QUT Digital Repository: http://eprints.qut.edu.au/29465



Similar documents
Simulating construction planning in a bridge project by. using virtual prototyping, integrated design and. resource allocation

This is the author s version of a work that was submitted/accepted for publication in the following source:

AUTOMATED CONSTRUCTION PLANNING FOR MULTI-STORY BUILDINGS

This is the Pre-Published Version

This is the Pre-Published Version.

Automated construction schedule creation using project information model

BIM Extension into Later Stages of Project Life Cycle

An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction

ESTIMATION AND PLANNING TOOL FOR INDUSTRIAL CONSTRUCTION SCAFFOLDING. *C. Kumar, S. M. AbouRizk, and Y. Mohamed

Visualisation Development for The Virtual Construction Site

INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2

Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry

PS.12. 4D Scheduling A Case Study

OPTIMIZATION MODEL OF EXTERNAL RESOURCE ALLOCATION FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEMS

Constraint-Directed Scheduling for Multi-Storey Building Projects

Technique (LOBST) for a Real estate sector

The management of the projects with MS Project

Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects

BIM and Lean Construction Can BIM remove waste from construction processes?

A Study of Virtual Prototyping in Construction Industry : A case study of Kwan Chung Public Housing Estate Project

Tall Building Form Generation by Parametric Design Process

4D GRID-BASED SIMULATION FRAMEWORK FOR FACILITATING WORKSPACE MANAGEMENT

Enhancing Building Quality With 6D BIM

PROGRAMMING TECHNIQUES. Chapter 5(Part 2)

Automated Micro-Planning and Real-time Tracking of Precast Building Components

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

Research RESOURCE SCHEDULING OF CONSTRUCTION PROJECTS USING GENETIC ALGORITHM Devikamalam. J 1, Jane Helena. H 2. Address for Correspondence

Automated Schedule Monitoring System for Precast Building Construction Using Enhanced - Geographic Information System (GIS)

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

The ACR : Advanced Design Features for a Short Construction Schedule

Virtual Reality Applications in Project Management Scheduling

An Interactive Visual Approach to Construction Project Scheduling

Prof. A. Ray Chaudhuri Department of Civil Engineering Adama Science and Technology University (ASTU), Adama, Ethiopia. I.D:

Project Time Management

ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY

The Task. for. PERI Construction-Exercise 2003

AUTOMATED PROJECT SCHEDULE AND INVENTORY MONITORING USING RFID

3D PLANNING. Visualization of construction schedules

CASE STUDY OF USING AN INTEGRATED 5D SYSTEM IN A LARGE HOSPITAL CONSTRUCTION PROJECT

Working Paper #3 THE APPLICATION OF CONSTRUCTION PROJECT MANAGEMENT TOOLS AN OVERVIEW OF TOOLS FOR MANAGING AND CONTROLING CONSTRUCTION PROJECTS

A Pattern-Based Approach for Facilitating Schedule Generation and Cost Analysis in Bridge Construction Projects

Applying the Chronographical Approach to the Modelling of Multistorey Building Projects

STUDY ON APPLICATION OF GENETIC ALGORITHM IN CONSTRUCTION RESOURCE LEVELLING

A GENETIC ALGORITHM FOR RESOURCE LEVELING OF CONSTRUCTION PROJECTS

Planning and Scheduling. Railway Maintenance Work. with TILOS

1 st year / / Principles of Industrial Eng. Chapter -3 -/ Dr. May G. Kassir. Chapter Three

A genetic algorithm for resource allocation in construction projects

Ming Lu, Yang Zhang, Jianping Zhang, Zhenzhong Hu, and Jiulin Li

PROJECT COST ESTIMATES & FEASIBILITIES

Synergy: Building Information Modeling and

A PRODUCTION PLANNING SUPPORT SYSTEM FOR CONSTRUCTION PROJECTS

Spec. Standard: 11/27/ Revision: 11/27/06

Automation in Construction

BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY

WORK SCOPE. Domains in which we work:

QUT Digital Repository:

Sage 200 Manufacturing Datasheet

QUEST The Systems Integration, Process Flow Design and Visualization Solution

Mastering Microsoft Project 2013

CHAPTER 8 PROJECT TIME-COST TRADE-OFF

Integrating BIM and Safety: An Automated Rule-Based Checking System for Safety Planning and Simulation

Project Time Management

BIM based Schedule Control for Precast Concrete Supply Chain

BUILDING INFORMATION MODELING (BIM) AND THE CONSTRUCTION MANAGEMENT BODY OF KNOWLEDGE

An Object-Oriented Environment for the Construction Planning of High-Rise Buildings

Hanson Building Products. precast basement solutions

Dynamic Change Management for Fast-tracking Construction Projects

d e n v e r a r t m u s e u m

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT Timo Hartmann

MAJOR LEARNING OUTCOMES ARCHITECTURE AND URBAN PLANNING 1ST CYCLE PROGRAMS GENERAL ACADEMIC PROFILE

MULTI-RESIDENTIAL BUILDING SOLUTIONS

New Zealand BIM Handbook Appendix D - BIM Uses definitions July A guide to enabling BIM on building projects

CONSTRUCTION WORKSPACE MANAGEMENT: THE DEVELOPMENT AND APPLICATION OF A NOVEL nd PLANNING APPROACH AND TOOL

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

PROJECT TIME MANAGEMENT

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

INTRODUCTION. Prakash Chandar. S¹, Dhivya Shree. G² ABSTRACT

Construction of precast reinforced concrete structures. Prefabricated reinforced concrete construction:

3D SCANNING: A NEW APPROACH TOWARDS MODEL DEVELOPMENT IN ADVANCED MANUFACTURING SYSTEM

Software engineering used in simulation of Flexible Manufacturing Systems

Project Time Management

PREPLANNING METHOD FOR MULTI-STORY BUILDING CONSTRUCTION USING LINE OF BALANCE

T109 Architectural Technology MTCU Code Program Learning Outcomes

Design/Construction Integration thru Virtual Construction for Improved Constructability Walid Thabet, Virginia Tech

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

CHECKLIST FOR SUBMISSION Construction Productivity Awards - Projects 2015

Location Based Scheduling In The Form Of Flow Line and Its Comparison to Cpm/Bar Chart Scheduling - doi: / IAU.IJEMME

How SolidWorks Speeds Consumer Product Design

Mobile 2D Barcode/BIM-based Facilities Maintaining Management System

Computing construction logic in a multi-calendar environment using the Chronographic Method

Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad

Visualization in 4D Construction Management Software: A Review of Standards and Guidelines

Industrial Case Study of Electronic Design, Cost and Schedule Integration

Review of Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs

SharePoint for Engineering Document Management & Control

Creating Automated Crane Work Plans Using Real Time Operational Data and Predictive Analysis

Transcription:

QUT Digital Repository: http://eprints.qut.edu.au/29465 Li, Heng and Chan, Neo and Guo, H.L. and Lu, Weisheng and Skitmore, Martin (2009) Optimizing construction planning schedules by virtual prototyping enabled resource analysis. Automation in Construction, 18(7). pp. 912-918. Copyright 2009 Elsevier.

Optimizing construction planning schedules by virtual prototyping enabled resource analysis Abstract The inherent uncertainty and complexity of construction work makes construction planning a particularly difficult task for project managers due to the need to anticipate and visualize likely future events. Conventional computer-assisted technology can help but is often limited to the constructability issues involved. Virtual prototyping, however, offers an improved method through the visualisation of construction activities by computer simulation enabling a range of what-if questions to be asked and their implications on the total project to be investigated. This paper describes the use of virtual prototyping to optimize construction planning schedules by analyzing resource allocation and planning with integrated construction models, resource models, construction planning schedules and site-layout plans. A reallife case study is presented that demonstrates the use of a virtual prototyping enabled resource analysis to reallocate space, logistic on access road and arrange tower cranes to achieve a 6-day floor construction cycle. Keywords: Construction Planning Schedule; Virtual Prototyping, Space, Resource Analysis. 1. Introduction It is well known that successfully completed construction projects are a result of careful planning and execution and established techniques, such as the critical path method (CPM) and bar charts, are commonly used to enable this to be done in a systematic way. This involves the project team allocating the different resources needed associated with the major method selected and decides on the appropriate sequence of assemblies. However, contractors project planners face many uncertain and complex tasks during construction period due to e.g., design errors and mismatch of what is planned and actually needed [1]. In addition, errors and mistakes in the construction planning schedule occur frequently as its compilation depends to a large extent on the project team s limited knowledge and experience [2]. As a result, a successfully tendered building project can be very much a gamble due to the main contractor inability to predict whether the project will result in a profit or a loss in advance of construction. For many projects, a major limitation is the lack of an effective computer-assisted technology for resource allocation and planning. Due to the complexity and the large number of factors involved, computers can be an efficient tool to help project planners. Such basic computer aids as bar charts and the critical path method are quite limited as they are unable to provide spatial construction features or resource and working space requirements [3,4]. More sophisticated methods combine the three traditional techniques

of resource allocation, resource levelling and Time-cost trade-off analysis. For example, Chan et al. [5], Hegazy [6], Leu and Yang [7] combine resource allocation and levelling using genetic algorithms (GAs); Li and Love [8] propose GAs for time-cost optimization problems; Hegazy and Kassab [9] combine a flowchart based simulation tool with the GA technique; and Wang et. al. [10] have developed a 4D Management for Construction Planning and Resource Utilization (4D-MCPRU) system which links a 3D geometrical model with resources to compute the resource requirement. None of these previous resource planning and allocation methods take the real productivity rate into account in analyzing the resources. The application of virtual prototyping (VP) technology helps solve this problem by allowing planners to consider objective productivity data to predict potential constructability problems and analyze resource allocation including equipment, space and labour to modify construction sequences to provide a comprehensive construction planning schedule [11]. The paper first describes the framework of integrated planning using the VP technology. Next, a case study is presented to demonstrate how the construction planning schedule is optimized. Future improvements to the VP technology are discussed and concluded in the final section. 2. The framework for integrated planning on VP technology 2.1. Definition of the Construction Model The Construction Model consists of two types of digital model. The first type is similar to the Building Information Management (BIM) model, which is a 3D model with information for the performance evaluation of the model. The key function of the BIM in the construction field is to allow planners to view their static realistic images and check for design errors and collisions. Temporary works are a critical element in construction planning [3] and this type of model is used to develop temporary work models generated by the parametric models. Details of the temporary work model are available in Huang et al. [12]. The second type of model is a detailed building component model, which is related directly to construction activities. The purpose of this model is as a design check and is also closely associated with the construction planning schedule. This type of model decomposes serial assembly models to develop a detailed construction activity. The decomposition of a product is a precondition of simulation and the assembly of parts is closely related to the simulation process. For example, assume the purpose of the simulation is to display the sequence of pouring concrete. One floor of the 3D concrete model will be decomposed into different assembly models (i.e. inner slab, half of outer slabs, outer wall, inner wall, each column) which are related to the sequence of the simulation (Fig. 1).

3D Model Construction Assembly Models Fig. 1. Decomposition of 3D building model 2.2. Definition of the Resources Model Two resources models can be identified: an equipment-based model and an activity-based model. Equipment-based Model - The equipment-based Model is a 3D-geometry model linked with the productivity rate of equipment in an Excel library database and physical capacity data. For example, the tower crane model contains graphical information that is the exact geometry, shape and dimension for space analysis and capacity (i.e. maximum capacity, maximum lifting height and maximum radius) for testing the operating capacity. Activity-based Model - The activity-based Model is a non-physical model linked with the productivity rate in an Excel library database. The fixing reinforcement activity is an example. The activity-base model is linked with the construction model by users when generating the VP simulation to develop one process activity in the system. 2.3 The importance of detailed simulation It is important for the construction planning schedule to have detailed activities. A master program does not show all the detailed activities that occur in a project. The planning activities should be elaborated as more details are required. In the construction planning schedule, it is very difficult for the project planners to consider the detailed activities, resource allocation and space requirement. Project planners pay a lot attention to the master program but tend to neglect detailed activities. They understand that resource allocation is a key factor in the construction planning schedule but they lack mathematical method to analyze resource allocation. The space required by construction activities is the most difficult element for them to analyze as space is static stage and dynamic. Since spaces required by activities change in all three dimensions through time [13-16], the time-space may conflict between activities. A detailed 4D planning schedule is required to compute the duration of each activity and associated space required. The activity concreting wall provides a good example (Fig. 2). It includes many types of activity related to time-space. Fixing reinforcement, erecting formwork and falsework, pouring, casting and dismantling formwork and falsework also require process time, space for crews to work and to temporarily store and

manage the materials and equipment items needed. There are many factors to be considered in this simple activity. All of them are directly related to the construction planning schedule. Activity Productivity Rate Need Fixing rebar Workers productivity rate Erecting formwork and falsework Workers productivity rate Pouring concrete Pouring speed and volume Completed Dismantling formwork and falsework Workers productivity rate Fig. 2. The detailed sequence for concreting wall Casting concrete Casting time 2.4. Implementation The database of the productivity rate and the construction planning schedule is stored in Microsoft Excel format. The virtual prototyping system is implemented using Visual Basic for Applications (VBA) in the DELMIA V5 environment, and Microsoft Excel to develop the productivity database and planning schedule linking with the 3D Model. VBA is an object-oriented programming language to develop specific functions. VBA provides a seamless link between the components of the model, supported by a powerful graphical user interface (GUI). The equipment-based model and the activity-based model link with the productivity rate of equipment and the activity s productivity rate respectively. 2.5. Integrated Construction Planning Schedule, Site Layout Planning and all construction process activities The 3D site layout model is developed based on the 2D site layout planning on the VP system. Through the VP technology, a process activity is generated by linking a construction model and an activity-based model or by putting a construction model and an equipment-base model together. Combining each process activity with the

construction planning schedule, along with the 3D site layout planning, a process simulation is developed (Fig. 3). Process Simulation Construction Planning Schedule (Excel) Process Activity T1 Construction Model Activity-base Model Productivity Rate Library (Excel) Process Activity T2 Construction Model Equipment-base Model DELMIA V5 Library Productivity Rate Library (Excel) Site Layout Planning Fig. 3. VP Structure 2.6. Resource Analysis In the construction field, all activity duration estimates are based on the experience of the project managers. The duration of activities is therefore often uncertain. One major function of the VP system utilizes real productivity data from the system database to verify and then adjust the resource allocation. Through the process simulation, resources, such as space, equipment and crew, can be analyzed. Most building construction projects rely on tower cranes to perform lifting and hoisting activities [17]. The tower crane is the most critical component of the construction planning schedule. Through 3D visualization and simulation of the tower cranes, the planner understands the planning in detail and is able to predict planning mistakes [18]. The following sections provides a case study to demonstrate how resource allocation is analyzed. 3. Case Study 3.1. Introduction The case study involves two residential building projects in Hong Kong. At the time of the research, the foundations of the two buildings were already completed. The site layout planning had also taken place. During construction, the project managers encountered different types of critical problems while planning the typical construction cycle. They would like to have visualization, digital and mathematical method to measure the constructability of the construction planning schedule. They provided the researchers with a preliminary construction planning schedule of a typical floor construction, comprising a 6-day cycle time slot - planning schedule (Fig. 4).

Fig. 4. Time slot- construction planning schedule The building had prefabricated concrete facades supported by in-situ concrete walls, a lift core and half an in-situ slab. The two buildings were named No.1 and No.2 respectively. The project managers divided the buildings into two working bays in the middle. The bays of building No.1 were named 1A and 1B. The bays of building No.2 were named 2A and 2B. The construction cycles of each bay were contiguous to fully utilize the tower crane. A set of steel formwork panels was applied for all the concrete walls and concrete slab. The project managers planned to construct the two buildings at the same time but only one set of steel formwork was used. Two tower cranes were installed on the construction site for lifting the formwork panels, prefabricated concrete façade, reinforcement bars and concrete buckets. One tower crane (T1) was installed between Bay 1A and Bay 1B while the other (T2) was installed in the middle of Bay 2A and Bay 2B (Fig. 5). The two tower cranes were of different capacities. The maximum radius of T1 was long enough to reach Bay 2B whereas the maximum radius of T2 could only reach the temporary storage space. There were two ways of lifting the steel formwork. One was directly lifting the formwork from bay 1A to bay 2A by using T1. The second was lifting the formwork from Bay 1A to the temporary storage space between the two buildings by T1 and then the formwork was lifted by T2 to Bay 2B. For pouring concrete, both Bay 1A and Bay 1B used the tower crane while a placing boom was used in Bay 2A and Bay 2B.

Fig. 5. The location of the two tower crane and the four bays The project planners encountered the following critical problems in the planning schedule 1. There was a limited storage area for storing facade elements, steel formworks, reinforcements and temporary supports as they needed to plan what materials would arrive, and when and where they would be stored. 2. There was a limited working area for workers and access road for material transportation such as transit mixers, transportation material truck for reinforcement and façade elements. 3. The preliminary planning durations of the activities were not computed mathematically. The project planners wanted to use the real productivity rate data to verify the construction planning schedule especially for the cranes as they were the critical elements of the whole construction planning schedule. 3.2. Preparation of the Construction Model and Resource Model A construction model for temporary work was developed based on the design drawings prepared by nominated subcontractor and the building component was built based on the process activities to decompose the suitable assembly models. The two tower cranes and the placing boom were built into the equipment-based Model. Their capacities were based on their capacity catalogues. The activity-based Model was prepared from previous projects. 3.3. Start from Preliminary Construction Planning Schedule The main construction method was to use one set of steel formwork for two buildings to reduce the cost of steel formwork However, there was not enough space for storing the steel formwork. The schedule of the project was represented by a simple time slot document. The researchers generated a template of a construction planning schedule in VP-Excel format for inputting the time slot planning data (Fig. 6). The planning schedule

was imported into the VP system. This allowed the users to link the process activities with their related Construction Models and Resource Models (Fig. 7). Fig. 6. Construction planning schedule in VP-Excel Format Fig. 7. Assignment of the tower crane to lift the façade in one process activity 3.4. Build site layout environment The project planners had finished the site layout planning before the researchers joined. The 2D site layout planning was used to build the 3D site layout environment, including the location of the two different types of tower crane, site office, storage area, passenger and material hoists and access road. The 3D site layout could provide a virtual construction site for the VP system to analyze the access road, space requirement and the assignment of tower cranes.

3.5. Analysis the resource allocation By integrating the preliminary construction planning schedule, site layout planning, construction models and resource models, the simulation of the construction process was developed to analyze resource allocation. All productivity data of the activities were obtained from numerous previous projects. The data was thus objective. Most major activities were related to the tower cranes, access road and space. These three factors were applied to these activities. The data included the duration of delivery material, as the material must be delivered to the site before the installation to prevent delays to other work. There were different types of productivity rate related to these three factors (Table 1). The users then defined activities linked with tower cranes, access road and space in order to analyze the accuracy of the construction planning schedule. Tower Crane Access Road Space The capacity of transit mixers The speed of pouring by using tower crane The speed of pouring by using placing boom The time of fixing rebar per area The lifting time of rebar The lifting time of steel formwork from the building to temporary storage platform The lifting time of steel formwork from 1B to 2B The rising time of the working platform The lifting time of rising and installation of facades Size of steel formwork Size of facade Area of temporary storage Area of storing reinforcement Area of storing façade Required quantity of reinforcement for 6 day cycle Required quantity of facade for 6 day cycle Table 1. Different types of productivity rates related to three factors Allocation on Access Road It was important that there was no overlapping of transportation routes in the planning of the access road logistic as there was only one access road for transportation on the site. The trucks carrying reinforcement / facade and transit mixer would stay on the access road. In particular, the transit mixer would stay on the access road approximately 10 hours for pouring concrete into a bay and so would obstruct the road. All types of trucks needed be arranged correctly to avoid any overlapping of transportation routes in the planning schedule. The VP system determined the number of transit mixers to be used based upon the required quantity of concrete for different working bays. Also, it computed the exact duration for pouring each bay by using the tower crane or placing boom since the speed of pouring by placing boom was double to that of pouring by tower crane. The VP system simulated the construction planning schedule and allocation of access road to find any conflicts of access road use.

Allocation on Tower Crane Planning the usage of the tower cranes was crucial to the timely and safe achievement of the 6 day floor planning schedule as the cranes were involved in various activities across the construction site and a large number of building components were installed by the cranes. Firstly, the VP system, based on the real productivity rate, was used to check the duration of the construction planning schedule used by the tower cranes and then adjust the activity duration. Secondly, the VP system based on the preliminary construction planning schedule was used to visualize and identify clashed activities by using tower cranes in the display and Gantt Chart respectively (Fig. 8). The user adjusted the construction planning schedule to eliminate the clashed activities. Fig. 8. Assignment of two tower cranes in Gantt Chart Space The space involved storage material, equipment, and working space in 3D through time. Because of the limited construction site area, the storage amount of reinforcement and façade needed to be considered. The VP system determined the number of trucks based upon the required quantity of reinforcement and facade for the 6 day cycle and then computed the capacity of storage area needed for the reinforcement and façade. Based on the availability of the access road, these data were then used to determine when the trucks come to site The project planners had an innovative idea for solving the limited construction site area. This was to build a temporary platform for storing the steel formwork for a short period. Through VP technology, the space with time could be analyzed accurately.

4. Future improvements to construction virtual prototyping Feedback from the project planners indicate that it would be better for the construction planning schedule to be developed together with the site layout planning in VP system. A good site layout planning can increase the productivity of construction activities, improve safety and avoid obstructing material and equipment movements on the construction site [19-21]. A comprehensive planning and efficient site layout are the main preliminary factors for successful construction management [22]. A computer-aided environment can support the site layout planning design. Ma et al.[23] developed an integrated site planning tool called the 4D Integrated Site Planning System (4D-ISPS) which integrates schedules, 3D models, resources and site spaces together with 4D CAD technology to provide 4D graphical visualization capability for construction site planning. 5. Conclusion The purpose of using VP technology for construction simulation is to assist project planners to better understand the construction process and predict possible mistakes. This paper describes how a construction model and resource model can be prepared for VP in support of the construction planning process. A case study demonstrates an application in which the VP system enabled the user to validate a proposed construction planning schedule. This shows that the VP system can be used for this purpose and site layout planning is a key issue in preparing the construction planning schedule. We are currently looking for other real projects to integrate site layout planning in order to optimize the construction planning schedule before building. References [1] H. Li, H.L. Guo, M. J. Skibniewski and M. Skitmore, Using the IKEA model and virtual prototyping technology to improve construction process management, Journal of Construction Engineering and Economics 26 (2008), 991-1000 [2] A.F. Waly and W.Y. Thabet, A virtual construction environment for preconstruction planning, Automation in Construction 12 (2002) 139 154 [3] B. Koo and M. Fischer, Feasibility study of 4D CAD in commercial construction, Journal of Construction Engineering and Management 126 (4) (2000) 251 260 [4] K.W. Chau, M. Anson and J.P. Zhang, Implementation of visualization as planning and scheduling tool in construction, Building and Environment 38 (2003) 713 719 [5] W. Chan, D. K. H. Chua, and G. Kannan, Construction Resource Scheduling with Genetic Algorithms, Journal of Construction Engineering and Management 122 (2) (1996) 125-132 [6] T. Hegazy, Optimization of Resource Allocation and Leveling Using Genetic Algorithms, Journal of Construction Engineering and Management 125(3) (1999) 167-175.

[7] S. S. Leu and C. H. Yang, GA-Based Multicriteria Optimal Model for Construction Scheduling, Journal of Construction Engineering and Management 125 (6) (1999) 420-427 [8] H. Li, and P. Love, Using improved genetic algorithms to facilitate time-cost optimization, Journal of Construction Engineering and Management 123(3) (1997) 233 237 [9] T. Hegazy and M. Kassab, Resource Optimization Using Combined Simulation and Genetic Algorithms, Journal of Construction Engineering and Management 129(6) (2003) 698-705 [10] H. J. Wang, J.P. Zhang, K.W. Chau and M. Anson, 4D dynamic management for construction planning and resource utilization, Automation in Construction 13 (2004) 575-589 [11] H. Li, T. Huang, C.W. Kong, H.L. Guo, A. Baldwin and N. Chan, J. Wong, Integrating design and construction through virtual prototyping, Automation in Construction 17 (2008) 915 922 [12] H. Li, H.L. Guo, M. J. Skibniewski and M. Skitmore, Using the IKEA model and virtual prototyping technology to improve construction process management, Journal of Construction Engineering and Economics 26 (2008), 991-1000 [12] T. Huang, C.W. Kong, H.L. Guo, A. Baldwin and H. Li, A virtual prototyping system for simulating construction processes, Automation in Construction 16 (2007) 576 585 [13] B. Akinci, M. Fischer, R. Levitt and R. Carlson, Formalization and automation of time-space conflict analysis, Journal of Computing in Civil Engineering 16(2) (2000a) 124-134 [14] B. Akinci, M. Fischer, R. Levitt and R. Carlson, Automated generation of work spaces required by construction activities, Journal of Construction Engineering and Management 128 (4) (2000b) 306-315 [15] W. Thabet and Y. Beliveau, Modeling work space to schedule repetitive floors in multistory buildings, Journal of Construction Engineering and Management 120 (1) (1994) 96-116 [16] P. Zouein and I. Tommelein, Time-space tradeoff strategies for space-schedule construction, Journal of Computing in Civil Engineering ASCE, New York, (1994) 1180 1187 [17] M. Al-Hussein, M. A. Niaz, H. Yu and H. Kim, Integrating 3D Visualization and Simulation for Tower Crane Operations on Construction Sites. Automation in Construction 15 (2006) 554-562 [18] K. Tantisevi, and B. Akinci, Simulation-Based Identification of Possible Locations for Mobile Cranes on Construction Sites. Journal of computing in civil engineering 22 (2008) 21-30 [19] F. Sadeghpour, O. Moselhi and S. Alkass, Computer-Aided Site Layout Planning, Journal of Construction Engineering and Management 132(2) (2006) 143-151 [20] T. M. Hegazy and E. Elbeltagi, EvoSite: Evolution-based model for site layout planning, Journal of Computing in Civil Engineering 13(3) (1999) 198 206 [21] I. D. Tommelein, R. E. Levitt and B. Hayes-Roth, SightPlan model for site layout, Journal of Construction Engineering and Management 118(4) (1992) 749 766

[22] K.W. Chau, M. Anson and J.P. Zhang, Four-Dimensional Visualization of Construction Scheduling and Site Utilization, Journal of Construction Engineering and Management 130 (4) (2004) 598 606 [23] Z.Y. Ma, Q.P. Shen and J.P. Zhang, Application of 4D for dynamic site layout and management of construction projects, Automation in Construction 14 (2005) 369-381