HYDROPOWER POTENTIAL OF NEUQUÉN PROVINCE
Hydropower potential of Neuquén province Existing structures Hydroelectric power plant Installed Power (MW) Annual Mean Energy (GWh/a) Alicurá 1.050 2.360 Piedra del Águila 1.400 5.500 Pichi Picún Leufú 261 1.080 El Chocón 1.200 3.600 Arroyito 128 720 Planicie Banderita 479 1.512 TOTAL 4.518 14.772
Hydropower potential of Neuquén province Order No. Name Installed Power (MW) 4 Atreuco 54 6 Buta Pailán 94 7 Caleufú (alim. Alicurá) 100 8 Calfulén 38 9 Cerro Rayoso 472 14 Coli Michicó 50 15 Collón Curá 376 16 Covunco 108 17 Curamileo 34 18 El Chacayal 181 19 El Chañar 69 20 Chihuido I 637 21 Chihuido II 228 24 Huaraco 48 25 Huitrín 210 26 La Invernada 322 27 La Rinconada 200 28 La Salada 34 29 Las Lajas 48 30 Loncopué 16 31 Los Guiones 30 33 Manzano Amargo 30 34 Matancilla 64 35 Michihuao 621 38 Pantanitos 190 41 Pini Mahuida 457 43 Puesto de Paja 38 45 Rincón de la Medialuna 270 46 Roblecillos 46 48 Segunda Angostura 120 50 Talhelum 240 Total 5425
Hydropower potential of Neuquén province Order Name Installed Power (MW) 4 Atreuco 54 6 Buta Pailán 94 9 Cerro Rayoso 472 14 Coli Michicó 50 16 Covunco 108 17 Curamileo 34 19 El Chañar 69 20 Chihuido I 637 21 Chihuido II 260 24 Huaraco 48 25 Huitrín 210 26 La Invernada 322 28 La Salada 34 29 Las Lajas 48 30 Loncopué 16 31 Los Guiones 30 33 Manzano Amargo 30 34 Matancilla 64 41 Pini Mahuida 457 46 Roblecillos 46 Total 3083
RÍO NEUQUÉN BASIN Area: 30,000 km2 (up to Paso de los Indios) Río Neuquén Length: 440 km Río Neuquén Flowrate: 309 m3/s at Paso de los Indios/La Higuera. Probable Maximum Rise in Level: 25.070 m 3 /sec Decamillenary Rise in Level: 20.200 m3/sec Rise in level: from May to July due to rainfalls, and from October to December due to thaw. Hydropower projects existing: Cerros Colorados Hydroelectric Complex
RÍO NEUQUÉN BASIN Portezuelo Grande has a handling capacity of up to 11,500 m 3 /sec rise in level, of which 7,900 m 3 /sec are derived to Los Barreales basin and 3,600 m 3 /sec must be derived to the Portezuelo Grande- El Chañar section that, under normal operating conditions, has a constant flow of 12 m 3 /sec. Cerros Colorados Hydroelectric Complex System to control rise in level and regulation of flows from Río Neuquén to ensure water supply for human consumption, irrigation and hydropower generation. It consists of the following dams: - Portezuelo Grande - Loma de la Lata - Planicie Banderita - Chañar It forms the following reservoirs: - Los Barreales - Mari Menuco - El Chañar Planicie Banderita Power Plant: - Installed Power : 479 MW - Annual Mean Energy: 1.512 GWh/year.
PRIORITIZED PROJECTS ON RÍO NEUQUÉN BASIN Chihuido I Chihuido II Cerro Rayoso Huitrín La Invernada Pini Mahuida El Chañar Los Guiones Colo Michicó
Chihuido I Multipurpose Project OBJECTIVES GREATER SAFETY BEST SUPPLY MORE ENERGY
Chihuido I Multipurpose Project WORK TECHNICAL DATA - Height: 105 Mts. - Length: 1,035 Mts. - Crest width: 12 Mts. - Dam crest elevation: 631 m.a.s.l. - Dam type: Concrete-faced rockfill (CFRD) -Number of machines: 4 Francis type turbines. - Power generation: 637 Mw. - Annual Mean Energy: 1.750 GWh/year. EXTRA HIGH VOLTAGE LINE (EHVL) 500 kv Line Interconnection Chihuido I Agua del Cajón 130 km 500 kv Transforming Station
Chihuido I Multipurpose Project FUTURE RESERVOIR AREA Chihuido I Lake
Chihuido II Project Nominal Power (MW) * 260 Mean Energy (GWh/year)* 1200 Maximum Elevation (m.a.s.l.)* 532 Nominal Fall (m)* 56 Dam length (m) 890 Reservoir Area (Km²) 65 Subject to the results of the optimization study with Chihuido I Preliminary draft and under Chihuido I compatibility study Additional basic research is needed to continue with the dam design
Pini Mahuida La Invernada Huitrín Cerro Rayoso Emhidro SEP, through an agreement entered into with Neuquén Mining Department, has carried out geological surveys of Pini Mahuida, La Invernada and Cerro Rayoso areas, to establish their regional geological and structural features. As part of the Studies Program of the Energy Sector (PESE, in Spanish) of the Department of Energy's Office, which is funded by the Andean Development Corporation (CAF, in Spanish) the development of the bidding construction projects has been tendered and awarded. The estimated date for the start of works is October 2015 and will be conducted by the consulting firms INTERTECHNE - HISSA - HCA and GRIMAUX. Pini Mahuida, La Invernada and Cerro Rayoso projects have been included in the Power Works for the National Development and Integration Plan prepared by the National Government in 2014 year.
CERRO RAYOSO River Neuquén Area Cerro Rayoso Reservoir Elevation (m.a.s.l.) 820 Fall(m) 115 Crown Elevation (m.a.s.l.) 825 Average Flow (m3/s) 242 Power (MW) 472 Generation(GWh) 2067 Geogra. Coord. (Latitude) S 37º 47 Geogra. Coord. (Longitude) W 69º 51 GEOGRAPHIC LOCATION
HUITRÍN River Neuquén Area Huitrín Reservoir Elevation (m.a.s.l.) 820 Fall(m) 51 Crown Elevation (m.a.s.l.) 825 Average Flow (m3/s) 245 Power (MW) 210 Generation(GWh) 921 Geogra. Coord. (Latitude) S 37º 39 Geogra. Coord. (Longitude) W 70º 01 GEOGRAPHIC LOCATION
LA INVERNADA River Neuquén Area La Invernada Reservoir Elevation (m.a.s.l.) 950 Fall(m) 84 Crown Elevation (m.a.s.l.) 955 Average Flow (m3/s) 226 Power (MW) 322 Generation(GWh) 1409 Geogra. Coord. (Latitude) S 37º 22 Geogra. Coord. (Longitude) W 70º 28 GEOGRAPHIC LOCATION
PINI MAHUIDA River Neuquén Area Pini Mahuida Reservoir Elevation (m.a.s.l.) 1070 Fall(m) 120 Crown Elevation (m.a.s.l.) 1073 Average Flow (m3/s) 225 Power (MW) 457 Generation(GWh) 2000 Geogra. Coord. (Latitude) S 37º 21 Geogra. Coord. (Longitude) O 70º 41 GEOGRAPHIC LOCATION
500 kv LINES PLANNED EL CORTADERAL POSSIBLE 500 KV LINE TO COMPLETE THE EVACUATION OF RÍO NEUQUÉN PLANTS PINI MAHUIDA 320 MW 30 Km LA INVERNADA 320 MW HUITRIN 210 MW CERRO CAYOSO 260 MW 500 KV LINE THAT IS PART OF CHIHUIDO I PROJECT CHIHUIDO I 670 MW References: Existing 500 kv Future 500 kv AGUA DEL CAJÓN Source: Cammesa
Los Guiones Colo Michicó Los Guiones Colo Michicó -Río Nahueve -Average Flow: 43 m3/s -Installed Power: 30 MW -Generation: 132 GWh/year -Río Neuquén -Average Flow: 105 m3/s -Installed Power: 50 MW -Generation: 223 GWh/year As part of the Argentine Secretary of Energy's PESE Program, which is funded by the CAF, the contract for the preparation of bidding construction projects, with estimated completion date of November 2015, is under preparation.
El Chañar Hydropower Plant Maximum Elevation (m.a.s.l.) 339.5 Nominal Fall (m) 8.81 Average Performance Level (Kwh/m3) 0.016 Nominal Power (MW) 24 Mean Energy (GWh/year) 139 Utilization Factor 68% The Pant is located at 6 km of a 132 kv HVL, which delivers the energy generated at Provincial Interconnected System (SIP) and, through it, to the National Interconnected System (SIN). The works will help to meet the growing demand for electricity in the country by taking advantage of the dam built and adding the necessary electromechanical equipment.
Power Distribution in Neuquén
High Voltage Grid in 2011 Neuquén province is head of 5 extra high voltage lines of 500 kv.
MAPA AREAS COMPONENTES DEL PA Color gris Área extractiva Color verde Área soporte Operating Area Vaca Muerta Geological Formation References Exploitation Area Support Area Projected Area Pini Mahuida La Invernada Huitrín Cerro Rayoso Chihuido I Chihuido II El Chañar Source: Strategic Study for the Territorial Development of Vaca Muerta Region. The challenge of sustainability in the region within the framework of unconventional hydrocarbon reservoir exploitation
THANK YOU www.emhidro.com.ar