INTRODUCTION. Prakash Chandar. S¹, Dhivya Shree. G² ABSTRACT
|
|
|
- Colleen Wilkins
- 10 years ago
- Views:
Transcription
1 International Journal of Emerging Engineering Research and Technology Volume 3, Issue 4, April 2015, PP ISSN (Print) & ISSN (Online) Integrating Building Information Modelling (BIM) and Construction Project Scheduling to Result in 4D Planning for a Construction Project with Relevant Illustrations Prakash Chandar. S¹, Dhivya Shree. G² 1 Asst. Professor, Department of Civil Engineering, S.R.M University, Chennai, India 2 Department of Civil Engineering, S.R.M University, Chennai, India ABSTRACT The present study is to understand about the benefits of 4D Planning to Construction project managers and the Construction industry. Integrating the construction schedule time with 3D modelling components and its parameters will result in 4D planning methodology. Earlier studies on 4D planning have proved to be useful for On-time delivery of the project. In turn the Construction manager is exempted from loses caused due to delay in project delivery. Here, the study involves the reanalysis of a project completed in traditional planning method and the same project is demonstrated in 4D planning method. All discrepancies of the executed project are determined and the same can be avoided while following 4D planning technique. Keywords: 4D Planning, 3D Modelling, Construction Manager, On-time delivery, Project Delivery. INTRODUCTION Indian Construction sector is yet to understand the advantages and benefits of 4D planning techniques. Only 10% of the construction projects are planned according to 4D planning methods and techniques. Rest 90% of the projects is still visualized based on 2D design documents with the additional aid of 3D modelling. This is interpreted as Building Information Modelling (BIM) which is primarily a three dimensional digital representation of a building and its intrinsic characteristics. Since the time schedule defines sequences of activities and allocates resources such as material and labor, it plays an important role in optimizing and managing a construction project. A 4D model is presented to define the order in which the segments should be constructed or demolished. The result of this step is a sequence which will be used as the process chain for simulation techniques. Then, a probabilistic 4D model is introduced by linking the 3D model of the project with generated probabilistic schedules from suitable scheduling software. Then a 4D simulation is created in suitable software which lists the sequence of works to be carried out in a date wise manner. The simulation model determines the idleness of resources and locates any potential bottlenecks. To achieve this, the developed simulation model should reflect the real world system. Live Project Details Builder: Sri Jyothi Builders Location: Urappakkam, Chennai, Tamil Nadu, India Plot Area: 1860 ft² (172.7 m²) Total Built-up Area: 4600 ft² (427 m²) *Address for correspondence: [email protected] International Journal of Emerging Engineering Research and Technology V3 I4 April
2 Project Status: Completed Total Project Value: 1.1 Cr Planned Project Duration: 1 year Planned Start: Sept 2012 Planned Finish: Sept 2013 Actual Finish: Dec 2013 Planned Construction cost: 60 Lakhs Actual Construction cost: 68 Lakhs 4D PLANNING AND SIMULATION PROCESS Based on the fundamental attributes required by 4D models the software selection may vary depending on construction project planning practice. As per the requirements of the research on 4D planning, the conventional 2D drawings are prepared in Autocad The 2D drawings are converted into 3D model in Revit Architecture 2014 and the Time Scheduling is done in Microsoft Office project Both the 3D model and the scheduling are integrated in Naviswork Manage 2014 for creating the 4D simulation. Further the features in Naviswork Manage 2014 enable us to do Material Management and Elemental Clash Detection of the project effectively. The figure1 shows the process of 4D simulation in a schematic representation. 2D Drawings in Autocad Figure1. Schematic representation of 4D Simulation process The Figure 2 shows the typical floor plan of the Ground, First and Second floor of the project. The areas respectively are Ground Floor ft² ( m²), First & Second Floor ft² ( m²) each. The 2D drawings form the basis for the development of the 3D model in Revit Architecture. The 2D drawings from Autocad can be exported to any desired 3D modelling software which supports Dwg. Format. The estimated quantities are based on the 2D drawings provided by the builder. 68 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015
3 Scheduling in MS Project Office Figure2. Typical Floor Plan of Ground, First & Second Floor On the basis of the information and details provided by the Construction Manager of the building, a MS Schedule is created according to the duration planned by the Builder which is shown in the figure 3. Figure3. As planned MS Project Schedule for the project Due to improper planning and scheduling the project was delayed by 3 months beyond the planned finish date. International Journal of Emerging Engineering Research and Technology V3 I4 April
4 A few of the issues faced during the execution which led to delay are described below: Conflict 1: Shortage of labor at Ground Floor roof slab. Conflict 2: Procurement of Material delayed during First floor. Conflict 3: Shortage of labor during First Floor roof slab. Conflict 4: Shortage of labor at Second floor wall plastering. Conflict 5: Procurement of flooring tiles delayed at First floor. Conflict 6: Delay in connection from Electricity Board. Conflict 7: Accidental collapse of scaffolding of Exterior Wall. Conflict 8: Delay due to lack of uniformity in Bathroom wall tiles. Table1. Shortage of Labour Conflict 1, 3 & 4 Work Description Laying Rebar for GF roof slab & beam Pouring concrete and Compacting for FF roof slab & beam Plastering SF walls Work Area 923 ft² (85.7 m²) 1666 ft² (154.7 m²) 5812 ft² (540 m²) No. of Labors 2 Bar benders 4 Masons 5 Masons required/day Total Working Days No. of Labors 1 Bar bender 2 Masons 3 Masons employed/ day No. of days Extended Planned Start 28/02/13 09/04/13 06/08/13 Planned finish 01/03/13 10/04/13 19/08/13 Actual Start 08/04/13 20/05/13 18/09/13 Actual Finish 11/04/13 23/05/13 09/10/13 Table2. Delay in Material Procurement- Conflict 2 & 5 Material Description(First Floor) Cement Fine Aggregate Coarse Aggregate MS Rod Vitrified Tiles- Flooring Quantity Units Bags ft³ ft³ Tons ft² Material Planned Order 06/05/13 06/05/13 06/05/13 06/05/13 20/08/13 Date Material Planned Delivery 14/05/13 14/05/13 14/05/13 14/05/13 09/09/13 Date Material Actual Order Date 14/06/13 14/06/13 14/06/13 14/06/13 10/10/13 Material Actual Delivery 04/07/13 04/07/13 04/07/13 04/07/13 13/11/13 Date No. of Days Delayed Table3. Delay Due to External Agent Conflict 6 Description Electricity Board Connection Planned Start 07/06/13 Planned Finish 17/06/13 Actual Start 22/07/13 Actual Finish 20/08/13 No. of Days Delayed 15 Days Table4. Accidental Delay Conflict 7 Work Description Exterior Wall Painting Planned Start 01/08/13 Planned Finish 28/08/13 Actual Start 13/09/13 Actual Finish 24/10/13 No. of Days Delayed 10 Days Cause of Delay Mishap of Scaffolding 70 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015
5 Table5. Delay Due to Material Replacement Conflict 8 Material Description Ceramic Bathroom Tiles Quantity 2000 ft² (186 m²) Quantity to be replaced 600 ft² (55.7 m²) Duration for Replacement 14 Days Cause of Replacement Non-Uniformity in colour of tiles Planned Start 19/06/13 Planned Finish 27/06/13 Actual Start 30/07/13 Actual finish 27/08/13 Due to the above conflicts the Project was delivered on December 2013 instead of September 2013.The Actual Schedule of the project is re-scheduled according to the delays occurred during the execution of the project as shown in the Figure 4. These problems could have been avoided by the using the 4D Planning Technique. 3D Modelling in Revit Architecture Figure4. Actual MS Project Schedule for the project The modelling process in Revit involves a sequence of stages in which each are going to be linked to the corresponding task in the MS Schedule by Naviswork Manage. The figure 5 shows the stage wise 3D modelling of the project. Figure5. Showing the Sequential Development of 3D Model in Revit Architecture International Journal of Emerging Engineering Research and Technology V3 I4 April
6 4D Simulation 4D simulation involves the step by step construction animation of the building tasks. Here, the work task from MS project office is linked to its corresponding building components. For example, the task of Laying Ground floor slab in schedule is linked or attached to its corresponding 3D slab element in the model. This integrating work of schedule and the 3D model is carried out in Naviswork Manage Figure6. 4D Simulation on day - 14/04/2013 Once all the tasks from the schedule are linked to their corresponding 3D elements, the 4D simulation can be viewed. The simulation shows the progress of tasks taking place on a Day-to-Day basis. Planning of the labor and resources can be done for any particular element of the building by simply scrolling down to a particular date in the course of construction in the simulation. The figure 6 shows the building elements which are planned to be executed as on date in green color which is differentiated from rest of the building. A video of the simulation from the start to the finish date can be exported to give a demo of the project to the client. Labor Management by Naviswork Manage The Timeliner feature of the Naviswork Manage software enables you to view the work tasks of the schedule along with the visual of the 3D model. Before executing any particular work task the required amount of Labor and Resources associated with the task is determined from the schedule. This feature of Naviswork enables to visualize the task and pre-plan the requirements without any error. This feature appears in Naviswork as shown in the figure 7. Figure7. Showing the Timeliner Bar along with the 3D model of the Building 72 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015
7 Material Management by Naviswork Manage Naviswork helps to manage procurement of materials efficiently at the start of every level of the building without any delay. During the 3D modelling process in Revit Architecture, extra parameters can be added to the 3D elements such as Material Order Date, Material Order status, Material Delivery Date, Material Delivery Status & Material Location under desired property section. As the construction progresses, the dates or values can be manually entered in the above parameters. Revit enables to create a schedule automatically as the values or dates are entered in the property section. The figure 8 shows the schedule created by Revit with property box showing the values entered for the parameters under construction sub-division. The schedule can be exported to excel if desired. Figure8. Showing the dates in Revit property section and its Schedule Naviswork Manage synchronizes with Revit at every stage of construction as the dates and values are entered in Revit to manage the material procurement. Naviswork creates a separate selection set for the parameters like Material Order Date, Material Order status, Material Delivery Date, Material Delivery Status & Material Location and its corresponding dates and values such as Material Order status- Not Ordered, Material Delivery status Not Delivered. And on selecting a particular selection set, Naviswork high lightens the selection in the 3D visual screen. The figure 9 shows the Material Order Date for First Floor which is to be ordered on 24/04/13. Figure9. Showing the Selction set Material Order Date 24/04/13 International Journal of Emerging Engineering Research and Technology V3 I4 April
8 RESULTS AND ANALYSIS The completed project is demonstrated in 4D technique and each stage of construction is considered for investigation. Primarily, a MS project schedule was created according to the planned duration of the builder. The delay of schedule in each work task is computed with area, quantity and is shown in the tables above. Another MS project schedule is created to show the actual work schedule with the delay. The reason for the delay is found to be Lack of planning and communication between the designing and execution team. By the use of 4D technique, the changes in documentation can be updated in simulation from time-totime. This keeps the site personal informed of the changes done in the schedule and take appropriate action for the work task. Further, the simulation helps to visualize the construction tasks in a better way. CONCLUSION This research proposed a simulation-based 4D modelling approach for planning and scheduling of Residential projects by integrating simulation and 4D modelling techniques. This research investigated the applications of 4D modelling for sequence assessment in the planning stage of Residential projects. This research investigated a new approach integrating simulation with 4D modelling to create a probabilistic 4D model. This approach can be a useful system to avoid delay in project delivery and hence can also avoid loses incurring due to the delay. REFERENCES [1] Jan Tulke and Jochen Hanff, 4D Construction sequence planning New process and data model, Bauhuas University, Germany. [2] Anamika Sharma, An Interactive Visual Approach to Construction Project Scheduling, Marquette University, [3] Lingyun Wang, Using 4D Modeling To Advance Construction Visualization In Engineering Education, CIC, Pennstate, May [4] Peter Smith, BIM & Project Cost Manager, ICEC, University of Technology Sydney, Australia, [5] Mohamad Kassem, Trevor Brogden, and Nashwan Dawood, BIM and 4D planning: a holistic study of the barriers and drivers to widespread adoption, JCEPM, November 14, [6] Satish A. Pitake and Prof. Dhananjay S. Patil, Visualization of Construction Progress by 4D Modeling Application, IJETT, Volume 4 Issue 7, july [7] Ahmad Doriani, Simulation-Based 4D Modeling for Planning and Scheduling of Elevated Urban Highway Reconstruction Projects, Concordia University, Canada, International Journal of Emerging Engineering Research and Technology V3 I4 April 2015
Automated Micro-Planning and Real-time Tracking of Precast Building Components
Automated Micro-Planning and Real-time Tracking of Precast Building Components A B S T R A C T Ms Rohini Prabhugaonker, ME-II, Construction & Management, D.Y Patil College of Engineering, Akurdi Prof.
General Comparison between 4D Software
General Comparison between 4D Software (Navisworks, Synchro professional, Vico control, itwo and Navigator) Comparison between 4D Software 4D BIM is the next generation of project management, including
Certified Instructors & Curriculum
Our Promise. TPM is dedicated to provide the most extensive and high-quality training programs to help you maximize your investment. Although the investment in time and money may seem substantial, it will
Application of MS Project Software for Time and Cost Management in Real Estate Construction
Application of MS Project Software for Time and Cost Management in Real Estate Construction Rohit Satish Gayawal M.B.A in Project & Construction Management, Swami Vivekananda Subharti Unversity, Meerut
Efficient Planning Scheduling And Delay Analysis Of Residential Project
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 3 Ver. I (May. - Jun. 2015), PP 126-133 www.iosrjournals.org Efficient Planning Scheduling
Cash Flow of High Rise Residential Building
Cash Flow of High Rise Residential Building Dipti R. Shetye 1, Dr. S.S.Pimplikar 2 1 Scholar, Civil Department, M.I.T Pune 2 H.O.D, Civil Department, M.I.T Pune E-mail- [email protected] ABSTRACT-
MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT 2009. Timo Hartmann [email protected]
Technical Paper #5 MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT 2009 Timo Hartmann [email protected] COPYRIGHT 2009 VISICO Center, University of Twente [email protected] Integrated
Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering
Building Information Modelling (BIM); How it Improves Building Performance R.P. Kumanayake Lecturer, Department of Civil Engineering R.M.P.S. Bandara Lecturer, Department of Mechanical Engineering Faculty
Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design
Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design Florian Aalami CEO ADAPT Corporation [email protected] What is BIM? The ability to model
A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY
ISTANBUL TECHNICAL UNIVERSITY FACULTY OF ARCHITECTURE DEPARTMENT OF DESIGN COMPUTING BIM 2037 / BUILDING INFORMATION MODELS INSTRUCTOR: Salih OFLUOĞLU A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL
Resource Scheduling of Construction Project: Case Study
Resource Scheduling of Construction Project: Case Study Rhuta Joshi 1, Prof. V. Z. Patil 2 1 Post Graduation Student of Construction and Management in Civil Engineering Department, BSCOER, Narhe, Pune,
Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects
Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects Ar. A. Cindrela Devi and K. Ananthanarayanan Abstract Resource continuity is a key issue for Mass housing construction
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the
PS.12. 4D Scheduling A Case Study
PS.12 4D Scheduling A Case Study Mr. Abhimanyu Basu PE PSP A 4D schedule is a 3 dimensional CAD model How long would it take. attached to the fourth dimension of time via a schedule. The concept of 4D
Tesla Outsourcing Services An Architectural & Engineering Company
Tesla Outsourcing Services An Architectural & Engineering Company Offices Our Spread USA UK Office India Office Canada Office Australia Office JBH-Tesla Design Group, Inc. 100 Executive Boulevard-Suite
Olilo's AEC Design Services. SrinSoft Inc, Partners of
Olilo's AEC Design Services SrinSoft Inc, Partners of Olilo provides design services that include design and analysis, cost estimation, 3D modeling, 2D drafting, conversion from 2D to 2D, quantity take-off,
MULTI-RESIDENTIAL BUILDING SOLUTIONS
MULTI-RESIDENTIAL BUILDING SOLUTIONS OUR EXPERTISE AT YOUR SERVICE Canam has been offering owners, real estate developers, architects, engineers and contractors an array of construction solutions since
Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,
Volume, Special Issue, ICSTSD Behaviour of Steel Bracing as a Global Retrofitting Technique Miss S. S. Nibhorkar M. E (Structure) Scholar, Civil Engineering Department, G. H. Raisoni College of Engineering
BIM: FOR PROJECT MANAGERS. 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am
BIM: FOR PROJECT MANAGERS ANA BAKER BRANDON GARRETT 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am 1 2 3 4 BIM Overview BIM Level of Development Evolution of the Drawing Process BIM Workflow
AC 2011-96: IMPLEMENTING BUILDING INFORMATION MODELING IN CONSTRUCTION ENGINEERING CURRICULA
AC 2011-96: IMPLEMENTING BUILDING INFORMATION MODELING IN CONSTRUCTION ENGINEERING CURRICULA Don Chen, University of North Carolina, Charlotte Professional Preparation Iowa State University, Ames, Iowa
Synergy: Building Information Modeling and
: Building Information Modeling and Assoc. Professor Rafael Sacks BIM Handbook Symposium Georgia Tech Atlanta, GA, 13 th March 2008 Introduction Both and BIM are deep process changes, in thinking and in
Mortenson Construction Virtual Mockups A Collaborative Solution
San Diego, CA February 10, 2011 Mortenson Construction Virtual Mockups A Collaborative Solution Rick Khan, LEED AP Senior Integrated Construction Manager Building what s next. Mortenson Construction Family
ENGINEERING AND TECHNOLOGY DEPARTMENT
ENGINEERING AND TECHNOLOGY DEPARTMENT Engineering and Technology Education focuses on technological knowledge and competence. It is designed to help students understand and to participate in the technological
C-2 Construction, Inc. - NAICS Codes
C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining
Abstract: BIM: A Technological Advancement in the Field of Architecture. Introduction:
BIM: A Technological Advancement in the Field of Architecture Abstract: BIM (Building Information Modeling), an innovative parametric software has seen widespread use in architecture design firms worldwide.
ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY
ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY HOWARD COUNTY MARYLAND ARCHITECTURAL DESIGN ACADEMY Architectural Design 1 Introduction / Overview of Course This course will introduce the basic principles
Prof. A. Ray Chaudhuri Department of Civil Engineering Adama Science and Technology University (ASTU), Adama, Ethiopia. E-mail I.D: amroyc@gmail.
Management in Construction Projects a case study SK. Nagaraju Lecturer, Department of Civil Engineering Adama Science and Technology University (ASTU), E-mail I.D: [email protected] B. Sivakonda
An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction
1666 An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction Hexu LIU 1, Zhen LEI 2, Hong Xian LI 3, Mohamed AL-HUSSEIN 4 1 Hole School of Construction
CAREER LYNX Constructing Careers in Architecture
Students will understand the job description, skills, and education of various Architecture and Planning related jobs. Students will use the newspaper to make inferences about the role of various professionals
ESTIMATION AND PLANNING TOOL FOR INDUSTRIAL CONSTRUCTION SCAFFOLDING. *C. Kumar, S. M. AbouRizk, and Y. Mohamed
ESTIMATION AND PLANNING TOOL FOR INDUSTRIAL CONSTRUCTION SCAFFOLDING *C. Kumar, S. M. AbouRizk, and Y. Mohamed Department of Civil and Environmental Engineering University of Alberta Edmonton, AB, Canada,
Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE
Autodesk Revit LEARNING PATH FUNDAMENTALS Duration: 3 days Cost: R5 500 (excl VAT) Revit MEP Duration: 3 days Cost: R5 500 (excl VAT) Revit Structure Duration: 3 days Cost: R5 500 (excl VAT) REVIT ADVANCED
Coordinating and Sharing Information with Revit Architecture and Revit Structure Best Practices!
Revit Architecture and Revit Structure Best Practices! Erleen Hatfield Thornton-Tomasetti Uk Jung SE304-1 This class identifies best practices using Revit Architecture and Revit Structure for sharing and
Get to know your Autodesk Design and Creation Suites 2014
Get to know your Design and Creation Suites 2014 Design and Creation Suites 2014 offer more tools and cloud services so you can take advantage of smoother workflows, better access to project information,
PREPLANNING METHOD FOR MULTI-STORY BUILDING CONSTRUCTION USING LINE OF BALANCE
PREPLANNING METHOD FOR MULTI-STORY BUILDING CONSTRUCTION USING LINE OF BALANCE Ricardo Mendes Jr. 1 and Luiz Fernando M. Heineck 2 ABSTRACT This paper reports one aspect of a research program devoted to
Virtual Reality Applications in Project Management Scheduling
71 Virtual Reality Applications in Project Management Scheduling Wael A. Abdelhameed University of Bahrain, [email protected] ABSTRACT This study concentrates on management of construction projects
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.
Revit MEP. Autodesk Navisworks
What is BIM? Autodesk BIM is an intelligent model-based process that helps owners and service providers achieve business results by enabling more accurate, accessible, and actionable insight throughout
NSW Payroll Tax Information for Contractors and Employment Agents
NSW Payroll Tax Information for Contractors and Employment Agents Deemed employees If a relevant contract or employment agency contract is not exempt, the hiring business or employment agency is deemed
Streamline your design-to-cost processes with Autodesk Navisworks
Quantification in Autodesk Navisworks 2015 Streamline your design-to-cost processes with Autodesk Navisworks Contents Overcome data disarray....................................................................................
Canterbury Skill Shortage List
Canterbury Skill Shortage List This is the revised Canterbury Skill Shortage List (CSSL), effective from 14 February 2014. Occupational group Occupation and ANZSCO number Required standard for work visa
LECTURE 10. Resource Allocation and Resource Leveling
LECTURE 10 Resource Allocation and Resource Leveling OUTLINE Review Lecture 9 Introduction The Three Categories Of Resources What Is Resource Allocation? What Is Resource Leveling? Why Level Resources?
AUTOMATED PROJECT SCHEDULE AND INVENTORY MONITORING USING RFID
24th International Symposium on on Automation & Robotics in in Construction (ISARC 2007) Construction Automation Group, I.I.T. Madras AUTOMATED PROJECT SCHEDULE AND INVENTORY MONITORING USING RFID Geetha
Fame Design Ltd (10295) Plot # A-115/116,BSCIC Hosiery I/A, Narayangonj, Bangladesh (+ 23.623412, +90.478442) 18.June.2014
Fame Design Ltd (10295) Plot # A-115/116,BSCIC Hosiery I/A, Narayangonj, Bangladesh (+ 23.623412, +90.478442) 18.June.2014 Identified Priority 1 Concerns 1 st Priority 1 Concern This column was checked.
SRISHTI TECHNICAL SERVICES L.L.C
SRISHTI TECHNICAL SERVICES L.L.C Coming under SRISHTI Group. is a team of experienced and qualified skilled specialists that provide expertise in Interior fit outs & BIM along with having a full qualified
NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE)
NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE) If your home or business is located within a 100-year floodplain and it was constructed through a County Building
A BIM Case Study: SELCEN Mimarlik
A BIM Case Study: SELCEN Mimarlik Final Submission 19 January 2012 Yekta Ipek 523101013 MBL607E::Building Information Models Instructor: Salih Ofluoglu Istanbul 2012 Building Information Models Final Submission
Building Information Modeling Based Time And Cost Planning In Construction Projects
Building Information Modeling Based Time And Cost Planning In Construction Projects Zoran Pučko University of Maribor, Faculty of Civil Engineering, Slovenia [email protected] Nataša Šuman University of
APPLICATIONS OF GIS IN INFRASTRUCTURE PROJECT MANAGEMENT
Int. J. Struct. & Civil Engg. Res. 2013 Sandip N Palve, 2013 Research Paper ISSN 2319 6009 www.ijscer.com Vol. 2, No. 4, November 2013 2013 IJSCER. All Rights Reserved APPLICATIONS OF GIS IN INFRASTRUCTURE
WESTERN MICHIGAN UNIVERSITY
WESTERN MICHIGAN UNIVERSITY Facilities Management Department DeVon Miller Building Commissioning Administrator 1 INTRODUCTION DeVon C. Miller, CPMP, LEED AP Building Commissioning Administrator Engineering
Technique (LOBST) for a Real estate sector
Journal Paper: Application of Line of Balance Scheduling Technique (LOBST) for a Real estate sector Authors: 1. Prof: Siddesh K Pai Assistant professor National Institute of construction Management & Research(NICMAR)
Technical Assignment 2
Architectural Engineering 2012 Senior Thesis -+ + Technical Assignment 2 Reston Station Phase 1 Garage Reston, VA Jonathan A Fisher Oct. 12, 2012 A d v i s o r : D r. R o b e r t L e i c h t Executive
Collaborating Across Disciplines with Revit Architecture, MEP, and Structure
Collaborating Across Disciplines with Revit Architecture, MEP, and Structure David Cohn AB104-3 Are you ready to take the next step and use building information modeling to share data across the entire
Canterbury Skill Shortage List
Canterbury Skill Shortage List This is the revised Canterbury Skill Shortage List, effective from 9 May 2016 Occupational Group Occupation and ANZSCO number Required standard for work visa applicants with
BIM and API Extensions
REVIT BUILDING INFORMATION MODELING BIM and API Extensions This whitepaper explains how the utility of BIM solutions such as Revit Structure software can be broadened through the use of specialized software
Scope of Building Information Modeling (BIM) in India
Journal of Engineering Science and Technology Review 2 (1) (2009) 165-169 Research Article JOURNAL OF Engineering Science and Technology Review www.jestr.org Scope of Building Information Modeling (BIM)
CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours)
CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours) Lecture Meets in 154 Baker Hall, Monday, Wednesday, and Fridays 9:30-10:25 AM Instructor Paul Crovella 219
BIM Extension into Later Stages of Project Life Cycle
BIM Extension into Later Stages of Project Life Cycle Pavan Meadati, Ph.D. Southern Polytechnic State University Marietta, Georgia This paper discusses the process for extending the implementation of the
HOW TO LINK AND PRESENT A 4D MODEL USING NAVISWORKS. Timo Hartmann [email protected]
Technical Paper #1 HOW TO LINK AND PRESENT A 4D MODEL USING NAVISWORKS Timo Hartmann [email protected] COPYRIGHT 2009 VISICO Center, University of Twente [email protected] How to link and present
reality Revit check Autodesk have long Identify possible Utilize structural Tool Works Building bcg.com
Autodesk Revit reality check for residential construction: Scott Babin Illinois Tool Works, Building Components Group AB6105-V Using Autodesk Revit for architectural and structural design in the residential
Notice to Property Owners
Modification or Repair of your Flood Prone Property Notice to Property Owners Rebuilding or Remodeling Your Home If your home or business sustained damage, or if you are making improvements to the structure
CHECKLIST FOR SUBMISSION Construction Productivity Awards - Projects 2015
CHECKLIST FOR SUBMISSION Construction Productivity Awards - Projects 2015 PROJECT NAME: - Please check by ticking: - The following list of printed documents is enclosed: Nomination Form, duly completed
D Sample Notices to Property Owners, Sample Affidavits, and Other Material
D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully
Professional CAD System
Professional CAD System > ARCHITECTS site plans > BUILDERS > RESIDENTIAL DESIGNERS floor plans elevations 3D models details sigma design BuildersCAD Complete System Only $ 995 Professional CAD System High
SCHEDULING AND PROJECT MANAGEMENT
SCHEDULING AND PROJECT MANAGEMENT Chapter Survey Scheduling Process Scheduling Methods Scheduling and cash management Who is the Project Manager Project Supervisory Team Project Life Cycle Tracking the
Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.
Planning & Scheduling CSTM 462 Managing a project through time and resources. The need for proper planning and scheduling. Project Management Objectives 1. Eliminate or reduce project RISK. 2. Obtain a
BECKHAM Bending the Curve
BECKHAM Bending the Curve Bending the Cost Curve like Beckham: Trends in Housing and Construction Costs Speakers Andrew Jakabovics, Enterprise Community Partners Sharon Dworkin Bell, National Association
ARCHITECTURAL TECHNICIAN PROGRAM (T132)
ARCHITECTURAL TECHNICIAN PROGRAM (T132) PROGRAM NAME COURSE CODE SCHOOL CENTRE LOCATION DURATION Architectural Technician T132 Construction Engineering Technology Casa Loma Campus 2 years (4 semesters)
NEW APPLICATIONS OF LINE OF BALANCE ON SCHEDULING OF MULTI-STOREY BUILDINGS
NEW APPLICATIONS OF LINE OF BALANCE ON SCHEDULING OF MULTI-STOREY BUILDINGS Ricardo Mendes Jr 1., Luiz Fernando, M. Heineck and Oscar L. Vaca Dep. de Engenharia de Produção e Sistemas, Laboratório de Gerenciamento
BIM and Project Planning
REVIT BUILDING INFORMATION MODELING BIM and Project Planning This white paper explores how the Revit building information model (BIM) can be linked with project planning systems to enable 4D construction
How To Understand The Design Process
The decision-making process in the design of residential structures Randa Ghattas Jeremy Gregory T. Reed Miller Randolph Kirchain March 215 cshub.mit.edu TABLE OF CONTENTS EXECUTIVE SUMMARY... 2 1 INTRODUCTION...
SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER
NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below
PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE
Sl.No. PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE Description of item Qty Unit Rate Amount 1 Demolishing tile work/cement concrete/( carefully taking out the closet and other
L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.
L_All_Vocatinal_Ed_Construction Sector: Construction Sr. No Specialisation Page No 1 Construction and Building Technology 02 1 P a g e 2 P a g e VOCATIONAL EDUCATIONAL QUALIFICATION FRAMEWORK (Sector -
Analysis II Façade Redesign: Architectural Precast Panels
Analysis II Façade Redesign: Architectural Precast Panels Analysis II Façade Redesign: Architectural Precast Panels Overview: This analysis covers the comparison of the current EIFS façade and my proposed
Outlook for the construction industry. Part One: BETA monitoring report Joinery ITO August 2013
Outlook for the construction industry Part One: BETA monitoring report Joinery ITO August 2013 Outlook for the construction industry August 2013 1 Table of contents ECONOMIC AND CONSTRUCTION OUTLOOK SUMMARY...
Revit and BIM for Facilities Management
Revit and BIM for Facilities Management Course Length: 1 day Revit and BIM for Facilities Management is a one day hands-on workshop that will introduce you to what Building Information Modeling is and
A Guide to... Home Renovation Incentive (HRI)
A Guide to... Home Renovation Incentive (HRI) About this guide This guide will tell you what you need to know if you are organising to have construction work done on your house and would like to avail
Performance by design. Autodesk Revit MEP
Performance by design. Autodesk Revit MEP Step up to the challenge. Autodesk Revit MEP software helps mechanical, electrical, and plumbing engineering firms meet the heightened demands of today s global
INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2
INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2 Hyun Cho 1, Ki Hwan Lee 1, Song Hyon Lee 1, Ta Lee 1, Hyun Jun Cho 1, Sung Hoon Kim 2 and
APPLICATION OF PROJECT MONITORING TOOLS FROM OWNER S PERSPECTIVE
Volume.02, Issue. 06, June 2014 ISSN (online): 2348 7550 APPLICATION OF PROJECT MONITORING TOOLS FROM OWNER S PERSPECTIVE 1 Dr. V. M. Topkar, 2 Pise Akshay H. 1,2 Civil and Environmental Engineering Department,
EMPLOYMENT APPLICATION
EMPLOYMENT APPLICATION Please fill out all information as completely and accurately as possible. If you re receiving this application through email, you may have to save this application to your computer,
Construction Technology COURSE OUTLINE
Technology COURSE OUTLINE 1. Course Title: Technology 2. CBEDS Title: Introduction to 3. CBEDS Number: 5501 4. Job Titles: Carpenters Concrete Laborers Managers Drywall installers Electricians Roofers
The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma
The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma Bart B. Barrett, B.S., P.E.1 Kerry S. Lee, M.B.A., P.E., M. ASCE2 Erik L. Nelson, Ph.D., P.E., M. ASCE3
Historic Preservation Tax Incentive Program General information and instructions for applying for a historic tax exemption
Historic Preservation Tax Incentive Program General information and instructions for applying for a historic tax exemption Page 1 of 8 There are Incentives Available for Rehabilitating Historic Structures!
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
Chapter. Restoration of Damaged Structures
5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.
Proceedings of Meetings on Acoustics
Proceedings of Meetings on Acoustics Volume 19, 2013 http://acousticalsociety.org/ ICA 2013 Montreal Montreal, Canada 2-7 June 2013 Architectural Acoustics Session 5aAAa: Room Acoustics Computer Simulation
STATE OF MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY 443 Lafayette Road North St. Paul, Minnesota 55155-4344 (651) 284-5065 or 1-800-DIAL-DLI
STATE OF MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY 443 Lafayette Road North St. Paul, Minnesota 55155-4344 (651) 284-5065 or 1-800-DIAL-DLI MINNESOTA RESIDENTIAL BUILDING CONTRACTOR AND RESIDENTIAL REMODELER
Ontology-Based Semantic Modeling of Safety Management Knowledge
2254 Ontology-Based Semantic Modeling of Safety Management Knowledge Sijie Zhang 1, Frank Boukamp 2 and Jochen Teizer 3 1 Ph.D. Candidate, School of Civil and Environmental Engineering, Georgia Institute
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY By Mohammad A. Ammar 1 and Emad Elbeltagi 2 ABSTRACT: Scheduling of construction projects that have multiple units, wherein activities
PROJECT COST ESTIMATES & FEASIBILITIES
PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed
Estimator: Miami Estimates Business: (305) 395-4362. Date Entered: 04/30/2008
Insured: Property: Claim Rep.: Business: Estimator: Miami Estimates Business: (305) 395-4362 Claim Number Policy Number Type of Loss Deductible Dates: Date of Loss: 10/24/2005 Dwelling $0.00 Other structures
Automated construction schedule creation using project information model
Automated construction schedule creation using project information model Aleš Mrkela Faculty of civil engineering, University of Maribor, Maribor, Slovenia Danijel Rebolj Faculty of civil engineering,
Building Information Modeling for Masonry (BIM-M)
Building Information Modeling for Masonry (BIM-M) Charles Clark, AIA, PE, LEED AP BD+C Vice President Engineering Services Acknowledgements Much of the information and images in this presentation are from
Exploring Ferrocement
2008 Exploring Ferrocement Exploring Ferrocement Ferrocement Workshop 2008 School of Planning and Architecture 2 Exploring Ferrocement Ferrocement Workshop 18 th 19 th December 2008 conducted by Dr. Anupama
C I T Y O F P E A R S A L L
The Largest City Between San Antonio and Laredo COMMUNITY DEVELOPMENT C I T Y O F P E A R S A L L A Business-Friendly, Family-Oriented Community Building Department Application Information (Please read
Design. Design. Certificates. Contact Information. Full-Time Faculty. Associate Degrees. Associate in Arts Degrees. Certificate of Achievement
Design Associate in Arts Degrees Architectural Design Computer-Aided Drafting Computer-Aided Drafting and Design Mechanical Design Students may earn one of the above-named associate degrees by completing