PS.12. 4D Scheduling A Case Study



Similar documents
BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

MULTI-RESIDENTIAL BUILDING SOLUTIONS

New Zealand BIM Handbook Appendix D - BIM Uses definitions July A guide to enabling BIM on building projects

Innovative capture and modeling of existing building conditions using 3D laser scanning. Entry B Submission

Scheduling Best Practices

BIM: FOR PROJECT MANAGERS CSI Southwest Region Conference Program 1B 8:45am 11:00am

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

How to Plan, Design & Implement A Bad Schedule Lessons Learned: The Scheduler as Generalist

Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.

Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group

Automated construction schedule creation using project information model

d e n v e r a r t m u s e u m

Design Build Institute of America (DBIA)

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering

VDC/BIM Services BEXEL Consulting/PSP-Farman

SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

CRITICAL PATH METHOD (CPM) SCHEDULES

Advancements in Construction Project Administration Session: 41 October 28, 2014

BIM and Project Planning

Building Information Modeling (BIM): A New Paradigm for Visual Interactive Modeling and Simulation for Construction Projects

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

INTRODUCTION. Prakash Chandar. S¹, Dhivya Shree. G² ABSTRACT

Scheduling Best Practices

Exhibit C: Scope of Work and Schedule of Deliverables

Spec. Standard: 11/27/ Revision: 11/27/06

Interoperable Learning Leveraging Building Information Modeling (BIM) in Construction Management and Structural Engineering Education

IPD, Lean and BIM: Hype or the Real Deal?

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

Primavera P6 Exercise Worksheet

BIM ACROSS THE DESIGN-BUILD-OPERATE LIFECYCLE

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191

Mortenson Construction Virtual Mockups A Collaborative Solution

Olilo's AEC Design Services. SrinSoft Inc, Partners of

Marketing Coordinator Bootcamp Session 2: ABCs of AEC

Subcontractor Involvement Project Tracking Progress Curves. CSTM 462 Fall 2012

MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT Timo Hartmann

Strategies for creating accurate updates of CPM construction schedules.

Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY

Resource Planning and Scheduling. CSTM 462 Resource Loading Fall 2012

General Comparison between 4D Software

Collaborative Scheduling using the CPM Method

3D Laser Scanning for Manufacturing Facilities Developing the Business Case. By Bill Campbell Founder, Digital Dimensions 360, LLC

Mitra Innovation Leverages WSO2's Open Source Middleware to Build BIM Exchange Platform

Understanding Media Asset Management A Plain English Guide for Printing Communications Professionals

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

The CM Perspective. Preconstruction Phase

Scheduling Glossary Activity. A component of work performed during the course of a project.

The use of BIM in plumbing projects creates deeper project knowledge, delivers a more robust product, and can reduce total project costs.

BIM and Lean Construction Can BIM remove waste from construction processes?

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.

Adopting a Continuous Integration / Continuous Delivery Model to Improve Software Delivery

DCMA 14-Point Assessment Metrics

Document management concerns the whole board. Implementing document management - recommended practices and lessons learned

BIM SOFTWARE EVALUATION MODEL FOR GENERAL CONTRACTORS

Industrial Case Study of Electronic Design, Cost and Schedule Integration

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE

INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2

EXHIBIT 2-2-C PROGRESS SCHEDULES

Buildings Construction Procurement Strategy

WORK PROGRAM GUIDELINES

Overview. Gaudi Design Tools. The Design Process. The Design Process. Overview. Target Audience

SECTION PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

Tobin Center for the Performing Arts

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

Chapter 2: Project Time Management

BIM and DWF REVIT BUILDING INFORMATION MODELING. About DWF. BIM and DWF

Software Development & Education Center. Microsoft Office (Microsoft Project 2010)

Design without compromise. Autodesk Revit. Architecture

Building Information Modelling and collaborative construction

Oracle Primavera Program Management Information System (PMIS) Solutions for Transportation Programs November, 2011

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into

School Construction Projects

CHAPTER - 5 CONCLUSIONS / IMP. FINDINGS

Execution Plan Template Design Modeling

Scheduling 101 CPM Basics. Phoenix Project Management Systems, LLC

7 ALLOW YOUR PARTNERSHIP TO EVOLVE

2012 BIM Guidelines and Standards (Rev. 00) University at Albany

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY

Enhancing Building Quality With 6D BIM

Automated Micro-Planning and Real-time Tracking of Precast Building Components

BIM Test At ASHRAE HQ

Project Time Management

PROJECT MANAGEMENT INNOVATION BASED ON BUILDING INFORMATION MODELING

Schedule Acceleration Techniques Using a CM

Transcription:

PS.12 4D Scheduling A Case Study Mr. Abhimanyu Basu PE PSP A 4D schedule is a 3 dimensional CAD model How long would it take. attached to the fourth dimension of time via a schedule. The concept of 4D scheduling has been around The initial objective of visualizing the phasing and sequencing of construction and communicating the scope to the lay for over 20 years. In the early years, producing 4D schedules was technologically challenging. These challenges stakeholders was achieved by constructing a 3D CAD model of lay in developing 3D models from 2D CAD drawings and in the entire program and linking the model to a schedule. As the relating these CAD elements to real schedules. Advances in 3D CAD model created was dimensionally accurate, the project technology are now pushing to make 3D CAD elements the norm. Off the shelf software are also making it easy to link team began to discover many other uses for the model such as logistics planning, site line studies, walk-thrus etc. schedule outputs from standard scheduling packages like Primavera or Microsoft Project to the CAD elements to produce effective 4D schedules. This article describes the issues CONTEXT OF 4D SCHEDULING faced and lessons learned from a 4D scheduling initiative. It is important to understand the context of 4D scheduling and some of the concepts and acronyms which are shaping this CASE REVIEW emerging field. The first is BIM which is short for building information model or modeling. BIM is a digital representation This case study is a 4D scheduling effort for a large construction program. The primary goal of this exercise was to help a group of non-technical stakeholders visualize the scope of design and construction and the phasing of the total building program being funded. Some of the dimensions of the program aimed to be conveyed through this effort were as follows: of the building process to facilitate exchange and interoperability of information in digital format. VDC or virtual design and construction is a term coined by CIFE at Stanford University. 3D CAD is three dimensional representations of objects. These 3D objects may simply be renderings or they may be models i.e., made up of components and have properties. The 4D in major elements of construction to be performed; 4D scheduling is the added dimension of time linked to the 3D Model. 5D is linking both schedule and estimates to a 3D phasing of program and sequencing of work; and, model. Figure 1 Assembling a 4D Schedule PS.12.1

ASSEMBLING A 4D SCHEDULE We used a 4D scheduling package to link a Primavera schedule to 3D CAD model to create the 4D schedule. Currently design information is generally available in 2D CAD. In some cases 3D CAD may be available. However a 3D CAD drawing or rendering is not sufficient for preparing a 4D schedule. A 3D model is required for preparing a 4D schedule. A 3D CAD will be a collection of points, lines and faces which convey no meaning. The 3D model on the other hand is made up of elements that have meaning in construction such as columns, beams, floors and walls etc. In current practice, where 2D drawings are the norm, the effort to prepare the 3D model is not trivial and takes substantial effort. In the case discussed in this article, we prepared the 3D models of buildings and site works from 3D renderings and 2D CAD information. The process of preparing a 4D schedule is shown in figure 1. Figure 2 illustrates how a 4D software assembles a 4D schedule. DRIVERS AND ENABLERS FOR 4D SCHEDULE In general, owners are driving the adoption of BIM. The General Services Administration (GSA) has mandated BIM and related initiatives such as 4D scheduling for all its projects starting in 2007. The Construction Users Roundtable (CURT) a group of owners of large facilities is also pushing its members to take an aggressive role in implementing BIM and associated technologies. General Motors is one such large owner who has taken the decision to use BIM for all its new projects. GM and other first users have reported big successes from their projects both in terms of savings in cost as well as in schedule. There are two important enablers which make it easier to use 4D scheduling. The first is the generally increasing acceptance and usage of 3D CAD and modeling. The major software vendors are focused on delivering 3D functionality. The second big factor in enabling 4D schedules is the availability of off-the-shelf software which can combine a schedule from a scheduling package and a 3D CAD model prepared with a standard CAD package and links them together. These 4D packages are platform neutral which means that they will accept scheduling and CAD information from most of the leading packages in their classes. WHERE 4D SCHEDULING IS BEING USED Reports of the use of 4D scheduling indicate certain areas of focus for the current use of 4D. Some examples of the areas of application and what they sought to achieve are given below: Visualization In the case study covered in this article, the initial and primary motivation for developing the 4D schedule was to enable non-technical senior stakeholders, who would approve the project, understand what the scope of the project was, when they could expect finished buildings to open and how their current operations would be impacted by the construction. Communications A corollary of the visualization effort is communication. The model was also used to communicate the intent of the program to a larger audience as a community relations initiative. Preconstruction planning A complex renovation of large occupied building which had to be done in phases and by moving around the occupants was first planned out using a 4D model. It was claimed that this Figure 2 Using a 4D Scheduling Package PS.12.2

project could not be done without the initial detailed planning and buy-in using the 4D model. The need to visualize and communicate drove one of the earliest initiatives in 4D scheduling for the Walt Disney Concert Hall in LA1. The job was so complex that it overwhelmed the sub-contractors. The contractor was driven to specially build a complete 4D model for the most complex part of the job. According to the report the contractor used the model to comprehend, confirm, communicate, coordinate and troubleshoot. The tool helped find logic busts in the schedule while there was still time to adjust. It verified constructability and checked work flow, access and hoisting. And it helped educate the team. But primarily, it was shown at monthly coordination meetings to preview the next 90 days of work. Claims and Dispute Resolution Supporting claims with visual demonstration of impact on schedule and cost is reportedly another area where 3D modeling and 4D Scheduling is finding use. BENEFITS OF 4D SCHEDULING It appears that the benefits of 4D Scheduling that are driving the use of 4D scheduling and 3D modeling are in both tangible and intangible categories. While the savings in cost and schedule, risk reduction, improved quality, reduction of RFIs and claims are tangible, an important intangible gain seems to be in using the models to communicate project parameters to non technical stakeholders and get their buy-in. Collaboration, Planning, Scheduling and Constructability The biggest payoff in cost and schedule reduction has been in the areas of collaboration, clash detection and coordination, planning and scheduling including logistics planning. There are a number of reports of successful use. The Denver Art Museum project, the first public project to use these high tech tools, is a success story and has been a proving ground for BIM and 4D scheduling [2]. According to the report use of the 3D digital model, prevented 1200 collision of steel elements and sped steel erection to the finish line three months early. The contractor then gave nearly $400,000 back to the owner. General Motors has committed all new projects to 3D modeling [3]. According to GM The approach has proven itself by helping the company build faster, better and safer with less cost and risk. HOW 4D SCHEDULING DIFFERS FROM CONVENTIONAL SCHEDULING 4D scheduling quickly challenges and changes many of the practices of conventional scheduling. 4D scheduling is not simply taking a conventional schedule and attaching CAD elements to activities. It forces the scheduler to think differently and adjust the way schedules are developed. Some of the considerations are as follows. Ring side seat A 4D schedule provides the scheduler with a ring side seat to the construction site. The scheduler is quickly able to move around, look outside, inside and under the building or site and verify the sequences he is planning. The constant visual feedback forces the scheduler to plan at greater depth and Figure 3 Start Excavation Must Choose a Side PS.12.3

refine logic to avoid visual incongruities in the representation. Management of Detail There may be issues of too little or too much detail depending on the stage of project definition and the granularity of the 4D representation desired. During early phases, with only sketchy intent or schematic drawings available, these may not be sufficient for generating 4D schedules. The necessary component details would need to be developed separately. At the other end, a finished construction model will likely show every element of construction. This may be too much for the scheduler who works at a certain higher level of abstraction. Even a fully developed 3D model from the A/E will require additional work for the scheduler. For example, the model from the A/E will likely show a continuous floor slab in its model. The scheduler on the other hand may require the 3D model to be further detailed in order to show the sequence of concrete pours and may need to use his or her own 3D modeling resources to develop these details. Management of hard and soft logic The visual connection to the schedule discourages generalizations. Long duration activities with overlapping relationships (SS, FF) sometimes create impressions of out of sequence logic busts. Finish to Start (FS) relationships are likely to gain in respectability while using of negative lags will get a reality check. The scheduler now has to make some choices earlier based on more refined decisions. It is no longer enough to have the activity Start excavation a particular area has to be chosen to start and another to end to make sense visually. Figure 3 illustrates such a point. Similarly, soft logic connections will also require greater planning and be less arbitrary to withstand challenges using visual common sense. Logic busts are easily detectable as shown in figure 4 below. Impact of Logistics A ringside seat for the scheduler will force him or her to factor in impact of logistics on the schedule right from the beginning. The availability of access, lay-down areas, and equipment sequences cannot be ignored. Managing what is not on A/E drawings This is a completely new challenge to the scheduler at many levels. First the scheduler has to find information which is generally not found in Construction Document (CD) packages. The CDs are prepared by the A/E while site information such as logistics etc is prepared by the CM or GC. Secondly the scheduler must get this information in a compatible 3D CAD package. WHAT 4D SCHEDULING DOES NOT DO While 4D scheduling adds an exciting new dimension to scheduling, it also does not currently support many important facets of current scheduling practice. The important current scheduling practices not supported are discussed below: Procurement and Offsite Activities: Because of its nature, 4D models do not support offsite activities such as the submittal approval and the procurement cycles, offsite work such as fabrication or activities like coordination etc. These important and often critical activities must be carried in the conventional schedule but cannot be displayed visually. Figure 4 Visual Indication of Logic Busts PS.12.4

Critical Path, Late Dates and Float Currently there are no built in features in the 4D package which facilitates showing the critical path and other data like total float and late dates. While showing critical path in a different color will make visual sense, it is not clear what value there may be in showing total float or late dates visually. Cost, Resources and Earned Value Currently 4D modeling does not support any advanced features of scheduling such as cost and resource loading, cashflow analysis and earned value analysis. It is not clear whether these features need to be supported in the 4D model or remain a part of the existing scheduling practice. LEARNING CURVE BARRIERS TO 4D SCHEDULING While 4D scheduling certainly seems to be proving its worth and is being funded more frequently both by owners and by construction managers (Ultimately by the owner), the steep learning curve to using 4D technology remains a significant barrier to its use at this point of time (early 2007). Some of the learning curve barriers are as follows. Learning CAD and 3D Modeling The scheduler will generally be quite an expert in reading and interpreting construction drawings. However these are generally in paper copies of 2D representation. Now the scheduler will need to learn how to navigate through a 3D CAD environment. This is one more thing to learn. It is not a trivial task and must be in addition to many facets of knowledge and training the schedulers need in the field of scheduling. Learning a 4D Package The 4D software packages offer substantial functionality in taking 3D CAD Model information and CPM scheduling information and linking them to produce a 4D schedule. Like any advanced software it takes training and many hours of hands-on use to get to an acceptable level of productivity. Need CAD Partner Currently the drawings and models available are generally not suitable for use in 4D schedules. The A/E practice is not generally aligned with the needs of BIM and 3D modeling. Current A/E practice produces 2D drawings or at best 3D CAD drawings which are renderings. The drawings are a collection of lines and points and do not make up elements like columns, beams and walls which can be used for a 4D schedule. A 4D scheduler needs a CAD partner who will bridge the gap between the drawings that are being produced and the 3D CAD model suitable for use in the 4D schedule. This may be a little or lot of work depending on the quality of the drawings. More Thorough Understanding of Scheduling 4D has added another level of difficulty to scheduling. The scheduler must consider more factors and have more interaction with the field to create the schedule. It not only places more responsibility on the scheduler but also calls for more active participation in the project execution. GSA 4D INITIATIVE The General Services Administration (GSA) is actively encouraging BIM and 4D Phasing [4]. The GSA website has published their intent as follows: 4D Phasing - The Office of the Chief Architect (OCA) is currently encouraging, documenting, and evaluating 3D, 4D, and building information modeling (BIM) technologies on a project-by-project need basis. GSA is supporting the understanding project phasing through the use of 4D models. 4D models, which combine a 3D model with time, allow A/Es, contractors, and GSA associates to communicate the proposed project phasing to all stakeholders. With 4D modeling, these stakeholders are able to better understand how the project affects them (e.g., - where the construction zones will be, where and when tenants will have to move to swing space, etc.). GSA is also able to use 4D models to understand projected construction schedules for funding purposes. SHAPING THE FUTURE The GSA has a modest goal for using 4D modeling. 4D scheduling has already proved its worth in complex construction scenarios in improving collaboration and communication and returning tangible benefits in cost savings and schedule reduction. The GSA initiative is a formal recognition of the role schedulers have to play in the paradigm shift toward a BIM world. This is an opportunity for schedulers and AACE International to pursue 4D projects and provide feedback to the standards setting bodies. Some of the issues which we need to tackle in shaping evolving technology and emerging standards of practice are as follows: Preserve CPM Scheduling Values While benefiting from the added level of detail that 3D models bring, we have to work hard to ensure that schedulers do not lose sight of the real values conventional scheduling provides in critical path and float analysis, earned value analysis, cost and resource loading studies etc. Understand Process Changes BIM and 4D scheduling are not only improving schedule by improving coordination and eliminating delays because of errors; they are also changing processes and work sequences and durations. Schedulers must stay abreast of these developments and use them in developing project plans and schedules in the future. PS.12.5

Align BIM model to scheduler needs: Currently there is a big gap between where 2D/3D CADS are and 3D models need to be. As standards of architectural practice evolve to meet BIM needs, schedulers must participate to ensure that the model elements that they need to develop 4D schedules are part of the 3D CAD model deliverables and are incorporated in the emerging BIM standards. Align Naming Conventions of Models Similar to the disconnect between how estimators and schedulers measure and aggregate quantities, a disconnect exists between how architects and schedulers view a job. How layers and components get named and used by the architect can make life easy or difficult for the downstream 4D scheduler. REFERENCES 1. Movie of Job that Defies Description is Worth More Than A Million Words. ENR 4/8/2002 2. Sharing High-Tech Tools Creates Rocky Mountain High. ENR 5/15/2006 3. Automotive Giant Commits New Projects to 3D Modeling. ENR 7/10/2006 4. 4D Scheduling, GSA.gov: Home > Buildings > Public Buildings > Design and Construction > 3D-4D Building Information Modeling > 4D Phasing Align 4D software The 4D software are evolving with usage. The more schedulers use the software and provide feedback and enhancement requests the better the software will become. Influence technology development BIM provides the framework for software vendors to develop analysis software that help planners, architects and engineers do their jobs. Examples are programs that can calculate usable space, do energy analysis or simulate the patterns and time it takes for crowds to exit a building etc. Schedulers should actively encourage vendors that develop tools and utilities which will help them. These tools and aids could be simple such as 3D models of equipment and structures or complex such analysis of truck movement during excavation. For example, software that matches site photos to the model and calculates progress would greatly ease schedule updating and earned value measurement. Abhimanyu Basu, PE PSP Basu Technology, Inc. 26 Manor House Drive Cherry Hill, NJ 08003, US Phone: +1.856.245.9082 Email: abhibasu@basutech.com 4D scheduling is moving from being a buzzword to reality. Its value in saving cost and time has been confirmed with field data. This presents an additional opportunity to schedulers for enhancing their value to the project team. 4D scheduling and BIM also offers new challenges for proactively shaping the tools and improving usability and productivity and establish standards of practice. Schedulers and AACE International must actively promote its use and seek out opportunities to influence the technology, the tools and the practice standards. ACKNOWLEDGMENTS I gratefully acknowledge the help and knowledge that Dr. Arie Schinnar, a scholar, a teacher and a private practitioner of CAD and architecture has provided in this initiative. Dr. Schinnar is the CAD partner without whose participation, insights and help this project could not have been completed. PS.12.6