

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

Project Cost Management

Project Management Center

PMP 2013 Exam Prep. Course Overview


Earned Value and Agile Reporting

PROJECTS SCHEDULING AND COST CONTROLS

DCMA DCMA-EA PAM October 2012

INSE 6230 Total Quality Project Management

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Project Management: Tracking Progress and Earned Value with MS Project 2003

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

earned value management

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

Earned value method as a tool for project control

Estimating Cost at Completion - Judgment & EV Information

A Framework for Project Metrics

Tracking Software Development Progress with Earned Value and Use Case Point

Project Cost Management - 2 Days

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Algebra Practice Problems for Precalculus and Calculus

Tracking Budgets and Schedules

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Training Seminars. Description. Core Courses: The core courses consist of the following:

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

Project Cost Management - 2 Days

PMP Exam Preparation Answer Key

COINS EVA Earned Value Analysis

Chapter 5: Project Cost Management

Module 5 Cost Management PMP Exam Questions

AACE International Recommended Practice No. 86R 14

Predicting progress on your project

PMI Lexicon of Project Management Terms

What is the Health of my Project?

Chapter 7: Project Cost Management. Munawar

Brief Introduction to Earned Value Management (EVM)

Simulation Exercises to Reinforce the Foundations of Statistical Thinking in Online Classes

plans based on actual cost, schedule and technical progress of work [1, 9].

What are the place values to the left of the decimal point and their associated powers of ten?

a 11 x 1 + a 12 x a 1n x n = b 1 a 21 x 1 + a 22 x a 2n x n = b 2.

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008

DICK BRODKORB FAX ( ) 3 THEN CHECK THE LOCATION YOU LL BE ATTENDING.

Over Target Baseline and Over Target Schedule Guide

Project Recovery. . It Can Be Done

Comparative Study for Software Project Management Approaches and Change Management in the Project Monitoring & Controlling

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Management Planning

Project Time Management

Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring)

Transcription:

The To Complete Performance Index transforming project performance Walt Lipke 1.1 PMI - Oklahoma City Chapter 1.0 +1 405 364 1594 waltlipke@cox.net www.earnedschedule.com Index 1.3 1.2 TCPI vs CPI TCPI CPI Threshold 0.9 0.8 0.7 0.0 0.2 0.4 0.6 0.8 1.0 Fraction Complete

Abstract The To Complete Performance Index (TCPI) from Earned Value Management describes the performance efficiency required to achieve a cost objective. Beyond its usual application, the TCPI indicator has a significant role in transforming project performance to effect a project recovery. This virtually unknown aspect is the focus of this presentation. 2

Overview Introduction Evaluation of EAC Further Examination Application to Project Recovery Evaluating the Recovery Strategy Schedule Analysis Summary & Conclusions 3

Introduction EVM provides a method of describing project performance numerically a significant improvement for assessing & reporting project status The most often used and best understood indicator from EVM is the Cost Performance Index, CPI = EV / AC CPI is a description of the efficiency of achieving the accomplishment with respect to the cost investment made 4

Introduction Whereas CPI describes the past, TCPI provides information about the future TCPI is defined as the work remaining to be accomplished divided by the amount of unspent funding TCPI = (BAC EV)/(TC AC) where TC = Target Cost or Desired Cost Outcome What does TCPI tell us? The index value describes the cost performance efficiency required for the remainder of the project to achieve the desired final cost 5

Evaluation of EAC Traditionally, TCPI is used by customers or oversight organizations to assess the reasonableness of an estimated final cost or Estimate at Completion (EAC) For this application, TCPI = (BAC EV) / (EAC AC) The customer evaluates the EAC provided by the PM from the value of the TCPI computed 6

Evaluation of EAC TCPI Value Predicted Outcome 100 1.00 Achievable > 1.10 Not Achievable 7

Evaluation of EAC When TCPI is equal to or less than 1.00, there is confidence that the EAC can be achieved Conversely, when TCPI is equal to or greater than 1.10 the project is considered to be out of control; the EAC is very likely unachievable Between the two declarative values, 1.00 and 1.10, the PM s actions become ever more critical to project success. Management intervention to improve cost performance very probably will be required to achieve the EAC 8

Evaluation of EAC TCPI vs CPI TCPI CPI Threshold Index 13 1.3 Exceed Threshold @ 0.35 1.2 TCPI 1.1 1.0 CPI = 0.850 0.9 0.8 0.7 0.0 0.2 0.4 0.6 0.8 1.0 Fraction Complete 9

Evaluation of EAC The planned final cost (BAC) will not be achieved if this performance, CPI = 0.850, continues TCPI continually increases as the project progresses, exceeding the threshold value of 1.10 at fraction complete of approximately 0.35 The rate of TCPI increase becomes ever larger as fraction complete increases. 10

Further Examination What is the evidence that when TCPI > 1.10, the project is irrecoverable? As far as I know, there have not been any empirical or theoretical studies to validate the claim. In the next few slides, we ll look at the behavior of TCPI in more detail and state my opinion 11

Further Examination A revealing view can be obtained using calculus from TCPI in a different form: TCPI = (1 EV%)/(CR CPI -1 EV%) where CR (Cost Ratio) = TC / BAC EV% = EV / BAC For notation simplicity: y = TCPI, x = EV%, a = CR, b = CPI -1 The equation to examine becomes: y = (1 x)/(a bx) 12

Further Examination As an example, let us analyze a project having cost performance which will not achieve the cost objective: CPI -1 = 120 1.20, CR= 110 1.10 The point of interest is when TCPI equals the threshold value (1.10) x = (ya 1)/(yb -1) = ((1.1 1.1) 1)/((1.1 1.2) -1) = 0.656 13

Further Examination What is the rate of increase of TCPI at the threshold value (1.10)? TCPI rate of increase with respect to fraction complete can be examined using the first calculus derivative: dy/dx = (b a)/(a bx) 2 At the point of interest (TCPI = 1.10), the derivative can be evaluated: dy/dx = (1.2 1.1)/(1.11)/(1 1 (1.2 0.656)) 2 = (0.1)/(1.1 0.7875) 2 = 1.024 14

Further Examination What happens to the rate of increase of TCPI when performance continues and fraction complete increases? EV% 0.656 dy/dx 1.024 0.700 1.479 0.750 2.500 15

Further Examination For modest increases in EV%, it is seen from the numbers in the table that dy/dx (i.e. the TCPI rate) has larger and larger rates of change Once the threshold is exceeded, there is little hope that management intervention can have positive impact the project is very rapidly becoming out of control Thus, the threshold value of 1.1010 for TCPI appears to be a reasonable criterion for making the assertion that the EAC put forth by the PM in the project status report is unachievable 16

Application to Project Recovery PMs applying EVM possess early warning tools Forecast of final cost, IEAC = BAC / CPI As an example, let s examine a project using the following data: CPI = 0.850, BAC = $1000, MR = $100 What is projected for the future? If CPI does not improve, BAC will be exceeded IEAC = 1000 / 0.850 = $1176 MR will be consumed, IEAC > TAB The project is headed for a budget overrun 17

Application to Project Recovery What is the PM s prerogative when the project is 80 percent complete? By calculating TCPI using TAB as the desired final cost and graphing it as shown previously, the answer is readily seen As observed in the next slide, the value of TCPI is so large it is nearly off the chart; the computed value is 1.259 18

Application to Project Recovery TCPI vs CPI TCPI CPI Threshold Index 1.3 1.2 1.1 1.0 0.9 0.8 0.7 TCPI = 1.259 @0.80 CPI = 0.850 0.0 0.2 0.4 0.6 0.8 1.0 Fraction Complete 19

Application to Project Recovery From our previous discussion, the PM knows that when TCPI 1.10 the project is regarded as irrecoverable and that additional funding is very likely needed In this instance, as uncomfortable as it may be, negotiation with the customer cannot be avoided Does the PM make the same decision when the project is 30 percent complete? 20

Application to Project Recovery The simple answer is No At 30 percent complete, TCPI = 0.937, a good number, yet the PM knows from IEAC that if the current performance does not improve the project will overrun the funding available (TAB) However, with this value for TCPI, the PM has an opportunity to take action thereby avoiding the overrun and the embarrassment of the impending negotiation if the present cost performance continues 21

Application to Project Recovery What is the period of opportunity for the PM to make a positive performance change? The PM has from the present status point until TCPI exceeds 1.10 to recover the project Is the period of opportunity sufficient for recovery to be successful? For our example, let s look at the graph 22

Application to Project Recovery TCPI vs CPI TCPI CPI Threshold Index 1.3 1.2 1.1 1.0 0.9 0.8 0.7 TCPI = 0.937 @ 0.30 TCPI > 1.10 @ 0.72 ΔEV% = 0.42 0.0 0.2 0.4 0.6 0.8 1.0 Fraction Complete 23

Application to Project Recovery For a project of reasonable size, having more than 40 percent of the period of performance to create and make an effective change, the PM has a very good chance for being successful with the recovery action 24

Evaluating the Recovery Strategy The TCPI has application, as well, in creating a viable recovery strategy a trade-off between cost and schedule performance to achieve the commitments to the customer (TAB & negotiated product delivery date) To resolve the condition of unsatisfactory cost performance, the PM creates a plan for transforming the cost performance from the present value of CPIa (actual value) to an improved efficiency, CPIs (strategy value) 25

Evaluating the Recovery Strategy TCPI plays a role in evaluating whether the change desired can realistically be achieved. For this purpose, the following formula for TCPI is used: TCPI = (1 EV%) / (CPIs -1 CPIa -1 EV%) As a rule of thumb, the envisioned performance change has a good likelihood of being achievable when the calculated value for TCPI is less than or equal to 1.00 indicating whether there is sufficient opportunity for the improvement to succeed 26

Schedule Analysis The To Complete Schedule Performance Index (TSPI) facilitates analysis similar to the TCPI TSPI is equal to the planned duration for the work remaining divided by the duration available: TSPI = (PD ES) / (TD AT) 27 where PD is the planned duration ES is the Earned Schedule TD is the total duration desired generally: PD, the negotiated duration (ND), or estimated duration (ED) AT is the actual time or duration at the time of computation

Schedule Analysis The use of TSPI is available for schedule management and control in a parallel manner to cost and TCPI Is the project schedule recoverable? What is the period of opportunity for the PM to make a positive schedule performance change? Is the period of opportunity sufficient for schedule recovery to be successful? Both TCPI & TSPI are needed to have complete capability for the cost schedule performance trade-off necessary for project recovery 28

Summary TCPI is definitely more than the simple calculation for determining the performance rate needed for the remaining work TCPI has application in evaluating the realism of the bottom up derived EAC it was shown that the value of 1.10 is a reasonable criterion for determining when a project is not recoverable and is out of control 29

Summary Use of TCPI was extended to the evaluation of the opportunity and the performance transformation envisioned for project recovery TCPI may also be used in creating the tactical changes of personnel and overtime adjustments Through Earned Schedule the methods described for TCPI are made applicable to schedule analysis, as well TCPI & TSPI have much to offer to the PM in his/her efforts for controlling and managing the project 30

References The To Complete Performance Index an expanded view, The Measurable News, 2009 Issue 2: 18-22 [W. Lipke] Project Recovery It Can Be Done, CrossTalk, January 2002: 26-2929 [W. Lipke] Practice Standard for Earned Value Management. Newtown Square, PA: Project Management Institute 2005. Earned Schedule website: www.earnedschedule.com com 31