Strategies for creating accurate updates of CPM construction schedules.
|
|
|
- Charlene Rogers
- 10 years ago
- Views:
Transcription
1 Session No Strategies for creating accurate updates of CPM construction schedules. Todd Dunn, P.E. Associate Professor, Rochester Institute of Technology Civil Engineering Technology Abstract: The paper describes practical approaches that students and practitioners can use to accurately update CPM construction schedules. It describes the importance of updates, and also explores common errors made during updates, and methods for correcting them. Its purpose is to provide students and professionals involved in CPM construction scheduling the tools to create reliable and accurate schedule updates using popular application software (Primavera Systems Inc.). Detailed means and methods employed when updating schedules are described. In particular, the paper describes the software settings and approaches for configuring the settings in an effort to achieve accurate, reliable schedule updates. Introduction: Creating CPM (Critical Path Method) schedules for construction projects is commonplace. Construction schedules include a group of activities which must be performed in order to complete, say, a new building. Every activity in a construction schedule has an estimated time duration to complete the activity. Examples of activities might include, Erect Structural Steel (with, for example, a ten day duration) or Install brick veneer on south wall. Critical path schedules are so-named because these time schedules highlight a subgroup of activities that lie on the critical path. The activities that lie on the critical path are important because a delay in completing any of these activities will result in a delay in completion of the project. Schedulers and/or construction project managers should update their CPM schedules on a regular basis in an effort to compare actual progress on the job with planned progress. Owners will want to know if the project is on schedule, and the only way to provide a quantitative answer to that question is to examine each activity in the schedule and record any progress that has occurred on that activity since the last update. Once the progress is accurately recorded, the application software used to create the schedule can perform calculations that will estimate start and end dates for the remaining (incomplete) activities in the schedule. This may result in a project completion date that has changed since the last update. Often, however, schedules are not updated regularly, in part because producing accurate updates to an on-going project is not a trivial endeavor. (Another reason regular schedule updates are sometimes ignored is that often owners and contractors loose enthusiasm and motivation for producing the updates. Part of this lethargy is due to their experience with flawed updates). In addition, the popularization of easy-to-use scheduling software has democratized CPM schedule writing...but it has also put scheduling in the hands of many inexperienced and poorly trained Page
2 practitioners. 2. The paper outlines, in detail, several straightforward approaches that can be employed to achieve accurate updates to CPM construction schedules. 1) The importance of accurate updates. Students in civil engineering technology programs often gain practice in developing CPM construction schedules. They are exposed to the essentials of creating activities, estimating activity durations, and establishing the relationships among activities in the network. Relationships between activities define the logic connection between them. For example, an activity named Form foundation walls could not begin until Pour footing concrete is completed. When students finish, they re usually successful in creating a complete CPM schedule that features a reasonable critical path through the network. In practice, CPM schedules are of limited value to owners/clients unless the schedules are periodically updated. The initial CPM schedule is not enough to satisfy most savvy owners/clients. They recognize that no project ever proceeds exactly as planned and, as such, will demand that the schedule be updated periodically as construction proceeds. They demand regular, accurate updates from their contractor or construction manager in an effort to assess the likelihood of a delayed completion, forecast cash outlays to the contractor, and to better coordinate the relocation of their staff and equipment to the new facility. Many textbooks dealing with construction project management in general, and scheduling in particular, devote ample space to the development of CPM schedules. Much less, if any, space is devoted to the procedures involved in updating (or statusing) the schedule. This paper examines strategies that can be used in the classroom to give students exposure to and practice in producing accurate updates to CPM schedules. 2) Understanding the data date : Students and practitioners need to recognize the difference between the data date and the project start date. The start date is intuitive; it s the launching date for the project as a whole. When updating a CPM schedule, it s crucial for students to understand the difference between the two dates. The data date can be loosely explained as today s date, or, more accurately, the date that someone (the student, the job s superintendent, the project manager, etc.) visited the job site and evaluated the actual progress of individual activities in the CPM schedule. The data date is sometimes referred to as today s date, but strictly speaking, this is incorrect. For example, the superintendent might have evaluated activities progress on a Friday, while the student scheduler might not input the changes into his/her software program until the following Monday. Regardless of the day the software is accessed, the data date remains Friday, the day of the on-site evaluation. 3) Evaluating progress on individual activities in the CPM schedule: Once the data date has been established, the student needs to carefully examine the CPM schedule in detail. He/she needs to critically appraise every activity in the schedule that either a) experienced progress of any kind during the time period since the last update or b) was slated to have progress during the same time period. Students are often careless in this step, Page
3 and it s crucial to convey to them the importance of taking the time to review every activity in the schedule that could have been affected during the time interval since the last update. This is especially important, since some of the available software applications allow the user the option to automatically update each activity as though it progressed according to its early dates. 1 Actual progress rarely matches planned progress for a group of activities. As such, students should be very wary about using this quick approach for statusing their activities. The scheduler can review %complete and/or remaining duration for activities when updating a CPM schedule. Most scheduling software applications employ a formula similar to the following one when evaluation progress on an activity: D R =D O (1-P) where: D R = remaining duration (usually expressed in days) for the activity D O = original estimated duration for the activity P = percent complete for the activity, expressed as a decimal. Use of this formula allows the scheduler to input the percent complete for an activity (P), and have the remaining duration (D R ) automatically calculated. Conversely, the remaining duration (D R ) can be input to produce the estimated percent complete (P). For example, suppose that when the schedule was originally developed, before construction began, the student estimated a 10 day duration for an activity called Form Footings. Thus, D O =10. Let s assume now that some time has passed, the project is underway, and the student is performing a schedule update. The superintendent tells the student that the form footings operation is, say, 40% complete as of the data date. Therefore, P=0.4. To calculate remaining duration, D R, we use: D R =D O (1-P) D R = 10(1-0.4) D R = 6 days. Form footings apparently needs an additional 6 days from the data date to complete. This 6 day value for D R is automatically folded into the schedule calculations by the application software. Forecasted start and finish dates for activities that are downstream ( successors ) to Form Footings are automatically calculated by the software, based on the assumption that 6 days are needed (from the data date) to complete the Form footings activity. Students can usually grasp this calculation easily, and are comfortable using percent complete (P) as a good indicator of progress. However, the superintendent was never asked his estimate of the remaining duration needed to complete the form footings activity on the jobsite. Is it, in fact, six days, as calculated by the above equation? In many cases the answer will be no. It s entirely possible that form footings is, indeed, 40% complete, but the superintendent might feel that, say, nine (9) additional days are needed to complete the activity. Page
4 Therefore, using percent complete (P) as the only reliable indicator of an activity s progress can be misleading, and can lead to significant errors when performing an update. Students are often not aware of the problems that can be sewn into a schedule by relying solely on this approach for updating activities. What students rarely appreciate, and what is often missing in textbooks dealing with CPM scheduling, is the fact that original durations (D O ) are often incorrect. On reflection, this makes perfect sense. When the CPM schedule is originally developed, the original durations (D o ) for activities are, at best, educated guesses. It is difficult, if not impossible, for a scheduler to forecast the exact length of time an activity will require (e.g. form footings) weeks or months in advance of performing the actual work. As work progresses on the jobsite, superintendents and project managers will discover that many of the first estimates for activities original durations will be flat-out wrong. If the error isn t corrected at the time of the schedule update, and the student is performing the update using percent complete (P) as the only input, the calculated result for remaining duration (D R ) will be incorrect. This error will cascade its way through the CPM via the relationships (logic ties) between activities, and produce an updated schedule that is inaccurate in its prediction of job completion. Two separate tactics can be used to address this problem, and students should be made aware of both. The first approach is to change the activity s original duration (D o ) at the time of the schedule update. Let s assume in the example above that the superintendent agrees that form footings is 40% complete, but also states that he thinks 9 days (from the data date) will be required to complete the work. Using the formula, we can reevaluate our estimate for the original duration, D O : D R =D O (1-P) 9 = D O (1-0.4) Solving for D O yields D O = 15. We see then that the original duration (D O ) must be changed to 15 days if the 40% complete (P) and 9 day remaining (D R ) are used in the formula. The initial guess (made, perhaps, months ago) for D O =10days was wrong. Changing D O will produce an accurate depiction of the activity s progress. Students can easily learn and use this approach. However, owners may not be receptive to receiving updated CPM schedules in which the original duration (D O ) for activities have been altered. Many owners use the originally-submitted CPM schedule as a baseline or target schedule against which future updates are compared. Changing original durations (D O ) during a schedule update can raise an owner s eyebrows; he/she is usually interested in comparing the contractor s actual progress versus the planned progress. Changing original (planned) durations for activities may be unacceptable to owners once the original CPM schedule has been submitted and reviewed. A second tactic for addressing the percent complete (P) vs. remaining duration (D R ) problem is to disable the formula within the scheduling software application. As mentioned, the formula is enabled by default in Primavera Project Planner version 3.1, (a popular software application package used to create and update CPM schedules). But the formula can easily be disabled by the software user. Once disabled, the link between percent complete (P) and Page
5 remaining duration (D R ) is broken. If the formula is disabled, students must recognize that when they update an activity in the schedule, they must provide values for both percent complete (P) and remaining duration (D R ). When the formula is disabled, the data value for one variable (say, P=40%) will not result in an automatic calculation for the other (remaining duration, D R ). Since remaining duration always governs calculation of the schedule and determines finish dates for the activity 1, it s crucial that the scheduler input remaining duration (D R ) for each affected activity during a schedule update. At their option, students can also input percent complete (P) for the activity, but P s value won t affect any schedule calculations done by the software. Our students are encouraged to use this approach (disabling the formula) for several reasons: a) Superintendents often have a better feel for the remaining duration (D R ) of an activity as opposed to its percent complete (P). As such, the updated CPM schedule will be more accurate. b) As shown in the previous example, enabling the formula and inputting percent complete (P) will produce incorrect results for remaining duration (D R ) if the initial guess for original duration (D O ) was wrong, as is often the case. c) As mentioned, owners often frown on the practice of altering activities original durations (D O ) when updated CPM schedules are presented to them. A numerical example, taken from an exam given to our students, is below. In each case, percent complete is 20%. However, as shown in the example, different completion dates can result depending on whether the formula is enabled or not. Page
6 Consider the activities below: The Primavera software allows you the choice of linking remaining duration and percent complete. If remaining duration and percent complete are linked, the software uses this formula: D R = D O (1 - P) where: D R is the remaining duration D O is the original duration P is percent complete, expressed as a decimal. a) Assume the following: Χ Today is March 5. Χ Remaining duration and % complete are linked. Χ Footings are 20% complete as of 5:00 p.m. today. Χ 7 day work week, no holidays. Determine the completion date for foundation walls. Answer: D R = D O (1-P) D R = 10 (1 0.2) D R = 8 days Footings: March days = March 21 b) Now, assume the following: Χ Today is March 5. Χ Remaining duration and % complete are not linked. Χ Footings are 20% complete, but remaining duration is estimated to be 9 days (as of 5:00 p.m. today) Χ 7 day work week, no holidays. Determine the completion date for foundation walls. Answer: D R = 9 days Footings: March days = March 14 Foundation Walls: March days = March 22 Page
7 4) Options during schedule calculations: Retained Logic vs. Progress Override : The scheduler can adjust settings that affect how the software will perform calculations during the update. One option that students should be made aware of is the progress override vs. retained logic option. 1 This option gives the student choices in how to handle out-of-sequence activities at the time of the update. An example of out-of-sequence activities might include the following: Activity A Activity B The arrow defines the relationship between activities A and B. The software uses relationship information in its calculation of start and completion dates for each activity. In this case, B is a successor to A. That means that B shouldn t begin until A is 100% finished. However, the shaded area tells us some work has actually progressed on B, even though the logic (relationship) dictates that A should be 100% complete prior to B s start. If the student chooses to schedule using retained logic, the software doesn t schedule the remaining duration of B until A is 100% complete. 1 For example, assume the superintendent reports that B has indeed started, and has a remaining duration ( Rem Dur in the graphic below) of 5 days as of the Jan. 4 data date (vertical blue line in graphic below). The resulting update would appear as below: Notice, however, that the remaining duration of 5 days begins after A is 100% complete, not at the data date (vertical blue line). This opens the door for confusion and miscommunication; the software setting ( retained logic ) mandates that the A be complete before it schedules remaining duration for B. This is the default setting for the Privavera software, and it s crucial that students are aware of this. The superintendent has told the scheduler that B has 5 days of remaining duration as of the Jan. 4 data date. It s unlikely that the superintendent is aware of the details of how the software performs calculations; he simply reported that as of today, Jan. 4, B has 5 days more work before it s complete. As such, students must be made aware of this potential problem. Toggling the software setting from Retained Logic to Progress Override can produce updates that are more accurate. When the student chooses progress override the Primavera software ignores network logic and allows the activity to progress without delay. 1 Page
8 Let s examine the above scenario using the progress override setting: The resulting update would appear as: Note now that B has a finish date of Jan 8, instead of Jan 11. Note, too, that the superintendent s estimate of five remaining day duration for B is accurately reflected in the update. Some writers have argued that using the progress override setting means, by definition, that the schedule model is invalid. 5 Nevertheless, the goal we stress to our students is to produce an accurate update of the CPM. Using the retained logic setting does, indeed, preserve the logic and sequencing originally envisioned by the scheduler when the CPM schedule was developed. But few, if any, projects unfold exactly as originally planned; to cling to the original logic at the price of an accurate update is, in our opinion, ill advised. Students need to understand that the original CPM is a model only. Producing an accurate, usable CPM schedule update requires that the scheduler evaluate current conditions on the job, and use this information as a basis for forecasting the time frames for the project s outstanding activities. 5) Revision of network logic and lags between activities: Even if progress override is switched on, the student updating CPM schedules can still run into problems if network logic (relationship between activities) conflicts with actual progress on the job. Many CPM schedulers frown on the practice of revising network logic at any point during the job s progress. 2 However, as the following example will show, results can be confusing if some logic isn t examined and revised during an update. Consider two activities tied via a finish to finish relationship. This logic dictates that activity B can t finish until A is completed: The diagonal slash through B indicates that work on B has started, but isn t yet complete. Page
9 Let s assume the superintendent reports that B started on 31Dec. and has six (6) days remaining duration as of the Jan. 4 data date. Even with progress override switched on, the resulting bar chart will appear as follows: Today is Jan. 4 and the superintendent said B needs six more days to finish. Thus, we d expect B to finish on Jan days = Jan. 10. However, note above that the finish-tofinish constraint prohibits the completion of B until A is done. This means that the software requires that B have eight days of remaining duration (from the Jan 4 data date) instead of the six days reported by the superintendent. Again, the logic contained in the original model has overruled the reports from the field. This problem presents itself clearly in the bar chart above because the blue progress indicator on activity B has extended beyond the Jan. 4 data date. Students should address this problem by breaking (removing) the finish-to-finish logic tie between the two activities. Common sense dictates that current field conditions (the superintendent s estimate that B needs six days to finish) should trump the logic tie that was envisioned when the CPM was developed (perhaps months ago). As of today, (the Jan. 4 data date), the logic tie is now moot. If the tie is broken, the resulting bar chart would appear as follows: This bar chart is a much better reflection of current conditions in the field. Moreover, its appearance is more believable; the blue progress bar for B doesn t extend beyond the Jan. 4 data date. Page
10 Summary: Students and practitioners are often called on to update existing CPM construction schedules using popular application software. While many of the applications are easy to use, care must be taken to ensure an accurate schedule update. Students should examine each and every activity in the schedule that could have been affected since the last update, and they must be aware of the details of the software settings that can affect calculates times for downstream activities. Students should re-examine network logic and activity durations at the time of the update and change them (if project specifications allow) if necessary to better reflect the reality of progress on the job. References: 1) Primavera Systems, Inc., Primavara Project Planner, version. 3.1 Reference Manual (included with software) 2) Korman, Richard, Critics can t find the Logic in Many of Today s CPM Schedules, Engineering News Record Cover Story, May 26, ) Zack, Jack G., Construction Scheduling Games and Ways to Win, Paper presented at the Primavera Users Group, Los Angeles, ) Associated General Contractors of America, Construction Planning & Scheduling, ) McDonald, Donald F., Tripping Hazards in Schedules, Presentation given at the 2002 annual meeting of the American Association of Cost Engineers, Portland, OR Biographical Information: Todd Dunn, P.E., is an Associate Professor in the Civil Engineering Technology program at the Rochester Institute of Technology. Prior to beginning his teaching career in 1992, he worked for three commercial construction contractors spanning eleven years. He worked in Asia for 2½ years on highway projects. He has extensive experience with CPM scheduling, and continues to consult. Page
Scheduling Best Practices
In this article, as part of a continuing series of articles regarding critical path method (CPM) scheduling, Warner reviews various facets of the process of preparing, analyzing and utilizing schedules
Almost everyone in the planning and scheduling profession
PS.02 The Great Negative Lag Debate Mr. Edward E. Douglas III CCC PSP, Mr. Timothy T. Calvey PE PSP, Mr. Donald F. McDonald Jr. PE CCE PSP, and Mr. Ronald M. Winter PSP Almost everyone in the planning
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them
Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
DCMA 14-Point Assessment Metrics
DCMA 14-Point Assessment Metrics The integrity of a CPM schedule is one of the critical factors in improving a project s likelihood of success 1! There is a well-established correlation between the quality,
Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006
Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006 ABSTRACT This paper presents several new ideas that users of CPM software should demand of their software suppliers to increase
Scheduling Best Practices
In a continuing series of articles on specific aspects of critical path method (CPM) scheduling, Warner examines various facets of the process of preparing, analyzing and utilizing schedules in project
Basic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group
Scheduling Best Practices Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group Paul Brough has experience in multiple phases of project management, including
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Brillig Systems Making Projects Successful
Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.
MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016
CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
// Taming an Unruly Schedule Using the 14-Point Schedule Assessment
// Taming an Unruly Schedule Using the 14-Point Schedule Assessment Dr. Dan Patterson, PMP CEO & President, Acumen February 2010 www.projectacumen.com Table of Contents Introduction... 3 The 14-Point Assessment...
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
MS PROJECT FOR CONSTRUCTION SCHEDULERS
MS PROJECT FOR CONSTRUCTION SCHEDULERS Copyright January 25, 2011 by Ron Winter, PSP F. Burak Evrenosoglu, PE CCE PSP Presented at The AACE International 55 th Annual Meeting June 22, 2011 Disneyland Hotel,
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Scott M. Francis, P.E., PSP Table of Contents 1. INTRODUCTION...
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.
Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
5. Creating a Gantt Chart
5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate
CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project
PERCEPTION PERT-PAC Using Microsoft Project 2000
PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Dashboards and Reporting for Program Management
MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
On the Rate of Return and Valuation of Non-Conventional Projects
On the Rate of Return and Valuation of Non-Conventional Projects Carlos Heitor Campani Professor of Finance at COPPEAD Graduate School of Business (Federal University of Rio de Janeiro) Research Associate
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
4 Keys to Driving Results from Project Governance
THOUGHT LEADERSHIP WHITE PAPER In partnership with Agile or Waterfall? 4 Keys to Driving Results from Project Governance You can t swing a project manager these days without hitting the debate of Agile
Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015
Donald R. McNatty, PSP FAACE November 18, 2015 1 Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order to preserve the quality of the audio for all attendees.
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
How to Plan, Design & Implement A Bad Schedule Lessons Learned: The Scheduler as Generalist
How to Plan, Design & Implement A Bad Schedule Lessons Learned: The Scheduler as Generalist North Florida Section Meeting Canaveral Council of Technical Societies Cocoa Beach, FL 20 March 2014 John Orr,
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?
HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans
WorkStream Management Driving Early Project Delivery with Phoenix Project Manager
Phoenix WorkStream Scheduling WorkStream Management Driving Early Project Delivery with Phoenix Project Manager Executive Summary As a team member on any project, you are focused on project delivery: meeting
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. This was one of four innovative practices was described by
The Roles of Functional and Cross-functional Planning in Managing the Enterprise Elliot Chocron Matthew Steigerwald Introduction
The Roles of Functional and Cross-functional Planning in Managing the Enterprise Elliot Chocron Matthew Steigerwald Introduction In 2003, General Motor s GVDP Operations Planning & Scheduling group responded
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
CDR.07. CPM Scheduling and How the Industry Views Its Use
CDR.07 CPM Scheduling and How the Industry Views Its Use Ms. Patricia D. Galloway, PE D elivering a project on time does not just mean signing a contract and hoping that the required completion date will
Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Seon-Gyoo Kim Abstract The construction environment has been changing rapidly over
Insights. Did we spot a black swan? Stochastic modelling in wealth management
Insights Did we spot a black swan? Stochastic modelling in wealth management The use of financial economic models has come under significant scrutiny over the last 12 months in the wake of credit and equity
PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...
CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........
INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT
LECTURE -01 TO PROJECT MANAGEMENT AND MS PROJECT 2 Objective LEARNING OBJECTIVES To learn Project Management Software and their Application to Civil Engineering Books Microsoft Office Project Step by Step
SCHEDULING AND PROJECT MANAGEMENT
SCHEDULING AND PROJECT MANAGEMENT Chapter Survey Scheduling Process Scheduling Methods Scheduling and cash management Who is the Project Manager Project Supervisory Team Project Life Cycle Tracking the
Tracking Project Progress
L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the
Time Off for ADP Workforce Now. Automatic Data Processing, Inc. ES Canada
Time Off for ADP Workforce Now Automatic Data Processing, Inc. ES Canada INSTRUCTOR GUIDE ADP s Trademarks The ADP Logo, ADP, ADP Workforce Now and IN THE BUSINESS OF YOUR SUCCESS are registered trademarks
Engineering and Construction
Engineering and Construction I Manage risk. Protect profit. Today s engineering and construction market is highly competitive, driving profit margins down as risks increase. It only takes one failed project
ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0
ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The
CHAPTER FIVE THE PROJECT SCHEDULE
CHAPTER FIVE THE PROJECT SCHEDULE THE 2012 ULTIMATE PROJECT MANAGEMENT MANUAL HERE S WHAT YOU LL LEARN Primary reasons for scheduling the project Ten characteristics of a good schedule Common scheduling
Planning and Managing Projects with Microsoft Project Professional 2013
Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important
Introduction. http://www.alexsbrown.com/ Page 1
Modeling Tough Scheduling Problems with Project Management Software Alex S. Brown, PMP, Strategic Planning Manager, Mitsui Sumitomo Marine Management (U.S.A.), Inc. Introduction Despite year-over-year
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Linear Schedules for Tunnel Projects
Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear
Scheduling. Getting Started. Scheduling 79
Scheduling 9 Scheduling An event planner has to juggle many workers completing different tasks, some of which must be completed before others can begin. For example, the banquet tables would need to be
Introduction. Book Structure
Fundamentals of Project Management, 4 th Edition Simple Solutions for Busy People By Joseph Heagney (A Book review by R. Max Wideman, FPMI) The views expressed in this article are strictly those of Max
Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
Leaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
Basic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management [email protected] 1 What is Project Management? A set of principles, methods, tools, and
Network Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Project Management Dr. James A. Bednar
Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce
MSP How to guide session 2 (Resources & Cost)
MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or
Lecture 8 (Chapter 11): Project Analysis and Evaluation
Lecture 8 (Chapter 11): Project Analysis and Evaluation Discounted cash flow analysis is a very powerful tool, but it is not easy to use. We have already seen one difficulty: How do we identify the cash
Accounting Basics. (Explanation)
Accounting Basics (Explanation) Your AccountingCoach PRO membership includes lifetime access to all of our materials. Take a quick tour by visiting www.accountingcoach.com/quicktour. Introduction to Accounting
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects
The Inner Workings of Oracle/Primavera P6. by Ron Winter, PSP Fellow of AACE International
The Inner Workings of Oracle/Primavera P6 by Ron Winter, PSP Fellow of AACE International Copyright April 4, 2016 ABSTRACT Oracle Primavera P6 scheduling software is noted for its diverse and extensive
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
HOW TO DESIGN AND IMPLEMENT AN EFFECTIVE PERFORMANCE MANAGEMENT PROGRAM
34 HOW TO DESIGN AND IMPLEMENT AN EFFECTIVE PERFORMANCE MANAGEMENT PROGRAM Kammy Haynes and Warren Bobrow Kammy Haynes, Ph.D. and Warren Bobrow, Ph.D. are principals in The Context Group, a management
Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide
Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Health Check Summary Reports Performance Trend Schedule Trace Schedule Compare Margin Tracker Health Check Indicators Missing Predecessors
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting
IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1
IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break
Oracle Primavera. P6 Resource Leveling Demo Script
Oracle Primavera P6 Resource Leveling Demo Script Script Team Information Role Name Email Primary Author L. Camille Frost [email protected] Contributor Reviewer Geoff Roberts [email protected]
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1 Introduction to Project Management Learning Objectives Describe the importance of creating plans to guide project
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Pharmaceutical forecasts address critical business questions for all
S A L ES & M A R K E TI NG I N SIGHTS Understanding Your Brand s Performance: Creating Robust Forecasts by Integrating Commercial and Clinical Drivers Art Cook, Nisha Gilra and Eric Persoff Pharmaceutical
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Rethinking the Relationship between Subject Line Length and Email Performance: A New Perspective on Subject Line Design
WHITE PAPER JANUARY 2009 Rethinking the Relationship between Subject Line Length and Email Performance: A New Perspective on Subject Line Design Thane Stallings Senior Analytic Consultant Epsilon Strategic
BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses
BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction
Using Fed Funds Futures to Predict a Federal Reserve Rate Hike
JOURNAL OF ECONOMICS AND FINANCE EDUCATION Volume 6 Number 2 Winter 2007 9 Using Fed Funds Futures to Predict a Federal Reserve Rate Hike Terrill R. Keasler and Delbert C. Goff 1 Abstract This paper demonstrates
We never talked directly about the next two questions, but THINK about them they are related to everything we ve talked about during the past week:
ECO 220 Intermediate Microeconomics Professor Mike Rizzo Third COLLECTED Problem Set SOLUTIONS This is an assignment that WILL be collected and graded. Please feel free to talk about the assignment with
APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS
APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS Mary F. McDonald, CQA President/Principal Consultant Individual Solution Options/Quality Services (ISO/QS), Inc. Austin, TX 78739 Tel: (512) 282-0181 E-mail:
1. Interpretation of this Schedule
Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer