European Subsea Cable Report & Forecast 2015-2025

Similar documents
The European offshore wind industry key trends and statistics February A report by the European Wind Energy Association

Wind Farm Zone. Offshore wind energy. in the Netherlands. Project & Site Description. # Borssele

The European offshore wind industry - key trends and statistics January A report by the European Wind Energy Association

VISION MISSION ABOUT A2SEA. Stay ahead in taking wind power offshore and the future of energy in a sustainable direction.

DONG Energy offshore wind experience

The installation and servicing

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS

Installation, future demands for recruitment and competencies. Speaker: Hans Schneider Date: 4 April 2013

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Dutch wind energy strength

Optimization of the coupled grid connection of offshore wind farms

Profile. Offshore Wind Projects. Sustainable EPC and Marine Contractors

UK content analysis of Robin Rigg Offshore Wind Farm operations and maintenance

Concepts for Transfer of Personnel in Offshore Wind

Cost Reduction Potential in the Offshore Grid

OFFSHORE WIND ENERGY IS GETTING CHEAPER

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

Fugro Q trading update

Employment in OWE in NL, 2010

HV Submarine Cable Systems Design, Testing and Installation

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Offshore Wind: some of the Engineering Challenges Ahead

EXPERIENCE WITH DP-SYSTEMS ON BOARD

Essex... A great location for offshore wind

De Industrie. KIvI Niria Jaarcongres De uitdagingen voor windenergie op zee. Ballast Nedam Offshore. Dolf Elsevier van Griethuysen

Danish Society for Naval Architecture and Marine Engineering, Danish Maritime Society, The Transport Innovation Network & Danish Wind Energy Group

Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh

October TKI Wind op Zee Cost reduction options for Offshore wind in the Netherlands FID

Network Interconnection of Offshore Wind

WIND ENERGY - THE FACTS PART III THE ECONOMICS OF WIND POWER

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

TKI Wind op Zee Subsidy schemes and tax regimes

Electricity market drivers

Why wind power works for Denmark

Polish Offshore Grid SA

AN INDEPENDENT ANALYSIS COMMISSIONED BY STATKRAFT UK

HIGH LEVEL REVIEW HELIDECK AND ACCOMMODATION Helideck and accommodation facilities on offshore platforms for wind farms. TenneT.

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

STATUS OF OFFSHORE WIND ENERGY DEVELOPMENT IN GERMANY

A E O L I S F O R E C A S T I N G S E R V I C E S WIND FARM ENERGY ASSESSMENT - FEASIBILITY STUDY. Kees van Vliet

MENA Wind Power Outlook

The UK Offshore Wind Experience

Offshore Wind in Germany

Trends in offshore wind economics the past and the future

INVESTING IN A TRANSITIONING SECTOR

Offshore Wind. IEEE Boston PES - November 16, 2010

A macro-economic viewpoint. What is the real cost of offshore wind? siemens.com / wind

Offshore Wind China 2010 Bergen, 15th March Olivier Angoulevant Nexans Norway AS

HVDC Light Cables. Submarine and land power cables

JEDI Capital Expenditure Update

INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS

Offshore Work Packages

OFFSHORE WIND PROCUREMENT

2015 CT Offshore A/S Diving Assistance Sub Station Debris Clearance WODS Wind Farm

Neart na Gaoithe Meet the buyer event. Chris Whitehead Facilitator

Supply Chain Opportunities and Management of Risk. Ian McCarlie

Grid connection of near shore wind farms

GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)

Offshore wind power: big challenge, big opportunity. Maximising the environmental, economic and security benefits

Environmental aspects of offshore wind energy. Jakob Asjes Jakob Asjes IMARES, Institute for Marine Resources and Ecosystem Studies

Borssele Wind Farm Zone

Premium Data Centre Europe Pricing, Business Model & Services

Viking Link Interconnector

Offshore wind farms in Europe

Wind and solar reducing consumer bills An investigation into the Merit Order Effect

installation, operations & maintenance

How Dutch innovations support 40% cost price reduction. June 13th 2013 How Dutch innovations support 40% cost price reduction 1

Feasibility Study of Deep Water Power Cable Systems. Enrico Colombo CESI S.p.A

Power System for Offshore Wind Power

An Enterprising Wind An economic analysis of the job creation potential of the wind sector in ireland

PPT Dutch offshore wind sector

3,000 MW installed capacity 1,700 wind turbines erected 1,200 members of staff

OFFSHORE WIND POLICY AND MARKET ASSESSMENT A GLOBAL OUTLOOK

Cost Reduction Monitoring Framework

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

SSE Greater Gabbard Offshore Wind Farm Supply Chain Engagement

Offshore Wind OPERATIONS & MAINTENANCE. A National Renewables Infrastructure Plan Stage 2 Information Paper

The Role of a Pension Fund in Renewable Energy Investments. Transformational NAMA in the Renewable Energy Sector May 2013

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES

SDE+ tender Borssele december 2015

6 Oktober KIVI Niria congres Offshore Wind De uitdaging. Eneco wind. Ernst van Zuijlen

Integrated cable solutions for offshore wind development

Annex 2C International comparisons of gas and electricity prices

High Voltage Direct Current Transmission

Energinet.dk and the Danish Energy System

Future Offshore Wind Power Sites -2025

Database of measurements on the offshore wind farm Egmond aan Zee

Transcription:

European Subsea Cable Report & Forecast 2015-2025 J/15/1226 May 2015 4C Offshore - OrbisEnergy Centre, Lowestoft, NR32 1XH T: +44 (0)1502 307 037 E: info@4coffshore.com

Table of Contents 1. Executive Summary 7 2. Market Development to Date 10 3. Subsea Cables 12 4. Cable Installation 15 5. Cable Monitoring 17 6. Cable Inspection 18 7. Cable Intervention and Repairs 18 8. Cable Faults 21 9. Weather Related Installation Delays 24 10. Market Share: Array Cable Supply 27 11. Market Share: Export Cable Supply 28 12. Market Share: Interconnector Cable Supply 29 13. Market Share: Array Cable Installation 30 14. Market Share: Export Cable Installation 31 15. Market Share: Interconnector Cable Installation 33 16. At a Glance: Subsea Cable Installation Companies and Their Assets 34 17. Transmission Policy Frameworks Overview 35 18. Country Overview: Belgium 40 19. Country Overview: Denmark 43 20. Country Overview: France 45 21. Country Overview: Germany 47 22. Country Overview: Netherlands 49 23. Country Overview: United Kingdom 53 24. Costs: Cable Supply Costs 55 25. Costs: Cable Installation Costs 57 26. Costs: Capital Expenditure 58 27. Forecasting Methodology 59 28. Forecasting Results: Cable demand and expenditure to 2025 61 29. Appendix: Project Pipelines by Country 68 30. Appendix: Future Wind Farm Opportunities 72 31. Appendix: Future Interconnector Opportunities 77 32. Appendix: Offshore Wind Subsea IMR Contracts 85 33. Appendix: Offshore Wind Subsea IMR Players Schematic 87 34. Appendix: German North Sea Grid Connections 88 35. Appendix: Baltic Sea Grid Connections 89

Table of Figures Figure 1. Summary of offshore wind subsea cable market development 2002-2014 7 Figure 2. Left: Percentage of incidents by problem and median delay length. Right: Number of incidents by delay and type of cable. 7 Figure 3. Number of players and market leaders for subsea cable and installation since 2010 9 Figure 4. Current (April 2015) and future (2025) installed capacity for the six main European markets 9 Figure 5.Offshore Wind CAPEX spend by country summed for period 2015-2025 10 Figure 6. Left: Demand for array, export, HVDC transmission and interconnector cabling 2015-2025 (km). Right: Expenditure on subsea cable supply and installation 2015-2025 (a portion of total CAPEX) 10 Figure 7. Water depth and distance to shore at installed or underway European projects 11 Figure 8. Percent of capacity being exported via transmission technology (MVAC, HVAC, HVDC) 11 Figure 9. Nysted's substation (HVAC transformer) and Helwin Alpha (HVDC converter station) 11 Figure 10. Offshore wind cabling to date plotted by offshore installation start year for projects to Q1 2015. From top left to bottom right: Cumulative cable type for all countries; cumulative array cable by country; cumulative HVAC export cable by country and cumulative MVAC export cable. 12 Figure 11. Left: Preparing for installation: array cable being wound on a carousel and Right: subsea power cable cross section 12 Figure 12. Ready for installation: export cable being wound on a carousel utilizing a tensioner 13 Figure 13. Four 66kV cable designs receiving qualification funding from the Carbon Trust's OWA. * Dry designs include an impermeable metallic sheath (e.g. lead sheath). 13 Figure 14. Single bipole arrangement schematic 14 Figure 15. Loading HVDC onto a cable lay vessel at the factory 15 Figure 16. Reef Subsea s Q1000 Jet trencher, Subsea 3M Cable Plough and DeepOcean's UT-1 trencher (has both jetting and meachanical wheel cutting modes) 16 Figure 17. Typical Survey Programme for a Round 2 UK Wind Farm 18 Figure 18. Thanet Export cable replacement. Photo: Subsea Energy Solutions. 19 Figure 19. Indicative CAPEX reduction potential of transmission initiatives and cost reduction options cited by respondents. Source: DNVGL 20 Figure 20. Left: Percentage of incidents by problem and median delay length. Right: Number of incidents by delay and type of cable. 21 Figure 21. Actual versus expected array cable rates at Gwynt-y-Môr 24 Figure 22. Significant delays attributable to weather 25 Figure 23. Example cable installation elements and influencing metocean components. Adapted from MojoMaritime 2014 26 Figure 24. Reducing weather risk during cable installation by optimising elements of the process. Adapted from MojoMaritime, 2014 26 Figure 25. Market share: array cable manufacture since 2010 27 Figure 26. Market share: export cable manufacture since 2010 28

Figure 27. Market share: interconnector cable manufacture for on and offshore cable length. Since 2010 29 Figure 28. Market share: array cable installation since 2010 30 Figure 29. Market share: Export cable installation since 2010 31 Figure 30. Market share: interconnector installation (subsea component) 33 Figure 31. European offshore wind and interconnector subsea cable installation companies, market share, clients and assets. *=vessel has installed interconnectors. Italics=vessel under construction 35 Figure 32. Estimated OFTO O&M expenditure per annum. *All costs inflated to 2014 values. 36 Figure 33. Results OFTO Tenders 1-3 and operations and maintenance body 37 Figure 34. Belgian Offshore Grid (BOG, configuration updated April 2015). Generating projects shown in green. 40 Figure 35. Belgium: Projects installed 41 Figure 36. Belgium: Investor types and owners for projects that are commissioned or in construction 41 Figure 37. Cumulative installations according to 4C's 2025 projection. For specific projects please see the Appendix. 42 Figure 38. Denmark: Projects installed 44 Figure 39. Denmark: Investor types and owners for projects that are commissioned or in construction 44 Figure 40. Cumulative installations according to 4C's 2025 projection. For specific projects please see the Appendix. 44 Figure 41. French offshore wind tender results. *Start years are analyst estimates, not necessarily the same as developer communications 45 Figure 42. Supply chain investments in France 46 Figure 43. Cumulative installations according to 4C's 2025 projection. For specific projects please see the Appendix. 46 Figure 44. The extension of the higher initial remuneration has opened further investment in German offshore wind. 48 Figure 45. Progress towards goals and grid allocation to date. Baltic Sea represented by dotting. 48 Figure 46 Germany: Investor types and owners for projects that are commissioned or in construction 48 Figure 47. Annual installations according to 4C's 2025 projection; cumulative installed capacity and the cumulative capacity of all projects in the developer pipeline. For specific projects see the Appendix. 49 Figure 48. Map of current and future Netherlands offshore wind projects 50 Figure 49. Netherlands progress to date and scale of future tenders 52 Figure 50. Cumulative installations according to 4C's 2025 projection. For specific projects please see the Appendix. 52 Figure 51. UK development to date; licensing rounds and progress to date. Note that more attrition of projects in development is likely. 54 Figure 52. Ownership of generating and under construction projects in the UK 54 Figure 53. Annual installations according to 4C's 2025 projection, cumulative installed capacity and the cumulative capacity of all projects in the developer pipeline. For specific projects see the Appendix. 54 Figure 54. Array cable manufacture costs versus array cable length; regression analysis and table of projects 55 Figure 55. HVAC cable manufacture costs versus array cable length; regression analysis and table of projects 56 Figure 56. HVDC cable manufacture costs and table of projects 57

Figure 57. Array cable supply costs versus array length; regression analysis and table of projects 57 Figure 58. Export cable supply costs versus length; regression analysis and table of projects 58 Figure 59. CAPEX modelling to 2025 59 Figure 60. Observed array cable lengths (km) plotted against the two predictive components (i)project capacity and (ii) number of turbines 60 Figure 61.(i) Observed substation capacity by construction start year and (ii)number of substations by project capacity 61 Figure 62.(i) Observed turbine capacity by construction start year, and (ii) Number of confirmed turbine orders by start year and turbine capacity 61 Figure 63. Cumulative annual offshore wind CAPEX to 2015-2025 and breakdown by country 62 Figure 64. Annual array cable demand (km) 2015-2025 by country, total array cable demand by country, supply expenditure by year and install expenditure by year. 63 Figure 65. Annual MVAC export cable demand (km) 2015-2025 by country plus total MVAC cable demand by country. 64 Figure 66. Annual HVAC export cable demand (km) 2015-2025 by country plus total HVAC cable demand by country. 65 Figure 67. Annual HVDC export cable demand (km) 2015-2025 by country plus total HVDC cable demand by country. 66 Figure 68. European HVDC interconnector cable demand for the period 2015-2025 plus annual and cumulative CAPEX for interconnector projects for the period 67 Figure 69. Expenditure on HVDC interconnector cable supply and installation for the period 2015-2025 67 Figure 70. Rate of installation data set : MW/Year increasing with start of offshore installation 68 Figure 71. Belgium: Project installations to 2025 69 Figure 72. Denmark: Project installations to 2025 69 Figure 73. France: Project installations to 2025 70 Figure 74. Germany: Project installations to 2025 70 Figure 75. Netherlands: project installations to 2025 71 Figure 76. United Kingdom: Project installations to 2025 71 Figure 77. Future UK offshore wind farm projects, awarded cable supply and manufacture contracts and contracts not yet announced (-) 72 Figure 78. Future German offshore wind farm projects, awarded cable supply and manufacture contracts and contracts not yet announced (-) 73 Figure 79. HVDC Transmission cable supply and installation contracts for German North Sea Converter Stations 74 Figure 80. Future Belgian offshore wind farm projects, awarded cable supply and manufacture contracts and contracts not yet announced (-) 74 Figure 81. Future Danish offshore wind farm projects, awarded cable supply and manufacture contracts and contracts not yet announced (-) 75

Revisions Revision A1 Date 13th May 2015 Prepared Richard Aukland and Richard Garlick Revision A2 Changes Minor edits Date 21st May 2015 Prepared Richard Aukland Checked and approved by Richard Aukland - Director of Research This document has been prepared in good faith on the basis of information available at the date of publication. 4C Offshore does not guarantee or warrant the accuracy, reliability, completeness or currency of the information in this publication nor its usefulness in achieving any purpose. Readers are responsible for assessing the relevance and accuracy of the content of this publication. 4C Offshore will not be liable for any loss, damage, cost or expense incurred or arising by reason of any person using or relying on information in this publication

Water Depth (m) Distance to Shore (km) 2. Market Development to Date Early offshore wind projects in Denmark, Netherlands, Sweden and the UK were all near shore and shallow water with an average of 6m water depth and 4km to shore (Figure 1). These pioneering projects included Denmark s 20 turbine Middelgrunden project and Irene Vorrink in the Netherlands. The proximity to shore allowed all projects before 2002 to avoid the requirement of high voltage transmission and instead use 33kV cables similar to those used for array cabling to export to shore. As projects became larger and were sited further from shore it became economic to introduce an offshore substation for stepping the voltage up from medium to high in order to reduce transmission losses. Two Danish projects, Horns Rev 1 (160MW, 18km) and Nysted (165.5MW, 11km) were the first to use offshore substations in 2002. Since then HVAC transmission has become the most common solution. Projects in the German EEZ, necessarily far from shore (often in excess of 100km) due to the presence of the protected Wadden Sea National Park and busy shipping lanes are connected to shore via high voltage direct current (HVDC) in order to reduce electrical losses associated with AC transmission. Figure 2 shows the proportion of capacity currently installed or underway that is being exported via the different technologies across Europe. HVAC is currently the most prevalent, with HVDC only used in Germany at present. MVAC is still being used on projects today, indeed the two European projects entering construction in Q1 2015 (Vattenfall s Kentish Flats Extension project and Westermeerwind in the Netherland s Ijsselmeer lake) are both close to shore and exporting at 33kV. This is reflected in the anomalously low water depth and distance from shore for projects underway in Q1 2015 (Figure 1). 35 45 30 40 Deeper & further 35 25 30 20 25 15 20 10 15 10 5 5 0 0 <=2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Year Water Depth Distance to Shore Figure 1. Water depth and distance to shore at installed or underway European projects 25% 12% 63% MVAC HVAC HVDC Figure 2. Percent of capacity being exported via transmission technology (MVAC, HVAC, HVDC) Figure 3. Nysted's substation (HVAC transformer) and Helwin Alpha (HVDC converter station) 4C Offshore :European Subsea Cable Report & Forecast 2015-2025 7

HVAC Export Cable (km) MVAC Export Cable (km) Total Cable (km) Capacity Entering Construction (GW) Total Array Cable (km) Between 2002 and 2014 Compound Annual Growth Rate (CAGR) for offshore wind cable installations averaged 30% year on year growth (Figure 4) with over 6000km of subsea cable installed at the end of 2014. 51% of cabling requirements are array cable and 31% HVAC export cable. By length only 7% is MVAC and 11% HVDC. Cable demand is driven largely by the UK and German markets with Denmark, Netherlands and Belgium contributing less. France, Norway and Portugal have no commercial scale deployments to date. It can be seen that MVAC export cabling is absent from the German market where projects have not been built close to shore. The appearance of the growth to decline in 2015 is misleading, this is a consequence of the fact that only Q1 projects have been included in these charts, a further 1.47GW of projects will start during the year. By comparison 2014 was a light year, with only 417MW entering construction. 7000 13 GW 3500 6000 11 GW 3000 51% Array Cable 5000 4000 30% CAGR 9 GW 7 GW 2500 3000 5 GW 2000 2000 3 GW 1500 1000 1 GW 1000 0 <=2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015-1 GW 500 Array MVAC Export HVAC Export HVDC Capacity 2015 projected 0 <=2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2000 1800 1600 1400 1200 1000 800 400 30% HVAC Cable 350 12% MVAC Cable 300 250 200 600 400 200 0 <=2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 United Kingdom Germany France Netherlands Denmark Belgium Norway Portugal 150 100 50 0 <=2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Figure 4. Offshore wind cabling to date plotted by offshore installation start year for projects to Q1 2015. From top left to bottom right: Cumulative cable type for all countries; cumulative array cable by country; cumulative HVAC export cable by country and cumulative MVAC export cable. 4C Offshore :European Subsea Cable Report & Forecast 2015-2025 8

10. Market Share: Array Cable Supply 9% 7% 23% Array Cable (km) 9% Nexans NSW Draka Offshore JDR Cable Systems NEXANS 491 NSW 406 DRAKA OFFSHORE 399 15% 19% NKT Cables Parker Scanrope Other JDR CABLE SYSTEMS 319 NKT CABLES 191 PARKER SCANROPE 162 OTHER 195 18% Figure 5. Market share: array cable manufacture since 2010 COMPANY PROJECTS - Anholt (2011): 160km for 111x Siemens SWT-3.6-120 turbines - Lincs (2011): 85.30km for 75x Siemens SWT-3.6-120 turbines - Riffgat (2012): 24km for 30x Siemens SWT-3.6-120 turbines - Borkum Riffgrund I (2013): 62km for 78x Siemens SWT-4.0-120 turbines - West of Duddon Sands (2013): 107km for 108x Siemens SWT-3.6-120 turbines - Westermost Rough (2013): 53km for 35x Siemens SWT-6.0-154 turbines - BARD Offshore 1 (2010): 107km for 80x BARD 5.0MW turbines - Trianel Windpark Borkum Phase 1 (2011): 65km for 40x Areva Wind M5000-116 turbines - Global Tech I (2012): 122km for 80x Areva Wind M5000-116 turbines - Humber Gateway (2013): 82km for 73x Vestas V112-3.0MW turbines - Kentish Flats Exension (2015): 30km for 15x MHI-Vestas V112-3.3MW turbines - Walney Phase 2 (2011): 52km for 51x Siemens SWT-3.6-120 turbines - Gwynt y Môr (2012): 148km for 160x Siemens SWT-3.6-107 turbines - Kårehamn (2012): 18km for 16x Vestas V112-3.0MW turbines - Teesside (2012): 10km for 27x Siemens SWT-2.3-93 turbines - EnBW Baltic 2 (2013): 84km for 80x Siemens SWT-3.6-120 turbines - Butendiek (2014): 87km for 80x Siemens SWT-3.6-120 turbines - London Array Phase 1 (2011): 209km for 175x Siemens SWT-3.6-120 turbines - Meerwind Ost/Sud (2012): 108km for 80x Siemens SWT-3.6-120 turbines - Belwind Alstom Haliade Demonstration (2013): 1.8km for 1x Alstom Power Haliade 150-6MW turbine - EnBW Baltic 1 (2010): 21km for 21x Siemens SWT-2.3-93 turbines - Walney Phase 1 (2010): 48km for 51x Siemens SWT-3.6-107 turbines - Amrumbank West (2013): 90km for 80x Siemens SWT-3.6-120 turbines - Eneco Luchterduinen (2014): 32km for 43x Vestas V112-3.0MW turbines - DanTysk (2012): 111km for 80x Siemens SWT-3.6-120 turbines - Northwind (2013): 51km for 72x Vestas V112-3.0MW turbines Announced Contracts not yet Supplied Dudgeon Nordsee One Sandbank Borkum Riffgrund II Gode Wind 01 and 02 Gemini Nordergründe 4C Offshore :European Subsea Cable Report & Forecast 2015-2025 9

22. Country Overview: Netherlands Context and Ambition The Fourth Balkenende cabinet (dissolved in 2010) envisaged a large role for offshore wind, projecting over 5GW by 2020 to assist in meeting the 14.5% share of gross final energy consumption to be generated from renewable sources. However, the incoming Rutte Cabinet I (dissolved in 2012) found itself operating in the context of global recession and chose to realign subsidies in favour of competition rather than industrial support, effectively grinding the industry to a halt. With petrochemicals, greenhouse horticulture and transport accounting for a major share of the Dutch economy, the Netherlands has a high per capita energy consumption. Much energy is imported, about a third of which is consumed and the remainder exported as crude oil or oil products. Compared with other European countries, the Netherlands has relatively large fossil fuel reserves with approximately twenty years of gas reserves. In 2013 the government published the National Energy Agreement for Sustainable Growth outlining a growth path defined by energy and climate objectives alongside gains in competitiveness, employment and exports. This supports long term aims within an international context, to achieve a completely sustainable energy supply system by 2050. Included were agreements to scale up renewable energy generation from 4.4% of total energy consumption in 2012 to 16% by 2023 and 14% by 2020 plus a target of 4450 MW operational offshore wind capacity by 2023 inclusive of the existing 1GW of secured capacity, to be supported through 18 billion of subsidies over five tender rounds. Routes to Market In order to implement the objectives of the Energy Agreement an offshore wind energy bill has been drafted (April 2015) outlining the new permitting and subsidy process for the first two sites of the Borssele wind farm zone (Figure 6). This will be the first tender in a series of five planned to secure 4450 MW of operational offshore wind capacity by 2023. Tender areas for development are restricted to those designated in the National Water Plan. Within areas, plots (kavels) are defined within which the wind farm can be built and under what conditions, based on the outcome of an environmental impact report and appropriate assessment. For each plot soil investigations and wind resource data will be made public to facilitate understanding of risks prior to bidding for subsidy. A new combined application procedure is being introduced for both licence and subsidy with the winner of the SDE+ subsidy receiving an exclusive development permit ( windvergunning ). The licence will combine the relevant licences needed under multiple acts, expediting development and reducing costs by an estimated 10%. The lowest bidder below the set maximum for the tender round is awarded the subsidy. The original suggested benchmark starting point for necessary offshore wind cost reductions is an average of 150/MWh in 2014, with an expected cost reduction of EUR 5 per MWh per year. The first subsidy applications are planned to be submitted from December 2015 to 31 st March 2016, with bids for site I, II or both sites accepted. Winners will be those with the lowest per kwh subsidy requirement. Maximum bids are not yet defined but suggested to be 150/MWh for a period of 15 years, a significant reduction on earlier proposals. The park must be operational within five years of the subsidy decision. 4C Offshore :European Subsea Cable Report & Forecast 2015-2025 10

Gemini Prinses Amaliawindpark Egmond aan Zee Eneco Luchterduinen 2017 Tender 2018 Tender 2019 Tender Lely Westermeerwind Irene Vorrink Borssele Site IV Borssele Site I Netherlands Borssele Site III Borssele Site II Figure 6. Map of current and future Netherlands offshore wind projects Development to Date Two commercial scale parks are currently operating in the Netherlands, 108MW Offshore Windpark Egmond Aan Zee (OWEZ) located 10km off the shore of Egmond aan Zee and 120MW Princes Amalia, 23km off the shore of Ijmuiden. Both started construction in 2006 under the so called Round 1 tender supported through the MEP (Environmental Quality Electricity Production) subsidy scheme, the precursor to the SDE scheme. In Round 2 twelve permits were granted, of which three were awarded SDE subsidies in 2010 following the tender process. From a total available budget of 4.5bn the Gemini project (formally comprised of BARD s Buitengaats and ZeeEnergie projects) received a maximum subsidy of 3.6bn and Eneco s Lucterduinen (formally known as Q10) received the remaining 989m. 129MW Luchterduinen, located 23km offshore from Noordwijk entered construction in July 2014 with full operation expected late 2015. Gemini (Northland, Siemens, HVC, Van Oord) began offshore cable work in March 2015 with full commissioning of the 600MW expected in 2017. The remaining nine Round 2 permits which have failed to secure a subsidy will lapse when the new energy bill comes into force. Excluding the nearshore 144MW Westermeerwind project, total offshore capacity commissioned or under construction totals 957MW. The SDE subsidies were awarded during a tender process in 2010. Parties with a building permit submitted a bid ( /MWh) which was corrected to allow for the distance to shore. Subsidies are valid for the first 2900 full load hours over 15 years, with payment equal to the difference between the bid price and the reference price. BARD s bid price is reported to be 170/MWh excluding the distance correction. 4C Offshore :European Subsea Cable Report & Forecast 2015-2025 11

Capacity Installed (MW) Early Demonstration, 19MW Round 1, 228MW 2019 Round 2, 729MW 2018 Nearshore, 144MW 2015 2017 2016 Commissioned In Construction Future 700MW Tender Figure 7. Netherlands progress to date and scale of future tenders Forecast to 2025 Following on from Westermeerwind and Gemini, remaining installations to 2025 will be driven by the tender rounds towards the government target of 4450MW. The 4C mid case growth scenario here has assumed a two-year delay in progress such that a full build-out will not be achieved in the forecast time frame. This is a rational assumption given the delays seen in all offshore tender plans in all European countries to date. 4500 4000 3500 3000 2500 2000 1500 1000 500 0 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Figure 8. Cumulative installations according to 4C's 2025 projection. For specific projects please see the Appendix. Summary Strengths and Weaknesses Strengths Weaknesses Over 1GW installed or committed to date. Revised enthusiasm for offshore wind under the 2013 Energy Agreement, with a target of 4450MW operational by 2023. Streamlined permitting being legislated. Tender areas already undergone preliminary screening. Clear plan for evenly distributed tenders from 2015-2019 Logistically suitable ports for construction and maintenance Future grid not dependent on offshore HVDC technology Previous postponement of offshore wind development and a habit of new Cabinets to change policy. Emphasis on reduction in costs as requirement for tenders. Scrapping of existing licenses will cost developers money Gemini, despite having been awarded a subsidy in 2010 did not enter construction until 2015 due to delays in reaching financial close - the project economics were improved through redesign. 4C Offshore :European Subsea Cable Report & Forecast 2015-2025 12