Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010

Similar documents
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

SECTION COST LOADED CRITICAL PATH SCHEDULE

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

EXHIBIT 2-2-C PROGRESS SCHEDULES

MODEL SCHEDULING SPECIFICATION

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

Spec. Standard: 11/27/ Revision: 11/27/06

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Applied Project Management ( APM )

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised )

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

CPM Scheduling with Primavera Unifier

OVERVIEW. Microsoft Project terms and definitions

CRITICAL PATH METHOD (CPM) SCHEDULES

SECTION PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

Design Consultant Project Management Requirements

Table 2-1: Elements of the Project Management Plan

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

technical tips and tricks

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision

California Department Of Transportation. Class # G0C094

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS

1. Interpretation of this Schedule

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction Why Do We Need Schedules?...

SCHEDULE AND BUDGETING

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

WORK PROGRAM GUIDELINES

P6 Analytics Reference Manual

SECTION CONSTRUCTION SCHEDULE B. Part 1 - General Work Included Related Requirements Reference Standards...

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS

ECDL / ICDL Project Planning Project Management Software Level 2. Syllabus Version 1.0 (UK)

Linear Schedules for Tunnel Projects

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B

Collaborative Scheduling using the CPM Method

Construction Project Scheduling: Keys to Success

Review of Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)

CIMS Information Systems Used to Manage Capital Projects. Samuel Hutchins September 14, 2010

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Earned Value Analysis Exercise

ECDL / ICDL Project Planning Syllabus Version 1.0

Scheduling Document Creation

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

5. Creating a Gantt Chart

<PROJECT NAME> PROJECT MANAGEMENT PLAN

Cash flow is the life line of a business. Many start-up

IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)

DCMA 14-Point Assessment Metrics

Project Management Fact Sheet:

PRINCE2 PLANNING AND CONTROL USING MICROSOFT PROJECT UPDATED FOR MICROSOFT OFFICE PROJECT 2007 PAUL EASTWOOD HARRIS

MS PROJECT FOR CONSTRUCTION SCHEDULERS

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Oracle Primavera. P6 Resource Leveling Demo Script

How To Use P6 For A Project Scheduling System

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)

Plug IT In 5 Project management

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

Contract / Construction Management. November 2006

Learn how to create web enabled (browser) forms in InfoPath 2013 and publish them in SharePoint InfoPath 2013 Web Enabled (Browser) forms

Producing a programme under the NEC form of contract

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 COST MANAGEMENT WITH EXPENSES

The Amazing History of Primavera Software

Session: Tue 1110 to How to Cost Load a schedule. OR Understanding the SDEF

Project Time Management

Demonstrate and apply knowledge of project management in

Oracle Primavera Program Management Information System (PMIS) Solutions for Transportation Programs November, 2011

Primavera Unifier v9.14 / 2014 EPPM Day Hands On Session Exercise Document

Construction Management Standards of Practice

Mastering Microsoft Project 2013

PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM. in an PAUL EASTWOOD HARRIS

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information

Mastering Microsoft Project 2010

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

1200 Project Control System Procedures

Transcription:

Designer & Builder Symposium Construction Scheduling Glenn Saito NAVFAC Pacific Construction Division December 1, 2010

FOCUS AREAS Current processes (where implemented) Scheduling specification changes for NAVFAC Pacific, Marianas, Hawaii and Diego Garcia projects P6 Migration Simplified invoice review & validation process payment tied to easily measurable schedule progress (Schedule Centric Invoicing) An early warning indicator of schedule problems detailed review and analysis of SureTrak schedules not required (Schedule Variance Control Chart) Detailed Contractor schedule of upcoming work, outages, closures and control activities Useful weekly planner for CMs & ETs (3-Week Look Ahead Schedule) 2 Naval Facilities Engineering Command

Unified Facilities Guide Specifications UFGS 01 32 17.xx 20 Network Analysis Schedule Section 01 32 17.05 20 Network Analysis Schedules (NAS) for D-B Section 01 32 17.00 20 Network Analysis Schedules (NAS) for D-B-B Inserted on all NAVFAC Pacific Marianas, Hawaii and Diego Garcia Projects Coordination is required with UFGS 01 20 00.xx 20 Price and Payment Procedures when cost loading Network Analysis Schedules is specified 3 Naval Facilities Engineering Command

NAVFAC Construction Scheduling NAVFAC Pacific, Marianas, Hawaii & DG Reqiurements Requirement based on contract value Requirement inserted in contracts below stated threshold values when requested by administering FEAD/ROICC UFGS 01 32 17.xx 20 required on all construction contracts REQUIREMENT Contract < $750 Contract > $750 UFGS 01 32 17.xx 20 SureTrak NAS schedules Schedule updates Cost loading Schedule Centric Invoicing Schedule Variance Control 3-Week Look Ahead Schedule 4 Naval Facilities Engineering Command

SOFTWARE Project schedules must be prepared and maintained using, Primavera P3 Primavera SureTrak Current mandated scheduling program Save files in Concentric P3 or current mandated scheduling program file format, compatible with the Governments version of the scheduling program Importing data into P3/SureTrak/current mandated scheduling program using data conversion techniques or third party software will be cause for rejection of the submitted Intent Allow KTR to use SureTrak/P3 if, Activity codes, code value assignments, layouts, filters, cost data and reports transfer intact during file import into the governments version of P6 Once uploaded, the governments version of P6 produces schedule reports that meet all requirements of UFGS 01 32 17.05 20 5 Naval Facilities Engineering Command

SCHEDULING PROGRAM UPGRADE: Primavera P6 Professional Project Management Primavera SureTrak 3.0 P6 Deployment to Construction Managers, 1 st push to NMCI machines complete 1 st push to OneNET machines OneNET testing in progress Dependent on outcome of testing, earliest deployment Apr 2011 SureTrak Deployment To Construction Managers, Required on machines to import SureTrak files into P6 6 Naval Facilities Engineering Command

SCHEDULER QUALIFICATIONS The designated Scheduler for the project shall have prepared and maintained at least 3 previous schedules of similar size and complexity of this contract using SureTrak/P3 or current mandated scheduling program. A resume outlining the qualifications of the Scheduler shall be submitted for acceptance to the Contracting Officer. Payment will not be processed until an acceptable Scheduler is provided 7 Naval Facilities Engineering Command

Cost Loading > $750K or when requested by the administering office Costs for incremental design preparation shall be assigned to the respective design phase submittal milestone(s). Material and Equipment Costs for which payment will be requested in advance of installation shall be assigned to their respective procurement activity (i.e., the material/equipment on-site activity). All other construction costs shall be assigned to their respective Construction Activities. Evenly disperse overhead and profit to each activity over the duration of the project. 8 Naval Facilities Engineering Command

EARNED VALUE REPORT Listing all activities having a budget amount cost loaded Compilation of total earnings on the project from notice to proceed to current progress payment request Show current budget, previous physical percent complete, to-date physical percent complete, previous earned value, to-date earned value and cost to complete on the report for each activity: 9 Naval Facilities Engineering Command

Earned Value Report Prepared by contractor and reviewed by government Agree on percent of work in-place SureTrak calculates payment amounts Previous Invoice percentage of work in-place Current Invoice percentage of work in-place verified by ET No. of days ahead/behind schedule (+ Ahead/ - Behind) SCHEDULE PERFORMANCE: Current Plan Top Bar Baseline Plan Bottom Bar 10 Naval Facilities Engineering Command

SCHEDULE VARIANCE CONTROL (SVC) DIAGRAM Submitted with each schedule submission Provide a SVC diagram showing, Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates Earned Value to-date Revise Cash Flow S-Curves when the contract is modified, or as directed by the Contracting Officer. 11 Naval Facilities Engineering Command

SCHEDULE PERFORMANCE INDEX (SPI) SPI = AE/PE PLANNED EARNINGS (PE) BASED ON BASELINE EARLY START ACTUAL EARNINGS (AE) FROM EARNED VALUE REPORT INVOICE DATE 2 mos. behind WIP projection EARLY WARNING INDICATORS: AHEAD OF SCHEDULE AE > PE and SPI >1 ON SCHEDULE PE = AE and SPI = 1 BEHIND SCHEDULE PE > AE and SPI < 1 MONITOR SCHEDULE VARIANCE TO MEASURE IMPROVEMENT 12 Naval Facilities Engineering Command

NARRATIVE REPORT Identify and justify, Progress made in each area of the project Critical Path Date/time constraint(s), other than those required by the contract Changes in the following; Added or deleted activities Original and remaining durations for activities that have not started Logic Milestones Planned sequence of operations Critical Path Cost Loading 13 Naval Facilities Engineering Command

NARRATIVE REPORT(Continued) Identify and justify, Any decrease in previously reported activity Earned Amount; Pending items and status thereof, including permits, changes orders, and time extensions; Status of Contract Completion Date and interim milestones; Current and anticipated delays (describe cause of delay and corrective actions(s)); Description of current and future schedule problem areas. Each entry in the narrative report will cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change. 14 Naval Facilities Engineering Command

3 Week Look Ahead Schedule More detailed day-to-day plan of upcoming work identified on the Project Network Analysis Schedule. Keyed to NAS activity numbers Updated each week to show the planned work for the current and following twoweek period Include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities Bar chart Maintained separately from the Project NAS on an electronic spreadsheet program Printed on 8 ½ by 11 sheets as directed by the Contracting Officer Activities shall not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work Three hard copies and one electronic file of the 3-Week Look Ahead Schedule shall be delivered to the Contracting Officer no later than 8 a.m. each Monday Reviewed during the weekly CQC Coordination Meeting 15 Naval Facilities Engineering Command

3-Week Look Ahead Schedule Excel Spreadsheet, Updated Weekly and maintained separately from NAS Duration less than 5 working days Associated NAS activity Identify control meetings, closures & outages 16 Naval Facilities Engineering Command

Questions??? 17 Naval Facilities Engineering Command