1 PICP Construction Permeable Interlocking Concrete Pavement Presenter: Frank Gandora, President Creative Hardscape Why PICPs The Big Picture Germany was first to develop PICPs 2005 Clean Water Act Federal Law U.S. National Pollutant Discharge Elimination System (NPDES) Storm Water Runoff is Primary source of pollutants. PICPs provide First stage filtration and Ground Water recharge. EPA is convinced that PICPs work! 2 Key things to know about PICPs PICPs meet or beat EPA and State regulations BMP Best Management Practice LID Low Impact Development PICPs eliminate ugly space consuming retention/detention ponds LEED Leadership in Energy & Environmental Design 3 1
2 PICP Design Basics 4 Three types of PICP Systems Full Exfiltration: Directs water to soil below Partial Exfiltration: Excess water directed to sewer or stream via outfall pipes. No Exfiltration: Required when soil has low permeability, or other site limitations. Basically a detention pond with an outlet. 5 Permeable Pavers Meet ASTM C 936 Meet ADA guidelines LEED Potential Many different shapes, colors, sizes to choose from. All the same advantages of Interlocking Concrete Pavers...and more. 6 2
3 Enjoy year round construction 7 The PICP System 8 Aggregate Gradations The Key to PICP Sub Base ASTM No. 2 Base ASTM No. 57 Bedding/Joints ASTM No
4 Equipment needed for PICP projects Track or Articulating loader Plate Compactor (13,000 lb/60 kn)or a 10 ton Roller for the Base and Sub base materials Larger Projects could use bucket screeds pulled with equipment or mechanical screeds to accelerate the screeding process Larger project use Mechanical Paver Installers 10 Loader and Plate ton Vibratory Roller 12 4
5 Mechanical Installation 13 Or, just install PICPs by hand 14 Installation Tips KEEP YOUR JOBSITE CLEAN So, what does that mean 15 5
6 Excavation as sediment trap Excavation & subbase installation separated by several days or weeks Excavate all but 6 in. (150 mm) Direct runoff, settle out sediment, drain out Construction resumes: excavate sediment & soil Section 3 16 Don t store on soil Good housekeeping Section 3 17 PICP Entrances to the project site. Dense graded base ramp over an open graded PICP base Section
7 Job Planning and material placement Dumping the near end first: avoid truck tires compacting the soil. Back drag teeth on bucket to loosen compacted soils. 19 Minimize Sediment Transport Keeping sediment away from the pavers Section 3 20 Stormwater pollut prevention Plan (SWPPP) Section
8 Edge Restraints for PICPs Commercial Vehicular Cast in place concrete Precast concrete Cut Stone Pedestrian & Residential Driveways All of the above Compacted base at perimeter with spiked edging 22 Residential driveway with DGA sides 23 Dense graded edge beam 24 8
9 Edge base contains bedding Section 6 25 Toweled Concrete Edge Restraint on Sidewalk Driveway Section 6 26 Compacting Aggregates.use water 27 9
10 Check your grades Not your School grades 28 Screed setting bed. Approx. ¾ to 1 inch higher than F.G. 29 Bigger screeds for speed 30 10
11 Snap Lines and begin Paver Installation Dense graded base along edges No. 8 stone Section 6 31 Initial layout same start as regular pavers Section 6 32 Mechanical or Hand Installation? 33 11
12 Depends on the project 34 Alignment Section 6 35 Compaction Section
13 Fill the joint openings A blower is very helpful too. Section 6 37 Final Jointing and Compaction Expect up to 3/4 in. (20 mm) downward movement during compaction Goal set pavers above final elevation 1/4 to 3/8 in. of drain & gutter inlets; or 1/8 to 1/4 in. for pedestrian/ada compliance Fill joints, sweep surface clean, compact Consider: compact before filling joints, replace cracked pavers (can t quickly remove after compaction with full joints) 60, 80 and 100 mm thick pavers: 5,000 lbf (22kN) 120 mm thick: 6,800 lbf (30 kn) Fill up joints with stone as needed, but NOT to top Fill to chamfer bottom Joints full, pavers compacted within 6 ft (2 m) of laying face at the end of each day 38 Joints filled collect a check Section
14 Maintenance 2 yrs residential street OR Remove weeds by hand most effective 7-8 yrs container storage NY New construction MN Section 9 40 When do you maintain? Inspect a couple of times a year. Then base cleaning on sediment loading Vacuum sweep 1 2x annually Don t use water to clean Extent of clogging? Check surface infiltration ASTM C1701 Do not power wash Seriously, power washing will drive sediment deeper into the joints. 41 Sweeper Effectiveness Least effective Regenerative air vacuum sweeper Use 1 2 times/year Most effective True vacuum sweeper Very powerful Restores highly clogged surfaces Sectio n 9 14
15 Winter Maintenance Snow melts faster lower risk of ice Surface does not heave when frozen Use normal plows dirty snow piles clog surface Deicing salts okay Sand can clog system use jointing material for traction Rubber blade NOT needed Section 9 43 Managing dirty snow Section 9 10 yrs street winter sand accumulation Massachusetts 44 A slide with no useful information at all Just filling in the gap between the last slide and the next one (which will be along in just a moment). No need to write this down, unless you feel compelled to do so. Nothing on this slide has to do with PICP construction. In fact I m not really sure why I bothered with it
16 Time for a Good Cigar [email protected] Thank You
Structural/Hydrologic Design & Maintenance of Permeable Interlocking Concrete Pavement
Structural/Hydrologic Design & Maintenance of Permeable Interlocking Concrete Pavement David R. Smith, Technical Director Interlocking Concrete Pavement InsCtute, Herndon, Virginia USA William F. Hunt,
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications describes construction of permeable interlocking concrete
Division 2 Section 32 14 13.19 Section 02795
Note: The text must be edited to suit specific project requirements. It should be reviewed by a qualified civil or geotechnical engineer, or landscape architect familiar with the site conditions. Edit
SECTION 02795 UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT
SECTION 02795 UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT Note: This guide specification is intended for use in the U.S. It describes construction of permeable interlocking concrete pavers on a permeable,
PERMEABLE INTERLOCKING CONCRETE PAVEMENT
[NOTE TO SPECIFICATION WRITER: This guide specification for the use of permeable interlocking concrete pavers for pedestrian and vehicular traffic application was developed based on the use of an open-graded
>S`[SOPZS 7\bS`Z]QYW\U 1]\Q`SbS >OdS[S\b
BSQV\WQOZ 5cWRS >S`[SOPZS 7\bS`Z]QYW\U 1]\Q`SbS >OdS[S\b / 0S 0Sab ab ;O ;O\O \OUS \O US[S\b US \b >` >`OQ OQbW OQ bwqs bw QS b] 1] 1]\b \b`] \b `]ZZ Ab `] Ab]` ]`[e [eob [e ObS` Ob S` @c @c\] \]TT \]
Permeable Interlocking Concrete Pavement
Permeable Interlocking Concrete Pavement A Comparison Guide to Porous Asphalt and Pervious Concrete Permeable pavement is becoming a major tool for on-site stormwater management. Background The past century
Permeable Interlocking Concrete Pavements
Permeable Interlocking Concrete Pavements Program 000003 Revised 1-29-08 Permeable Interlocking Concrete Pavements This program is registered with the AIA/CES and ASLA CPE for continuing education professional
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications describes construction of permeable interlocking concrete
SUDAS Revision Submittal Form
SUDAS Revision Submittal Form Status Date: As of 3/13/15 Topic: Permeable interlocking pavers Manual: Design & Specs Manual Location: Design Section 5L-1; Spec Section 7080 Requested Revision: Reason for
SECTION 32 14 00 PERVIOUS INTERLOCKING CERAMIC PAVERS
SECTION 32 14 00 PERVIOUS INTERLOCKING CERAMIC PAVERS Pervious interlocking pavers.doc Note: This guide specification for U.S. applications describes construction of permeable interlocking ceramic pavers
Pervious Pavers. By: Rich Lahren. Hebron Brick & Block Supply
Pervious Pavers By: Rich Lahren Hebron Brick & Block Supply Stormwater Management and Control Issues Past emphasis was on flood control Today s emphasis is also on pollution More impermeable areas are
Guidelines for. Permeable Pavement
What is permeable pavement? Guidelines for Permeable Pavement When rainwater falls on conventional pavement, such as concrete, it accumulates and then flows across and off of this impervious surface as
Sustainable Site Pavement Systems
Sustainable Site Pavement Systems Permeable Interlocking Concrete Pavement Training for Design Professionals ICPI Presentation #003 Presented by: Brent Davis - Design Consultant Belgard Engineered Solutions
Permeable Interlocking Concrete Pavements
Permeable Interlocking Concrete Pavements Rick Crooks, Director of Business Development Mutual Materials Co. Bellevue, WA 1-800-477-3008 [email protected] Stormwater Management Approaches: Restrict
Industry Guidelines for Permeable Interlocking Concrete Pavement in the United States and Canada. David R. Smith, Technical Director
Industry Guidelines for Permeable Interlocking Concrete Pavement in the United States and Canada David R. Smith, Technical Director PICP Drivers It costs less NPDES MS4 permit compliance EPA permit for
40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT
40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT 40-9.01 GENERAL 40-9.01A Summary Section 40-9 includes specifications for furnishing and installing concrete pavers for permeable interlocking concrete pavement
Permeable Interlocking Concrete Pavements
Permeable Interlocking Concrete Pavements Rick Crooks, Director of Business Development Mutual Materials Co. Bellevue, WA 1-800-477-3008 [email protected] Stormwater Management Approaches: Restrict
Permeable Interlocking Concrete Pavement (PICP) A Low Impact Development Tool Training for Schools and Universities
Permeable Interlocking Concrete Pavement (PICP) A Low Impact Development Tool Training for Schools and Universities Presented by: Interlocking Concrete Pavement Institute The Low Impact Development Center,
SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT
PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT A. The requirements for construction of permeable interlocking concrete pavement: 1. Install the interlocking
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?
SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)
SPECIFICATIONS INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) Part 1 General 1.1 CONFORMITY Conforms to the requirements of the general conditions of the contract.
Permeable Paving System with StormAbsorb Technology
Permeable Paving System with StormAbsorb Technology The water management solution. ideal for LEED projects 2 a better way to solve water management issues Increasingly, water management is an important
GUIDE SPECIFICATIONS FOR CONSTRUCTION OF AQUAPAVE PERMEABLE STORMWATER MANAGEMENT SYSTEM
GUIDE SPECIFICATIONS FOR CONSTRUCTION OF AQUAPAVE PERMEABLE STORMWATER MANAGEMENT SYSTEM SECTION 32 14 13.19 AquaPave Permeable Interlocking Concrete Pavement Note: This guide specification is for the
CASFM Stormwater Quality Field Trip June 23rd, 2011
CASFM Stormwater Quality Field Trip June 23rd, 2011 The 2011 CASFM Stormwater field trip included 42 attendees coming from as far south as Colorado Springs up to the Denver area and another 12 who joined
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
Permeable Pavement Operation & Maintanence Guide
Permeable Pavement Operation & Maintanence Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems
Permeable Interlocking Concrete Pavement A Low Impact Development Tool. Training for Design Professionals
Permeable Interlocking Concrete Pavement A Low Impact Development Tool Training for Design Professionals Presented by: Interlocking Concrete Pavement Institute (ICPI) The Low Impact Development Center,
Permeable Pavers. calstone.com. Permeable Interlocking Concrete Pavements (PICP s)
Permeable Pavers Permeable Interlocking Concrete Pavements (PICP s) CBC Title 24/ADA Compliant LEED Functional Optimum balance of surface infiltration and joint interlock Available in a 6 x 9 Quarry Stone
Pervious Concrete Pavement Maintenance and Operations Guide
Pervious Concrete Pavement Maintenance and Operations Guide NRMCA Pervious Concrete Pavement Maintenance and Operations Guide Pervious concrete pavement is a Portland cement-based, rigid permeable pavement
Permeable Interlocking Concrete Pavements. The Stormwater Problem
Permeable Interlocking Concrete Pavements The Stormwater Problem 1 Stormwater Management Objectives Water Quantity Accommodate water volumes & peak flows Water Quality Control pollutant levels A Low Impact
SECTION 02780 UNIT PAVERS. Logo Display hidden notes to specifier by using Tools / Options / View / Hidden Text.
SECTION 02780 UNIT PAVERS Logo Display hidden notes to specifier by using Tools / Options / View / Hidden Text. PART 1 GENERAL 1.1 SECTION INCLUDES A. Interlocking unit pavers and accessories with sand-filled
Building Your Interlocking Concrete Pavement to Last a Lifetime
Building Your Interlocking Concrete Pavement to Last a Lifetime A Guide for Consumers Contents Building Your Interlocking Concrete Pavement to Last a Lifetime.... 3 What Does Installation Involve?....
Permeable Pavement Construction Guide
Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce
LID-01 Permeable Paving Systems
Greenville County Technical Specification for LID-01 Permeable Paving Systems 1.0 Permeable Paving Systems 1.1 Description Permeable Paving Systems are a best management practice that captures stormwater
Dave Laurie, CTR. Sales Manager, Commercial Sales DESIGNED TO CONNECT
Dave Laurie, CTR Sales Manager, Commercial Sales DESIGNED TO CONNECT Permeable Pavements For Sustainable Development Agenda Unit paver technology Permeable Interlocking Concrete Paver - research, technical
Industry Guidelines for Permeable Interlocking Concrete Pavement in the United States and Canada
Summary 10 th International Conference on Concrete Block Paving Industry Guidelines for Permeable Interlocking Concrete Pavement in the United States and Canada David R. Smith, Technical Director Interlocking
Low Impact Development Permeable Paving
Low Impact Development Permeable Paving An education initiative funded by the Department of Ecology June 11, 2013 How to Participate in a Webinar chat send to host Polling box will appear at first poll
ICPI TECH SPEC NUMBER 10 Application Guide for Interlocking Concrete Pavements
ICPI TECH SPEC NUMBER 10 Application Guide for Interlocking Concrete Pavements This technical bulletin provides an overview of interlocking concrete pavements for a range of applicatons. The Interlocking
DEVELOPMENT OF AN ASCE STANDARD FOR PERMEABLE INTERLOCKING CONCRETE PAVEMENT
DEVELOPMENT OF AN ASCE STANDARD FOR PERMEABLE INTERLOCKING CONCRETE PAVEMENT David K. Hein, P. Eng. Vice-President, Applied Research Associates Inc., 5401 Eglinton Avenue West, Suite 204, Toronto, ON,
Installing Porous Pavement Waukesha County Dept. of Parks & Land Use Storm Water BMP Design and Installation Workshop March 11, 2009
Installing Porous Pavement Waukesha County Dept. of Parks & Land Use Storm Water BMP Design and Installation Workshop March 11, 2009 Presented by Willie Gonwa, P.E., Ph.D. West Allis, Wisconsin Porous
Design, Construction and Maintenance of Permeable Pavements Case Studies and Technical Resources Robert Bowers, P. Eng.
Design, Construction and Maintenance of Permeable Pavements Case Studies and Technical Resources Robert Bowers, P. Eng. Source: CH2M Hill The Presenter Robert Bowers, P.Eng., LEED GA [email protected] Director
NEUPAVE. Permeable Pavers. A Permeable Eco-Friendly Beauty
NEUPAVE Permeable Pavers A Permeable Eco-Friendly Beauty As the first in Malaysia to manufacture this new paving technology, is a paving alternative to more traditional types of hardscape flooring materials,
Concrete pavers with sand filled joints. Bedding sand 1-1/2 in. (25-40 mm) thick
TECH SPEC N U M B E R 10 Visit www.icpi.org for guide specifications and detail drawings for a range of applications. Edge restraint/curb as required by design Application Guide for Interlocking Concrete
Porous Pavement Alternatives Cost Analysis
Porous Pavement Alternatives Cost Analysis Prepared by Century West Engineering for Metro This cost analysis compares the construction costs of six different types of pavement for three different scenarios.
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
AUSTRALIAN PAVING CENTRE
AUSTRALIAN PAVING CENTRE The Concept 02 The concept of Ecopave permeable paving is already well established in many countries where development threatens already over-stretched drainage and river systems.
Storm Drain Inlet Protection for Construction Sites (1060)
Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain
Storm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
Block and Gravel Inlet Protection (BIP)
Block and Gravel Inlet Protection (BIP) Practice Description Block and gravel inlet protection is a sediment control barrier formed around a storm drain inlet by the use of standard concrete block and
Caltrans non-standard Special Provisions Pervious Concrete. David Akers Feb 28, 2012
Caltrans non-standard Special Provisions Pervious Concrete David Akers Feb 28, 2012 Section Paragraph Content 19 RSS 19-5.03B Changes title of the section 19-5.03B USAGE NOTES FOR PERVIOUS CONCRETE AND
Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.
4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall
AquaPaver & SF-Rima Permeable Interlocking Concrete Pavers
F.P.O. Need SF-Rima THE TREMRON GROUP Permeable Paver Guide AquaPaver & SF-Rima Permeable Interlocking Concrete Pavers MIAMI 11321 NW 112th Court Medley, FL 33178 800.567.1480 or 305.825.9000 Fax 305.823.6614
Storm Drain Inlet Protection for Construction Sites (1060)
Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain
4.1. Permeable Pavement Systems
4.1. Permeable Pavement Systems Permeable Pavement provides the structural support of conventional pavement, but allows stormwater to drain directly through the surface into the underlying stone base and
Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations
SWPPP for Park Operations 2 Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations Bordered by Lake Washington & Lake Sammamish, the City of Bellevue has more than 60 miles of streams,
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Seattle Public Utilities Green Stormwater Infrastructure: O&M Program
Seattle Public Utilities Green Stormwater Infrastructure: O&M Program O&M Maintenance Package O&M Maintenance Package 1. Landscape Maintenance Manual 2. NDS/LID Maintenance Manual for ROW 3. Identifiable
Installation PowerPoint for Grasscrete Formers
Installation PowerPoint for Grasscrete Formers 1 This document describes the two single-use tools utilized to create the Grasscrete product. The original Former is a vacuum formed light gauge plastic mold
Storm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
ALKS SIDEW II. TK TK TK TK TK TK TK TK 40 BOSTON COMPLETE STREETS GUIDELINES DRAFT - JULY 2011 BOSTON TRANSPORTATION DEPARTMENT
40 Sidewalk Materials Materials and Sidewalk Zones Permeable Pavement Accessibility The key components of sidewalk construction are material selection and installation. These two aspects should come together
APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS
APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS The following section provides descriptions, advantages, limitations, and schematics of allowable best management practices (BMPs) for
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
CHAPTER 5. Storm Sewer
CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water
Pervious Pavement SYSTEMS THINKING. THE NEW DESIGN PROBLEM and the Role of the Civil Engineer. LOW IMPACT DEVELOPMENT Introduction
Pervious Pavement Options and Design Guidelines (with LID example projects) SYSTEMS THINKING Need to think differently about the problem Whole System Design Site & Project Relationships Integrated Design
Jon E. Zufelt, PhD, PE ERDC-CRREL Anchorage, Alaska
Jon E. Zufelt, PhD, PE ERDC-CRREL Anchorage, Alaska Outline Why am I here? What exactly am I going to talk about? Energy Independence and Security Act Permeable Pavements in Cold Regions White Paper for
Vehicle Tracking Pad
Stormwater Quality Best Management Practices Construction Sites s When to use: Where construction vehicles leave active construction areas onto surfaces where runoff is not checked by sediment controls
Aqua-Bric PERMEABLE PAVERS
Aqua-Bric PERMEABLE PAVERS Essential Pavers for Plazas, Walkways, Entrances and Parking Lots Belden Brick Aqua-Bric Permeable Pavers PERMEABLE PAVING IS A DESIGNED APPLICATION TO MANAGE STORM WATER RUN-OFF
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting
Best Management Practice Fact Sheet 7: Permeable Pavement
Publication 426-126 Best Management Practice Fact Sheet 7: Permeable Pavement David J. Sample, Assistant Professor and Extension Specialist, Biological Systems Engineering, Virginia Tech Lia Doumar, Undergraduate
Advancements in Permeable Pavements
Advancements in Permeable Pavements Engineers Workshop Saint Vincent College March 14 & 15 2013 Permeable Pavements There are several different words that are used to describe a pavement that water drains
Guidelines for Control of Water Runoff on Small Lots. Revised 6/09
Guidelines for Control of Water Runoff on Small Lots Revised 6/09 Table of Contents Introduction and Purpose 3 Administrative Procedures 3 Plan Submittal Requirements 3 General Design Criteria 4 Dry Wells
Standard Operating Procedures Storm Drain System Maintenance
s Storm Drain System Maintenance SECTIONS 1. Storm Drain System Inspections 2. Storm Drain System Cleaning 3. Storm Drain System Repairs 4. Proper Disposal of Material Storm Sewer System Cleaning Directive
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts Submitted to: Town of Sudbury December 2011 Table of Contents 1.0 Introduction... 1 1.1 Responsibility...
Interlocking Concrete Paving Stones
Interlocking Concrete Paving Stones Manufacturers of Quality Masonry Products Table of Contents Balboa 1 Roman 2 Euro-Cobble 3 Tri-Cobble 4 Circle Cobble 5 Old World Cobble 6 FlagStone 7 Chumash 8 Holland
ICPI TECH SPEC NUMBER 8
ICPI TECH SPEC NUMBER 8 CONCRETE GRID PAVEMENTS 1999 ICPI Tech Spec No. 8 Interlocking Concrete Pavement Institute - All rights reserved Revised April 2006 Perforated concrete paving units as pavement
SUSTAINABILITY INITIATIVE: 01-02 PERMEABLE PAVEMENT: ADAPTING TO STORMWATER MANAGEMENT CHALLENGES
PERMEABLE PAVEMENT: ADAPTING TO STORMWATER MANAGEMENT CHALLENGES SUSTAINABILITY INITIATIVE: 01-02 : ADAPTING TO STORMWATER MANAGEMENT CHALLENGES Impermeable surfaces, such as streets, parking lots, and
Green Alley. Handbook. The Chicago. Richard M. Daley, Mayor City of Chicago. An Action Guide to Create a Greener, Environmentally Sustainable Chicago
The Chicago Green Alley Handbook An Action Guide to Create a Greener, Environmentally Sustainable Chicago Printed on recycled paper, 30% post-consumer waste Richard M. Daley, Mayor City of Chicago Cheri
Note: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change.
CHANNEL DrAiNS Durable Designed for maximum durability and drainage, NDS Channel Drains are a proven alternative to traditional concrete drains. UV inhibitors in the grates, channel and component parts
CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT
Volkert Field Office 80 M Street SE, Suite 725 Washington, DC 20003 RIVERSMART WASHINGTON - CONSTRUCTION RIVERSMART MACFARLAND, RIVERSMART LAFAYETTE AND GREEN ALLEYS CHEVY CHASE D.C. Contract No.: DCKA-2013-C-0160
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
Operation & Maintenance Document Templates
Appendix G Operation & Maintenance Document Templates The following templates are provided to assist project applicants in preparing stormwater treatment measure maintenance plans, which municipalities
Storm Drain Inlet Protection - IP
Storm Drain Inlet Protection - IP DEFINITION A temporary protective device formed around a storm drain drop inlet to trap sediment. PURPOSE To prevent sediment from entering storm drainage systems, prior
PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS
BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS Check here for Address or phone number change the fiscal year (July 1 June 30), and date(s) maintenance was performed. Under Inspection,