MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT Timo Hartmann

Size: px
Start display at page:

Download "MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT 2009. Timo Hartmann t.hartmann@ctw.utwente.nl"

Transcription

1 Technical Paper #5 MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT 2009 Timo Hartmann COPYRIGHT 2009 VISICO Center, University of Twente

2 Integrated Project Management Software Report (2009) Timo Hartmann From January to April 2009 I taught the class Integrated Project Management for Master students at the University of Twente. During the class, students generated a scope-cost-time integrated project plan using Building Information model based project management applications. This report summarizes the student s experiences with the used software as the students reported them weekly. The report evaluates the different software packages according to their ability to support project planning tasks, their ability to exchange information between different project management tasks (interoperability), and their ability to support team work during project planning efforts according to these reports. It is important for readers to understand that this report, therefore, does not evaluate the real functionality of the different software applications, but the functionality as it was perceived by the students of the class. Overall, the class project showed that it is possible to create integrated project plans for simple construction projects with commercially available software. However, the project also showed that there are large differences between how well the various software modules support project planning and that most of the packages the students used in the class do not support team work during the creation of project plans well. 1

3 Contents Integrated Project Management Software Report (2009)...1 Contents...2 Introduction...3 Software Packages...6 Evaluation of Project Management Functionality...7 Building Modeling...7 Cost Estimating...9 Scheduling and 4D...10 Resource Balancing and Cash Flow...11 Conclusion...11 References

4 Introduction In the master class Integrated Project Management I teach how to integrate the different project management aspects of time, cost, and scope into an overall project plan. The class assumes that project managers require information and communication technologies to achieve a seamless integration between these three aspects. Therefore, one of the major focuses of the class is on how to best apply building information model (BIM) based project management software to generate such integrated project plans. During the class students have to explore the current technological possibilities to integrate project management data by learning the functionality of BIM based applications and applying them to establish an integrated project plan for a real world project. In 2009 the students developed an integrated project plan for a two storey mixed used building for a local theater company in Hengelo, the Netherlands. The functions of the planned building comprise the storage of the group s theater props, the hosting of the group s offices, and the provision of a recital room. From a technical and managerial standpoint this project is very small and simple and, thus, it represents a great case to learn and understand the possibilities that BIM based applications offer to establish integrated project plans. This would not have been possible in the scope of a Master class if the class had used a more complicated project. I taught the class from February-2, 2009 to March-30, 2009 to 14 Construction Management and Engineering students. I divided these 14 students in three groups of five, five, and four students. In the first week of the class I introduced the class to the students. In the second week, I then introduced the students to the concept of BIM and gave them the task to evaluate a number of BIM project management applications and choose an initial application suite for establishing an integrated project plan in the rest of the class. At the beginning of every consecutive week I then conducted one lecture that theoretically introduced one project management concept and how project managers can theoretically integrate the concept into an overall project plan. In the rest of the week, each of the groups was then responsible to integrate the concept I taught in the lecture in their overall project plan. The groups had to choose an overall group work strategy, the BIM based software applications for the integration task, learn these software applications, and, finally, generate and integrate the week s required part of the project plan. To show their achievements, the students had to report their week s work within a weekly report that outlines the strategy they used during the week, summarizes the new part of the integrated project plan, and evaluates the usefulness of the BIM based software they chose to support them in the generation of the project plan part. Table 1 outlines the overall structure of the class. 3

5 Table 1 - Weekly outline of the class Week Project Management Concept Student Group Task 1 Introduction 2 Preliminary Evaluation and Choice of BIM software. 3 Product Management Generate a 3D BIM model of the project. 4 5 Cost Estimating Develop a detailed cost estimate of the project. 6 Scheduling Create a critical path schedule of how to realize the project. 7 Schedule Evaluation 8 Resource Balancing Visualize the schedule using a 4D model. Use the 4D visualization to optimize the schedule from week 3. Create a line of balance diagram to assign and level resources to the schedule tasks. Evaluate the relations of several allocation alternatives on the initial estimate. Also consider the cash flow across your planned project duration. Optimize schedule, cash flow, and resource allocation. 4

6 During the final exam week of the project the students then had to integrate a number of changes into their final integrated project plan. The main objective of this last assignment was to test how well the students integrated each of the project management sub-concepts into their overall project plan. Figure 1 shows the final class assignment. Figure 1 - Final class assignment: Change order management This report summarizes the findings from this class with respect to how well the different BIM based software products that the students chose supported their integrated project management efforts. The report is structured as follows: I start with a general overview about the software packages the students 5

7 chose to use throughout the class. I then provide an overview about how well the different packages supported the creation of each of the project plan parts, including an assessment of the interoperability between the applications. Each section also summarizes the main points of critic of the students that can serve as recommendations for software developers. The report also quickly evaluates how the different software packages supported group team work activities Software Packages Before the students started with their direct work on the integrated project plan, they had to evaluate and choose a number of BIM based applications that they planned to use for the rest of the course. I conducted this exercise so that the students learn how to quickly evaluate and choose different software applications for a given task. I supported them with this task by giving them a list of possible applications (Figure 2). I made clear that this list is not complete and that they can choose other applications if they intend to do so and if they have access to a license of the other application. During this exercise the three student groups developed the following criteria to evaluate the different applications: Group 1: applicability and interoperability Group 2: interoperability and user-friendliness Group 3: modeled level of detail, practical utilization, and interoperability After their evaluations the three groups decided to use the following BIM based applications in the class: Group 1 & 2: VICO software suite (Constructor, Estimator, 5D Presenter, Control) Group 3: Autodesk Revit as a BIM authoring tool, Tocoman BIM solutions for cost estimation, Microsoft Project for scheduling, Navisworks for 4D visualization, and Vico Control for line of balance scheduling The main reasons for group 1 and 2 to choose the VICO software suite were: VICO software offers a complete product suite, The programs seem to work quite intuitively, Data exchange seemed to be easy, The existence of easy to use training guides. The main reasons for group 3 to choose the combination of Revit, Tocoman, MS Project, Navisworks, and Control were: Good user reviews for the Tocoman software, and The interoperability of Autodesk Revit with the Tocoman software. 6

8 Figure 2 - Initial list of possible BIM applications for use within the class Evaluation of Project Management Functionality Building Modeling All three student groups chose for a hierarchical modeling approach by dividing the different components of the building into a Product Breakdown Structure (PBS). The groups then assigned the 7

9 responsibility to model the different components of the PBS to different group members. During modeling, all groups reported struggles with missing detail in the 2D drawings. This might point to a general problem of existing BIM authoring tools: Currently, users of authoring tools need to enter building information in a very high level of detail and little functionality to hierarchically organize a building information model exists. Such functionality, however, is needed to support the process of how engineers design facilities by carefully balancing the level of detail of information according to the design decisions they plan to make in a specific planning stage. To support this process, BIM authoring tools need to offer functionality to enable a flexible and hierarchical modeling approach allowing engineers to switch between different levels of detail easily. Overall, the two groups that used VICO Constructor did not report about their use of the software in detail. The group that used Revit as a BIM authoring tools reported three problems they encountered during modeling: Revit, by default, creates automated links between building components, such as, for example, links between doors, walls, and foundations. These links then allow the software to automatically adjust the dimensions of one building component according to changes in the dimensions of another linked building component. However, the logic behind these updates was often not consistent with the logic of the design of the building. The group, for example, reported that Revit automatically cut gaps into foundation elements of a wall according to the position of a door in that wall. However, the design of the building assumed that wall foundations run continuous under the planned doors within the wall. The group was not able to couple structural Revit elements with information about loading conditions and materials and non-structural elements without a warning. It was not clear from the group report how such a warning influenced the modeling work of the group in detail. The group was not able to use either of the two team work functions, work sharing and linked models that Revit offers. In particular, the use of the work sharing functionality requires access to a shared network drive, which was not available to the students. It remains questionable whether shared network drives are always available in practice and whether this is the most convenient and safest method to organize teamwork. The group was also not able to leverage the linked models functionality, as this functionality would require that the group can subdivide the overall building system into sub-systems with little interferences between the chosen subsystems. Due to the complexity of such a subdivision the group decided that it was not feasible to see the linked model function as well and decided to organize the modeling work sequentially. The accumulated overall times required to model the project in the respective BIM authoring tool vary significantly between the groups. Group 1 (Vico) reported 22.3 hours of modeling and learning the software, group 2 (Vico) reported 34 hours, and Group 3 (Revit) reported 56.5 hours. From these times it seems that learning the and modeling in the Vico Constructor software is easier and less time consuming 8

10 than learning the and modeling in Revit software. However, as the class only provides three data points this claim requires further validation. Cost Estimating The possibility to create cost estimates using quantities extracted automatically from the 3D BIM model worked for all three groups. Within one week all groups were able to produce a cost estimate using either the VICO Estimator tool or the Tocoman software. This shows that it is feasible to use BIM during cost estimation processes. However, we were not able to assess the overall accuracy of the automated quantity take-off in detail. During the class the students also encountered a number of problems while using the two applications with respect to user interface and data input. One inherent problem occurred with the creation of so called recipes. Such recipes define the required construction steps and resources that allow the calculation of costs based on BIM objects quantities that are extracted from the model (Eastman et al. 2008: 220). The two student groups that used the Vico Estimator software reported that it is not an easy process to create new recipes for specific BIM objects. It is necessary to follow many steps in the process and students suggested that a better user interface to define new recipes might have been helpful. The student group that used the Tocoman software was not available to create or manipulate estimates themselves. This was due to the setup of the Tocoman software that linked to recipes on a central server. To this server only staff at Tocoman had access. The missing possibility to alter existing or create new recipes significantly hindered the work of this group. Additionally, this group criticized the large number of steps that were necessary to link recipes with 3D model objects. In the area of interoperability between scope and cost VICO Estimator and Tocoman showed some problems. It took the two student groups that used VICO Estimator quite some time to set up an initial Estimator project that allowed them to import quantities. VICO Estimator requires that specific project settings are set up in the right way at the initial generation of a new estimation project. If the settings are not set up right, an automated quantity take off is not possible. One of the groups did not set up the project in the right way at the outset and lost much time till it discovered this error. Further, students reported that VICO Estimator produced some unclear warnings upon the change of a link to a specific Estimator project within VICO Constructor. Next to VICO Constructor, the Tocoman software also showed some problems with its interoperability with Autodesk Revit and Microsoft project. The main problem with Revit interoperability was that Tocoman did not recognize certain Revit objects during its quantity take-off, such as foundation objects. This required the student group to model their building with a limited number of building components in Revit. It seems like this work around might be a big barrier for the adoption of the Tocoman software in practice. In summary, the experiences of the student groups are that it is possible to link 3D BIM objects with recipes to establish cost estimates. However, the functionality of the BIM cost estimating software still needs to be improved further. It is still cumbersome to link 3D model objects with estimating recipes and the possibilities to visualize the resulting cost estimates are limited. Further, it seems to be of uttermost importance during the estimating process that estimators are able to quickly and easily adjust recipes and in some cases create completely new estimates from scratch. 9

11 Scheduling and 4D To create a construction schedule, the VICO software suite exports recipe and quantity information directly from VICO estimator into VICO control that automatically established construction activities from this information. Similar, it is possible for users to export this information from Tocoman to Microsoft project. Afterward the students had to manually add relations between these different activities to arrive at a critical path schedule. Overall, all groups were able to develop a construction schedule, however, both groups reported a number of problems during this process. The two groups that used the VICO software reported that they had problems to get accustomed to the user interface of VICO Control because Control s interface differs much from the other VICO modules. Further, the huge amount of functionality that VICO Control offers is confusing and makes it hard to learn the software. Again, the group struggled with the fact that VICO does not allow multiple database users and thus team work, by for example, at the same time changing estimate information in VICO Estimator and working on a schedule in VICO Control was not possible for two different students at the same time. Finally, the group reported that VICO Control did not import some items from VICO Estimator and the project managers should be careful with respect to the automated exchange function between these two parts of the VICO suite. The group that used the link between the Tocoman software and Microsoft Project also reported a number of problems with the process. The main problem was that the total time for each activity is calculated by Tocoman under the assumption of the use of one resource unit for every task. The students had to manually adjust this number to accelerate the schedule by using more than one resource unit using the resource functionality in Microsoft Project. Thus, students could simply use the scheduling functionality of Microsoft Project in conjunction with Tocoman. Additionally, the group was never able to establish an automated data exchange between Tocoman and Microsoft Project on all of their computers. Due to a bug in the Tocoman software they only managed to connect Tocoman and Microsoft project on the laptop of one group members. The group contacted the Tocoman support group who informed the students that this is a known problem and that at the moment no workaround exists for this problem. After the students created the construction schedule they then visualized this schedule using 4D animations. The students that used the VICO suite reported that there was only a very small amount of work necessary to arrive at the 4D visualization of their schedule as all information that they needed to create was already stored in one central database. The students only needed to open this database in the VICO 5D Presenter software. In contrary, the group that used the Tocoman software had to do a number of additional work steps. First, this group had to manually import the Microsoft Project schedule and the Revit model into the Autodesk Navisworks software. Then, in Navisworks, the students had to manually relink each of the 3D building components with the respective schedule activities. Using the 4D simulation the students then optimized the duration of their initial schedule by changing relations between tasks and by accelerating other tasks. However, this optimization through the concurrent adjustment of construction sequence and through the acceleration of single activities was not easily possible for the two groups that used the VICO suite because it required that students added 10

12 additional resources for an acceleration within the cost estimate of VICO Estimator, while they had to update of the construction sequence within VICO Control. Further, once updated a re-import of the updated information was necessary in VICO 5D Presenter. Overall, it seems like both chosen application suites showed some problems with the interoperability between the cost estimate and the schedule. While MS Project allowed the adjustment of both resource loading of a schedule and the sequences in one application, it could not communicate resource loading with the Tocoman estimate. Contrarily, VICO control allowed interoperability between the estimate and the schedule, however, students had to adjust resource loading and sequence information in two different applications of the VICO suite. Resource Balancing and Cash Flow To balance the resource allocation of the project schedule all three groups used the line of balance functionality within VICO Control. To do so, the group that created the schedule in Microsoft Project, started with their line of balance schedule in VICO from scratch and was able to meaningfully analyze the resource requirements of their schedule. Surprisingly, the two groups that used the VICO suite throughout the class struggled with creating a sound and meaningful line of balance schedule. This was mainly due to the fact that line of balance schedules to balance resource allocations are only meaningful for schedule tasks that repeat at different project locations over time. Most of the activities that VICO Control imported automatically from the estimate in VICO Estimator did not represent such repetitive activities. In the end, ironically, only the group that had to manually recreate a completely new Line of Balance schedule next to their critical path schedule in Microsoft Project was able to make meaningful resource balancing decisions using the VICO Control software. This episode might point to a general trade off that project managers have to make when planning with integrated project management software. On one hand, a completely integrated project plan can save much time and effort during the planning phase and allows for quick adjustment of specific information. On the other hand, there are situations where an integrated project plan cannot display information in a meaningful way to enable sound project management decisions and project managers are advised to recreate some information using another format that is not directly interoperable with the rest of the project plan. Surprisingly, none of the groups was able to optimize their schedule under considering of project cash flow. The students did not find meaningful functionality to do so neither in VICO Control nor in Microsoft project. One group manually created a cash flow diagram within Microsoft Excel. However, the group s approach did not lend itself well to iteratively improve the planned schedule as after every change in the schedule or to assigned resources the group had to manually update the cash flow diagram in Microsoft Excel. Due to this labor intensive process, the group was not able to evaluate many different schedule options. The missing functionality to evaluate cash flow activities within an integrated project plan comes as a surprise because cash flow management is one of the most important activities of overall project management. Conclusion This report summarizes the effort of three student groups to create an integrated project plan for a small mix used building during the class Integrated Project Management that I taught at the Twente 11

13 University in Two student groups used the VICO application suite and one group chose to use a combination of Revit, Tocoman, Microsoft Project, and VICO Control to generate the integrated project plan. Overall, all student groups succeeded to establish an integrated project plan using their chosen software solutions. However, the students were not able to meaningfully use advanced project management functionality, such as, line of balance schedules or cash flow analyzes, to optimize the project plan after its first generation. While this is partly a problem of missing experience on the student side, better functionality within the used BIM applications was also a barrier for the students. In light of the main advantage of having an integrated project plan the ability to evaluate different plan alternatives quickly through an integration of scope, cost, and time the practical applicability of the chosen software applications remains currently questionable. In particular, the following problems that the students in the class encountered seem to be major barriers for the practical use of the used software applications: It was not easily possible for the students to work in parallel by distributing sub-tasks among team members. While most of the software offers some functionality to work in parallel, this functionality was either limited to some of the necessary tasks or it required a sophisticated server environment that was not available for the students and might not always be available in practical contexts. The tendency of the software vendors to integrate functionality within relatively closed application suites made it hard for the students to balance integration of project data with the functionality that different applications offer. A good example for this shortcoming is the struggle of the VICO groups to meaningfully use the line of balance scheduling application. It might have been a better strategy to manually reenter project data into VICO Control that specifically lend itself to a line of balance analysis, similar to what the group did that did not apply the VICO suite for integrating the project plan. Only when applications enable project managers meaningfully to use the more advanced schedule analysis functionality, project managers will be able to fully leverage the potential of integrated project planning. Overall, project managers who wish to use the software applications the students applied during the class should make an informed and balanced judgment about the level of integration that is required for their project management tasks at hand and how well the existing software applications can support such an integration. Acknowledgements I thank Forest Olaf Peterson from Stanford University's CIFE for his valuabel input to a preliminary draft of this report. Obviously, this report would not have been possible without the hard and enthusiastic work of the students that took my class in 2009 thanks again for the great time I had with you throughout the class. 12

14 References Eastman, C.M., Eastman, C., Teicholz, P., Sacks, R., & Liston, K BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors. Wiley & Sons: Hoboken, New Jersey. Appendix A Summary of Results from Group C This appendix presents parts of the project plan of group C to give the reader a better understanding of the work of the students during the class. 3D Models of the Building 13

15 14

16 Cost Estimate Cost estimate basic Name Quantity Unit EUR total Window, Wood 70 M Steel Beam 695 M Stair, Steel 98 EA Roof, Light Beam + Steel Sheet 1394 M Internal Wall, Sandlime Brick 449 M Internal Wall, Gypsumboard 905 M Internal Door, Wood 43 EA Handrail, Steel 14 M Garage Door, Steel Sheet 2 EA Floor Slab, Hollow Core Slab Concrete 1359 M Floor Slab, 150 mm 1009 M External Wall, Timber Frame + Steel Sheet Cassette 1277 M External Entrance Door, Wood 7 EA Edge Beam, Precast 226 M Subtotal Cost driver Percentage Mark up EUR total More detailing 5% Site costs 5% General costs 7% Profit and risk 4% Insurances 0,40% Total

17 Schedule 16

Interoperable Learning Leveraging Building Information Modeling (BIM) in Construction Management and Structural Engineering Education

Interoperable Learning Leveraging Building Information Modeling (BIM) in Construction Management and Structural Engineering Education Interoperable Learning Leveraging Building Information Modeling (BIM) in Construction Management and Structural Engineering Education Eric L. Richards and Caroline M. Clevenger, PhD Colorado State University

More information

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering Building Information Modelling (BIM); How it Improves Building Performance R.P. Kumanayake Lecturer, Department of Civil Engineering R.M.P.S. Bandara Lecturer, Department of Mechanical Engineering Faculty

More information

Abstract: BIM: A Technological Advancement in the Field of Architecture. Introduction:

Abstract: BIM: A Technological Advancement in the Field of Architecture. Introduction: BIM: A Technological Advancement in the Field of Architecture Abstract: BIM (Building Information Modeling), an innovative parametric software has seen widespread use in architecture design firms worldwide.

More information

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE Autodesk Revit LEARNING PATH FUNDAMENTALS Duration: 3 days Cost: R5 500 (excl VAT) Revit MEP Duration: 3 days Cost: R5 500 (excl VAT) Revit Structure Duration: 3 days Cost: R5 500 (excl VAT) REVIT ADVANCED

More information

Automated construction schedule creation using project information model

Automated construction schedule creation using project information model Automated construction schedule creation using project information model Aleš Mrkela Faculty of civil engineering, University of Maribor, Maribor, Slovenia Danijel Rebolj Faculty of civil engineering,

More information

Feasibility Analysis of Initiating Building Information Modeling (BIM) for HVAC systems by General Contractors

Feasibility Analysis of Initiating Building Information Modeling (BIM) for HVAC systems by General Contractors Feasibility Analysis of Initiating Building Information Modeling (BIM) for HVAC systems by General Contractors Hussein Abaza, Ph.D. Southern Polytechnic State University, 1100 South Marietta Parkway, Marietta

More information

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY ISTANBUL TECHNICAL UNIVERSITY FACULTY OF ARCHITECTURE DEPARTMENT OF DESIGN COMPUTING BIM 2037 / BUILDING INFORMATION MODELS INSTRUCTOR: Salih OFLUOĞLU A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL

More information

Hybrid Model for Developing BIM Software Extensions

Hybrid Model for Developing BIM Software Extensions Journal of Advanced Management Science Vol. 3, No. 3, September 2015 Hybrid Model for Developing BIM Software Extensions Jesus N. Zaragoza-Grife, Romel G. Solis-Carcaño, and Gilberto A. Corona-Suarez Faculty

More information

General Comparison between 4D Software

General Comparison between 4D Software General Comparison between 4D Software (Navisworks, Synchro professional, Vico control, itwo and Navigator) Comparison between 4D Software 4D BIM is the next generation of project management, including

More information

BIM and Digital Fabrication

BIM and Digital Fabrication REVIT BUILDING INFORMATION MODELING BIM and Digital Fabrication This whitepaper examines how structural building information models are being used for the digital fabrication of structural steel and the

More information

Certified Instructors & Curriculum

Certified Instructors & Curriculum Our Promise. TPM is dedicated to provide the most extensive and high-quality training programs to help you maximize your investment. Although the investment in time and money may seem substantial, it will

More information

Streamline your design-to-cost processes with Autodesk Navisworks

Streamline your design-to-cost processes with Autodesk Navisworks Quantification in Autodesk Navisworks 2015 Streamline your design-to-cost processes with Autodesk Navisworks Contents Overcome data disarray....................................................................................

More information

Coordinating and Sharing Information with Revit Architecture and Revit Structure Best Practices!

Coordinating and Sharing Information with Revit Architecture and Revit Structure Best Practices! Revit Architecture and Revit Structure Best Practices! Erleen Hatfield Thornton-Tomasetti Uk Jung SE304-1 This class identifies best practices using Revit Architecture and Revit Structure for sharing and

More information

CHAPTER 2 QUANTITY TAKE-OFF

CHAPTER 2 QUANTITY TAKE-OFF CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate

More information

AC 2011-96: IMPLEMENTING BUILDING INFORMATION MODELING IN CONSTRUCTION ENGINEERING CURRICULA

AC 2011-96: IMPLEMENTING BUILDING INFORMATION MODELING IN CONSTRUCTION ENGINEERING CURRICULA AC 2011-96: IMPLEMENTING BUILDING INFORMATION MODELING IN CONSTRUCTION ENGINEERING CURRICULA Don Chen, University of North Carolina, Charlotte Professional Preparation Iowa State University, Ames, Iowa

More information

BIM and Project Planning

BIM and Project Planning REVIT BUILDING INFORMATION MODELING BIM and Project Planning This white paper explores how the Revit building information model (BIM) can be linked with project planning systems to enable 4D construction

More information

Synergy: Building Information Modeling and

Synergy: Building Information Modeling and : Building Information Modeling and Assoc. Professor Rafael Sacks BIM Handbook Symposium Georgia Tech Atlanta, GA, 13 th March 2008 Introduction Both and BIM are deep process changes, in thinking and in

More information

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3 7EH,

More information

Building Information Modeling Based Time And Cost Planning In Construction Projects

Building Information Modeling Based Time And Cost Planning In Construction Projects Building Information Modeling Based Time And Cost Planning In Construction Projects Zoran Pučko University of Maribor, Faculty of Civil Engineering, Slovenia zoran.pucko@um.si Nataša Šuman University of

More information

Olilo's AEC Design Services. SrinSoft Inc, Partners of

Olilo's AEC Design Services. SrinSoft Inc, Partners of Olilo's AEC Design Services SrinSoft Inc, Partners of Olilo provides design services that include design and analysis, cost estimation, 3D modeling, 2D drafting, conversion from 2D to 2D, quantity take-off,

More information

CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours)

CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours) CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours) Lecture Meets in 154 Baker Hall, Monday, Wednesday, and Fridays 9:30-10:25 AM Instructor Paul Crovella 219

More information

Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad

Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad Debasis Sarkar 1 & Raj Modi 2 Associate Professor and Head, Department of Civil Engineering, School of Technology,

More information

reality Revit check Autodesk have long Identify possible Utilize structural Tool Works Building bcg.com

reality Revit check Autodesk have long Identify possible Utilize structural Tool Works Building bcg.com Autodesk Revit reality check for residential construction: Scott Babin Illinois Tool Works, Building Components Group AB6105-V Using Autodesk Revit for architectural and structural design in the residential

More information

THE CONCEPT OF HIERARCHICAL LEVELS; AN OVERALL CONCEPT FOR A FULL AUTOMATIC CONCRETE DESIGN INCLUDING THE EDUCATION OF CONCRETE.

THE CONCEPT OF HIERARCHICAL LEVELS; AN OVERALL CONCEPT FOR A FULL AUTOMATIC CONCRETE DESIGN INCLUDING THE EDUCATION OF CONCRETE. THE CONCEPT OF HIERARCHICAL LEVELS; AN OVERALL CONCEPT FOR A FULL AUTOMATIC CONCRETE DESIGN INCLUDING THE EDUCATION OF CONCRETE. THE CASE MatrixFrame VERSUS EuroCadCrete. ABSTRACT: Ir. Ron Weener 1. The

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

Autodesk Robot Structural Analysis Professional 2010. Break it down before you build it up.

Autodesk Robot Structural Analysis Professional 2010. Break it down before you build it up. Autodesk Robot Structural Analysis Professional 2010 Break it down before you build it up. Building Information Modeling for Structural Engineering Integrated tools for modeling, coordination, analysis,

More information

Turner Innovation Series BIM Conference Istanbul May 2012. Brian Krause, Dan Gramer, Turner Construction Company

Turner Innovation Series BIM Conference Istanbul May 2012. Brian Krause, Dan Gramer, Turner Construction Company 1 Why BIM? Excessive Re-Work and Waste TURNER INNOVATION SERIES May 2012 BIM for Design, Preconstruction, & Construction Brian Krause Manager, Integrated Building Solutions bkrause@tcco.com Value Value

More information

INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2

INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2 INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2 Hyun Cho 1, Ki Hwan Lee 1, Song Hyon Lee 1, Ta Lee 1, Hyun Jun Cho 1, Sung Hoon Kim 2 and

More information

An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction

An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction 1666 An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction Hexu LIU 1, Zhen LEI 2, Hong Xian LI 3, Mohamed AL-HUSSEIN 4 1 Hole School of Construction

More information

Organizing 3D Building Information Models with the help of Work Breakdown Structures to improve the Clash Detection process

Organizing 3D Building Information Models with the help of Work Breakdown Structures to improve the Clash Detection process Organizing 3D Building Information Models with the help of Work Breakdown Structures to improve the Clash Detection process Final Report S. Gijezen T. Hartmann K. Th. Veenvliet H. Hendriks N. Buursema

More information

Linear Schedules for Tunnel Projects

Linear Schedules for Tunnel Projects Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear

More information

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction

More information

Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education

Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education Keith E. Sylvester, Ph.D. and Charlotte Dietrich, Undergraduate Student East Carolina University Greenville,

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Module 4 6/15/2010. After completing the Project Activities and Task Section, learn the difference between an activity and a task.

Module 4 6/15/2010. After completing the Project Activities and Task Section, learn the difference between an activity and a task. Project Activities and Tasks Module 4 Module Objectives After completing the Project Activities and Task Section, participants i will be able to: learn the difference between an activity and a task. define

More information

APPLYING CLOUD COMPUTING TECHNOLOGY TO BIM VISUALIZATION AND MANIPULATION

APPLYING CLOUD COMPUTING TECHNOLOGY TO BIM VISUALIZATION AND MANIPULATION APPLYING CLOUD COMPUTING TECHNOLOGY TO BIM VISUALIZATION AND MANIPULATION Tien-Hsiang Chuang 1, Bo-Cing Lee 1, and I-Chen Wu 1 * 1 Department of Civil Engineering, National Kaohsiung University of Applied

More information

INTRODUCTION. Prakash Chandar. S¹, Dhivya Shree. G² ABSTRACT

INTRODUCTION. Prakash Chandar. S¹, Dhivya Shree. G² ABSTRACT International Journal of Emerging Engineering Research and Technology Volume 3, Issue 4, April 2015, PP 67-74 ISSN 2349-4395 (Print) & ISSN 2349-4409 (Online) Integrating Building Information Modelling

More information

STUDENT COLLABORATION AS THE FOUNDATION FOR LEARNING BIM SOFTWARE: IDEAS FROM A PROJECT-BASED INTRODUCTION

STUDENT COLLABORATION AS THE FOUNDATION FOR LEARNING BIM SOFTWARE: IDEAS FROM A PROJECT-BASED INTRODUCTION STUDENT COLLABORATION AS THE FOUNDATION FOR LEARNING BIM SOFTWARE: IDEAS FROM A PROJECT-BASED INTRODUCTION Christopher Monson, RA, Associate Professor, cmonson@caad.msstate.edu Building Construction Science

More information

How To Design A Bim Project

How To Design A Bim Project BIM Virtual Construction & Integrated Project Delivery Randy LaNear BIM Manager Barnhart - Heery Synonyms & Related Terms Integrated Practice Integrated Project Delivery Virtual Building (Environment)

More information

Collaboration. Jason Howden. Archaus Architects

Collaboration. Jason Howden. Archaus Architects Jason Howden Archaus Architects Over View Why Collaborate? Basic Principles Coordination of Architectural, Structural and MEP Disciplines Interference and Clash Detection Copy Monitor Best Practise Data

More information

The Benefits of Management Information Systems to the Professional Practice

The Benefits of Management Information Systems to the Professional Practice The Benefits of Management Information Systems to the Professional Practice SAICE 15th Annual Conference on Computers in Civil Engineering By Dr James A Robertson PrEng & Reg M Barry, Financial Director,

More information

BIM and API Extensions

BIM and API Extensions REVIT BUILDING INFORMATION MODELING BIM and API Extensions This whitepaper explains how the utility of BIM solutions such as Revit Structure software can be broadened through the use of specialized software

More information

Design without compromise. Autodesk Revit. Architecture 2010

Design without compromise. Autodesk Revit. Architecture 2010 Design without compromise. Autodesk Revit Architecture 2010 BIM Simply a Better Way of Working Deliver projects faster, more economically, and with enhanced potential for reduced environmental impact.

More information

A Methodological Shift in Building Design through Development of Collaborative Design Platforms

A Methodological Shift in Building Design through Development of Collaborative Design Platforms ctbuh.org/papers Title: Authors: Subject: Keywords: A Methodological Shift in Building Design through Development of Collaborative Design Platforms Jonatan Schumacher, CORE Studio, Thornton Tomasetti Matthew

More information

Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry

Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry Meena R. Nageeb, MS Texas A&M University College Station, Texas Bradly T. Johnson, PhD Colorado State University Fort

More information

BIM Extension into Later Stages of Project Life Cycle

BIM Extension into Later Stages of Project Life Cycle BIM Extension into Later Stages of Project Life Cycle Pavan Meadati, Ph.D. Southern Polytechnic State University Marietta, Georgia This paper discusses the process for extending the implementation of the

More information

Structural BIM Technology Certificate Program

Structural BIM Technology Certificate Program Structural BIM Technology Certificate Program Program Description 160 Credit Hours of Instruction Program Completion Time - 6 Months Upon Completion VDCI/cadteacher Technology Certificate Awarded STRUCTURAL

More information

Introduction to Project Management ECE 480. Erik Goodman

Introduction to Project Management ECE 480. Erik Goodman Introduction to Project Management ECE 480 Erik Goodman What is Project Management? a method for organizing tasks a structured framework to help a group work productively tools to aid in task sequencing,

More information

Professional Engineers Providing Structural Engineering Services In Buildings

Professional Engineers Providing Structural Engineering Services In Buildings GUIDELINE Professional Engineers Providing Structural Engineering Services In Buildings 1995 Published by Association of Professional Engineers of Ontario Revised 12/11/98 CONTENTS INTRODUCTION...3 PART

More information

Building Information Modeling (BIM): A New Paradigm for Visual Interactive Modeling and Simulation for Construction Projects

Building Information Modeling (BIM): A New Paradigm for Visual Interactive Modeling and Simulation for Construction Projects First International Conference on Construction in Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi, Pakistan Building Information

More information

Module Code 4AZ500 Pre-requisite None CAD BIM DESIGN CONCEPT DRAFTING SOFTWARE 2D 3D

Module Code 4AZ500 Pre-requisite None CAD BIM DESIGN CONCEPT DRAFTING SOFTWARE 2D 3D Module Title ARCHITECTURAL CAD Module Code 4AZ500 Pre-requisite None Date of Approval Module Level 4 Credit value 20 Total Number of Learning Hours 200 Key Words (10 words maximum) Module Delivery Online/Distance

More information

and 2010: rprise Increasingly, must ation, es, partners, s intelligence.

and 2010: rprise Increasingly, must ation, es, partners, s intelligence. Autodesk Vault 2012 Autodesk Vault 2012 and Microsoft SharePoint 2010: Providing Accesss to Design Data Across the Enter rprise Increasingly, to succeed, businesses must collaborate effectively y both

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

BIM Software Framework for Prefabricated Construction: Case Study Demonstrating BIM Implementation on a Modular House

BIM Software Framework for Prefabricated Construction: Case Study Demonstrating BIM Implementation on a Modular House 6 th International Conference on Structural Engineering and Construction Management 2015, Kandy, Sri Lanka, 11 th -13 th December 2015 SECM/15/167 BIM Software Framework for Prefabricated Construction:

More information

Using BIM to Eliminate Construction Site Hazards Life Cycle Safety Stage Repair, Operations, and Maintenance Brian Krause, Turner Construction Company

Using BIM to Eliminate Construction Site Hazards Life Cycle Safety Stage Repair, Operations, and Maintenance Brian Krause, Turner Construction Company for, bkrause@tcco.com Top Loss Drivers 2007-2012 Material Handling for Struck by Object Safety Survey: Top 12 Most Important: BIM Overlay BIM Safety Group Initiative 12. Complete accident investigation

More information

AUTOMATED CONSTRUCTION PLANNING FOR MULTI-STORY BUILDINGS

AUTOMATED CONSTRUCTION PLANNING FOR MULTI-STORY BUILDINGS AUTOMATED CONSTRUCTION PLANNING FOR MULTI-STORY BUILDINGS Tang-Hung Nguyen 1 ABSTRACT This paper outlines a computer-based framework that can assist construction planners and schedulers in automatically

More information

Quantity Takeoff. Dr. Ahmed Elyamany

Quantity Takeoff. Dr. Ahmed Elyamany Quantity Takeoff Dr. Ahmed Elyamany 1 Outline Importance of Quantity Takeoff Preparation of Quantity Takeoff Measurement Units Measuring excavation, P.C footings, Beams, Columns, slabs, and stairs. Solved

More information

The structure of accounting systems: how to store accounts Lincoln Stoller, Ph.D.

The structure of accounting systems: how to store accounts Lincoln Stoller, Ph.D. The structure of accounting systems: how to store accounts Lincoln Stoller, Ph.D. balances In my most recent article I considered the simplest accounting system consisting of a single file of general ledger

More information

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material,

More information

PS.12. 4D Scheduling A Case Study

PS.12. 4D Scheduling A Case Study PS.12 4D Scheduling A Case Study Mr. Abhimanyu Basu PE PSP A 4D schedule is a 3 dimensional CAD model How long would it take. attached to the fourth dimension of time via a schedule. The concept of 4D

More information

SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION

SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION version 1.0_042011 www.foresightsports.com TABLE OF CONTENTS INTRODUCTION 1 COMPONENTS-AT-A-GLANCE 2 SPACE DIMENSIONS

More information

Design without compromise. Autodesk Revit. Architecture

Design without compromise. Autodesk Revit. Architecture Design without compromise. Autodesk Revit Architecture Definitive Design From conception to construction documentation, design projects within an intuitive environment. Building information modeling and

More information

FABRICATION DRAWINGS A Paradigm Shift

FABRICATION DRAWINGS A Paradigm Shift INNOVATIVE DIMENSIONS Presented by Fitzpatrick Engineering Group March 2013 2012 Finalist Innovation in Structural Engineering DRAWINGS A Paradigm Shift 19520 Catawba Avenue, Ste 311 Cornelius, NC 28031-3711

More information

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY HOWARD COUNTY MARYLAND ARCHITECTURAL DESIGN ACADEMY Architectural Design 1 Introduction / Overview of Course This course will introduce the basic principles

More information

CASE STUDY OF USING AN INTEGRATED 5D SYSTEM IN A LARGE HOSPITAL CONSTRUCTION PROJECT

CASE STUDY OF USING AN INTEGRATED 5D SYSTEM IN A LARGE HOSPITAL CONSTRUCTION PROJECT 664 CASE STUDY OF USING AN INTEGRATED 5D SYSTEM IN A LARGE HOSPITAL CONSTRUCTION PROJECT Tanmaya Kala 1, Olli Seppänen 2, Claire Stein 3 ABSTRACT 3D models for constructability analysis, quantity takeoff,

More information

BIM ACROSS THE DESIGN-BUILD-OPERATE LIFECYCLE

BIM ACROSS THE DESIGN-BUILD-OPERATE LIFECYCLE Division BIM ACROSS THE DESIGN-BUILD-OPERATE LIFECYCLE Mark Sawyer General Manager, Division Trimble Navigation Limited, Inc. Lifecycle Strategy PROJECT TEAM s Engineers General Contractor Subcontractors

More information

A CASE STUDY IN STRUCTURAL DRAFTING, ANALYSIS AND DESIGN USING AN INTEGRATED INTELLIGENT MODEL

A CASE STUDY IN STRUCTURAL DRAFTING, ANALYSIS AND DESIGN USING AN INTEGRATED INTELLIGENT MODEL A CASE STUDY IN STRUCTURAL DRAFTING, ANALYSIS AND DESIGN USING AN INTEGRATED INTELLIGENT MODEL Reid Senescu 1, Andrew Mole 2, and Anthony Fresquez 3 ABSTRACT One of the promises of Interoperability and

More information

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans

More information

Data Management for Civil Infrastructure

Data Management for Civil Infrastructure Data Management for Civil Infrastructure 5 Things You Need to Know Now BROUGHT TO YOU BY: INTRODUCTION Industry trends that impact collaboration and data management practices Volume. Digital tools are

More information

Business Process Discovery

Business Process Discovery Sandeep Jadhav Introduction Well defined, organized, implemented, and managed Business Processes are very critical to the success of any organization that wants to operate efficiently. Business Process

More information

BIM BASICS AIRAH PRESENTATION SERIES. Mark Jacobson National BIM Operations Manager AE Smith & Son

BIM BASICS AIRAH PRESENTATION SERIES. Mark Jacobson National BIM Operations Manager AE Smith & Son BIM BASICS AIRAH PRESENTATION SERIES Mark Jacobson National BIM Operations Manager AE Smith & Son Presentation Content What will be covered Common terms and software utilised A basic overview of BIM workflows

More information

WEB-ENABLED MODEL-BASED CAD FOR THE ARCHITECTURE, ENGINEERING AND CONSTRUCTION INDUSTRY

WEB-ENABLED MODEL-BASED CAD FOR THE ARCHITECTURE, ENGINEERING AND CONSTRUCTION INDUSTRY WEB-ENABLED MODEL-BASED CAD FOR THE ARCHITECTURE, ENGINEERING AND CONSTRUCTION INDUSTRY Jack C. P. Cheng 1, Kincho H. Law 2, Yu Zhang 3 and Charles S. Han 2 1 Department of Civil and Environmental Engineering,

More information

Introduction to the Data Migration Framework in Microsoft Dynamics by Ruben Barron

Introduction to the Data Migration Framework in Microsoft Dynamics by Ruben Barron Introduction to the Data Migration Framework in Microsoft Dynamics by Ruben Barron Senior Consultant - Blue Horseshoe Solutions. 1 Table of Contents Intro to the Data Migration Framework (DMF)... 3 DMF

More information

Questions and Answers

Questions and Answers AutoCAD Architecture 2010 Questions and Answers AutoCAD Architecture 2010 software the version of AutoCAD software for architects. Creating designs and documentation is much more efficient using the software

More information

BI Analytics for Dynamics CRM Helps High Concrete Deliver Timely, Accurate Reporting and Analysis Strategy Companion

BI Analytics for Dynamics CRM Helps High Concrete Deliver Timely, Accurate Reporting and Analysis Strategy Companion Case Study BI Analytics for Dynamics CRM Helps High Concrete Deliver Timely, Accurate Reporting and Analysis High Concrete is part of the High Industries family that provides steel bridge fabrication and

More information

WebSphere Business Modeler

WebSphere Business Modeler Discovering the Value of SOA WebSphere Process Integration WebSphere Business Modeler Workshop SOA on your terms and our expertise Soudabeh Javadi Consulting Technical Sales Support WebSphere Process Integration

More information

PROJECT MANAGEMENT INNOVATION BASED ON BUILDING INFORMATION MODELING

PROJECT MANAGEMENT INNOVATION BASED ON BUILDING INFORMATION MODELING PROJECT MANAGEMENT INNOVATION BASED ON BUILDING INFORMATION MODELING CHANGHUA LI Hefei University, Office of Science and Technology, China drch88@aliyun.com LEON PRETORIUS University of Pretoria, Department

More information

Microsoft Office Access 2007 which I refer to as Access throughout this book

Microsoft Office Access 2007 which I refer to as Access throughout this book Chapter 1 Getting Started with Access In This Chapter What is a database? Opening Access Checking out the Access interface Exploring Office Online Finding help on Access topics Microsoft Office Access

More information

Autodesk Revit Architecture. Design without compromise.

Autodesk Revit Architecture. Design without compromise. Autodesk Revit Architecture Design without compromise. Definitive Design From conception to construction documentation, design projects within an intuitive environment. Building information modeling and

More information

ASHULIA APPARELS LTD. Client Summary Report

ASHULIA APPARELS LTD. Client Summary Report Revision : Issue 1 Date: 18 March 2014 ASHULIA APPARELS LTD Samad Mansion, Sec # 6, Block # kha, Road No# 1, Plot #14, Shenpara Parbata, Mirpur, Dhaka (23.8065N,90.3683E) 4th March 2014 Client Summary

More information

Custom Web Development Guidelines

Custom Web Development Guidelines Introduction Custom Web Development Guidelines Unlike shrink wrap software, custom software development involves a partnership between the architect/programmer/developer (SonicSpider) and the owner/testers/users

More information

Autodesk Inventor 2013

Autodesk Inventor 2013 Autodesk Inventor 2013 AMS CAD + CAFM Solutions amscad.com Image courtesy of Brimrock Group Inc. and Mechanix Design Solutions Inc. Autodesk Inventor Takes You From 2D to 3D Digital Prototyping The Inventor

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Vico Office R3.0 Help

Vico Office R3.0 Help 1 Vico Office R3.0 Help User guide 2 Contents 3 Vico Office R3.0 Help Revision 1 4 Vico Office Introduction Welcome to Vico Office, Vico's integrated Virtual Construction environment. The Vico Office Suite

More information

BIM Test At ASHRAE HQ

BIM Test At ASHRAE HQ This article was published in ASHRAE Journal, April 2011. Copyright 2011 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. Posted at www.ashrae.org. This article may not be

More information

Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design

Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design Florian Aalami CEO ADAPT Corporation florian@adaptsoft.com What is BIM? The ability to model

More information

d e n v e r a r t m u s e u m

d e n v e r a r t m u s e u m d e n v e r a r t m u s e u m The Denver Art Museum Expansion will be a dramatic addition to the downtown Denver skyline and will help place Denver among the top art centers in the nation. The new addition

More information

How To Develop Software

How To Develop Software Software Engineering Prof. N.L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture-4 Overview of Phases (Part - II) We studied the problem definition phase, with which

More information

PROCUREMENT, FABRICATION & CONSTRUCTION

PROCUREMENT, FABRICATION & CONSTRUCTION SmartPlant Enterprise PROCUREMENT, FABRICATION & CONSTRUCTION 2 Balancing Act PROCUREMENT, FABRICATION, AND CONSTRUCTION represent a complex balancing act between profit-making and risk-taking that requires

More information

Practical Strategy and Workflow for Large Projects: A Realistic Solution

Practical Strategy and Workflow for Large Projects: A Realistic Solution Practical Strategy and Workflow for Large Projects: A Realistic Solution Marco Brasiel/Diego Faria Frazillio & Ferroni SE3193 This class presents a strategy for development of structural projects using

More information

Industrial Case Study of Electronic Design, Cost and Schedule Integration

Industrial Case Study of Electronic Design, Cost and Schedule Integration Industrial Case Study of Electronic Design, Cost and Schedule Integration Sheryl Staub 1, Martin Fischer 2 and Melody Spradlin 3 1 Project Engineer, Hathaway/Dinwiddie Construction Group Santa Clara, CA

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Scott M. Francis, P.E., PSP Table of Contents 1. INTRODUCTION...

More information

ARCHITECTURAL DESIGN SOFTWARE SOLUTION

ARCHITECTURAL DESIGN SOFTWARE SOLUTION www.visionrez.com www.itwbcg.com ARCHITECTURAL DESIGN SOFTWARE SOLUTION A multibillion dollar company with nearly 100 years of history, ITW today designs and manufactures fasteners and components, equipment

More information

The Client Time Sheet and Payroll Software Buying Guide by Vertex Systems

The Client Time Sheet and Payroll Software Buying Guide by Vertex Systems The Client Time Sheet and Payroll Software Buying Guide by Vertex Systems Traditional methods for capturing time and piece counts for people with disabilities in your vocational programs can cost your

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

TDWI strives to provide course books that are content-rich and that serve as useful reference documents after a class has ended.

TDWI strives to provide course books that are content-rich and that serve as useful reference documents after a class has ended. Previews of TDWI course books offer an opportunity to see the quality of our material and help you to select the courses that best fit your needs. The previews cannot be printed. TDWI strives to provide

More information

Developing 6D BIM Energy Informatics for GDL LEED IFC Model Elements

Developing 6D BIM Energy Informatics for GDL LEED IFC Model Elements Proceedings of the 2012 International Conference on Industrial Engineering and Operations Management Istanbul, Turkey, July 3 6, 2012 Developing 6D BIM Energy Informatics for GDL LEED IFC Model Elements

More information

How To Implement Lean And Bim On An Infrastructure Project

How To Implement Lean And Bim On An Infrastructure Project CHALLENGES AND OPPORTUNITIES IN IMPLEMENTING LEAN AND BIM ON AN INFRASTRUCTURE PROJECT Bhargav Dave 1, Stefan Boddy 2 and Lauri Koskela 3 ABSTRACT: It has been realised through research and practice that

More information