Porous Pavement Alternatives Cost Analysis



Similar documents
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010

Updates on Pervious Pavement Design and Construction. Jason T. Peterein, P.E. June 19, 2012

Caltrans non-standard Special Provisions Pervious Concrete. David Akers Feb 28, 2012

Installing Porous Pavement Waukesha County Dept. of Parks & Land Use Storm Water BMP Design and Installation Workshop March 11, 2009

Guidelines for. Permeable Pavement

APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS

Permeable Interlocking Concrete Pavements. The Stormwater Problem

Pervious Pavers. By: Rich Lahren. Hebron Brick & Block Supply

Permeable Pavement Operation & Maintanence Guide

Permeable Interlocking Concrete Pavements

Pervious Pavement SYSTEMS THINKING. THE NEW DESIGN PROBLEM and the Role of the Civil Engineer. LOW IMPACT DEVELOPMENT Introduction

AquaPaver & SF-Rima Permeable Interlocking Concrete Pavers

Permeable Pavement Construction Guide

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

CID STREET INFRASTRUCTURE ASSESSMENT

LID-01 Permeable Paving Systems

Dave Laurie, CTR. Sales Manager, Commercial Sales DESIGNED TO CONNECT

Division 2 Section Section 02795

Building Your Interlocking Concrete Pavement to Last a Lifetime

CASFM Stormwater Quality Field Trip June 23rd, 2011

Permeable Interlocking Concrete Pavements

ALKS SIDEW II. TK TK TK TK TK TK TK TK 40 BOSTON COMPLETE STREETS GUIDELINES DRAFT - JULY 2011 BOSTON TRANSPORTATION DEPARTMENT

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

The AASHO Road Test site (which eventually became part of I-80) at Ottawa, Illinois, was typical of northern climates (see Table 1).

Permeable Pavers. calstone.com. Permeable Interlocking Concrete Pavements (PICP s)

Pervious Pavement. An Infiltration BMP A LID Technique. Dan Huffman Vice President, National Resources National Ready Mixed Concrete Association

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

Sustainable Site Pavement Systems

AUSTRALIAN PAVING CENTRE

A Solution to Clogging of Porous Pavements

Permeable Pavement Treatment Capacity

SUDAS Revision Submittal Form

Underground Injection Control Storm Water Information

SECTION UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT

C. Section TESTING LABORATORY SERVICE.

Storm Water Runoff. Managing. A Self-Assessment Guide for Wisconsin Businesses. Storm water runoff is coming. This guide provides businesses

Permeable Interlocking Concrete Pavement

Low Impact Development Permeable Paving

1800 Washington Boulevard, Baltimore, MD TTY Users Larry Hogan, Governor Boyd

Advancements in Permeable Pavements

Permeable Paving System with StormAbsorb Technology

Low Impact Development Checklist

Permeable Interlocking Concrete Pavements

Table 4.9 Storm Drain Inlet Protetion Applicable for

4.1. Permeable Pavement Systems

PICP Construction. Why PICPs The Big Picture. Key things to know about PICPs

Guidelines for Control of Water Runoff on Small Lots. Revised 6/09

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT

Permeable Interlocking Concrete Pavement (PICP) A Low Impact Development Tool Training for Schools and Universities

Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST BID PROPOSAL

Interlocking Concrete Pavement as an Alternative to Asphalt Concrete for Howard Road, Westley, California

NEUPAVE. Permeable Pavers. A Permeable Eco-Friendly Beauty

PERMEABLE INTERLOCKING CONCRETE PAVEMENT

Construction Specifications for Keyhole Pavement Coring and Reinstatement

Final 1 st Edition January 2006 A GUIDELINE FOR THE DESIGN AND CONSTRUCTION OF ASPHALT PARKING LOTS IN COLORADO

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Stormwater Credit Open House Q&A

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Local Road Assessment and Improvement Drainage Manual

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.

Design, Construction and Maintenance of Permeable Pavements Case Studies and Technical Resources Robert Bowers, P. Eng.

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

Waukesha County. Municipal Separate Storm Sewer System (MS4) Permit Annual Report to the Land Use Parks & Environment Committee

Costs for Green Infrastructure and Stormwater Controls

Jon E. Zufelt, PhD, PE ERDC-CRREL Anchorage, Alaska

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

Design and Construction of a Pavement for Tracked Military Vehicles

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

Best Management Practice Fact Sheet 7: Permeable Pavement

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

VA DEQ STORMWATER DESIGN SPECIFICATION NO. 7 PERMEABLE PAVEMENT. VERSION 2.0 January 1, 2013 SECTION 1: DESCRIPTION

PE01 Permeable Interlocking Concrete Pavements - Design and Construction Guide

40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT

>S`[SOPZS 7\bS`Z]QYW\U 1]\Q`SbS >OdS[S\b

LABORATORY TESTING AND MODELING FOR STRUCTURAL PERFORMANCE OF FULLY PERMEABLE PAVEMENTS: FINAL REPORT

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

SECTION STORM DRAINAGE TABLE OF CONTENTS

Structural/Hydrologic Design & Maintenance of Permeable Interlocking Concrete Pavement

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

SECTION PERVIOUS INTERLOCKING CERAMIC PAVERS

When Water Comes to Town What Happens

CHAPTER 5. Storm Sewer

GREEN INFRASTRUCTURE DESIGNS BIOSWALE/HYBRID DITCH

Quality Assurance Concepts. Outline

SUSTAINABILITY INITIATIVE: PERMEABLE PAVEMENT: ADAPTING TO STORMWATER MANAGEMENT CHALLENGES

Transcription:

Porous Pavement Alternatives Cost Analysis Prepared by Century West Engineering for Metro This cost analysis compares the construction costs of six different types of pavement for three different scenarios. The purpose of the analysis is to give builders a way to compare the relative costs of porous pavements. The cost estimates are based on a number of assumptions and on one engineering firm s designs. Porous and conventional pavement costs vary depending on site conditions, market conditions, engineering designs, local permit requirements and other factors. In addition, this memo presents costs for construction only and does not take into account lifetime cost of each pavement. Metro encourages the use of porous surface options when appropriate and in jurisdictions that permit it, but Metro does not promote any particular pavement material. 1. INTRODUCTION Due to current requirements for management of stormwater runoff, a number of new technologies have emerged in recent years to manage both the quality and quantity of stormwater runoff associated with urban development. One technology that has received increased attention is porous pavement. Porous pavement allows disposal of runoff via direct infiltration from the developed surface. This ability to use paved surfaces to dispose of storm water offers a number of benefits including; efficient use of developable land by utilizing the paved footprint on a site for stormwater management; improved treatment compared with other stormwater BMP s; and reducing runoff to rivers, lakes, and streams reducing erosion and storm surge and improving overall water quality. One of the barriers to wider use of porous pavements is the perception that porous pavement is more costly than conventional pavement and related stormwater management systems. In order to provide a better understanding of the true costs of porous pavement compared to other paving systems, the Metro Sustainability Center has undertaken a study to estimate the relative costs for a number of pavement systems both porous and non-porous. The objective is to provide comparisons that will be helpful to land developers and municipalities in the planning and design of site improvements. Century West Engineering has been commissioned to perform the analysis and summarize their findings and results. This memo presents the findings and conclusions of this study. 2. DESIGN SCENARIOS Three scenarios were considered. Included were: Neighborhood Roadway A roadway roughly consistent with a 200 city block. Assuming 50 lots, the street would access eight homes. The width would be sufficient to accommodate two 12 travel lanes with 10 for parking on one side of the street. Based on these requirements the street s paved area would total 6,800 SF. It is assumed that the street will be curbed; however, sidewalks were not considered for this study. page 1

Parking Lot A parking lot for a small business. The lot would include ten 10 x20 stalls and a 50 x24 drive aisle. The total area would be 3,200 SF. Curbs, but no sidewalks, are assumed. Driveway A driveway large enough for three cars with room for some maneuvering. 800 SF of pavement is assumed. 3. DESIGN ALTERNATIVES Six pavement sections were considered for the three scenarios listed above. These included: Porous Asphalt Pavement Pervious Concrete Pavement Permeable Interlocking Concrete Pavers Porous with a Geo-cellular grid Conventional Asphalt plus Drainage Structures Conventional Concrete plus Drainage Structures Each section was designed based on uniform assumptions of traffic loading for a 20-year life to produce pavement sections that will perform comparably. The pavement sections presented are based on conservative assumptions resulting in thicker sections than might be typically used. Actual sections for a particular application will depend on site specific soil conditions and traffic loadings. 3.1. PAVEMENT DESIGN 3.1.1. Structural Section Traffic loading for each scenario was determined based on Equivalent Axle Loadings (EALs) anticipated over a 20 year period and Average Daily Truck Traffic (ADtt). Both construction and operational traffic were considered. Based on these assumptions the following traffic loads were projected. Neighborhood Roadway 25,000 EALs, ADtt=3.5 Parking Lot 14,000 EALs, ADtt=1.9 Driveway Minimal Traffic Soils were assumed to have fair suitability for subgrade construction. A California Bearing Ratio (CBR) of 5 was used for pavement section design. The surface course strength for porous asphalt was considered roughly equal in strength to its non-porous counterpart. However, for concrete the compressive strength of pervious concrete is roughly 2,500 psi, considerably less than the 4,350 psi assumed for non-porous. To offset this difference, thicker slabs are specified for pervious concrete. In this study, concrete slab thicknesses were increased by 50% to offset the lower strength of pervious concrete. Traditionally, for porous asphalt and pervious concrete surfaces, the aggregate section has consisted of coarse aggregate that serves as the structural section and as a recharge bed for the storage and disposal of storm runoff. This layer was frequently overlaid with a choker course consisting of more finely graded rock. The choker course fills in the larger void space at the surface of the coarse aggregate layer and provides a more stable working surface for construction. In recent years, a use of a finely graded choker course over a coarse aggregate recharge bed, has been replaced with the use of a finer overall section. This is the approach taken for this study. Uniform-graded aggregate is used. Although a wide range of aggregate grades have been and are used for base courses, 1½ -1/4 was assumed for this study. This aggregate has similar structural properties to the aggregate used for non-porous pavements. The resulting sections are comparable to their non-porous counterparts. The main difference is that porous sections may be thicker due to the need for storage of runoff. This is discussed further in the following section. page 2

For permeable interlocking concrete pavers and geo-cellular reinforced sections, aggregates such as ODOT ¾ -#4 or 1 -#4 are used. These maintain the void ratios necessary for storage while retaining structural properties needed for resistance to rutting from turning, braking, and acceleration movements. For conventional paved surfaces, standard dense graded aggregates were assumed. Many of the published design guidelines utilize AASHTO specifications for aggregate base rock. To better relate porous pavement designs to local standards, we have attempted to use commonly available gradations. ODOT specifications for base rock were utilized where possible. 3.1.2. Stormwater Storage For the porous pavement alternatives, storage of stormwater is considered in the design. A typical porous pavement section must be capable of storing the precipitation total for the design storm event and allowing that total to infiltrate within 24 hours following that event. The design storm event used in the Portland area is a 10-yr/24-hr event. According the City of Portland s Stormwater Management Manual, the precipitation total for this event is equal to 3.4 inches. Given that the aggregate used in most porous pavement sections has a void ratio of approximately 40%, a minimum thickness required for stormwater storage in porous pavement sections is determined from the following calculation. Min. Aggregate = 3.4 inches = 8.5 inches 0.40 This is the minimum thickness used for storage of storm runoff in this study. Depending on structural requirements for a specific pavement section, and the void ratio of aggregate used for a specific application, this thickness may vary. 3.1.3. Based on the above traffic loads and soil characteristics, the following pavement sections were designed. Although each system has its own unique regimen for maintenance, the sections listed are roughly equivalent and, with proper care and maintenance, provide adequate levels of service over a 20-year lifespan. 4. COST ANALYSIS Paving costs for each of the three scenarios was estimated. Unit costs for construction were estimated based on recent bids for similar work by local contractors. A summary of the costs is given below. Driveway Pervious Concrete 6 9 2½ -1½ $7,570 Porous Asphalt 3 9 2½ -1½ $4,330 Permeable Pavers Paver 9 1 -#4 $11,760 Geocell 9 ¾ -#4 $3,930 Conventional Concrete 4 4 1-0 $5,330 Conventional Asphalt 3 6 1-0 $3,520 page 3

Parking Lot Pervious Concrete 8 9 2½ -1½ $44,930 Porous Asphalt 3 9 2½ -1½ $25,960 Permeable Pavers Paver 1 $57,150 Geocell 9 ¾ -#4 $24,680 Conventional Concrete 5 6 1-0 $32,200 Conventional Asphalt 3 8 1-0 $23,680 NeigHBorhood Road Pervious Concrete 8 9 2½ -1½ $95,360 Porous Asphalt 4 9 2½ -1½ $58,920 Permeable Pavers Paver 1 $110,260 N/A N/A N/A N/A Conventional Concrete 5 6 1-0 $72,320 Conventional Asphalt 4 8 1-0 $57,540 The costs assumed key items related to the construction of each improvement. Maintenance costs were not included. For the non-porous alternatives, costs for drainage facilities were included for the Neighborhood Road and the Parking Lot. For the Neighborhood Road this included four inlets, two manholes, and 300 LF of 12 storm sewer. For the Parking Lot this included a single inlet and 50 LF of 12 storm sewer. No drainage was assumed for the driveway. Overflow drainage facilities were included for the porous pavement alternatives to capture excess stormwater that may not infiltrate. Overflow drainage facilities may not be necessary for sites with highly permeable soils. This would lower overall costs for these alternatives. Overflow drainage facilities for the Neighborhood Road section included two inlets, one manhole, and 35 LF of 12 storm sewer. For the parking lot, a single inlet and 65 LF of storm sewer were assumed. As with the non-porous driveway, no drainage facilities were assumed. No water quality facilities such as ponds or swales were considered. page 4

5. MAINTENANCE OF POROUS SURFACES For some porous pavement surfaces, periodic maintenance is necessary to help ensure the surfaces do not plug with debris and cease to function as designed. Based on monitoring of porous pavement surfaces conducted by the City of Portland, pervious concrete and porous asphalt surfaces are susceptible to plugging. Pressure washing of the surfaces every three years is recommended to help alleviate plugging of the surface and ensure a high infiltration rate is maintained. Pressure washing is not recommended for permeable interlocking concrete pavers and geo-celluar grid reinforced gravel. 6. CONCLUSIONS In general, porous asphalt and pervious concrete are cost competitive, particularly where larger areas are involved. This is primarily due to the fact that no drainage is required. For smaller areas, such as the driveway, where drainage was not included in the cost, non-porous alternatives were less. The most expensive alternative in all scenarios were permeable interlocking concrete pavers. This was due to the fact that placing the pavers is much more labor intensive. However, this could still be a preferred alternative where a highly ornate, ornamental finish is desired. reinforced with a geo-cellular grid tended to be the least expensive. However, this low initial cost comes with the drawback that periodic maintenance of the surface will be needed to maintain the gravel surface. The decision to select porous versus non-porous paving depends on the particular needs of the owner, site specific constraints, and the proposed use of the improved area. Based on this review, porous pavements are cost effective or close to cost neutral alternatives when all development costs are considered. page 5